No. J-11015/455/2007-IA.II (M)
Government
of India
Ministry of Environment & Forests
Paryavaran Bhavan,
C.G.O. Complex, Lodi Road,
New Delhi-110 003.
Dated the 11th
May, 2011
To
M/s
Hindustan Zinc Limited
Rajpura
Dariba Complex,
P.O.Dariba,
District
Rajsamand-313 211,
Rajasthan
E-mail:
kabir.ghosh@vedanta.co.in
Subject: Bamania Kalan Lead and Zinc Ore Mining
Project(M.L.No. 39/83) of M/s Hindustan Zinc Limited located in Village
Sindesar Kalan, Tehsil Relmagra, District Rajsamand, Rajasthan -environmental clearance regarding.
Sir,
This has reference to your letter No.
VP(RDM)-84(iii)/201-11 dated 05.10.2010 and subsequent letter dated 25.12.2010
on the subject mentioned above. The
project was earlier prescribed Terms of Reference (TORs) by the Ministry of
Environment and Forests on 14.09.2007 for undertaking detailed EIA study for
the purpose of obtaining environmental clearance suggesting to get the unified mining lease with a unified mining plan
for the purpose of environmental clearance. As the amalgamation of lease has
since not happened, the proposal was considered leasewise. The proposal
is for renewal of mining lease which
fell due on 29.10.2005 and opening of a new mine for production of 0.12million
tonnes per annum(million TPA)TPA of
lead and zinc ore.
2. The
total mine lease area of the project is 383.78ha, out of which 328.07ha is an
agricultural land, 24.29ha is grazing land and 31.42ha is others (Bilanam
Government Land). No forestland
involved. It has
been stated that surface rights will be required only for 4.5ha within the mine
lease, out of which, an area of 1.5ha is kept
for service shaft and associated structures, 0.75ha for industrial buildings
and roads, 0.5ha for waste dump and 1.5ha is for green belt. The Banas River
passes through the mine lease area. It has been reported that there are
no faults / major fractures connecting river with mineralized zone and no
percolation of river water is expected in the mine.
3. No national park/wildlife
sanctuary/biosphere reserve/tiger reserve/elephant reserve etc. are reported to
be located in the core and buffer zone of the mine and that the area does not
report to form corridor for Schedule-I fauna.
..2/-
-2-
4. The mine working will be
underground mechanized using sub level top slicing method. The targetted
production capacity of the mine is 0.12million TPA and the life of mine is 15years. The ore from this mine will
be treated in the existing beneficiation plant of Sindesar Khurd Mine. The ore
transportation will be done through underground tunnel. The topography of the area is flat and reported
to lies between 25001?52? to 25003?14? N Latitude and 74008?35?
to 74011?04? E Longitude in Survey of India topo sheet No. 45K/4, at
an elevation of 486m AMSL. The
underground mining will be carried out at the depth of 130m from the land
surface. The ground water table
reported to ranges between 5-10m below the land surface during post-monsoon
season and 10-15m below the land surface during pre-monsoon season. The mine
working will intersect the ground water table. Based on the hydro-geological
study, it has been reported that the radius of influence of pumped out water
will be 50m. Further, the stage of
groundwater development is reported to be 85% and 80% in core and buffer zone
respectively and thereby these are
designated as critically exploited areas. The pumped out water will be
used to meet the water requirement of the mine, which is estimated as 60m3
per day. The difference of the
requirement will be obtained from the Matri Kunda Dam. It has been reported
that there are 1599 people in the core zone of the mine; however, no
displacement of population and R&R has been envisaged. It has been reported that a total of 30,000m3 of
waste rock will be generated due to mine development work during the mine life,
out of which majority will be used in void filling in underground and 20% will
be dumped in the earmarked dump yard. It has been envisaged that green belt
will be developed in an area of 1.5ha.
5. The
public hearing of the project was held combinedly for both the mine leases i.e.
ML No.39/83 and ML No.10/89 on 05.08.2010 for proposed combined production of
1000TPD from both the leases. The Indian Bureau of Mines had approved mining
plan of the project on 27.04.2007 for lease area of 383.78ha. The Mining Engineer, Rajasmand,
Government of Rajasthan vide letter No.
