No. J-11015/202/2010-IA.II(M)

Government of India

Ministry of Environment & Forests

Paryavaran Bhawan,

CGO Complex,

New Delhi-110510.

To

Dated: 23rd March 2011

The Chairman & Managing Director,

M/s Gujarat Power Corporation Ltd.,

Block No.8, 6th Floor, Udhyog Bhavan,

Sector-11, GANDHINAGAR – 382011.

 

Sub:     Ghogha-Surka Lignite Mine (2.25 MTPA in 1355 ha) and Khadsaliya-I (1 MTPA in 711.42.47 ha) and Khadsaliya-II Lignite Mine (0.75 MTPA in 914.14.92 ha) of M/s Gujarat Power Corp. Ltd., located in Taluka and district Bhavnagar, Gujarat - Terms of Reference  (TOR) – reg.

 

Sir,

 

            This is with reference to letter no. GPCL/Mining/MoEF/31880 dated 21.04.2010 along with the application which was considered in the EAC (T&C) meeting held on 9.07.2010 and subsequent letters dated 29.06.2010, dated 10.12.2010 and 31.01.2011 submitting the revised applications for TOR for the 3 projects individually. The proposals were considered in the EAC (T&C) meeting held on 21st -22nd February 2011.

 

The Committee was informed that 3 mining leases adjoining one another have been allotted to the company to partially meet the coal of the linked pit-head TPP for which an EC has already been obtained. It was informed that the project is at a distance of 1.5 km to 2 km from the coast (Arabian Sea/Gulf of Kambat). It was informed that baseline data was generated a few years ago for the TPP. It was informed that the sea coastline is about 4km in the eastern direction of the proposed Ghogha-Surka project and about 1.5km from Khadsaliya-I and 1.5 km from Khadsaliya-II project. No forestland is involved.  It was informed that the Forest & Environment Department, Government of Gujarat had sent letter to addressed to Dr. Bharat Bhushan, Director, IA Div. MOEF vide letter no ENV-10-2010-1069-E dated 5th August 2010 along with map providing details of the location of the project vis-à-vis CRZ. The letter states that as per demarcation of the CRZ boundary and HTL and superimposition of the proposed mining areas on the said map, these mining areas are outside the CRZ area. 

 

The Committee observed that the ML area is about 3.5 km from the HTL. The Committee noted that a river is running along the Khadsaliya Blocks. The Committee observed that Khadsaliya block areas could have a high sulphur and pyrite content which may require to be addressed at the EIA stage and if present, a treatment plant would require to be established. The Committee desired that the option of coal evacuation by rail/conveyor mode instead of by road should be examined. The Committee recommended that these issues should also be incorporated while granting TOR.

 

The Committee after discussions prescribed the following TOR subject to the aforesaid clarifications/submission of documents:

(i)         The Committee desired that a map from a recognised institution should be furnished whether the project falls in CRZ (highest tide level) area and in case it does, clearance from the CRZ from the Gujarat CZMA would be an essential pre-requisite for consideration of the proposal for EC.

(ii)        An integrated EIA-EMP Report should be prepared for a combined peak capacity of the three lignite projects addressing the combined environmental impacts of the projects including the aspects of mineral transportation and issues of impacts on hydrogeology, plan for conservation of flora/fauna and afforestation/ plantation programme. Baseline data collection can be for any season except monsoon. The Committee desired that in view of the fact that the Notification for NAAQM standards have been revised, a fresh baseline one-season data for the environmental quality may be generated as per the latest Notifications.

(iii)       The EIA-EMP report should also cover the environmental impacts and management plan for the individual project specific activities and those activities which have an inter-connection (transportation of mineral, power, water, colony, lignite stockyard, lignite handling plant, transportation and usage of approach roads from mine ) and also the combined impacts of the two projects on the environment of the region, and the environmental quality – air, water, land, biotic community, etc. through collection of baseline data and information generation on impacts through prediction modelling.

(iv)       A map specifying locations of the State, District and Project location.

(v)        A Study area map of the core zone and 10km area of the buffer clearly delineating the major topographical features such as the land use, ecologically sensitive areas such as Biosphere Reserves/National Parks/WL Sanctuaries/ Elephant Reserves, forests (Reserved/Protected), migratory corridors of fauna, and areas where endangered fauna and plants of medicinal and economic importance are found in the area, surface drainage of rivers/streams/nalas/canals, locations of human habitations, major constructions including railways, roads, pipelines, major industries/mines and other polluting sources.

