No.J-11015/108/2006-IA.II(M)

Government of India

Ministry of Environment & Forests

Paryavaran Bhawan,

C.G.O.Complex, Lodi Road,

New Delhi -110003.

 

Dated: 17th May 2007

To

Shri Chanakya Choudhary,

Chief Resident Executive,

M/s Tata Steel Ltd.,

(M/s Tata Iron & Steel Co. Ltd.),

Jeevan Bharati Building Tower1,

10th Floor, 124 Connaught Circus,

New Delhi-110001.

 

Sub:    West Bokaro Opencast Coal Mine Project (4.7MTPA to 7 MTPA) of M/s Tata Iron & Steel Co. Ltd. (M/s Tata Steel Ltd.), located in village Bharagutu, Tehsil Ghatotand, District Hazaribagh, Jharkand - environmental clearance ? reg.

Sir,

 

            This has reference to your letter No. TSLDEL/369/2006 dated 20.04.2006 along with your application and subsequent letters dated 12.06.006, 06.10.2006, 18.01.2007 and 12.04.2007 on the above-mentioned subject. The Ministry of Environment & Forests has considered your application.  It has been noted that the project is for expansion of the existing West Bokaro Opencast Coal Mine Project in terms of production capacity from 4.7 million tonnes per annum (MTPA) to 7 MTPA of coal . The total lease area is 1740 ha of which 31 ha is agricultural land, 910 ha is forestland, 603 ha is  wasteland, 42 ha is surface water bodies, and 114 ha is green belt. Forestry clearance has been applied for. There are no National Parks, Wildlife Sanctuary, Biosphere Reserves found in the 10 km buffer zone. However, the study area contains a number of medicinal plant species and a few endangered fauna River Bokaro flows through the mine lease and at a distance of 0.5 m from the cola washery and workshop. In addition, the Chota Nadi (south) and the Chuta Nala  (200m north)  flow adjacent to the lease boundary. The RL of riverbed varies from 329-339 m and that o the mine ranges from 340-364m and the HFL of the river is 336 m. The project involves modification of the natural drainage by construction of embankment, which is 3m higher than the HFL of the river flowing adjacent and along the quarry area and an in-pit drainage system for protection against flood/mine inundation. Of the total lease area, area for excavation is 987 ha, 158 ha is for OB dumps, 119 ha is for infrastructure, 33 ha is for roads, 114 ha is for green belt, 21 ha is for tailings pond, 41 ha is for CHP, 225 ha is for township, and 42 is others. Mining will be opencast by mechanised method. The rated capacity of the mine is 7 MTPA of coal production. The capacity of the existing two washeries (II and III) is being augmented from 4.7 MTPA (II of 2.66 MTPA capacity and III of 2.1 MTPA capacity) to 5.5 MTPA and eventually to 7 MTPA (2.5 MTPA + 4.5 MTPA). In addition to existing crusher at the pithead, an additional CHP is proposed. Mineral transportation of 6000 TPD of coal is by road to pithead for crushing and from there to washery for mineral beneficiation and from thereto the railway siding through aerial ropeway and the remaining 17,000 TPD is by closed conveyors to the 2nd washery covering a distance of 4km and from thereto by aerial ropeway to loading site for transport by railways. The capacity of the ropeway and the wagon loading sites are being augmented to handle the expansion in capacity and the consequent increase in mineral transportation and loading. Ultimate working depth of the mine is 250m below ground level (bgl). Present working depth is 100m bgl. Water table is in the range of 1.60- 2.32 m bgl in the core zone and 1.60- 7.80 m bgl in the buffer zone. Mining has intersected water table. Approval from the Central Ground Water Authority has been obtained on 01.12.2005. Average water requirement is 13075 m3/d, which will be met from river Bokaro (8762 m3/d) and from mine pit water (4313 m3/d). Of this, 7718 m3/d is for coal beneficiation, of which 2724 m3/d will be fresh water. There will be no discharge of wastewater from the coal washery and from the CHP as they are designed as zero-discharge units.  An estimated 564.7 Mm3 of OB will be generated in the balance life of mine which will be completely backfilled and reclaimed with plantation leaving a void of 20 ha which is to be converted into a water body. No additional OB dumps or dumping on existing dumps is proposed. The three existing OB dumps have been reclaimed. Clean coal and midlings of 5.6 MTPA capacity and coarse washery rejects generated in washeries will be used in the linked steel plant/power plant while the washery rejects and tailings will be sold to brick kiln manufacturers. Project involves R&R of 7 villages in the core zone ? Baragutu, Banji, Duni, Parasbera, Pundi, Durkusmar and Kedla involving displacement of 839 families. Balance life of the mine at the rated capacity of 7 MTPA is 25 years. Public Hearing was held on 17.10.2005. NOC has been obtained on 31.10.2005. The Mining Plan has been approved by Ministry of Coal on 27.09.2006. Capital cost of the project is Rs. 3157 crores.