KHA.AA./ RAJ.II/CC-MAJOR/ML39/83/NAVINI/68/04/1347 dated 07.05.2008
stated that the said mine lease in accordance to the definition as provided in
the letter of the Directorate dated 09.01.2006 does not fall in Aravalli Hills.
The capital cost of the project is Rs.23.24Crores.
The capital cost for environmental protection measures is proposed as Rs.22.5Lakhs and the annual recurring
cost towards the environmental protection measures is proposed as Rs.4Lakhs. It was reported that there
is no court case pending against the project, however it was clarified that
there is a matter pending in the Tribunal for final decision regarding
execution of lease which is linked to grant of environmental clearance.
6. The Ministry of
Environment and Forests has examined the application in accordance with the EIA
Notification, 2006 and hereby accords environmental
clearance under the provisions thereof to the above mentioned Bamania
Kalan Lead and Zinc Ore Mining Project(M.L.No. 39/83) of M/s Hindustan Zinc
..3/-
-3-
Limited, for an annual production capacity of 0.12million tonnes of lead and zinc ore involving total mining lease area of 383.78ha, subject to implementation of the following
conditions and environmental safeguards.
A. Specific Conditions
(i)
Environmental clearance is
granted subject to final outcome of Hon?ble Supreme Court of India in Contempt
Petition (C) 412/2004 in IA No. 833 in Writ Petition (C)No. 202 of 1995, as may
be applicable to this project.
(ii)
Environmental clearance is
granted subject to final outcome of the Hon?ble Tribunal in the matter.
(iii)
The
project proponent shall obtain Consent to Establish and Consent to Operate from
the Rajasthan State Pollution Control Board and effectively implement all the
conditions stipulated therein.
(iv)
The environmental clearance
is subject to approval of the State Landuse Department, Government of Rajasthan
for diversion of agricultural land for non-agricultural use, as may be
applicable to this project.
(v)
Necessary
prior permission from the Competent Authority as may be applicable for use of
grazing land for mining purpose shall be obtained.
(vi)
The project
proponent shall develop fodder plots in the non-mineralised area in lieu of use
of grazing land.
(vii)
The project proponent shall
ensure that no natural watercourse and/or water resources shall be obstructed
due to any mining operations.
(viii)
It shall be also ensured
that there is no flooding of the mine due to the Banas river passing through
the mine lease. Necessary safeguard
measures in this regard shall be taken right from the initial stages and a disaster
management plan addressing this issue shall be put in place.
(ix)
The top soil shall temporarily be
stored at earmarked site(s) only and it should not be kept unutilized for long.
The topsoil shall be used for land reclamation and plantation.
(x)
The over burden generated
during the mining operation shall be stacked at
earmarked dump site only and it should not be kept active for a long period of
time and its phase-wise stabilization shall be carried out. The over burden dump shall be scientifically
vegetated with suitable native species to prevent erosion and surface run off.
Monitoring and management of rehabilitated areas shall continue until the
vegetation becomes self-sustaining. Compliance status shall be submitted to the
Ministry of Environment & Forests and its Regional Office located at
Lucknow on six monthly basis.
..4/-
-4-
(xi)
Catch drains and siltation
ponds of appropriate size should be constructed to arrest silt and sediment
flows from over burden dump. The water so collected should be utilized for
watering the mine area, roads, green belt development etc. The drains should be
regularly desilted particularly after monsoon and maintained properly.
Garland
drain (size, gradient and length) shall be constructed around over burden dump
and sump capacity should be designed keeping 50% safety margin over and above
peak sudden rainfall (based on 50 years data) and maximum discharge in the area
adjoining the mine site. Sump capacity should also provide adequate retention
period to allow proper settling of silt material. Sedimentation pits should be
constructed at the corners of the garland drains and desilted at regular
intervals.
(xii)
Dimension of the retaining
wall at the toe of dump should be based on the rain fall data.
(xiii)
Regular monitoring of
subsidence movement on the surface over working area and impact on water
bodies/vegetation/ structures/ surrounding shall be continued till movement
ceases completely. In case of observation of any high rate of subsidence
movement, appropriate measures shall be taken to avoid loss of life and
material. Cracks shall be effectively plugged with ballast and clayey
soil/suitable material.
(xiv)
Necessary safeguard measures
shall be taken to guard against any mine subsidence.
