`MINUTES FOR 86th MEETING OF THE RECONSTITUTED EXPERT APPRAISAL COMMITTEE (INDUSTRY) TO BE HELD DURING 20th to 22nd OCTOBER, 2008

 

VENUE :           Scope Complex, Core 6, 5th Floor, CHT Conference

                          Room, Ministry of Petroleum and Natural Gas, Lodi

                          Road, New Delhi - 110 003

 

1.0           Opening Remarks of the Chairman

 

2.0            Confirmation of the Minutes of 85th Meeting of the Expert Appraisal          Committee (Industry) held during 23rd -25th September, 2008.

 

The Minutes of the 85th minutes held during 23rd -25th September 2008 were confirmed

 

3.0                      Consideration of the Projects

 

20th October, 2008

 

4.0      New Proposals :

4.1       Integrated Steel Plant at Nimidha, Dhenkanal, Orissa by M/s MGM Steels Ltd. (EC)

 

The project authorities and their consultant gave a detailed presentation on the salient features of the project and proposed environmental protection measures to be undertaken as per Draft Terms of References (TORs) awarded during the 69th Meeting of the Expert Appraisal Committee (Industry) held during 4th–6th July, 2007 for preparation of EIA/EMP.  All the steel plants are listed at S.N. 3(a)(a) under Primary Metallurgical process and appraised at Central level.

 

 

            PAs informed to the Committee that M/s MGM Steels Ltd. have proposed to set up an Integrated Steel Plant at Motanga, Dhenkanal, Orissa. Mahanadi Elephant reserve is at about 13 to 15 kms from the project area.  Total project area is 74.39 ha. and is allotted by IDCO.  No national park, wild life sanctuary and reserve forests are located within 10 km radius of the project. Total cost of the project is Rs. 424.135 Crores instead of Rs. 422.00 Crores earlier proposed. Rs 25.50 Crores and Rs. 17.50 Crores are earmarked towards capital cost and recurring cost/annum for environment pollution control measures respectively. Following are the details of products :

 

 

 

 

 

 

Production

Capacity

Sponge Iron    

2,10,000 MTPA

Hot Metal        

1,31,000 MTPA

Crude Steel

2,50,000 MTPA

Coal Washery

5,00,000 MTPA

Power 

                        WHRB

                        AFBC

32 MW

16 MW

16 MW

Saleable

Billet   

2,42,553 MTPA

Pig Iron

62,000 MTPA

 

 

 

 

 

 

 

 

 

 

 

 

     

 

 

 

 

 

Iron ore (DRI & BF grade), Lime stone, Coal, Dolomite, BF Coke, Manganese, Quartzite, Burnt Lime, Burnt Dolo and Ferro Alloy will be used as raw material. PAs informed to the Committee about the process details of the steel plant and pollution control methods adopted. PAs informed to the Committee that no coke oven plant will be installed. Imported coke will be used.  Coal washery (5,00,000 TPA) will also be installed.

 

       Air quality monitoring was carried out at 8 locations and the parameters are found to vary in the following range: SPM (90.1-170.2 mg/m3), RPM (18.3-39.8 mg/m3), SO2 (6.8–19.8 mg/m3) & NOx (6-17 mg/m3).  ESP, fan, stack etc. will be provided to DR kiln, Sinter plant and Blast furnace. Dust suppression system like dense fog system and water sprinkling system will be provided at raw material handling areas. Ash conditioners will be installed to control fugitive ash dust pollution at loading and transport points. Dust collectors at crushers, transfer points of conveyors, raw material and coal yard. Dust extraction system comprising of suction hood, duct, bag filters, fan, stack etc. will be provided to Induction Furnace, DRI screening section and coal crushing & screening section.

     

      Total make up water requirement from Brahmani River will be 406 m3/h instead of 401 m3/h proposed earlier and permission is obtained vide letter dated 19th June, 2009. The water consumption will be 25 m3/Ton of steel but committee emphasized to control water consumption within 16 m3/T of steel as per standard.  Clarifier and sludge pond will be installed to remove suspended solids, which will be used for land filling. Acid water will be neutralized by lime. Treated effluent will be used for horticulture. No wastewater will be discharged and ‘Zero’ discharge will be adopted. 

 

      Slag, dust and char will be generated as solid waste. Dust collected from bag filters and ESP will be sent to nearby material handling area.  Char from DR kiln was proposed to sold to outside customers but committee asked to use in AFBC boiler for generating power.  BF slag will be used in slag cement production. SMS slag will be used in road making.  BF dust, Sinter plant dust, Bag house dust of SMS will be recyled to Sinter plant.  Fly ash and bottom ash generated will be used for brick and road making and cement production. Coal middling will be used in-house. Coal rejects, accretion & lumpy waste will be used for land filling. Other waste material which can not be used will be dumped in separate area.

 

       Green belt is proposed in 25 ha of area but Committee asked to develop in 33 % area.  Acoustic enclosures and silencers will be provided. 42 MW power will be required.  32 MW and 10 MW power will be sourced from CPP and grid respectively.

The Committee deliberated upon the issues raised during the Public Hearing / Public Consultation meeting conducted by the Orissa State Pollution Control Board on 29th May, 2008. The issues raised included upgradation of hospital, provision of adequate air pollution control measures, local area development, employment, repair of village roads and canal bridge have satisfactorily been incorporated in the final EIA/EMP report.

            After detailed deliberations, the Committee found the final EIA/EMP report adequate and suggested to stipulate following specific conditions alongwith other environmental conditions while considering for accord of environmental clearance after submission of feasibility report for railway siding at mine site to the steel plant alongwith consent from the Railway Department and rechecking of ground level concentration (GLC) data :

 

  1. Efforts should be made to reduce RSPM levels in the ambient air and a time bound action plan should be submitted. On-line ambient air quality monitoring and continuous stack monitoring facilities for all the stacks and sufficient air pollution control devices should be provided to keep the emission levels below 100 mg/Nm3.
  2. Hot gases from DRI kiln should be passed through Dust Settling Chamber (DSC) to remove coarse solids and After Burning Chamber (ABC) to burn CO completely and used in waste heat recovery boiler (WHRB).  The gas then should be cleaned in ESP before leaving out into the atmosphere through ID fan and stack.  Electrostatic precipitator (ESP) should be provided to DRI plant, WHRB and ABC boilers to control air emissions.  Bag filter/scrubber should be provided induction furnace.  Gas cleaning plant having dust catcher and bag filter should be provided to blast furnace (BF).
  3. Gaseous emission levels including secondary fugitive emissions from all the sources including blast furnace should be controlled within the latest permissible limits issued by the Ministry and regularly monitored. Guidelines / Code of Practice issued by the CPCB should be followed. The emission standards issued by the Ministry in May, 2008 for the sponge plants should be followed.
  4. Vehicular pollution due to transportation of raw material and finished product should be controlled.  Proper arrangements should also be made to control dust emissions during loading and unloading of the raw material and finished product.
  5. Prior permission for the drawl of 406 m3/day water from Brahmani River from the concerned department should be obtained. No wastewater should be discharged outside the premises and ‘Zero’ effluent discharge should be ensured.
  6. The water consumption should not exceed 16 m3/Ton of Steel as per prescribed standard.
  7. Ground water monitoring around the solid waste disposal site / secured landfill (SLF) should be carried out regularly and report submitted to the Ministry’s Regional Office at Bhuvaneswar, CPCB and JSPCB.
  8. AFBC Plant should be installed before installation of Sponge Iron Plant so that utilization of char in the AFBC boiler is ensured.  All the char from DRI plant, coal washery rejects and middling should be utilized in AFBC boiler of power plant and no char should be disposed off anywhere else. All the blast furnace (BF) slag should be granulated and provided to cement manufacturers for further utilization. SMS slag should be properly utilized. Oily waste should be provided to authorized recyclers/ reprocessors. 
  9. A time bound action plan should be submitted to reduce solid waste, its proper utilization and disposal.
  10. Proper handling, storage, utilization and disposal of all the solid waste shall be ensured and regular report regarding toxic metal content in the waste material and its composition, end use of solid/hazardous waste should be submitted to the Ministry’s Regional Office at Bhuvaneswar, OPCB and CPCB.
  11. Proper utilization of fly ash should be ensured as per Fly Ash Notification, 1999 as amendment in 2003.
  12. As proposed, green belt should be developed in 33 % area.
  13. All the recommendations made in the Charter on Corporate Responsibility for Environment Protection (CREP) for the Steel Sector should be implemented.

4.2       Foundry Unit (M.S. Casting, 2,800 MTPA) at Plot No. 185/A, Industrial Development Corporation, Kalunga, District Sundergarh, Orissa by M/s Agravanshi Minerals Pvt. Ltd.  (EC)

Project authorities didn’t attend the meeting and it was decided that proposal should be considered afresh whenever requested by the PAs.

 

4.3       Expansion of Integrated Steel Plant at Siltara Growth Centre, Siltara, Raipur, Chhattisgarh by M/s Corporate Ispat Alloys Ltd. (EC)

The project authorities and their consultant gave a detailed presentation on the salient features of the project and proposed environmental protection measures to be undertaken as per Draft Terms of References (TORs) awarded during the 76th Meeting of the Expert Appraisal Committee (Industry) held during 28th–30th November, 2007 for preparation of EIA/EMP.  All the Integrated Steel Plants are listed at S.N. 3(a) under Primary Metallurgy Industries and appraised at the Central level. 

 

             PAs informed to the Committee that M/s Corporate Ispat Alloys Ltd. have proposed for the expansion of Integrated Steel Plant at Siltara Growth Centre, Siltara, Raipur, Chhattisgarh. Total project area is 176 acres and expansion will be carried out on additional 150 acres land situated adjacent to the existing plant boundary.  No National Park & wild life sanctuary is located within 10 km. radius of the project site.  Total cost of the project is Rs. 2,060.00 Crores. Rs. 125 Crores and Rs. 25.00 Crores will be earmarked towards total capital cost and recurring cost/annum towards environmental pollution control measures respectively.  Following will be the details of plant facilities to be installed :

 

Name of Unit

Existing Units

Proposed Capacity

Blast Furnace

--

0.8 MTPA with CPP of 24 MW (WHRB)

Sinter plant

--

1.20 MTPA

Coke Oven

--

0.3 MTPA with CPP of 24 MW (WHRB)

Oxygen plant

--

200 TPD

DRI Plant

0.15 MTPA (500 x 1 TPD) with 15 MW (WHRB + AFBC) Power Plant

0.8 MTPA with CPP of 60 MW  (WHRB)

Steel Making Shop

0.40TPA

0.80 MTPA

Rolling Mill

0.30 MTPA

0.90 MTPA

Captive Power Plant

DRI 12 MW

105 MW

 

Boiler 3 MW

24 MW (using blast furnace gas)

 

 

18 MW (using coke oven waste gas)

 

 

60 MW (using DRI plant waste gas)

 

            During presentation, PAs informed that following will be the details of existing and proposed facilities:

 

Name of Unit

Existing Units

Expansion units

Total Capacity

Blast Furnace

--

0.8 MTPA

0.8 MTPA

Sinter plant

--

1.20 MTPA

1.20 MTPA

Coke Oven

--

0.3

0.3

Oxygen plant

100 TPD

200 TPD

300 TPD

DRI Plant

0.15 MTPA

0.8 MTPA

0.95 MTPA

Steel Melting Shop

0.40 TPA

0.80 MTPA

1.2 MTPA

Rolling Mill

0.30 MTPA

0.90 MTPA

0.90 MTPA

Captive Power Plant

15 MW

DRI gas-12 MW

AFBC- 3 MW

102 MW

BF gas-24 MW

CO gas-18 MW

DRI gas+AFBC-60 MW

117 MW

 

            The Committee also noted that coal based sponge iron plant and captive power plant (CPP) are not allowed in Siltara, Urla and Borjhara and, therefore, in the present proposal also no sponge iron plant (0.8 MTPA) and CPP (60 MW) will be allowed until and unless permission for the same is obtained from the State Govt. of Chhattisgarh and the proposed configuration will be as follows :

 

Name of Unit

Existing Units

Expansion units

Total Capacity

Blast Furnace

--

0.8 MTPA

0.8 MTPA

Sinter plant

--

1.20 MTPA

1.20 MTPA

Coke Oven (Non-recovery type)

--

0.3

0.3

Oxygen plant

100 TPD

200 TPD

300 TPD

DRI Plant

0.15 MTPA

-

0.15 MTPA

Steel Melting Shop

0.40 TPA

0.80 MTPA

1.2 MTPA

Rolling Mill

0.30 MTPA

0.90 MTPA

0.90 MTPA

Captive Power Plant

15 MW

DRI gas-12 MW

AFBC- 3 MW

42 MW

BF gas-24 MW

CO gas-18 MW

57 MW

 

            Iron ore, coal, dolomite, quartzite, limestone will be used as raw material.  BF to manufacture Pig Iron, Sinter Plant to manufacture sinter for the use in BF, Coke Oven (non-recovery type) to produce low ash metallurgical coke for use in BF, SMS and rolling mill to produce steel will be installed.  WHRB of 24 MW (using BF waste gas), 21 MW (using coke waste gas oven and 60 MW (using DRI Plant waste gas) will be installed.  Coke oven (non-recovery) gas will be used for heating.