(vi)       Land use map (1: 50,000 or 100,000) based on a recent satellite imagery of the study area may also be provided with explanatory note of the land use.

(vii)      Map showing the core zone delineating the agricultural land (irrigated and irrigated, uncultivable land (as defined in the revenue records), forest areas (as per records).

(viii)      Details of Original land use (agricultural land/forestland/grazing land/wasteland/water bodies) of the area Impacts of project, if any on the landuse, in particular, area (in ha) agricultural land/forestland/grazing land/water bodies falling within the lease/project and acquired for mining operations.

(ix)       Contour map at 3 m intervals and Site plan of the mine showing the various proposed break-up of the land for mining operations such as the quarry area, OB dumps, green belt, safety zone, buildings, infrastructure, CHP, ETP, Stockyard, township/colony (within and adjacent to the ML), undisturbed area and if any, in topography such as existing roads, drains/natural water bodies are to be left undisturbed along with any natural drainage adjoining the lease/project and modification of thereof in terms of construction of embankments/bunds, proposed diversion/rechannelling of the water courses, etc., approach roads, major haul roads, etc.

(x)        Break up of lease/project area as per different land uses and their stage of acquisition.

(xi)       Break-up of lease/project area as per mining operations.

(xii)       Impact of changes in the land use due to the start of the combined projects since much of the land being acquired is agricultural land.

(xiii)      Collection of one-season (non-monsoon) primary base-line data on environmental quality - air (PM10, PM2.5, SOx and NOx), noise, water (surface and groundwater), soil.

(xiv)      Map of the study area (core and buffer zone clearly delineating the location of various stations superimposed with location of habitats, other industries/mines, pouting sources. The number and location of the stations should be selected on the basis of the proposed impacts in the downwind (air)/downstream (surface water)/groundwater regime (based on flow). One station should be in the upwind/upstream/non-impact/non-polluting area as a control station. The monitoring should be as per CPCB guidelines and parameters for water testing for groundwater as per ISI standards and surface water as per CPCB guidelines.

(xv)      Study on the existing flora and fauna in the study area carried out by an institution of relevant discipline and the list of flora and fauna duly authenticated separately for the core and buffer zone and a statement clearly specifying whether the study area forms a part of the migratory corridor of any endangered fauna.

(xvi)      Details of mineral reserves, geological status of the study are and the seams to be worked, ultimate working depth and progressive stage-wise working scheme until end of mine life should be reflected on the basis of the approved rated capacity and calendar plans of production from the approved Mining Plan. Geological maps should be included.

(xvii)     Details of mining methods, technology, equipment to be used, etc.  rationale for selection of that technology and equipment proposed to be used vis-à-vis  the potential impacts. The Committee observed that Khadsaliya block areas could have a high sulphur and pyrite content which may require to be addressed at the EIA stage and if present, a treatment plant would require to be established.

(xviii)    The Committee noted that a river is running along the Khadsaliya Blocks. Impact of mining on hydrology, modification of natural drainage, diversion and channelling of the existing rivers/water courses flowing though the ML and adjoining the lease/project and the impact on the existing users and impacts of mining operations thereon.

(xix)      Detailed water balance should be provided. The break up of water requirement for each the mine operations should be given separately.

(xx)       Source of water for use in mine, sanction of the competent authority in the State Govt. and impacts vis-à-vis the competing users.

(xxi)      Impact of mining and water abstraction use in mine on the hydrogeology and groundwater regime of within the core zone and 10km buffer zone including long–term modelling studies on. The Committee noted that since the ultimate working depth is 110m bgl, impacts of sea water ingress and cutting into groundwater aquifer shall be studied. Details of rainwater harvesting and measures for recharge of groundwater should be reflected.

(xxii)     Impact of blasting, noise and vibrations.

(xxiii)    Impacts of mining on the AAQ, predictive modelling including ISCT-3 (Revised) or latest model available.

(xxiv)    The Committee desired that the option of coal evacuation by rail/conveyor mode instead of by road should be examined. Impacts of mineral transportation – within and outside the lease/project along with flow-chart. Impacts of transportation, handling, transfer of mineral and waste on air quality, generation of effluents from workshop, management plan for maintenance of HEMM, machinery, equipment. Details of various facilities to be provided in terms of parking, rest areas, canteen, and effluents/pollution load from these activities.