(xv)
All the mine entries shall
be above the highest flood level to avoid any anticipated flooding of mine from
the surface water during the rainy season.
(xvi)
In areas where
subsidence is anticipated in shallow mineral
occurrence, such areas be identified and provided with garland drains to
ensure draining of water and avoid ingress of the same in to the underground
mine.
(xvii)
The
project authorities shall check the possibility of existence of fault(s) before
deciding about the thickness of safe barrier required to be maintained between
the working face and the water bodies, if any, in consultation with the
Director General Mines & Safety (DGMS). De-pillaring should also be carried
out after taking prior approval of the DGMS.
(xviii)
The project
proponent shall carry out conditioning of the ore with water to mitigate
fugitive dust emission, without affecting flow of ore in the ore processing and
handling areas.
..5/-
-5-
(xix)
Green belt shall be
developed in an area of 1.5ha all along the mine lease area in a phased manner
and shall be completed within first five years. In addition, plantation shall
be raised over the OB dump, along the roads etc. in consultation with the local
DFO / Agriculture Department.
(xx)
Effective safeguard
measures, such as regular water sprinkling shall be carried out in critical
areas prone to air pollution and having high levels of particulate matter such
as loading and unloading point and all transfer points. Extensive water
sprinkling shall be carried out on haul roads. It should be ensured that the
Ambient Air Quality parameters conform to the norms prescribed by the Central
Pollution Control Board in this regard.
(xxi)
The project authority should implement suitable conservation
measures to augment ground water resources in the area in consultation with the
Regional Director, Central Ground Water Board.
(xxii)
Regular monitoring of ground
water level and quality shall be carried out in and around the mine lease by
establishing a network of existing wells and installing new piezometers during
the operation. The periodic monitoring [(at least four times in a year-
pre-monsoon (April-May), monsoon (August), post-monsoon (November) and winter
(January); once in each season)] shall be carried out in consultation with the
State Ground Water Board/Central Ground
Water Authority and the
data thus collected may be sent regularly to the
Ministry of Environment and Forests and its Regional Office Lucknow, the
Central Ground Water Authority and the Regional Director, Central Ground Water
Board. If at any stage, it is observed that the groundwater table is getting
depleted due to the mining activity, necessary corrective measures shall be
carried out. It shall be ensured that the
groundwater table is not depleted; rather efforts should be made to improve the
water table in the area.
(xxiii)
Suitable rainwater
harvesting measures on long term basis shall be planned and implemented in
consultation with the Regional Director, Central Ground Water Board.
(xxiv) Necessary prior clearance from Central Ground Water
Authority shall be obtained for pumping of groundwater.
(xxv)
The project proponent shall obtain necessary prior permission of the competent
authority for drawl of requisite quantity of
surface water from the Matri Kunda Dam.
(xxvi) The proponent shall make necessary arrangements as
envisaged for installation of RO plant through a joint venture for supplying
drinking
..6/-
-6-
water to the nearby areas as well as to the mine
workers. It shall be ensured that high
fluoride groundwater is not used for drinking at any stage.
(xxvii) Vehicular emissions should be kept under control
and regularly onitored. Measures shall be taken for maintenance of vehicles
used in mining operations and in transportation of mineral. The vehicles should
be covered with a tarpaulin and shall not be overloaded.
(xxviii)
Digital processing of
the entire lease area using remote sensing technique should be done regularly
once in three years for monitoring land use pattern and report submitted to
Ministry of Environment and Forests and its Regional Office, Lucknow.
(xxix)
The project
authorities should undertake sample survey to generate data on pre-project
community health status within a radius of 1 km from proposed mine.
(xxx)
The safeguard
measures to avoid occupational health impact due to lead dust and lead
poisoning shall be taken.
(xxxi)
Pre-placement medical
examination and periodical medical examination of the workers engaged in the
project shall be carried out and records maintained. For the purpose, schedule
of health examination of the workers should be drawn and followed accordingly.
(xxxii) Sewage treatment plant shall be installed for the
colony. ETP shall also be provided for the workshop and the wastewater
generated during mining operation.
(xxxiii) Quality of mine discharge shall be monitored and
necessary treatment as may be required shall be given to the mine water before
discharge so as to conform the prescribed standards.