            Air quality monitoring was carried out at 8 locations and the maen values for SPM (162-478 mg/m3), RSPM (76-187 mg/m3), SO2 (5.5 – 8.9 mg/m3) & NOx (24.6 – 51.8 mg/m3) are within the permissible limits.  ESPs will be provided to FBC based power plant, DRI kiln, coke oven and sinter plant to control particulate matter to 100 mg/Nm3.  ESP/Bag filters will be provided to DRI plant also. Fume extraction system with bagfilters will be provided to SMS. Dust extraction system to BF stock house; GCP and sludge disposal system will be provided to BF. Dust suppression system to raw material handling area will be provided. Adequate stack height will be provided to rolling mill and other plants.  DE & DS system alongwith dust collectors will be provided to coke oven plant.  Water quenching will also be done. 

 

            Total water requirement from Kharoon River is revised from 1,250 m3/h to 3,000 m3/day and further revised to 380.50 m3/h.  Permission for the 2 MGD water is obtained from CSIDC / WRO and permission for additional water will be obtained. Cooling tower blowdowns from blast furnace, sinter plant, SMS, rolling mill, DRI and CPP will be resued for dust scrubbing, sinter nodulizing, slag quenching, ash handling respectively. Closed circuit cooling will be used to reduce water consumption.  Rolling mill overflow will be taken to settling tank for removal of scales and then reused. Acidic water will be neutralized by lime.  ETP will be installed for the treatment of process effluent and treated water will be reused for gardening purpose or for slag granulation. Maximum water will be recycled and reused in the process.  ‘Zero’ discharge will be adopted.

                                                     

            Char will be used in AFBC boiler. BF slag and fly ash will be used for cement making. Iron ore fines, mill scales from rolling mill, scrap, BF dust/sludge, coke breeze from coke oven plant, flue dust from SMS, DRI and sinter plant will be used in sinter plant in making sinter, which will be used in BF.  Bottom ash will be used for road making. SMS slag will be given for metal recovery and also used in road making. Raw water treatment, ETP sludge, muck etc will be disposed as land fill material and soil conditioner. Solid waste and ash will be dumped in dump yard and ash pond. 

 

Green belt will be developed in 33% land area. Power will be sourced from WHRB and CPP.

The Committee noted that no public hearing/consultation is required due to project being located in notified Siltara Industrial Area as per Section (iii), Stage (3), Para (i)(b) of EIA Notification 2006.  The Committee also clarified to PAs that no coal based sponge iron plant (0.8 MTPA) and CPP (60 MW) will be installed without prior permission for the same from State Govt. of Chhattisgarh and Ministry.

            After detailed deliberations, the Committee found the final EIA/EMP report adequate and suggested to stipulate following specific conditions alongwith other environmental conditions while considering for accord of environmental clearance :

 

1.      No coal based sponge iron plant and captive power plant should be installed without prior permission from the State Govt. of Chhattisgarh (banned as per the order of the Govt. of Chhattisgarh dated 16th March, 2007) and Ministry.

2.      Efforts should be made to reduce RSPM levels in the ambient air and a time bound action plan should be submitted. On-line ambient air quality monitoring and continuous stack monitoring facilities for all the stacks and sufficient air pollution control devices should be provided to keep the emission levels below 100 mg/Nm3. 

3.      Electrostatic precipitator (ESP) should be provided to AFBC boilers, coke oven and sinter plant to control air emissions below 100 mg/Nm3. Gas cleaning plant having dust catcher and pulse jet bag filters should be provided to blast furnace (BF).  

4.      Gaseous emission levels including secondary fugitive emissions from blast furnace and sinter plant should be controlled within the latest permissible limits issued by the Ministry and regularly monitored. Guidelines / Code of Practice issued by the CPCB should be followed. The emission standards issued by the Ministry in May, 2008 for the sponge plants should be followed.

5.      Vehicular pollution due to transportation of raw material and finished product should be controlled.  Proper arrangements should also be made to control dust emissions during loading and unloading of the raw material and finished product.

6.      All the standards prescribed for the coke oven plants should be followed as per the latest guidelines. Proper and full utilization of coke oven gases in power plant using waste heat recovery steam generators should be ensured and no flue gases shall be discharged into the air.

7.      Closed circuit cooling should be adopted to reduce fresh water consumption. Acidic and alkaline effluent from DM water plant should be neutralized and reused for various activities in the plant.  Phenolic effluent should be treated in BOD plant and used for quenching of hot coke.  No wastewater should be discharged outside the premises and ‘Zero’ effluent discharge should be ensured.

8.      Prior permission for the drawl of 380.50 m3/h water from Kharoon River should be obtained from the concerned department.

9.      The water consumption should not exceed 16 m3/Ton of Steel as per prescribed standard.

10.  Continuous monitoring of Total Organic Compounds (TOC) shall be done at the outlet of ETP (BOD plant).

11.  Ground water monitoring around the solid waste disposal site / secured landfill (SLF) should be carried out regularly and report submitted to the Ministry’s Regional Office at Bhopal, CPCB and CECB.

12.  Char should be used in AFBC boiler. All the blast furnace (BF) slag should be granulated and provided to cement manufacturers for further utilization.  Fly ash should be used for cement making. Iron ore fines, mill scales from rolling mill, scrap, BF dust/sludge, coke breeze from coke oven plant, flue dust from SMS, DRI and sinter plant should be used in sinter plant in making sinter. Bottom ash should be used for road making. SMS slag should be given for metal recovery and properly used. All the other solid wastes including broken refractory mass should be properly disposed off in environment-friendly manner. Oily waste should be provided to authorized recyclers/reprocessors.

13.  A time bound action plan should be submitted to reduce solid waste, its proper utilization and disposal.

14.  Proper handling, storage, utilization and disposal of all the solid waste shall be ensured and regular report regarding toxic metal content in the waste material and its composition, end use of solid/hazardous waste should be submitted to the Ministry’s Regional Office at Bhopal, CECB and CPCB.

15.  Proper utilization of fly ash should be ensured as per Fly Ash Notification, 1999 as amendment in 2003.

16.  As proposed, green belt should be developed in 33 % area.

17.  All the recommendations made in the Charter on Corporate Responsibility for Environment Protection (CREP) for the Steel Sector should be implemented.

 

            4.4       Expansion of Sponge Iron Plant (30,000 to 60,000 TPA) alongwith Captive Power Plant (WHRB, 2x10 MW; AFBC, 1x35 MW) at Sy. No. 138-A/1, Belagal, Bellary, Karnataka by M/s Benaka Sponge Iron Pvt. Ltd. (EC)

 

The project authorities and their consultant gave a detailed presentation on the salient features of the project and proposed environmental protection measures to be undertaken as per Draft Terms of References (TORs) awarded during the 68th Meeting of the Expert Appraisal Committee (Industry) held during 19th–21st June, 2007 for preparation of EIA/EMP. All the sponge iron plants are listed at S.N. 3(a)(b) under Category ‘A’ if the capacity is 200 TPD and above. Total capacity of the proposed plant is 200 TPD and is appraised at the Central level.

 

            PAs informed to the Committee that M/s Benaka Sponge Iron Pvt. Ltd. have proposed for the expansion of Sponge Iron Plant (30,000 to 60,000 TPA) alongwith Captive Power Plant (WHRB, 2x10 MW; AFBC, 1x35 MW) at Sy. No. 138-A/1, Belagal, Bellary, Karnataka. Total project area is revised from 11 acres to 21.41 acres.  Total cost of the project is revised from Rs. 9.36 Crores to Rs. 58.86 Crores.  Rs. 5.00 Crores are earmarked for environment pollution control measures.

            Iron ore (52,500 TPA), coal (27,000 TPA) and limestone (900 TPA) will be the basic raw materials required for the production of sponge iron. The iron ore will be crushed to the required size and fed to the kiln heated at predetermined temperature and then passed to the rotary cooler for cooling.  After that magnetic sponge iron and non-magnetic char will be separated in the product separation system.

             Air emissions will be treated in Gas Cleaning Plant (GCP) etc. Air-cooled condenser system will be adopted to reduce fresh water consumption. Total ground water requirement is revised to 425 m3/day against the earlier proposed 175.6 m3/day. Regarding ‘Permission’ for the drawl of 175.6 m3/day ground water, a letter from CGWA is submitted indicating location of the project in non-critical areas.  Blow down water will be used for green belt development and dust suppression. Domestic effluent will be treated in STP and treated water will be used for green belt development. Solid waste will be generated in the form of sludge from wet scrubber, bag filter etc.  Char will be used in AFBC boiler and dried sludge will be used in CPP as fuel.  Dust from bag filter, ESP and fly ash will be provided to cement & brick manufacturing plants. Green belt will be developed in 33 % area. 500 KVA power will be required. 

The Committee deliberated upon the issues raised during the Public Hearing / Public Consultation meeting conducted by the Karnataka Pollution Control Board on 19th June, 2008. The issues like non-use of pollution control measures, water, electricity to villagers, diseases in the nearby villagers, decrease in yield in agriculture etc. were discussed and have satisfactorily been incorporated in the final EIA/EMP report.

           

            After detailed deliberations, the Committee found the final EIA/EMP report adequate and suggested to stipulate following specific conditions alongwith other environmental conditions while considering for accord of environmental clearance :

 

  1. Efforts should be made to reduce RSPM levels in the ambient air and a time bound action plan should be submitted. On-line ambient air quality monitoring and continuous stack monitoring facilities for all the stacks and sufficient air pollution control devices should be provided to keep the emission levels below 100 mg/Nm3.
  2. Hot gases from DRI kiln should be passed through Dust Settling Chamber (DSC) to remove coarse solids and After Burning Chamber (ABC) to burn CO completely and used in waste heat recovery boiler (WHRB).  The gas then should be cleaned in ESP before leaving out into the atmosphere through ID fan and stack.
  3. Secondary fugitive emissions from blast furnace and sinter plant should be controlled within the latest permissible limits issued by the Ministry and regularly monitored. Guidelines / Code of Practice issued by the CPCB should be followed. The emission standards issued by the Ministry in May, 2008 for the sponge iron plants should be followed.
  4. Vehicular pollution due to transportation of raw material and finished product should be controlled.  Proper arrangements should also be made to control dust emissions during loading and unloading of the raw material and finished product.
  5. Prior permission for the drawl of from 425 m3/day from the State Ground Water Board /Central Ground Water Authority (SGWB/CGWA) should be obtained.
  6. New DRI kiln should be provided with waste heat recovery boiler (WHRB) to make use of flue gases generated during the process. All the char from existing and proposed DRI plant should be utilized in AFBC boiler of power plant and no char should be disposed off anywhere else. AFBC boiler should be installed simultaneously alongwith the DRI plant to ensure full utilization of char from the begning. All the other solid / hazardous waste generated shall be properly utilized or disposed off in environment friendly manner.
  7. Proper utilization of fly ash should be ensured as per Fly Ash Notification, 1999 and subsequent amendment in 2003. All the fly ash should be provided to cement and brick manufacturers for further utilization and bottom ash should be used for land filling. 
  8. Green belt should be developed in 33 % area.
  9. All the recommendations made in the Charter on Corporate Responsibility for Environment Protection (CREP) for the Steel Sector should be implemented.

 

 

4.5       Expansion of Sponge Iron Unit  (32,500 to 90,000 TPA) alongwith Captive Power Plant (5 MW; WHRB 2 MW and AFBC 3 MW) at Sy. No. 280, 281, Halakundi Village, Bellary Taluka and District Karnataka by M/s Sigma Solid Strips Pvt. Ltd. (EC)

 

The project authorities and their consultant gave a detailed presentation on the salient features of the project and proposed environmental protection measures to be undertaken as per Draft Terms of References (TORs) awarded during the 73rd Meeting of the Expert Appraisal Committee (Industry) held during 24th–26th October, 2007 for preparation of EIA/EMP.  All the Sponge Iron Plant > 200 TPD capacity have been kept at S.N. 3(a) under Category ‘A’ under Primary Metallurgy Industries and appraised at Central level. 

 

             PAs informed to the Committee that existing capacity of Sponge Iron plant is 125 TPD and additional 175 TPD sponge Iron alongwith Captive Power Plant (5 MW; WHRB 2 MW and AFBC 3 MW) will be installed.  Bellary RF is located at 1.1 kms in West direction of the project site.