 

2.         The Ministry of Environment & Forests hereby accords environmental clearance for the above-mentioned West Bokaro Opencast Coal Mine Project of M/s Tata Iron & Steel Ltd. (M/s Tata Steel Ltd.) for expansion in production of coal to 7 MTPA annual rated capacity in a total lease area of 1740 ha under Section 12 of the Environmental Impact Assessment Notification, 2006 and subsequent amendments thereto and under Para 2.1.1 of MOEF Circular dated 13.10.2006 subject to the compliance of the terms and conditions mentioned below:

 

A.        Specific Conditions

 

(i)         No mining operations shall be undertaken in the forestland until clearance has been obtained under the provisions of FC Act, 1980.

 

(ii)        The embankment along the River Bokaro shall be designed taking into account the highest flood level, based on past data, along the quarry area at the mine boundary along the River Bokaro so as to guard against mine inundation. The slope of the embankment shall at least 2:1 towards the ML and shall be stabilised by plantation. The height of the embankment shall be at least 5 m higher than the HFL.

 

(iii)       Topsoil should be stacked properly with proper slope at earmarked site(s) and should not be kept active and shall be used for reclamation and development of green belt.

 

(iv)       No new external OB dumps shall be created for storing OB. Monitoring and management of existing reclaimed dumpsites should continue until the vegetation becomes self-sustaining. Compliance status should be submitted to the Ministry of Environment & Forests and its Regional office located at Bhubaneshwar on an yearly  basis.

 

(v)        Catch drains and siltation ponds of appropriate size should be constructed to arrest silt and sediment flows from soil, OB and mineral dumps. The water so collected should be utilised for watering the mine area, roads, green belt development, etc. The drains should be regularly desilted and maintained properly.

Garland drains (size, gradient and length) and sump capacity should be designed keeping 50% safety margin over and above the peak sudden rainfall and maximum discharge in the area adjoining the mine site. Sump capacity should also provided adequate retention period to allow proper settling of silt material.

 

(vi)       Dimension of the retaining wall at the toe of the dumps and OB benches within the mine to check run-off and siltation should be based on the rainfall data.

 

(viii)                 Crushers at the CHP should be operated with high efficiency bag filters, water sprinkling system should be provided to check fugitive emissions from crushing operations, conveyor system, haulage roads, transfer points, etc.

 

(ix)      Drills should be wet operated.

 

(x)       Controlled blasting should be practiced only during daytime with use of delay detonators. The mitigative measures for control of ground vibrations and to arrest the fly rocks and boulders should be implemented.

 

(xi)      Area brought under afforestation shall not be less than 1260 ha which includes reclaimed external OB dump (212.5 ha), backfilled area (974 ha), along ML boundary, along roads, green belt (502.5 ha),  in undisturbed areas and in colony within the mine lease area by planting native species in consultation with the local DFO/Agriculture Department. The density of the trees should be around 2500 plants per ha.

 

(xii)           A Progressive Closure Plan shall be implemented by reclamation of quarry area of 974 ha which shall be backfilled and afforested by planting native plant species in consultation with the local DFO/Agriculture Department. The density of the trees should be around 2500 plants per ha. The balance 20 ha of decolaed area being converted into a water reservoir shall gently sloped along the upper benches and stabilised and reclaimed with plantation.

 

(xiii)    A Conservation Plan for endangered species found in and around the project area shall be formulated and for the medicinal plants (in-situ and ex-situ) shall be prepared and implemented in consultation with the State Forest and Wildlife Departments. Separate funds shall be earmarked for implementation of the various activities there under and the status thereof shall be regularly reported to this Ministry and the MOEF Regional Office, Bhubaneshwar

 

(xiii)         No groundwater shall be used for the mining/project activities. Additional water required, if any, shall be met by recycling/reuse of  the water from the existing  activities and from rainwater harvesting measures.