(xxxiv) Provision shall be made for the housing of
construction labour within the site with all necessary infrastructure and
facilities such as fuel for cooking, mobile toilets, mobile STP, safe drinking
water, medical health care, crèche etc. The housing may be in the form of
temporary structures to be removed after the completion of the project.
(xxxv) The critical parameters such as RSPM
(Particulate matter with size less than 10µm i.e., PM10 and with
size less than 2.5µm i.e., PM2.5), NOX in the ambient air
within the impact zone, peak particle velocity at 300m distance or within the
nearest habitation, whichever is closer shall be monitored periodically .
Further, quality of discharged water shall also be monitored [(TDS, DO, PH and
Total Suspended Solids (TSS)]. The monitored data shall be uploaded on the
website of the company as well
..7/-
-7-
as displayed on a display board at the
project site at a suitable location near the main gate of the Company in public
domain. The circular No. J-20012/1/2006-IA.II(M) dated 27.05.2009 issued by
Ministry of Environment and Forests, which is available on the website of the
Ministry www.envfor.nic.in shall also be referred in this regard for its compliance.
(xxxvi) A Final Mine Closure Plan along with details of
Corpus Fund should be submitted to the Ministry of Environment & Forests 5
years in advance of final mine closure for approval.
B. General
conditions
(i)
No
change in mining technology and scope of working should be made without prior
approval of the Ministry of Environment & Forests.
(ii)
No
change in the calendar plan including excavation, quantum of mineral lead and
zinc ore and waste should be made.
(iii)
Conservation
measures for protection of flora and fauna in the core & buffer zone should
be drawn up in consultation with the local forest and wildlife department and
effectively implemented.
(iv)
Four
ambient air quality-monitoring stations should be established in the core zone
as well as in the buffer zone for RSPM (Particulate
matter with size less than 10micron i.e., PM10) and NOx
monitoring. Location of the stations
should be decided based on the meteorological data, topographical features and
environmentally and ecologically sensitive targets and frequency of monitoring
should be undertaken in consultation with the State Pollution Control Board.
(v)
Data
on ambient air quality RSPM (Particulate matter with
size less than 10micron i.e., PM10) & NOx should be regularly submitted to the
Ministry of Environment and Forests including its Regional office located at
Lucknow and the State Pollution Control Board / Central Pollution Control Board
once in six months.
(vi)
Fugitive
dust emissions from all the sources should be controlled regularly. Water
spraying arrangement on haul roads, loading and unloading and at transfer
points should be provided and properly maintained.
(vii)
Measures
should be taken for control of noise levels below 85 dBA in the work
environment. Workers engaged in operations of HEMM, etc. should be provided
with ear plugs / muffs.
(viii)
Industrial
waste water (workshop and waste water from the mine) should be properly
collected, treated so as to conform to the standards
..8/-
-8-
prescribed under GSR 422 (E) dated
19th May, 1993 and 31st December, 1993 or as amended from
time to time. Oil and grease trap should be installed before discharge of
workshop effluents.
(ix)
Personnel
working in dusty areas should wear protective respiratory devices and they
should also be provided with adequate training and information on safety and
health aspects.
Occupational health surveillance
program of the workers should be undertaken periodically to observe any
contractions due to exposure to dust and take corrective measures, if needed.
(x)
A
separate environmental management cell with suitable qualified personnel should
be set-up under the control of a Senior Executive, who will report directly to
the Head of the Organization.
(xi)
The
funds earmarked for environmental protection measures should be kept in
separate account and should not be diverted for other purpose. Year wise
expenditure should be reported to the Ministry of Environment and Forests and
its Regional Office located at Lucknow.
(xii)
The
project authorities should inform to the Regional Office located at Lucknow
regarding date of financial closures and final approval of the project by the
concerned authorities and the date of start of land development work.
(xiii)
The
Regional Office of this Ministry located at Lucknow shall monitor compliance of
the stipulated conditions. The project authorities should extend full
cooperation to the officer (s) of the Regional Office by furnishing the
requisite data / information / monitoring reports.
(xiv)
The
project proponent shall submit six monthly reports on the status of compliance
of the stipulated environmental clearance conditions including results of
monitored data (both in hard copies as well as by e-mail) to the Ministry of
Environment and Forests, its Regional Office Lucknow, the respective Zonal
Office of Central Pollution Control Board the State Pollution Control Board.