M/s Sigma Solid Strips Pvt. Ltd. have proposed for the expansion of Sponge Iron Plant Sponge Iron Unit  (32,500 to 90,000 TPA) alongwith Captive Power Plant (8 MW) at Sy. No.  280, 281, Halakundi Village, Bellary Taluka and District, Karnataka.  Total area acquired is 20 acre. Total cost of the project is revised from Rs. 16.57 Crores to Rs. 37.57 Crores. Rs. 1.82 Crores and Rs. 10.00 Lakhs are earmarked towards capital cost and recurring expenditure / annum for environment pollution control measures respectively.

 

            Iron ore (89,400 TPA), Coal (47,400TPA) and limestone (1,312 TPA) will be used as raw materials. Direct Reduction of Iron ore or pellets will be carried out to manufacture sponge iron which contains 90% metallic iron and balance unreduced iron oxide and gangue in the ore.  The process of sponge iron making will aim to remove oxygen from the iron ore to make the ore porous/ spongy.

                                                                                                                                                                        Ambient air quality is monitored at 10 locations and all the values are within the permissible limits. Flue gases from ESP will be treated in Gas cleaning plant and ventury scrubber and passed through stack. Total ground water requirement will be 280 m3/day and permission from Central Ground Water Board is obtained.  All the water will be used for cooling purpose and no wastewater will be generated. Domestic wastewater will be treated in Sewerage Treatment Plant and used for green belt development. Solid waste (10 TPD) in the form of sludge from wet scrubber and bag filter will be generated.  Char/dolochar generated in the kiln will be used in FBC boilers to generate power.

 

            Out of 20 acre, 6.60 acre is earmarked for green belt development. 1500 KVA power will be required.  LDO/HSD oil will be used as fuel for initial start-up and process stabilization.

The Committee deliberated upon the issues raised during the Public Hearing / Public Consultation meeting conducted by the Karnataka Pollution Control Board on 11th July, 2008. The issues included dust and smoke control, installtion of air pollution control measures, basic facilities and construction of Kalyan matap to Halkundi village and employment were discussed and have satisfactorily been incorporated in the final EIA/EMP report.

            After detailed deliberations, the Committee found the final EIA/EMP report adequate and suggested to stipulate following specific conditions alongwith other environmental conditions while considering for accord of environmental clearance :

 

  1. Efforts should be made to reduce RSPM levels in the ambient air and a time bound action plan should be submitted. On-line ambient air quality monitoring and continuous stack monitoring facilities for all the stacks and sufficient air pollution control devices should be provided to keep the emission levels below 100 mg/Nm3.
  2. Hot gases from DRI kiln should be passed through Dust Settling Chamber (DSC) to remove coarse solids and After Burning Chamber (ABC) to burn CO completely and used in waste heat recovery boiler (WHRB).  The gas then should be cleaned in ESP before leaving out into the atmosphere through ID fan and stack.
  3. Secondary fugitive emissions from blast furnace and sinter plant should be controlled within the latest permissible limits issued by the Ministry and regularly monitored. Guidelines / Code of Practice issued by the CPCB should be followed. The emission standards issued by the Ministry in May, 2008 for the sponge plants should be followed.
  4. Vehicular pollution due to transportation of raw material and finished product should be controlled.  Proper arrangements should also be made to control dust emissions during loading and unloading of the raw material and finished product.
  5. Prior permission for the drawl of from 280 m3/day from the State Ground Water Board /Central Ground Water Authority (SGWB/CGWA) should be obtained.
  6. New DRI kiln should be provided with waste heat recovery boiler (WHRB) to make use of flue gases generated during the process. All the char from existing and proposed DRI plant should be utilized in AFBC boiler of power plant and no char should be disposed off anywhere else. AFBC boiler should be installed simultaneously alongwith the DRI plant to ensure full utilization of char from the begning. All the other solid / hazardous waste generated shall be properly utilized or disposed off in environment friendly manner.
  7. Proper utilization of fly ash should be ensured as per Fly Ash Notification, 1999 and subsequent amendment in 2003.  All the fly ash should be provided to cement and brick manufacturers for further utilization and bottom ash should be used for land filling. 
  8. As proposed, green belt should be developed in 6.60 acre (33 %) out of total 20 acres.
  9. Permission and recommendations of the State Forest Department regarding impact of the proposed plant on the surrounding Bellary reserve forest (1.1 km, West) should be obtained and implemented.
  10. All the recommendations made in the Charter on Corporate Responsibility for Environment Protection (CREP) for the Steel Sector should be implemented.

4.6       Pig Iron Plant (42,000 TPA) at Village Nathiya-Nawagaon, Kanker, Chhattisgarh by M/s Jiwan Lal Jain (EC)

The project authorities and their consultant gave a detailed presentation on the salient features of the project and proposed environmental protection measures to be undertaken as per Draft Terms of References (TORs) awarded during the 73rd Meeting of the Expert Appraisal Committee (Industry) held during 24th–26th October, 2007 for preparation of EIA/EMP.  Pig iron plants are listed at S.N. 3(a) under primary metallurgy industries under Category ‘A’. 

 

            PAs informed to the Committee that M/s Jiwan Lal Jain have proposed for the Pig Iron Plant (42,000 TPA) at Village Nathiya-Nawagaon, Kanker, Chhattisgarh.  Total project area is revised from 5.00 ha. to 3.04 ha. Total cost of the project is Rs. 20.00 Crores. Proposed site is close to iron ore mine at village Barbaspur, Kankar, C.G.

 

            Quartzite (1,470 TPA), Iron ore (67,200 TPA), Coke (29,400 TPA), dolomite (63,000 TPA), Manganese (19,800 TPA), Limestone (6,300 TPA) will be used as raw materials. Pig Iron will be manufactured using conventional blast furnace. Lump iron ore, coke limestone, dolomite, Manganese ore and quartzite will be charged from the top and hot air at 1000oC will be blown for the bottom into the furnace.  The hot coke reaching from the top will react with O2 of hot air and generate heat and Co and will react with iron oxide of iron ore and will form iron which will melt in the lower zone called hearth.  SiO2 and Al2O3 of iron ore and coke ash will combine with Cao & MgO of limestone and dolomite to form slag floating on the top of the molten metal.  Mg ore will be added to control ‘S’ in the metal.  Molten metal will be cast in a pig casting machine to form solid pig iron.  Slag is granulated by spraying water with high presence.

 

            Dust catcher will be provided to the blast furnace to collect the dust, which will be used in sinter plant. Ventury scrubber and cyclone will be provided. Covered conveyor will be provided to the stock house, screen, feeder and discharging points. BF gas will be used for reheating the stoves.  Total water requirement will be 10,000 m3/day.  Sludge water mixture from gas cleaning plant will be sent to clarifier, treated chemically and decanted.  All the treated wastewater will be recycled and reused in the process for dust suppression and green belt development.  No wastewater will be discharged. Slag generated will be granulated and sold to cement manufacturers.

                       

             Green belt will be developed in 1.04 ha (35 %) area out of total 3.04 ha.  1,250 KW electricity will be sourced from CSEB.   

The Committee deliberated upon the issues raised during the Public Hearing / Public Consultation meeting conducted by the Chhattisgarh Environment Conservation Board on 26th May, 2008 have satisfactorily been incorporated in the final EIA/EMP report.

            After detailed deliberations, the Committee found the final EIA/EMP report adequate and suggested to stipulate following specific conditions alongwith other environmental conditions while considering for accord of environmental clearance :

1.      On-line stack monitoring facilities for all the stacks and sufficient air pollution control devices should be provided to keep the emission levels below 100 mg/Nm3.  All the gases from blast furnace after cleaning in gas cleaning plant (GCP) should be used as fuel for reheating the stoves.

2.      Secondary fugitive emissions from blast furnace should be controlled within the latest permissible limits issued by the Ministry and regularly monitored. Guidelines/Code of Practice issued in this regard by the CPCB should also be followed.

3.      Prior permission for the drawl of 10,000 m3/day water should be obtained from the concerned department.

4.      All the blast furnace slag should be granulated and provided to cement manufacturers for further utilization.  All the dust from the air pollution control equipments should be recycled and reused in the Sinter plant.

5.      All the recommendations made in the Charter on Corporate Responsibility for Environment Protection (CREP) for the Steel Plants should be strictly implemented.

4.7      Expansion of Pelletization Plant into Integrated Steel Plant (1.1 MTPA) alongwith WHRB Power Plant (2x30 MW) at Siltara Industrial Growth Centre, Phase-I, Mandhar, Raipur, Chhattisgarh by M/s Sarda Energy & Minerals Ltd. (EC)

 

The project authorities and their consultant gave a detailed presentation on the salient features of the project and proposed environmental protection measures to be undertaken as per Draft Terms of References (TORs) awarded during the 79th Meeting of the Expert Appraisal Committee (Industry) held during 18th to 20th March, 2008 for preparation of EIA/EMP.  All the Integrated Steel Plants are listed at S.N. 3(a) under Primary Metallurgy Industries under Category ‘A’ and appraised at the Central level. 

 

            PAs informed to the Committee that M/s Sarda Energy & Minerals Ltd. have proposed for the expansion of Pelletization Plant into Integrated Steel Plant (1.1 MTPA) and Captive Power Plant (250 MW) at Siltara Industrial Growth Centre, Phase-I, Mandhar, Raipur, Chhattisgarh. Pelletization Plant is existing and Integrated Steel Plant (0.11 MTPA) is proposed as per details given below :

 

S.N.

Project Details

Under installation (TPA)

Proposed Capacity (TPA)

 

Phase-I

Phase-II

Total

1

Palletization Plant

6,00,000

--

--

6,00,000

2

Coke Oven

--

--

5,20,000

5,20,000

3

Sinter Plant

--

--

13,00,000 (2x60 m2)

13,00,000

4

Blast Furnace

--

--

7,90,000

(2x450 m3)

7,90,000

5

Electric Arc Furnace

--

5,00,000

(2x40T)

6,00,000

(1x90T)

11,00,000

6

CCM (2x3 Strand & 1x4 Strand)

--

4,70,000

(2x3 Strand)

6,00,000

(1x4 Strand)

10,70,000

(3x7 Strand)

7

Rolling Mill

--

3,50,000

6,00,000

9,50,000

8

Power plant (WHRB based on coke oven & BF gases)

--

--

2x30 MW

60 MW

9

Oxygen Plant

--

--

2x150 TPD

300 TPD

 

            During presentation, PAs informed that power plant (60 MW, 2x30 MW) exists.  Power plant and sponge iron plant proposed earlier are withdrawn since no coal based power plant and sponge iron plant is allowed in the Urla, Borjhara and Siltara Industrial Growth Centre in Chhattisgarh as per the order of the Govt. of Chhattisgarh dated 16th March, 2007.  Therefore, proposal is considered without coal based sponge iron plant and power plant.

 

            Total land acquired is revised from 142.45 ha. to 204.45 ha.  Total cost of the project earlier proposed as Rs. 3,255.00 Crores is revised to Rs. 2,393.00 Crores due to no installation of coal based sponge iron plant and CPP.  Rs. 7.25 Crores and Rs. 0.75 Crores earmarked towards capital cost and recurring cost/annum earmarked for environment pollution control measures are revised to Rs. 190.00 Crores and Rs. 26.35 Crores.  Besides Rs. 1.00 Crs. is earmarked for green belt development.

 

            Imported Coke (51,10,000 TPA), DRI (15,70,000 TPA), Iron Ore fines for Sinter (12,35,000 TPA), Limestone (1,95,000 TPA) Dolomite (1,17,700 TPA), SMS Limestone (2,90,000 TPA), Scrap (1,20,000 TPA) and non-coking coal (16,63,200 TPA) will be used as used as raw material.

 

      Coke oven (5,10,000 TPA, non-recovery type), Sinter Plant (7,88,000 TPA), Blast Furnace (7,88,000 TPA), Billet caster Rolling Mill, Power Plant (2x30 MW) FBC, 2x75, CFBC boiler and WHRB (1x40 MW) will be manufactured as per conventional procedures.

 

Air quality monitoring was carried out at 12 locations and the parameters are found to vary in the following range: SPM (169-350 mg/m3), RSPM (57-106 mg/m3), SO2 (6–13 mg/m3) & NOx (7-18 mg/m3).  ESP will be provided to control flue gas from sinter plant to 100 Mg/Nm3.  Flue gas will also be generated from BF plant, pellet plant, EAF, sinter plant and rolling mill and cleaned in ESP to control emissions below 50 Mg/Nm3.  Dust and fume extraction system will be provided to raw material handling area and SMS. Bagfilter/deduster will be provided to coke oven plant. ESP will be provided to Sinter plant. Gas cleaning plant comprising of dust catcher and wet cleaning system will be provided to Blast furnace. Fume extraction system with cyclone and bag filter will be installed for Electric Arc Furnace.  Heat recuperator will be provided to rollling mill. ESP/bag filter will be provided to power plant. Adequate stack height will be provided to all the plants. Water sprinkling system will be installed to control fugitive emissions. Bag filters and cyclones will be provided for de-dusting in material handling areas. All internal roads will be black topped/concrete. ESP, multi-cycone, bag filter, deduster will be provided to pellet plant.