 

(xv)     Regular monitoring of groundwater level and quality should be carried out by establishing a network of exiting wells and construction of new peizometers. The monitoring for quantity should be done four times a year in pre-monsoon (May), monsoon (August), post-monsoon (November) and winter (January) seasons and for quality in May. Data thus collected should be submitted to the Ministry of Environment & Forests and to the Central Pollution Control Board quarterly within one month of monitoring.

 

(xvi)         The Company shall put up artificial groundwater recharge measures for augmentation of groundwater resource. The project authorities should meet water requirement of nearby village(s) in case the village wells go dry due to dewatering of mine.

 

(xvii)       ETP should also be provided for workshop, coal washery and CHP. There shall be Zero discharge of wastewater from CHP and the coal washeries.  Effluents from the tailings pond shall be treated to conform to prescribed standards in case of discharge into any water course outside the lease.

 

(xviii)     An STP shall be provided for the township/colony to treat the domestic effluents to prescribed standards and for their reuse in project activities.

 

(xix)         R&R shall be based on norms laid down by the State Government and shall not be inferior than that in the National R&R Policy and shall be completed within a specified time-frame.

 

(xxvi)   For monitoring land use pattern and for post mining land use, a time series of landuse maps, based on satellite imagery (on a scale of 1: 5000) of the core zone and buffer zone, from the start of the project until end of mine life shall be prepared once in 3 years (for any one particular season which is consistent in the time series), and the report submitted to MOEF and its Regional office at Bhubaneshwar.

 

(xix)    A Final Mine Closure Plan along with details of Corpus Fund should be submitted to the Ministry of Environment & Forests for approval 5 years in advance of final mine closure for approval.

 

(xx)           Consent to Operate shall be obtained before expanding mining operations.

 

B.        General Conditions

 

(i)                 No change in mining technology and scope of working should be made without prior approval of the Ministry of Environment and Forests.

 

(ii)               No change in the calendar plan including excavation, quantum of mineral coal and waste should be made.

 

(iii)             Four ambient air quality monitoring stations should be established in the core zone as well as in the buffer zone for SPM, RPM, SO2 and NOx monitoring.  Location of the stations should be decided based on the meteorological data, topographical features and environmentally and ecologically sensitive targets in consultation with the State Pollution Control Board.

 

(iv)             Fugitive dust emissions (SPM and RPM) from all the sources should be controlled regularly monitored and data recorded properly. Water spraying arrangement on haul roads, wagon loading, dump trucks (loading and unloading) points should be provided and properly maintained.

 

(v)               Data on ambient air quality (SPM, RPM, SO2 and NOx) should be regularly submitted to the Ministry including its Regional Office at Bhubaneshwar and to the State Pollution Control Board and to the Central Pollution Control Board once in six months.

 

(vi)             Adequate measures should be taken for control of noise levels below 85 dBA in the work environment. Workers engaged in blasting and drilling operations, operation of HEMM, etc should be provided with ear plugs/muffs.

 

(vii)           Industrial wastewater (workshop and wastewater from the mine) should be properly collected, treated so as to conform to the standards prescribed under GSR 422 (E) dated 19th May 1993 and 31st December 1993 or as amended from time to time before discharge. Oil and grease trap should be installed before discharge of workshop effluents.

 

(viii)         Vehicular emissions should be kept under control and regularly monitored. Vehicles used for transporting the mineral should be covered with tarpaulins and optimally loaded.

 

(ix)             Environmental laboratory should be established with adequate number and type of pollution monitoring and analysis equipment in consultation with the State Pollution Control Board.

 

(x)               Personnel working in dusty areas should wear protective respiratory devices and they should also be provided with adequate training and information on safety and health aspects.

            Occupational health surveillance programme of the workers should be undertaken periodically to observe any contractions due to exposure to dust and to take corrective measures, if needed.

 

(xi)             A separate environmental management cell with suitable qualified personnel should be set up under the control of a Senior Executive, who will report directly to the Head of the company.

 

(xii)           The funds earmarked for environmental protection measures should e kept in separate account and should not be diverted for other purpose. Year-wise expenditure should be reported to this Ministry and its Regional Office at Bhubaneshwar.

 

(xiii)         The Regional Office of this Ministry located at Bhubaneshwar shall monitor compliance of the stipulated conditions. The Project authorities shall extend full cooperation to the office(s) of the Regional Office by furnishing the requisite data/ information/monitoring reports.

 

(xiv)         A copy of the will be marked to concerned Panchayat/ local NGO, if any, from whom any suggestion/representation has been received while processing the proposal.