The proponent shall upload the status of compliance of the environmental
clearance conditions, including results of monitored data on their website and
shall update the same periodically. It shall simultaneously be sent to the
Regional Office of the Ministry of Environment and Forests, Lucknow, the
respective Zonal Office of Central Pollution Control Board and the State
Pollution Control Board.
(xv)
A copy of the clearance letter shall be
sent by the proponent to concerned Panchayat, Zila Parisad/ Municipal
Corporation, Urban Local Body and the
Local NGO, if
any, from whom
suggestions/ representations, if any, were received while processing the
proposal. The
..9/-
-9-
clearance letter shall also be put on the website of the Company by the
proponent.
(xvi)
The
State Pollution Control Board should display a copy of the clearance letter at
the Regional office, District Industry Centre and the Collector?s office/
Tehsildar?s Office for 30 days.
(xvii)
The environmental statement for each financial year ending 31st
March in Form-V as is mandated to be submitted by the project proponent to the
concerned State Pollution Control Board as prescribed under the Environment
(Protection) Rules, 1986, as amended subsequently, shall also be put on the
website of the company along with the status of compliance of environmental clearance conditions and shall also be sent to the Regional Office
of the Ministry of Environment and Forests, Lucknow by e-mail.
(xviii)
The
project authorities should advertise at least in two local newspapers of the
District or State in which the project is located and widely circulated, one of
which shall be in the vernacular language of the locality concerned, within 7
days of the issue of the clearance letter informing that the project has been
accorded environmental clearance and a
copy of the
clearance letter is available
with the State Pollution Control Board and also at web site of the Ministry of
Environment and Forests at http://envfor.nic.in and a copy of the same should be
forwarded to the Regional Office of this Ministry located at Lucknow.
7. The Ministry or any other competent
authority may alter/modify the above conditions or stipulate any further
condition in the interest of environment protection.
8. Failure to comply with any of the
conditions mentioned above may result in withdrawal of this clearance and
attract action under the provisions of the Environment (Protection) Act, 1986.
9. The above conditions will be enforced
inter-alia, under the provisions of the Water (Prevention & Control of
Pollution) Act, 1974, the Air (Prevention & Control of Pollution) Act,
1981, the Environment (Protection) Act, 1986 and the Public Liability Insurance
Act, 1991 along with their amendments and rules made thereunder and also any
other orders passed by the Hon?ble Supreme Court of India/High Court of Rajasthan
and any other Court of Law relating to the subject matter.
(SATISH.C.GARKOTI)
Scientist `F`
Copy to:
(i)
The Secretary, Ministry of
Mines, Government of India, Shastri Bhawan, New Delhi.
..10/-
-10-
(ii)
The Department of Mines
& Geology, Government of Rajasthan, Secretariat, Jaipur.
(iii)
The Secretary, Department of
Environment, Government of Rajasthan, Secretariat, Jaipur.
(iv)
The Chief Conservator of
Forests, Central Region,
Ministry of Environment and Forests,
B-1/72, Sector-A, Aliganj,
Lucknow-226020.
(v)
The Chief Wildlife Warden,
Government of Rajasthan, Van Bhawan, Vanki Path, Jaipur-302 005, Rajasthan.
(vi)
The Chairman, Central
Pollution Control Board, Parivesh Bhavan, CBD-cum-Office complex, East Arjun Nagar, New
Delhi-1100032.
(vii)
The Member Secretary,
Central Ground Water Authority, A-2, W3, Curzon Road Barracks, K.G. Marg, New
Delhi-110001.
(viii)
The Chairman, Rajasthan
State Pollution Control Board, 4, Institutional area, Jhalana, Doongri, Jaipur.
(ix)
The Controller General,
Indian Bureau of Mines, Indira Bhavan, Civil Lines, Nagpur-440 001.
(x)
The District Collector,
Rajsamand District, Rajasthan.
(xi)
EI Division, Ministry of
Environment and Forests, Paryavaran Bhavan, C. G. O. Complex, Lodi Road, New Delhi-110 003.
(xii)
Monitoring File.
(xiii)
Guard File.
(xiv)
Record File.
(SATISH.C.GARKOTI)
Scientist `F`