 

Total water requirement from River Kharun earlier proposed as 50,160 m3/day is revised to 9,092 m3/day (2 MGD) and is again revised to 8,780 m3/day.  Permission for the drawl of water is obtained from Water Resources Department, Govt. of Chhattisgarh vide letter dated 27th October, 2008.  All the treated wastewater will be recycled / reused for dust suppression and green belt development and no effluent will be discharged. ‘Zero’ discharge will be adopted.

 

            ESP dust (10,000 TPA), GCP dust (788 TPA), dust from deducting units (5,610 TPA), BF slag (1,97,500 TPA), SMS slag (76,800), scrap (14,583 TPA) will be generated as solid / hazardous waste.  SMS slag will be reused as road ballast or road fill material.  Fly ash will be sold to brick plants to cement plants.  Scrap will be used in SMS.  GCP dust will be used in sinter plant.  BF slag will be granulated and sold to cement plants.

 

Green belt will be developed in 67.47 ha out of total 204.45 ha.  Acoustic enclosures will be provided.  Power (250 MW) will be required for the proposed Integrated Steel Plant.  Coal (16,63,200 TPA) and LDO (50 m3/day) will be used as fuel.

 

                        ‘Consent to Establish’ for the existing Pelletization Plant (6,00,000 TPA) has been accorded by the Chhattisgarh Environment Conservation Board vide letter no. 5613/TS/CECB/ 2006 dated 10.11.2006.  Construction work related to pelletisation plant is in full swing.

 

The Committee noted that no public hearing is required as per Section (iii), Stage (3), Para (i)(b) of EIA Notification, 2006 since the unit is located in the notified Siltara Industrial Growth Centre, Phase-I, Mandhar, Raipur, Chatisgarh area.

           

            After detailed deliberations, the Committee desired submission of action plan for the generation and utilization of blast furnace slag alongwith the copies of MOU signed with the cement manufacturers, which will be examined internally in the Ministry itself without calling PAs.  The Committee found the final EIA/EMP report adequate and suggested to stipulate following specific conditions alongwith other environmental conditions after submission of above mentioned information:

 

  1. No coal based sponge iron plant and captive power plant shall be installed without prior permission from the State Govt. of Chhattisgarh (banned as per the order of the Govt. of Chhattisgarh dated 16th March, 2007) and Ministry.
  2. Efforts should be made to reduce RSPM levels in the ambient air and a time bound action plan should be submitted. On-line ambient air quality monitoring and continuous stack monitoring facilities for all the stacks and sufficient air pollution control devices should be provided to keep the emission levels below 100 mg/Nm3. 
  3. Electrostatic precipitator (ESP) to sinter plant and ESP/bag filter should be provided to WHRB to control gaseous emissions. Bag house should be provided to BF–Dry gas cleaning system. Gas cleaning plant having dust catcher and bag filter should be provided to blast furnace (BF). Bagfilter / deduster should be provided to coke oven plant. Gas cleaning plant comprising of dust catcher and wet cleaning system should be provided to blast furnace. ESP, multi-cycone, bag filter, deduster should be provided to pellet plant. Fume extraction system with cyclone and bag filter should be provided to electric arc furnace. Heat recuperator should be provided to rollling mill. ESP/bag filter should be provided to power plant.
  4. Gaseous emission levels including secondary fugitive emissions from blast furnace and sinter plant should be controlled within the latest permissible limits issued by the Ministry and regularly monitored. Guidelines / Code of Practice issued by the CPCB should be followed. The emission standards issued by the Ministry in May, 2008 to control fugitive emissions should be followed.
  5. Vehicular pollution due to transportation of raw material and finished product should be controlled.  Proper arrangements should also be made to control dust emissions during loading and unloading of the raw material and finished product.
  6. All the standards prescribed for the coke oven plants should be followed as per the latest guidelines. Proper and full utilization of coke oven gases in power plant using waste heat recovery steam generators should be ensured and no flue gases shall be discharged into the air.
  7. Total water requirement from Kharun River should not exceed 8,780 m3/day m3/day.  No ground water should be used. Acidic and Alkaline effluent from DM water plant should be neutralized and reused in the plant. No phenolic effluent should be generated. All the wastewater from process and domestic sources should be treated and recycled and reused.  No wastewater should be discharged outside the premises and ‘Zero’ effluent discharge should be ensured.
  8. The water consumption should not exceed 16 m3/Ton of Steel as per prescribed standard.
  9. Ground water monitoring around the solid waste disposal site / secured landfill (SLF) should be carried out regularly and report submitted to the Ministry’s Regional Office at Bhopal, CPCB and CECB.
  10. All the blast furnace (BF) slag should be granulated and provided to cement manufacturers for further utilization. SMS slag should be properly utilized.  Fly ash should be sold to brick plants to cement plants.  Scrap should be used in SMS.  Sinter dust, GCP dust, SMS dust, Scale, Iron ore fines should be used in sinter plant. All the other solid wastes including broken refractory mass should be properly disposed off in environment-friendly manner. Oily waste should be provided to authorized recyclers/reprocessors.
  11. A time bound action plan should be submitted to reduce solid waste, its proper utilization and disposal.
  12. Proper handling, storage, utilization and disposal of all the solid waste shall be ensured and regular report regarding toxic metal content in the waste material and its composition, end use of solid/hazardous waste should be submitted to the Ministry’s Regional Office at Bhopal, CECB and CPCB. 
  13. Proper utilization of fly ash should be ensured as per Fly Ash Notification, 1999 as amendment in 2003.
  14. As proposed, green belt should be developed in 33 % area.
  15. All the recommendations made in the Charter on Corporate Responsibility for Environment Protection (CREP) for the Steel Sector should be implemented.

4.8       Expansion of Pulp and Paper Mill (2,45,000 to 4,00,000 TPA) by installation of Hard Wood Pulp Mill (300 BD TPD) and bagasse based Pulp Mill (500 BD TPD) at Kagithapuram, District Karur, Tamil Nadu by M/s Tamil Nadu Newsprint & Papers Ltd. (EC)

The project authorities and their consultant gave a detailed presentation on the salient features of the project and proposed environmental protection measures to be undertaken as per Draft Terms of References (TORs) awarded during the 73rd Meeting of the Expert Appraisal Committee (Industry) held during 24th–26th October, 2007 for preparation of EIA/EMP.  All the pulp and paper manufacturing units have been kept at SN. 5 (i) under Category ‘A’ and are appraised at the Central Level. 

 

             PAs informed to the Committee M/s Tamil Nadu Newsprint & Papers Ltd. have proposed for the expansion of Pulp and Paper Mill (2,45,000 to 4,00,000 TPA) by installation of Hard Wood Pulp Mill (2,45,000 to 4,00,000 TPA) by installation of Hard Wood Pulp Mill (300 BD TPD) and bagasse based Pulp Mill (500 BD TPD) at Kagithapuram, District Karur, Tamil Nadu.  Environmental clearance for the existing pulp and paper mill (2,45,000 TPA) has already been accorded vide Ministry’s letter dated 10th April, 2006.  Now, it is proposed to enhance capacity of newsprint and printing and writing paper 2,45,000 TPA to 400,000 TPA by installing a new paper machine (1,55,000 TPA) including Elemental Chlorine Free (ECF) hardwood pulp mill (300 TPD) and a bagasse pulp mill (500 TPD) based on ECF bleaching.  Out of total 375 acres, 4 acre will be used for expansion. Total cost of the project is revised from Rs. 725.00 Crores to Rs. 1,000.00 Crores including Rs. 128.00 Crores towards the pollution control measures. 

 

             Bagasse pulp mill is based on the elementary Chlorine-free (ECF) method and generated surplus 45,000 TPA pulp. It is proposed to convert this 45,000 TPA pulp into value added paper by addition of new paper machine of 1,55,000 TPA capacity. One new paper machine (1,55,000 TPA) and one coal fired boiler (125 TPH) will be installed.  Thus, pulp and paper production will enhanced as per details given below:

 

Item (s)

Units

Pre MEP

Post MEP

Chemical hardwood pulp

TPD

300

330

Chemical bagasse pulp

TPD

500

550

Paper (as per Consent)

TPA

2,45,000

4,00,000

 

  PAs informed to the Committee about the raw material requirement after Mill Development Plan (MDP).  During expansion, it is proposed to augment the following :

 

-           One new continuous digester (200 BD TPD) unbleached pulp production (for baggase pulping line).

-           Replacement of existing drum washers for brown stock washing with 3 twin roll for achieving 600 TPD unbleached pulp production (for bagasse pulping line).

-           Replacing of existing screening plant with pressure knitters alongwith 4 stage screening and cleaning system to achieve pulp production (600 BD TPD) unbleached pulp production (for bagasse pulping line)

-           Augmentation of hard wood pulping lime to achieve bleached pulp production (330 BD TPD).

-           Installation of new power boiler (24 MW).

-           Augmentation of existing wastewater treatment facilities.

            Ambient air quality was monitored during September, 2004–September, 2005. The power boiler will be installed and particulate matter will be < 150 mg/Nm3.  Fugitive emissions will be controlled by sprinkling water on unpaved roads.  High efficiency ESPs have been installed to recovery boiler and new lime kiln in September, 2007 to control particulate emissions and will also be provided to control particulate emissions from the new paper machine and coal fired boiler alongwith the stacks of adequate height to disperse emissions.  Odour is controlled by collecting gas and burning. Direct contact evaporating is eliminated in the new recovery boiler. H2S and Mercaptan is monitored and report submitted to the concerned agency.  On-line stack monitoring of SPM, SO2, NOx and H2S is carried out. Dust extraction system at lime godown and water sprinklers in coal yard and baggase yard have been provided to control fugitive emissions. The plant generates about 15,000 m3/day methane gas and a biomethanation plant is installed in 2003.

 

            Total water requirement for the existing MEP project is 66,380 m3/day, which will enhance to 75,750 m3/day although initially, it was informed that no additional water will be required.  PWD’s consent for the drawl of 72,000 m3/day for the drawl of water from River Cauvery is obtained. No new water treatment plant or equipment is proposed during expansion but ETP will be augmented due to ageing of existing secondary clarifiers.  Total wastewater discharge after MDP #2 will be 38,340 m3/day, further revised to 31,700 m3/day by March, 2009. Existing wastewater treatment is having adequate capacity to treat the wastewater generated during expansion. Primary and Secondary treatment facilities have been provided. Spill liquor from paper mill and chemical recovery areas will be collected and properly treated.  Chlorine di-oxide plant is recently installed in May, 2008 and Elemental Chlorine-free (ECF) bleaching method is used to bring down the pollution load.  The water consumption in the existing plant is 81 m3/T of paper against the imit of 100m3/T. and AOx level is 0.51 Kg/T of paper against the limit of 1 Kg/T. The new paper machine will be designed for a specific consumption of 12 m3/T of paper with a wastewater generation of 10 m3/T of paper (Limit is 80 m3/T). PAs also informed that Effluent Water Lift Irrigation Scheme (TWELTIS) is continuing since 1993 and 1700 acres barren land is irrigated converting into lush green fields where sugarcane, groundnut, coconut etc. are grown. The cultivated area is further extended by 500 acres.  Besides other parameters, AOx and TOC levels are monitored.

 

            PAs also informed that colour in the effluent is reduced from 250 to 190 Pt-Co due to installation of oxygen delignification and closing down of brown loop in the hardwood line as a part of Mill Development Plan (MDP).  Ferrous oxide is used to optimize the colour.  Falling film black liquor eveporation plant is installed in September, 2007 to handle black liquor. Biomethanation plant is installed and is in operation since September, 2007. However, additional reactor is installed and additional gas will be generated wef November, 2008.  The water reservoirs are used to store the treated wastewater during monsoon season to avoid discharge of treated effluent ionto canal. 

 

Two lime kilns with ESP have been installed as per CREP requirement. Additional fly ash (96 TPD) will be generated and supplied to cement manufacturers.  Additional ETP sludge (5 TPD) will be generated from the new paper machine which will be re-burnt in the boilers and will also provided to the cement manufacturers. The chip dust and pith will be used as fuel in the boilers. Waste pulp from WWTP will be provided to card board and egg tray manufacturers. .

            Out of total 741.2 acres, 196.3 acres (26.5 acres) is covered by green belt. Green belt is developed in 176 ha (433.50 acres).  24 MW power will be generated.

 

The Committee deliberated upon the issues raised during the Public Hearing / Public Consultation meeting conducted by the Tamil Nadu Pollution Control Board on 10th July, 2008. The issues raised included air borne emissions, climate change, community welfare, drinking water supply, ground water and effluent quality, sewage discharge into Pugalur canal, effluent sludge incineration, soil quality, dust emissions, emplyment in TNPL, road construction etc. and have satisfactorily been incorporated in the final EIA/EMP report.