 

(xv)           State Pollution Control Board should display a copy of the clearance letter at the Regional  Office, District Industry Centre and Collector?s Office/Tehsildar?s Office for 30 days.

 

(xvi)         The Project authorities should advertise at least in two local newspapers widely circulated around the project, one of which shall be in the vernacular language of the locality concerned within seven days of the clearance letter informing that the project has been accorded environmental clearance and a copy of the clearance letter is available with the State Pollution control Board and may also be seen at the website of the ministry of Environment & Forests at http://envfor.nic.in.

 

3.         The Ministry or any other competent authority may stipulate any further condition for environmental protection.

 

4.         Failure to comply with any of the conditions mentioned above may result in withdrawal of this clearance and attract the provisions of the Environment (Protection) Act, 1986.

 

5.         The above conditions will be enforced inter-alia, under the provisions of the Water (Prevention & Control of Pollution) Act, 1974, the Air (Prevention & Control of Pollution) Act, 1981, the Environment (Protection) Act, 1986 and the Public Liability Insurance Act, 1991 along with their amendments and Rules.

 

 

 

(Dr.T.Chandini)

Director

Copy to:

1.      Secretary, Ministry of Coal, Shastri Bhawan, New Delhi.

2.      Secretary, Department of Environment & Forests, Government of Jharkand, Secretariat, Ranchi.

3.      Chief Conservator of Forests, Regional office (EZ), Ministry of Environment & Forests, A/3 Chandrashekarpur, Bhubaneshwar ? 751023.

4.      Chairman, Jharkand State Pollution Control Board, TA Building, HEC Complex, PO Dhurwa, Ranchi.

5.      Chairman, Central Pollution Control Board, CBD-cum-Office Complex, East Arjun Nagar, New Delhi -110032.

6.      Member-Secretary, Central Ground Water Authority, Ministry of Water Resources, Curzon Road Barracks, A-2, W-3 Kasturba Gandhi Marg, New Delhi.

7.      District Collector, Hazaribagh, Government of Jharkand.

8.      Monitoring File    9.         Guard File       10.       Record File

 

 

 

(Dr.T.Chandini)

Director


No.J-11015/108/2006-IA.II(M)

Government of India

Ministry of Environment & Forests

Paryavaran Bhawan,

C.G.O.Complex,

New Delhi -110510.

 

Dated: 3rd December 2007

To

Chief Resident Executive,

M/s Tata Steel Ltd.,

(M/s Tata Iron & Steel Co. Ltd.),

Jeevan Bharati Building Tower1,

10th Floor, 124 Connaught Circus,

New Delhi-110001.

 

CORRIGENDUM

 

Sub:    West Bokaro Opencast Coal Mine Project (4.7MTPA to 7 MTPA) of M/s Tata Iron & Steel Co. Ltd. (M/s Tata Steel Ltd.), located in village Bharagutu, Tehsil Ghatotand, District Hazaribagh, Jharkand - environmental clearance ? reg.

 

Sir,

 

            Attention is invited to this Ministry?s environmental clearance letter No. No.J-11015/108/2006-IA.II(M) dated 17.05.2007 on the above subject and the following corrections inserted in the EC letter Specific condition No. (xi):

 

(i)         The words ?OB dump (212.5 ha)? shall  be replaced by ?OB dump (85 ha)?

(ii)        The words ?green belt (502.5 ha)? shall be replaced by ?green belt (201 ha)?.

           

All other conditions remain the same.

(Dr.T.Chandini)

Director

Copy to:

9.      Secretary, Ministry of Coal, Shastri Bhawan, New Delhi.

10.  Secretary, Department of Environment & Forests, Government of Jharkand, Secretariat, Ranchi.

11.  Chief Conservator of Forests, Regional office (EZ), Ministry of Environment & Forests, A/3 Chandrashekarpur, Bhubaneshwar ? 751023.

12.  Chairman, Jharkand State Pollution Control Board, TA Building, HEC Complex, PO Dhurwa, Ranchi.

13.  Chairman, Central Pollution Control Board, CBD-cum-Office Complex, East Arjun Nagar, New Delhi -110032.

14.  Member-Secretary, Central Ground Water Authority, Ministry of Water Resources, Curzon Road Barracks, A-2, W-3 Kasturba Gandhi Marg, New Delhi.

15.  District Collector, Hazaribagh, Government of Jharkand.

16.  Monitoring File       9.         Guard File       10.       Record File.

 

 

 

(Dr.T.Chandini)

Director