(xxv)     Details of waste generation – OB, topsoil – as per the approved calendar programme, and their management shown in figures as well explanatory chapter with tables giving progressive development and mine closure plan, green belt development, backfilling programme and conceptual post mining land use. OB dump heights and terracing should based on slope stability studies with a max of 28o angle as the ultimate slope. Sections of dumps (ultimate) (both longitudinal and cross section) with relation to the adjacent area should be shown.

(xxvi)    Flow chart of water balance. Treatment of effluents from workshop, township, domestic wastewater, mine water discharge, treatment details, etc. Details of STP in colony and ETP in mine. Recycling of water to the max. possible extent.

(xxvii)   Occupational health issues. Baseline data on the health of the population and measures for occupational health and safety of the personnel and manpower for the mine.

(xxviii)   Impact and management of wastes and issues of rehandling and backfilling and progressive mine closure and reclamation.

(xxix)    Disaster Management Plan.

(xxx)     Integrating in the Env. Management Plan with measures for minimising use of natural resources - water, land, energy, etc.

(xxxi) Progressive Green belt and afforestation plan (both in text, figures as well as in tables) and reasons for selection of species for the afforestation/plantation programme.

(xxxii)    Conservation Plan for the endangered/endemic flora and fauna found in the study area and for safety of animals visiting/residing in the study area and also those using the study area as a migratory corridor.

(xxxiii) Mine closure issues, post mining land use and restoration of land to pre- mining (agricultural use).

(xxxiv) Including cost of EMP (capital and recurring) in the project cost and for progressive

            and final mine closure plan.

(xxxv) Details of R&R.  Detailed R&R Plan with data on the existing socio-economic status of the population in the study area and broad plan for resettlement of the displaced population, site for the resettlement colony, alternate livelihood concerns/employment for the displaced people, civic and housing amenities being offered, etc and the schedule of the implementation of the R&R Plan.

(xxxvi)   Public Hearing should cover the details of notices issued in the newspaper, proceedings/minutes of public hearing, the points raised by the general public and commitments made in a tabular form. If the Public Hearing is in the regional language, an authenticated English Translation of the same should be provided.

(xxxvii)In built mechanism of self monitoring of compliance of environmental regulations.

(xxxviii)  Status of any litigations/ court cases filed/pending on the project.

(xxxix)   Authenticated English translation of all material provided in Regional languages.

(xxxx)    Copy of clearances/approvals – such as Forestry clearances, Mining Plan Approval, NOC form Flood and Irrigation Dept. (if req.), etc.

 

The following general points should be noted:

(i)         All documents should be properly indexed, page numbered.

(ii)        Period/date of data collection should be clearly indicated.

(iii)       Authenticated English translation of all material in Regional languages provided/enclosed with the application.

(iv)       After the preparation of the draft EIA-EMP Report as per the aforesaid TOR, the proponent shall get the Public Hearing conducted as prescribed in the EIA Notification 2006 and take necessary action for obtaining environmental clearance under the provisions of the EIA Notification 2006.

(v)                The letter/application for EC should quote the MOEF file No. and also attach a copy of the letter prescribing the TOR.

(vi)              The copy of the letter received from the Ministry on the TOR prescribed for the

project should be attached as an annexure to the final EIA-EMP Report.

(vii)      The final EIA-EMP report submitted to the Ministry must incorporate the issues in TOR and that raised in Public Hearing. The index of the final EIA-EMP report, must indicate the specific chapter and page no. of the EIA-EMP Report where the specific TOR prescribed by Ministry and the issue raised in the P.H. have been incorporated.

(viii)      The details of the EIA-EMP Report should be summarised in the Mining Sector Questionnaire posted on the MOEFG website with all sections duly filled in and furnished along with the EIA-EMP (Final) Report.

 

The following additional points are also to be noted:

(i)                  Grant of TOR does not necessarily mean grant of EC.

(ii)                Grant of TOR/EC to the present project does not necessarily mean grant of TOR/EC to the captive/linked project.

(iii)               Grant of TOR/EC to the present project does not necessarily mean grant of approvals in other regulations such as the Forest (Conservation) Act 1980 or the Wildlife (Protection) Act, 1972.

(iv)       The EIA-EMP Report should be got prepared only from a Consultant who is registered with QCI.

 

Yours faithfully,

 

 

 

(Dr.T.Chandini)

Director

Copy to: Chairman, Gujarat State Pollution Control Board, Paryavaran Bhavan, Sector 10-A,

Gandhinagar – 382010.