It was brought to the notice of the Committee that Ministry has received telegraphic representations and a Court case viz. T.N. Subramanian vs. TNPCB and others filed in the Madurai High Court against the M/s TNPL and were placed before the Committee.  PAs clarified that the said court case is still not admitted in the Court and will be suitably replied whenever admitted. At the same time, PAs claimed that they have already implemented all the recommendations of the Justice Swamy Committee by installing ECF technology, stopping discharge to Pulgal canal, enhancing land irrigation area etc. besudes many more modifications to control pollution.

            After detailed deliberations, the Committee found the final EIA/EMP report adequate and suggested to stipulate following specific conditions alongwith other environmental conditions while considering for accord of environmental clearance :

 

1.      As proposed, Elemental Chlorine Free (ECF) bleaching technology should be adopted in hardwood pulp mill, bagasse pulp mill and paper machine. 

2.      Continuous stack monitoring facilities for all the stacks and sufficient air pollution control devices viz. Electrostatic precipitator (ESP) and bag filters etc. should be provided to control gaseous emissions below 100 mg/Nm3. Monitoring of H2S and Mercaptan alongwith other parameters should be ensured and report submitted to Ministry’s Regional Office at Bangalore, TNPCB and CPCB regularly.

3.      Secondary fugitive emissions from all the sources should be controlled within the latest permissible limits issued by the Ministry and regularly monitored. Guidelines / Code of Practice issued by the CPCB should be followed.

4.      AOx levels should be controlled less than 1 kg/ton of paper manufactured as per E(P) Act.

5.      The odours and gases from cooking / stripping column, evaporator hot well and hot condensate tank should be burnt in the incinerator.

6.      Permission for the drawl of 75,750 m3/day from River Cauvery water should be obtained from the concerned department.

7.      Total water consumption should not exceed as mentioned in the Corporate Responsibility for Environment Protection (CREP) guidelines.  Efforts should be made to reduce the quantity of water intake and maximize use of recycled water.

8.      The process effluent should be treated in Effluent Treatment Plant (ETP) through primary, secondary and tertiary treatment methods.  Effluent discharged should be colour free.  Treated effluent (filtrate) should be used for the green belt development and discharge to the nearby drain only after conforming to the standards prescribed by the TNPCB and under E(P) Act, whichever are more stringent.

9.      Chemical recovery plant should be installed for the treatment of black liquor.  In order to achieve colour reduction, tertiary treatment system like activated filter, multi-media filter etc. should be explored.

10.  Adequate number of influent and effluent quality monitoring stations should be installed in consultation with the TNPCB and controlled within the permissible limits for all the parameters.  One of the water quality monitoring station should be at 100 m downstream of confluence of the treated effluent discharge point in the nearest water body.

11.  Efforts should be made to reduce total dissolved solids (TDS) in the effluent and effluent discharged should not exceed 80 m3/T of paper produced as per the norms prescribed in the E(P) Act.

12.  Action plan should be prepared for further colour removal from the effluent and submitted to the Ministry, its Regional Office at Bangalore, TNPCB and CPCB and implemented.

13.  Regular ground water monitoring should be carried out for all the relevant parameters where effluent is discharged.

14.  Efforts should be made for the utilization of lime sludge and mud in the cement plants. Sludge dewatering system should be installed.  ETP sludge should be used as manure.

15.  Action plan for the disposal of Reverse Osmosis (RO) rejects shoild be prepared and submitted to the Ministry’s Regional Office at Bangalore, TNPCB and CPCB within three months of issue of this letter.

16.  Proper utilization of fly ash should be ensured as per Fly ash Notification, 1999 and subsequent amendment in 2003.

17.  Green belt should be developed in 33 % area.

18.  All the commitments made to the public during public hearing should be satisfactorily implemented.

19.  All the recommendations made in the Charter on Corporate Responsibility for Environment Protection (CREP) for Pulp and Paper Sector should be strictly implemented.

 

 

4.9       Integrated Steel plant (3.0 MTPA) at Nagarnar Village, Jagdalpur Tehsil, Bastar District, Chhattisgarh by M/s National Mineral Development Corporation Limited. (TOR)

The project authorities and their consultant gave a detailed presentation on the salient features of the project and proposed environmental protection measures to be undertaken alongwith the draft Term of References for the preparation of EIA/EMP. All the Integrated steel plants are listed at S.N. 3(a) under Primary Metallurgical Industry under Category ‘A’ are appraised at the Central level.

 

M/s National Mineral Development Corporation Ltd. have proposed for the Integrated Steel Plant (3.0 MTPA) at Village Nagar nagar, Tehsil Jagdalpur, District Bastar, Chhattisgarh.  Total project area is 402.8 ha. (288.79 ha. private land and 114.01 ha. Govt. land already allocated by the Govt. of Chhattisgarh vide Gazate Notification No. 33 dated 17.08.2001.  Environment clearance for steel plant (0.1 MTPA) was accorded vide MOEF letter no J-11011/455/2006-IA-II (I) dated 5th October, 2007.  Kanger RF (5 km, SE), Ultnar RF (7.9 km, NW), Kakadpasar RF (5.3, NW), Chalanguda RF (8.5 km., NW) and Metawada RF (13.6 km. NW) are located within 10 km radius of the project site. Total cost of the project is Rs. 16,353.00 Crores. Rs. 1,300.00 Crores are allocated towards total capital cost and recurring cost/annum for environmental pollution control measures.

 

During presentation, PAs informed that a Power Blowing Station (3x30 MW) will be installed for power generation from BF gas in addition to the facilities earlier proposed.  No sponge iron plant will be installed.  Following will be the facilities after revision :

 

S.N.

Facilities

Configuration

1.   

Coke oven plant with CDCP

2x67 ovens, 7.0 m tall

2.   

Sinter Plant

1x460 m2

3.   

Blast furnace

1x 4500 m3

4.   

De-sulphurisation units

2x175 m3

5.   

Pig casting machine

3x1700 TPD

6.   

Slag granulation plant

Catering capacity for production of 848,700 granulated slag

7.   

Basic oxygen furnace

2x175 T

8.   

Ladle furnace

2x175 T

9.   

RH-OB

1x175 T

10.   

Thin slab caster coupled with hot strip mill

2x1 strand

11.   

Hot strip mill with finishing train

6 strands

12.   

Oxygen Plant

1x1900 TPD

13.   

Calcination plants

-           Lime Plant

-           Dolo Plant

 

2x500 TPD

 

1x300 TPD

14.   

Power Blowing Station (BF gas based)

3x30 MW

 

Following will be the size of the project :

 

-          Gross hot metal from 3.32 MTPA

-          Liquid steel from 3.00 MTPA

-          Production of finished long product will be 2.896 MTPA HR Coils

Final saleable product mix will be :

 

S.N.

Items

Annual production (Tones)

A

Pig Iron

272,800

B

Hot strip mill

 

C

HR coils / sheets / plates

 

1

HR Plates - (IS 2062, IS 5986, IS 8500, IS 3039)

400,000

2

HR Plates - (IS 2002 &  IS 2041)

400,000

3

API-5L quality plates – upto x80

500,000

4

HR Sheets (IS 3196)

200,000

5

LPG cylinders (IS 6240)

200,000

6

HR coils (IS 10748, IS 1079)

946,000

7

High Carbon Steel (1100-1650) and other alloy steel

50,000

8

Silicon Steel (DIN 46400-3)

100,000

9

Automotive Steel

 

 

-          1250-1524

50,000

 

-          1525-1650

50,000

 

Total

2,896,000

 

            Iron ore lump (BF grade, 1,237.000 MTPA), Iron ore fines (4,200,500 MTPA), Iron ore lumps (SMS grade, 38100 MTPA), Lime stone fines (292,600 MTPA), lime stone (SMS grade 584,700 MTPA), Dolomite fines for SP (388,600 MTPA), Dolomite fines (SMS grade 172,700 MTPA) Quartzite (51,300 MTPA), Coking coal (2,591,200 MTPA) Non-coking coal (564,000 MTPA), Purchased DRI (208,100 MTPA), Scrap (33,400 MTPA), Fe-Mn (1,500 MTPA), Fe-si (7,400 MTPA), Si-Mn (30,000 MTPA), Aluminium (6,000 MTPA) and Fluorospar (2,250 MTPA will be used as raw materials.

            Steel will be produced through BF-BOF degasser route alongwith coke oven, sinter plant and Rolling / Finishing. Cast house and stock house dust emission control system will be provided to Blast furnace. Coke Oven (recovery type) will be installed and essential by-products like ammonia, crude tar and elemental Sulphur will be recovered. Land based coke side dust extraction system will be provided to Coke oven.  In addition, Naphthalene scrubbing and solar oil regeneration unit will be installed to remove and recover naphthalene from coke oven gas.  Sinter plant, Blast furnace, Steel making (SMS) and continuous casting shop will be installed.     

 

            BF gas Coke oven gas, mixed gas (BF & CO gas), BOF will be used to generate power.  Part of the BF gas will be supplied to CDP Plant, Cast house; Co to BOF shop & CCM shop and coke oven and BF gas to coke oven battery, hot strip mill, sinter plant hot strip mill, lime and dolomite plant.  Work zone emission will be kept below 10 mg/m3.

Total water requirement from Sabri River will be 3747 m3/hr.  Individual shop-wise wastewater treatment facilities will be provided.  All the effluent will be treated and used for ash handling, dust suppression and green belt development. No effluent will be discharged and ‘zero’ discharge will be adopted. Sewage sludge will be used as manure for green belt development.

 

Blast furnace (BF) slag (848,700 TPA) will be granulated and sold to cement plants.  BF sludge (23,000 TPA) will be partly used in Sinter Plant and partly dumped in dump area.   BF flue dust (53,140 TPA) will be 100% reused in Sinter Plant.  BOF slag (3,15,000 TPA) will be 100% reused in construction and as rail ballast. BOF sludge will be reused in BOF after briquetting.  Waste refractories (45,000 TPA) Dolo fines, Mill scales, lime fines and cinder will be recycled / reused.

 

Green belt will be developed in 33 %. Total power requirement will be 251 MVA instead of 251 MW proposed earlier. The power required will be sourced from Chhattisgarh State Electricity Board (CSEB).

After deliberating on the facts presented the Expert Appraisal Committee (Industry) recommended the proposal for the preparation of EIA/EMP as per the following TORs :

1.      Present land use should be prepared based on satellite imagery.

2.      Location of national parks/wildlife sanctuary within 10 km. radius should specifically be mentioned.

3.      Permission and recommendations of the State Forest Department regarding impact of proposed plant on the surrounding reserve forests viz. Kanger RF (5 km, SE), Ultnar RF (7.9 km, NW), Kakadpasar RF (5.3, NW), Chalanguda RF (8.5 km., NW) and Metawada RF (13.6 km. NW) should be included.

4.      Actual land requirement, classification of land, acquisition status, rehabilitation and resettlement as per the policy of the Govt. of Chhattisgarh should be incorporated.

5.      Site-specific micro-meteorological data using temperature, relative humidity, hourly wind speed and direction and rainfall should be collected.

6.      A list of industries containing name and type in 25 km radius should be incorporated.

7.      Residential colony should be located in upwind direction.

8.      List of raw material required and source should be included.

9.      Manufacturing process details for all the plants viz. Blast Furnace, Sinter Plant, Pellet Plant, Coke Oven Plant, Oxygen Plant, Steel Melting Shop, Continuous Casting Machine, Rolling Mill etc. should be included.

10.  A chapter on type and full details of coke oven plant including pollution control methods and justification for installing recovery type of coke oven should be included.

11.  Ambient air quality at 8 locations within the study area of 10 km., aerial coverage from project site with one AAQMS in downwind direction should be carried out.

12.  The suspended particulate matter present in the ambient air must be analyzed for the presence of poly-aromatic hydrocarbons (PAH), i.e. Benzene soluble fraction.  Chemical characterization of RSPM and for incorporating of RSPM data.

13.  Impact of the transport of raw material and finished product on the surrounding environment should be assessed and provided

14.  Determination of atmospheric inversion level at the project site and assessment of ground level concentration of pollutants from the stack emission based on site-specific meteorological features. Air quality modeling for steel plant for specific pollutants needs to be done. 

15.  Plant-wise air pollution control measures proposed for the control of gaseous emissions from all the sources should be incorporated.

16.  A note on control of fugitive and secondary emissions from as per CPCB guidelines from all the sources should be incorporated.

17.  One season data for gaseous emissions during winter season is necessary.

18.  Permission for the drawl of 3,747 m3/hr make up water from Sabri River from the concerned department and water balance data including quantity of effluent generated, recycled and reused and discharged should be provided. Methods adopted/to be adopted for the water conservation.

19.  Surface water quality of nearby rivers (60 m upstream and downstream) and other surface drains at eight locations must be ascertained. 

20.  Ground water monitoring minimum at 8 locations and near solid waste dump zone, Geological features and Geo-hydrological status of the study area are essential as also.  Ecological status (Terrestrial and Aquatic) is vital.

21.  A note on treatment of wastewater from different plants including coke oven plant, recycle and reuse for different purposes should be included.

22.  Action plan for solid/hazardous waste generation, storage, utilization and disposal particularly BF slag and fly ash and copies of MOU signed with the Cement manufacturers regarding utilization of BF slag and flyash should be included.

23.  Generation and utilization of waste/fuel gases from BF plant and their utilization in the CPP have to be set out.

24.  Risk assessment and damage control needs to be addressed.

25.  Occupational health of the workers needs elaboration.

26.  Green belt development plan in 33 % area and a scheme for rainwater harvesting have to be put in place.

27.  Socio-economic development activities need to be elaborated upon.

28.  A note on identification and implementation of Carbon Credit project should be included.

29.  An Action Plan for the implementation of the recommendations made for the Steel Plants in the CREP guidelines must be prepared.

30.  Total capital cost and recurring cost/annum for environmental pollution control measures should also be included.

31.  A tabular chart for the issues raised and addressed during public hearing/public consultation should be provided.

32.  Any litigation / court case pending against the proposal should also be included.

 

The Expert Committee (Industry) decided that PAs may be communicated the above ‘TORs’ for the preparation of EIA/EMP.  As soon as the draft EIA/EMP report is prepared as per the ‘General Structure of EIA’ given in Appendix III and IIIA in the EIA Notification, 2006, the same may be submitted by the PAs to the Chhattisgarh Environment Conservation Board (CECB) for conducting public hearing as per EIA Notification, 2006.  On finalization of EIA/EMP prepared as per TORs addressing all concerns set out EIA/EMP should be submitted to the MOEF for prior environmental clearance.

 

4.10    Integrated Steel Plant (1.0 MTPA) at Village Gidan / Sagoni, Tehsil Batiagarh, District Damoh, Madhya Pradesh by M/s SPJ Steel & Minerals Pvt. Ltd. (TOR)

            The project authorities and their consultant gave a detailed presentation on the salient features of the project and proposed environmental protection measures to be undertaken alongwith the draft Term of References for the preparation of EIA/EMP. All the Integrated steel plants are listed at S.N. 3(a) under Primary Metallurgy Industries under Category ‘A’ are appraised at the Central level.

 

            M/s SPJ Steel & Minerals Pvt. Ltd. have proposed for Integrated Steel Plant at Village Gidan / Sagoni, Tehsil Batiagarh, District Damoh, Madhya Pradesh.  Total project area is 600 ha. including 500 ha Govt. and 100 ha. private land. However, during discussion, PAs informed that the project area is revised to 300 ha. instead of 600 ha. proposed earlier.  Earlier, it was informed that Sakari and Ghorakhuri reserve forests are located within 10 km. radius of the project but now 10 reserve forests have been identified. Total project cost is Rs. 3,117.00 Crores. Rs. 273.00 Crores and Rs. 25.7 Crores are earmarked towards capital cost and recurring cost/annum for environment pollution control measures. Earlier, PAs proposed to install following facilities:

 

S.

N.

Facility

Product

Units

Production Quantity

1st Yr.

2nd Yr.

3rd Yr.

4th Yr.

Total production

1

Coal Washery

(2 x 0.75 Mn TPA)

Clean Non-Coking Coal

TPA

7,50,000

-

7,50,000

-

15,00,000

2

DRI plant (4x350 TPD, 6x500 TPD)

DRI

TPA

1,68,000

1,68,000

3,37,948

3,37,948

10,11,895

3

Ferro-Alloy Plant (2 x 15 MVA)

SiMn

TPA

22,869

22,869

-

-

45,738

4

Iron Ore Beneficiation Plant (1x 0.5 Mn TPA)

Iron Ore Concentrate

TPA

-

-

4,71,274

-

4,71,274

5

Iron Ore Pellet Plant (1x0.5 Mn TPA)

Iron Ore Pellet

TPA

-

-

4,96,027

-

4,96,027

6

Sintering Plant (1x 0.2 Mn TPA)

 

TPA

-

-

-

1,80,246

1,80,246

  7

SMS-1 (8x20t IF)

Molten Metal (Crude Steel)

TPA

-

-

2,36,286

2,36,286

4,72,572

8

SMS-2 (2 x 90t EAF, 2 x 90t LF, 2 x 90t VD)

Steel Billets

TPA

-

-

5,10,163

5,10,163

10,20,326

9

Rolling mill (1x0.6 Mn TPA Bar Mill, 1x0.6 Mn TPA Section Mill)

Bar, Light & Medium Sections

TPA

-

-

4,80,000

4,80,000

9,60,000

10

Lime & Dolo calcination plant (2 x 300 TPD)

Calcined Lime

TPA

-

-

1,53,300

-

1,53,300

Calcined Dolomite

TPA

-

-

-

38,700

38,700

11

CPP (2x20MW, 2x60MW)

Captive Power

MW

20

20

60

60

160

12

Blast Furnace

(1x 300 Cum)

Pig Iron

TPA

-

-

-

1,40,831

1,40,831

13

Oxygen plant

(1x 300 TPD)

Oxygen

Nm3/yr

-

-

-

90

90

 

During the presentation, PAs informed to the Committee that capacity of the Coal washery capacity is revised from 2x7,50,000 TPA to 1x7,50,000 TPA. The annual production from the Oxygen plant has been revised to 57,000 TPA.  After the proposed revision, the facilities to be installed will be as under:

 

S.

N.

Facility

Product

Units

Production Quantity

1st Yr.

2nd Yr.

3rd Yr.

4th Yr.

Total production

1

 

Coal Washery

 

Clean Non-Coking Coal

TPA

-

-

7,50,000

-

7,50,000

2

DRI plant

DRI

TPA

1,68,000

1,68,000

3,37,948

3,37,948

10,11,895

3

Ferro-Alloy Plant

SiMn

TPA

22,869

22,869

-

-

45,738

4

Iron Ore Beneficiation Plant

Iron Ore Concentrate

TPA

-

-

4,71,274

-

4,71,274

5

Iron Ore Pellet Plant

Iron Ore Pellet

TPA

-

-

4,96,027

-

4,96,027

6

Sintering Plant

 

TPA

-

-

-

1,80,246

1,80,246

  7

SMS-1

Molten Metal (Crude Steel)

TPA

-

-

2,36,286

2,36,286

4,72,572

8

SMS-2

Steel Billets

TPA

-

-

5,10,163

5,10,163

10,20,326

9

Rolling mill

Bar, Light & Medium Sections

TPA

-

-

4,80,000

4,80,000

9,60,000

10

Lime & Dolo calcination plant

Calcined Lime

TPA

-

-

1,53,300

-

1,53,300

Calcined Dolomite

TPA

-

-

-

38,700

38,700

11

CPP

Captive Power

MW

20

20

60

60

160

12

 

Blast Furnace

 

Pig Iron

TPA

-

-

-

1,40,831

1,40,831

13

 

Oxygen plant

 

Oxygen

TPA

-

-

-

57,000

57,000

 

            Iron ore (16,71,835 TPA), non-coking coal (31,20,000 TPA), Dolomite (72.830 TPA), Limestone (3,03.294 TPA), Quartzite (29,222 TPA), Cokes (1,20,640 TPA), Manganese ore (1,13,966 TPA) will be used as raw materials.

            The proposed plant will produce DRI, billets, pig iron, long steel bars / sections and ferro alloy products and will install coal washery, DRI Plant, ferro-alloy plant, iron ore beneficiation plant, sinter plant, steel melting shop, rolling mill, lime and dolo calcinations plant, BF with pig caster and slag granulation pit, oxygen plant and CPP (160 MW).

 

            Integrated Steel Plant will be based on DRI-IF/BF-EAF-LF-VD route to minimize dependence on coke.  Lumps and fines generated from DRI plant will be fed to EAF and IF respectively.  Cold pig required for IF will be produced in MBF. Coal washery, beneficiation plant and pellet plant will be provided to use low-grade material.  Finally, material will pass through CCM and subsequently to rolling mill for producing finished products like long bars and steel sections etc. Coal washery will be provided to separate clean coal as overflow and middling as underflow.           

 

PAs informed to the Committee that data for March-May, 2008 is collected but Committee emphasized to collect the same for the winter season i.e. December, 2008-February, 2009.  ESP will be provided to DRI kilns, sinter plant, pellet plant and CPP to control emission within 100 mg/Nm3. Hot waste gases from rotary kiln after passing through Dust settling chamber (DSC) will be burnt in ABC and fed to WHRB for generating power.  The gas will be cleaned in ESP before being released through ID fan and stack.  Swiveling hood for fume extraction, speark arrester and dust extraction system with bag filters will be provided to induction furnace.  Cyclones will be provided to coal washery. However, during presentation, PAs informed that dust emissions from coal washery and Iron ore beneficiation plant will be controlled by water sprinkling/dry fog system/bag filters.  Cyclone separator followed by two-stage venturi scrubber will be provided to blast furnace.  Adequatre stack height will be provided to Reheating furnace of rolling mill. Dust extraction system with pulse jet bag filter will be provided to SMS, ferro alloy plant, pelletization plant, lime and dolo plant.  Dust from raw material handling area, stock piling and material transfer points will be controlled by dust suppression with plain water and Dry fog dust suppression system. Dust extraction system will be provided at screening and material transfer points.

 

Total water requirement will be 3,000 m3/hr and met from nearest water source viz. Gidannala, Jam river, Sonar River or ground water.  The effluent will be treated in Effluent Treatment Plant (ETP).  Water from coal washery and BF gas cleaning plant will be treated in thickener and the overflow will be reused in the plant.  Underflow from the thickener will be sent to press filter and recovered cake will be recylcled in sinter plant. Wastewater from slag granulation will be taken to settling pond and resued with make-up water in Slag granulation. Cooling tower blowdown will be reused in greenbelt development and water sprinkling system. Acidic and alkaline effluent from DM water plant will be neutralized in neutralization pit and used for ash transfer. All the treated wastewater will be used for dust suppression and green belt development.  Tailings from Beneficiation Plant will be discharged to tailing pond and over flow water will be re-circulated.  Effluents containing Oil and grease after passing through oil and grease traps will be resued in the plant. Domestic effluent will be treated in septic tank followed by soakpit.

 

Char and middlings/rejects from coal washery will be used CFBC boiler to generate power. ESP dust will be utilized in Sinter making. Kiln accretions and miscellaneous waste will be used for filling low-lying areas and clay making for various purposes in steel plant. Pellet dust from Iron ore pelletization plant will be utilized in pellet plant and sinter plant. Sinter dust will be recycled in sinter plant. Slag from SMS and ferro alloy plant will be used for road, building construction and filling low-lying areas. However, during presentation PAs informed that Slag from SMS will be used in the land fill, boulder soling of plant roads and partly in sinter making. Spent refractory will beused for construction and filling of low-lying areas. Granulated BF slag will be sent to nearby cement plants.  Fly ash and bottom ash will be used in brick making, cement manufacturing, road construction and land fill. Unutilized fly ash will be disposed off in ash pond. ETP sludge will be disposed off in low-lying areas.  Flue dust from DRI, BF, SMS, Iron ore fines, limestone, dolomite fines and rejects generated from different shops will be recycled and reused in sinter plant. Scrap will be used for steel making in SMS.  Sewage sludge from the septic tank will be used as manure.  Used oil and batteries will be sold to authorized recyclers / re-processors.

 

            Green belt will be developed in 33% area.  Total power requirement will be 130 MW and met from CPP (160 MW).

 

After deliberating on the facts presented the Expert Appraisal Committee (Industry) recommended the proposal for the preparation of EIA/EMP as per the following TORs :

 

1.      Present land use should be prepared based on satellite imagery.

2.      Location of national parks / wildlife sanctuary within 10 km. radius should specifically be mentioned.

3.      Permission and recommendations of the State Forest Department regarding impact of proposed expansion on all the surrounding reserve forests, if any should be included.

4.      Actual land requirement, classification of land, acquisition status, rehabilitation and resettlement as per the policy of the Govt. of M.P. should be incorporated.

5.      Site-specific micro-meteorological data using temperature, relative humidity, hourly wind speed and direction and rainfall should be collected.

6.      A list of industries containing name and type in 25 km radius should be incorporated.

7.      Residential colony should be located in upwind direction.

8.      List of raw material required and source should be included.

9.      Manufacturing process details for all the plants viz. coal washery, DRI Plant, ferro-alloy plant, iron ore beneficiation plant, sinter plant, steel melting shop, rolling mill, lime and dolo calcinations plant, BF with pig caster, slag granulation pit, oxygen plant and CPP etc. should be included.

10.  A note on coal dust injection system in TRT (Top Recovery) should be incorporated.

11.  Ambient air quality at 8 locations within the study area of 10 km., aerial coverage from project site with one AAQMS in downwind direction should be carried out during Dec., 2008-February, 2009.

12.  The suspended particulate matter present in the ambient air must be analyzed for the presence of poly-aromatic hydrocarbons (PAH), i.e. Benzene soluble fraction.  Chemical characterization of RSPM and for incorporating of RSPM data.

13.  Impact of the transport of raw material and finished product on the surrounding environment should be assessed and provided.

14.  Determination of atmospheric inversion level at the project site and assessment of ground level concentration of pollutants from the stack emission based on site-specific meteorological features. Air quality modeling for steel plant for specific pollutants needs to be done. 

15.  Plant-wise air pollution control measures proposed for the control of gaseous emissions from all the sources should be incorporated.

16.  A note on control of fugitive and secondary emissions from as per CPCB guidelines from all the sources should be incorporated.

17.  One season data for gaseous emissions during winter season is necessary.

18.  Permission for the drawl of 3,000 m3/hr water from nearest water source viz. Gidannala, Jam river, Sonar River or ground water from the concerned department and water balance data including quantity of effluent generated, recycled and reused and discharged should be provided. Methods adopted/to be adopted for the water conservation.

19.  Surface water quality of nearby rivers (60 m upstream and downstream) and other surface drains at eight locations must be ascertained. 

20.  Ground water monitoring minimum at 8 locations and near solid waste dump zone, Geological features and Geo-hydrological status of the study area are essential as also.  Ecological status (Terrestrial and Aquatic) is vital.

21.  A note on treatment of wastewater from different plants, recycle and reuse for different purposes should be included.

22.  Action plan for solid/hazardous waste generation, storage, utilization and disposal particularly char, BF slag, SMS slag, middlings and fly ash. Assurance that 100 % char will be used in the FBC boiler and copies of MOU regarding utilization fly ash should be included.

23.  MOU signed with the Cement manufacturers for utilizing granulated BF slag should be included.

24.  Generation and utilization of waste/fuel gases from BF plant and their utilization in the CPP have to be set out.

25.  Risk assessment and damage control needs to be addressed.

26.  Occupational health of the workers needs elaboration.

27.  Green belt development plan in 33 % area and a scheme for rainwater harvesting have to be put in place.

28.  Socio-economic development activities need to be elaborated upon.

29.  A note on identification and implementation of Carbon Credit project should be included.

30.  An Action Plan for the implementation of the recommendations made for the Steel Plants in the CREP guidelines must be prepared.

31.  Total capital cost and recurring cost/annum for environmental pollution control measures should also be included.

32.  A tabular chart for the issues raised and addressed during public hearing/public consultation should be provided.

33.  Any litigation / court case pending against the proposal should also be included.

 

The Expert Committee (Industry) decided that PAs may be communicated the above ‘TORs’ for the preparation of EIA/EMP.  As soon as the draft EIA/EMP report is prepared as per the ‘General Structure of EIA’ given in Appendix III and IIIA in the EIA Notification, 2006, the same may be submitted by the PAs to the Madhya Pradesh Pollution Control Board (SPCB) for conducting public hearing as per EIA Notification, 2006. On finalization of EIA/EMP prepared as per TORs addressing all concerns set out EIA/EMP should be submitted to the MOEF for prior environmental clearance.

4.11     Integrated Steel Plant (2.0 MTPA) at Sy. No. 15, 16, 17 and 29, Village Kunikere, Taluka and District Koppal, Karnataka by M/s ILC Industries Ltd. (TOR)

            The project authorities and their consultant gave a detailed presentation on the salient features of the project and proposed environmental protection measures to be undertaken alongwith the draft Term of References for the preparation of EIA/EMP. All the integrated steel plants are listed at S.N. 3(a) under Primary Metallurgy Industries under Category ‘A’ and are appraised at the Central level. 

            M/s ILC Industries Ltd. have proposed for the Integrated Steel Plant (2.0 MTPA) at Sy. No. 15,16,17 and 29, Village Kunikere, Taluka and District Koppal, Karnataka. No National Park/Wild life sanctuary/Reserve Forest is located within 10 km radius of the project. Total project area is 46.37 acres. Total cost of the project is Rs. 717.40 Crores.  Initially PAs informed that following will be installed:

 

S.N.

Plants

Capacity

1

Blast furnace for pig iron making

1 x 262 m3

2

EOF furnace for steel making

1 x 25 t

3

Ladle refining furnace for secondary refining

1 x 25t

4

Billet caster for casting liquid steel into billets

1 x 2 strand

5

Bar and rod mill for producing TMT bars

One

6

Captive power plant

6 MW

 

During presentation, PAs have revised the configuration and informed that following will be installed:

 

S.N.

Plants

Capacity

1

Sponge Iron unit

4 x 150 TPD

2

EOF furnace for steel making

25 T

3

Ladle refining furnace for secondary refining

25 T

4

Billet caster for casting liquid steel into billets (1 x 2 strand)

25 T

5

Bar and rod mill for producing TMT bars

2,06,000 TPA

6

Captive power plant

12 MW

 

            Coke (390 TPD), Iron ore (979 TPD), Dolomite (74 TPD), Limestone (114 TPD), Manganese ore (12 TPD), Quartzite (24 TPD) and DRI (77 TPD) will be used as raw material. However, during presentation PAs informed that Iron ore, coal and Dolomite will be used as raw materials and have their own iron ore mine facility.

            Sponge iron plant, Energy optimization furnace (EOF) followed by continuous casting through billet caster and rolling of the cast billets in rolling into the TMT bars will be installed.

 

            BF gas will be used to generate power in the CPP (6 MW).  Bag filters, gas cooler, cyclones and chimney will be provided to steel melt shop (SMS).  Bag filters and stacks will be provided to BF.  Tall chimney will be provided to CPP.   Bag filters/ESPs will be provided to DRI kilns. Bag filters will be provided to product separation/storage house, stock house, cooler discharge building, intermediate bins, coal injection building, coal and iron ore crusher/screen house, etc. of sponge iron plant.  Waste gases from DRI kilns will successively passed through Dust settling chambers, After combustion chambers, WHRB and finally ESP before venting to atmosphere through a stack of adequate height. Fugitive emissions will be controlled by material transfer points, product handling will be controlled by bag filters/dust suppression systems. Water sprinkling will be carried out in loading, unloading and storage areas.

 

Total water required from borewells/Tungbhadra dam backwater will be 22.33 LPD instead of 2 MGD (68.50 LPD) proposed earlier. Cooling water re-circulation system will be provided to minimize fresh water requirement.  Domestic effluent will be treated in sewage treatment plant and used for the green belt development. Oil and grease will be removed from contaminated water by oil traps and skimming devices.

 

Char will be used as fuel in FBC boilers or sold to brick manufacturing units. Flue dust will be used for manufacturing Fly ash bricks. Fly ahs will be utilized in cement making. Kiln accretions will be used as sub-base material for road construction or landfill.

 

Green belt will be developed in 33 % area. Power (21,000 KVA) will be sourced from Grid substation of KPTCL instead of GESCOM as proposed earlier.  CPP (6 MW) is proposed.  Fuel oil will be used in reheating furnace of rolling mill, SMS and power plant.

 

After deliberating on the facts presented the Expert Appraisal Committee (Industry) recommended the proposal for the preparation of EIA/EMP as per the following TORs :

 

1.      Present land use should be prepared based on satellite imagery.

2.      Location of national parks / wildlife sanctuary within 10 km. radius should specifically be mentioned.

3.      Permission and recommendations of the State Forest Department regarding impact of proposed expansion on the surrounding reserve forests, if any should be included.

4.      Actual land requirement, classification of land, acquisition status, rehabilitation and resettlement as per the policy of the Govt. of Karnataka should be incorporated.

5.      Site-specific micro-meteorological data using temperature, relative humidity, hourly wind speed and direction and rainfall should be collected.

6.      A list of industries containing name and type in 25 km radius should be incorporated.

7.      Residential colony should be located in upwind direction.

8.      List of raw material required and source should be included.

9.      Manufacturing process details for all the plants viz. Sponge iron plant, EOF, LRF, billet caster, bar and rod mill, CPP etc. should be included. Details of facilities with their capacities proposed alongwith quantity of products to be produced should also be included.

10.  Ambient air quality at 8 locations within the study area of 10 km., aerial coverage from project site with one AAQMS in downwind direction should be carried out.

11.  The suspended particulate matter present in the ambient air must be analyzed for the presence of poly-aromatic hydrocarbons (PAH), i.e. Benzene soluble fraction.  Chemical characterization of RSPM and for incorporating of RSPM data.

12.  Impact of the transport of raw material and finished product on the surrounding environment should be assessed and provided

13.  Determination of atmospheric inversion level at the project site and assessment of ground level concentration of pollutants from the stack emission based on site-specific meteorological features. Air quality modeling for steel plant for specific pollutants needs to be done. 

14.  Plant-wise air pollution control measures proposed for the control of gaseous emissions from all the sources should be incorporated.

15.  A note on control of fugitive and secondary emissions from as per CPCB guidelines from all the sources should be incorporated.

16.  One season data for gaseous emissions during winter season is necessary.

17.  Permission for the drawl of 22.33 LPD water from borewells/Tungbhadra dam backwater from the concerned department and water balance data including quantity of effluent generated, recycled and reused and discharged should be provided. Methods adopted/to be adopted for the water conservation.

18.  Surface water quality of nearby rivers (60 m upstream and downstream) and other surface drains at eight locations must be ascertained. 

19.  Ground water monitoring minimum at 8 locations and near solid waste dump zone, Geological features and Geo-hydrological status of the study area are essential as also.  Ecological status (Terrestrial and Aquatic) is vital.

20.  A note on treatment of wastewater from different plants including coke oven plant, recycle and reuse for different purposes should be included.

21.  Action plan for solid/hazardous waste generation, storage, utilization and disposal particularly char and fly ash. Assurance that 100 % char will be used in the FBC boiler and copies of MOU regarding utilization of ash should be included.

22.  Generation and utilization of waste/fuel gases from DRI plant and their utilization in the CPP have to be set out.

23.  Risk assessment and damage control needs to be addressed.

24.  Occupational health of the workers needs elaboration.

25.  Green belt development plan in 33 % area and a scheme for rainwater harvesting have to be put in place.

26.  Socio-economic development activities need to be elaborated upon.

27.  A note on identification and implementation of Carbon Credit project should be included.

28.  An Action Plan for the implementation of the recommendations made for the Steel Plants in the CREP guidelines must be prepared.

29.  Total capital cost and recurring cost/annum for environmental pollution control measures should also be included.

30.  A tabular chart for the issues raised and addressed during public hearing/public consultation should be provided.

31.  Any litigation / court case pending against the proposal should also be included.

 

The Expert Committee (Industry) decided that PAs may be communicated the above ‘TORs’ for the preparation of EIA/EMP.  As soon as the draft EIA/EMP report is prepared as per the ‘General Structure of EIA’ given in Appendix III and IIIA in the EIA Notification, 2006, the same may be submitted by the PAs to the Karnataka Pollution Control Board (KPCB) for conducting public hearing as per EIA Notification, 2006.  On finalization of EIA/EMP prepared as per TORs addressing all concerns set out EIA/EMP should be submitted to the MOEF for prior environmental clearance.

4.12    Integrated Steel Plant (2.0 MTPA) at Sy. No. 156-196 & 316-38, Village Vanganuru and Sy. No. 178 A to 338 at Village Bandaladinne, Mandal Tadipatri, District Ananthapur, Andhra Pradesh by M/s Vasitva Ispat Ltd. (TOR)

         

            The project authorities and their consultant gave a detailed presentation on the salient features of the project and proposed environmental protection measures to be undertaken alongwith the draft Term of References for the preparation of EIA/EMP. All the integrated steel plants are listed at S.N. 3(a) under Category ‘A’ and appraised at the Central level. 

 

            M/s Vasitva Ispat Ltd. have proposed for the Integrated Steel Plant (2.0 MTPA) at Sy. No. 156-196 & 316-38, Village Vanganuru and Sy. No. 178 A to 338 at Village Bandaladinne, Mandal Tadipatri, District Ananthapur, A. P.  During presentation, PAs informed that they have acquired land for 2.0 MTPA but planning to install 0.45 MTPA in Phase-I. Total land recquired is 1,440 acres instead of 1437.93 acres proposed earlier. 1,000 acres out of 1,440 acres is already acquired. There will be 280 oustees due to acquisition of land. Vanganuru and Bandaladinne villages are located at 2 km. Total cost of the project is Rs. 800.00 Crores.  Following facilities will be provided:

 

S.N.

Facilities

Production capacity (MTPA)

 

1

Coke-oven batteries

0.20

2

Sinter Plant

0.45

3

Blast furnace

0.38

Pig casting machine (EOF)

4

EOF

0.41 (Liquid steel)

Ladle refining furnace

5

Billet caster

0.4 MTPA

Rolling mill for TMT

6

One rolling mill for structural steel

0.28

 

During presentation, PAs informed that following facilities will be installed:

 

S.N.

Facilities

Production capacity (MTPA)

 

1

Coke-oven batteries

0.275

2

Sinter Plant

0.64

3

Blast furnace

0.472

          Pig casting machine (EOF)

4

Energy Optimising Furnace (EOF)

0.45 Liquid steel

          Ladle refining furnace

5

Continuous Casting Machine

0.441

          Rolling mill for TMT

6

Rolling mill

0.305

          Captive Power Plant

7

Coke oven gas based

12 MW

8

BF gas based

8 MW

 

            Iron ore lumps (2,50,000 TPA), Iron ore fines (4,65,140 TPA), coking coal (3,67,481 TPA) Limestone (1,00,000 TPA), Dolomite (80,000 TPA), Scrap (19,000 TPA), Ferro Alloys (8,600 TPA), Burnt lime (36,000 TPA), Manganese ore (10,000 TPA) and quartzite (8,000 TPA) will be the raw materials required.

            Sinter (0.41 MTPA), lump iron ore (0.26 MTPA) will be used as raw material to produce hot metal (0.38 MTPA). 95 % Hot metal (0.36 MTPA) will be routed to EOF to produce liquid steel (0.41 MTPA) which will be sent to LRF & CCF to produce billets (0.40 MTPA).  Billets (0.12 MTPA) will be routed to rolling mill at Hyderabad and 0.28 MTPA at Tadipatri.  Hot metal will be used for pig casting.

Non-recovery type of coke oven batteries, sinter plant, blast furnace, pig-casting machine, EOF, ladle refining furnace, continuous casting machine, rolling mills will be installed. TMT bars, angles, channels, beams, flats (0.45 MTPA) in phase-I will be manufactured. In Phase-I, technological process route viz. (O-SP-BF-EOF-LRF-CCM-RM will be adopted. The main products will be rolled products viz. TMT bars, Angles, Channels, Beams, flats etc.

 

ESP will be provided to control dust and air pollution within 150 mg/Nm3.  The furnace stack emissions will be maintained within CPCB standards. Dust suppression system will be provided at raw material handling plant, conveyors; fugitive emissions control at BF-SMS etc., gas cleaning plant at sinter plant, BF, SMS etc, Coke oven gas will be burnt at the oven itself and waste heat will be used in generation of power. Fume extraction system consisting of hood, ducting, fan and stack will be provided to SMS.  GCP will be provided to BF and EOF.

Total ground water requirement is revised from 2.2 MGD to 2.4 MGD from Penna River during presentation. The wastewater generated will be treated in suitable treatment facilities and recycled back to the process and reused in green belt development and dust suppression at raw material handling system. Sewage will be treated in sewage treatment plant (STP). The wastewater from GCP will be sent to thickners for separation of slurry and clean water.  The slurry after drying will be sent to sinter plant.  Clean water will be recycled.  Scales and oil will be separated from water coming from CCM and rolling mill and recycled.

 

Raw material handling fines, product fines, ESP flue dust, sludge and slag will be generated as solid waste.  Iron ore fine, coke fines, limestone fines and burnt lime fine, mill scale, steel making slag, gas cleaning plant dust, ETP sludge etc. will be used in sinter plant.  EOF slag will be utilized to the maximum extent possible. Granulated BF slag (0.16 MTPA) will be used in Cement manufacture.

 

Greenbelt will be developed in 260 acres (23%) out of a total area of 1,440 acres but committee asked to do plantation in 33 % area.

 

            Out of total power (19 MW) requirement, 1 MW will be sourced from state grid.  However during presentation, PAs informed that power requirement will be 30 MW and will be met from auxiliary generation (20 MW) and Grid (8.0 MW). Power (20 MW) will be sourced from CPP utilizing coke oven (12 MW) and BF gases (8 MW). 

 

After deliberating on the facts presented the Expert Appraisal Committee (Industry) recommended the proposal for the preparation of EIA/EMP as per the following TORs :

1.      Present land use should be prepared based on satellite imagery.

2.      Location of national parks/wildlife sanctuary within 10 km. radius should specifically be mentioned.

3.      Permission and recommendations of the State Forest Department regarding impact of proposed expansion on the surrounding reserve forests, if any, should be included.

4.      Actual land requirement, classification of land, type of the land acquired/to be acquired, acquisition status etc. should be incorporated.

5.      An action plan for rehabilitation and resettlement as per the policy of the Govt. of A.P. covering all relevant aspects should be incorporated.

6.      Site-specific micro-meteorological data using temperature, relative humidity, hourly wind speed and direction and rainfall should be collected.

7.      A list of industries containing name and type in 25 km radius should be incorporated.

8.      Residential colony should be located in upwind direction.

9.      List of raw material required and source should be included.

10.  Manufacturing process details for all the plants viz. coke oven, sinter plant, blast furnace, pig-casting machine, EOF, ladle refining furnace, continuous casting machine, rolling mills etc. should be included.

11.  A chapter on type and full details of coke oven plant including pollution control methods and justification for installing non-recovery type of coke oven should be included.

12.  Ambient air quality at 8 locations within the study area of 10 km., aerial coverage from project site with one AAQMS in downwind direction should be carried out.

13.  The suspended particulate matter present in the ambient air must be analyzed for the presence of poly-aromatic hydrocarbons (PAH), i.e. Benzene soluble fraction.  Chemical characterization of RSPM and for incorporating of RSPM data.

14.  Impact of the transport of raw material and finished product on the surrounding environment should be assessed and provided

15.  Determination of atmospheric inversion level at the project site and assessment of ground level concentration of pollutants from the stack emission based on site-specific meteorological features. Air quality modeling for steel plant for specific pollutants needs to be done. 

16.  Plant-wise air pollution control measures proposed for the control of gaseous emissions from all the sources should be incorporated.

17.  A note on control of fugitive and secondary emissions from as per CPCB guidelines from all the sources should be incorporated.

18.  One season data for gaseous emissions during winter season is necessary.

19.  Permission for the drawl of 2.4 MGD water from Penna River / bore wells from the concerned department and water balance data including quantity of effluent generated, recycled and reused and discharged should be provided. Methods adopted/to be adopted for the water conservation.

20.  Surface water quality of nearby rivers (60 m upstream and downstream) and other surface drains at eight locations must be ascertained. 

21.  Ground water monitoring minimum at 8 locations and near solid waste dump zone, Geological features and Geo-hydrological status of the study area are essential as also.  Ecological status (Terrestrial and Aquatic) is vital.

22.  A note on treatment of wastewater from different plants including coke oven plant, recycle and reuse for different purposes should be included.

23.  Action plan for solid/hazardous waste generation, storage, utilization and disposal particularly char and fly ash.

24.  MOU signed with the Cement manufacturers for utilizing granulated BF slag should be included.

25.  Generation and utilization of waste/fuel gases from coke oven and BF plant and their utilization in the CPP have to be set out.

26.  Risk assessment and damage control needs to be addressed.

27.  Occupational health of the workers needs elaboration.

28.  Green belt development plan in 33 % area and a scheme for rainwater harvesting have to be put in place.

29.  Socio-economic development activities need to be elaborated upon.

30.  A note on identification and implementation of Carbon Credit project should be included.

31.  An Action Plan for the implementation of the recommendations made for the Steel Plants in the CREP guidelines must be prepared.

32.  Total capital cost and recurring cost/annum for environmental pollution control measures should also be included.

33.  A tabular chart for the issues raised and addressed during public hearing/public consultation should be provided.

34.  Any litigation / court case pending against the proposal should also be included.

 

The Expert Committee (Industry) decided that PAs may be communicated the above ‘TORs’ for the preparation of EIA/EMP.  As soon as the draft EIA/EMP report is prepared as per the ‘General Structure of EIA’ given in Appendix III and IIIA in the EIA Notification, 2006, the same may be submitted by the PAs to the A.P. Pollution Control Board (APPCB) for conducting public hearing as per EIA Notification, 2006.  On finalization of EIA/EMP prepared as per TORs addressing all concerns set out EIA/EMP should be submitted to the MOEF for prior environmental clearance.

 

              

4.13     Integrated Steel Plant (1.1 MTPA) alongwith Captive Power Plant (50 MW) at Block Neersa, District Dhanbad, Jharkhand by M/s Adhunik Corporation Ltd.

 

               Project authorities didn’t attend the meeting and it was decided that proposal should be considered afresh whenever requested by the PAs.

 

 

4.14        Integrated Steel Plant (0.3 MTPA, Sponge Iron, Pelletization Plant, Beneficiation Plant, Captive Mine, Beneficiation and Captive Power Plant (60 MW) at Gram Tarpongi, Tehsil Dharsiwa, District Raipur, Chhattisgarh by M/s Euro Pratik Ispat Pvt. Ltd.

 

            Project authorities didn’t attend the meeting and it was decided that proposal should be considered afresh whenever requested by the PAs.

 

4.15     Expansion of Steel Plant by installing Induction Furnace (2x15 T) alongwith Continuous Casting Machine (1x2 Strands) at P-3513, Kanjilal Avenue, Durgapur, District Burdwan, West Bengal by M/s Bhagat Jee Steels Pvt. Ltd. (EC)

The project authorities and their consultant gave a detailed presentation on the salient features of the project and proposed environmental protection measures to be undertaken alongwith the draft Term of References for the preparation of EIA/EMP. All the Induction Furnaces (< 15 TPH) are kept under Category ‘A’ and appraised at the Central level. The proposed induction furnace is of 2x15 TPH capacity. Durgapur critically polluted area is located at a distance of 1 km from the project site.

            M/s Bhagat Jee Steels Private Limited has proposed to expand the existing steel plant by installing Induction Furnace (2x 15T) alongwith Continuous Casting Machine (1x2 Strands) at P-3513, Kanjilal Avenue (Small Industrial Area developed by Asansol Durgapur Development Authority), Durgapur, District Burdwan, West Bengal.  The proposed IF alongwith CCM will be set up within the premises of existing plant having an area 5 acres. River Damodar flows at a distance of 5 km from the proposed project site.  Durgapur is located at a distance of 1 km from the project site. No National park/ Reserve Forest / Wildlife Sanctuary is located with in 10 km radius of the project site.  Total cost of the proposed expansion will be Rs. 2,155.23 Lakhs. Rs. 200.00 Lakhs and Rs. 20.00 Lakhs are earmarked towards total capital cost and recurring cost/annum for environmental pollution control measures.

           

            PAs informed to the Committee that total production of ingots is 23,040 TPA from Induction Furnace (1x3T & 1x5T). After installation of another Induction Furnace (7 T), the production capacity will be 43,200 TPA (23,040 TPA + 20,160 TPA). After commissioning of the proposed Induction Furnace (2x15 T) with CCM, the total production of the plant will be 1,29,600 TPA (43,200 TPA + 86,400 TPA).

 

Facilities

Existing

Proposed expansion

Induction Furnace

 1x3 T & 1x5 T

1x7 T

 2x15 T

Continuous Casting Machine

--

1x2 Strands

 

Raw materials required will be Sponge Iron (83,279 TPA), M.S. Scraps (20,225 TPA), Ferro Manganese/Silico Manganese (450 TPA), Ferro Silicon (450 TPA), Aluminium Shots (12.5 TPA).

 

The process involves the charging of raw materials consisting mainly of Sponge Iron, Scrap etc. into the Crucible of Induction Furnace at a high temperature of 15500C. Sponge iron is sandwiched between scraps in the crucible and agitation of furnace is so high that the Sponge Iron takes little time to attain molten state. As soon as the mix charge is melted, necessary Ferro alloys and de-oxidizers are added.  The liquid metal is poured in slag pot whereby through centre column, bottom plate, the metal is passed in C.I. Duplex Ingot Moulds fitted above the bottom plate. The casted Ingots will be carried out by EOT crane.

 

Emissions from Induction furnace will be controlled by bag filters. Dry fogging system will be provided at Raw material handling area and material transfer points to control fugitive emissions. Dust collected from dust control systems will beused in land/road development as boulders. Dust collected from bag filter will be sent to sinter plants for recycling. Induction furnace will be provided with independent Spark arrestor, Bag filter & I D fan. Telescopic fume collection hood would be provided at the top of furnace. Flue gases from the furnace will be passed through a chimney of adequate height.  Fugitive emissions from raw material handling, conveying and screening operations will be controlled by bag filters. Clean BOF gas will be used as a gaseous fuel in the steel plant. Dust extraction system will be provided at the torpedo ladle hot metal discharging areas to avoid high fugitive emissions during unloading of hot metal. Particulate matter from hot metal pre-treatment will be controlled by providing fabric filters.

Water requirement of 40 KLD instead of 1,000 KLD proposed earlier, will be supplied by Durgapur Projects Limited. Cooling water will be recycled after settling.  Water from the scrubbing system will be recycled. No liquid effluent will be discharged from the process. Domestic wastewater will be discharged through septic tank followed by soak pit and used for greenbelt.

 

Slag generated (6,900 TPA) will be used for land levelling and compacting of roads etc. Bag filter dust (430 TPA) will be used in sinter plant. Mill scale (90 TPA) will be used in land development. Steel scrap (3,600 TPA) will be re-used in steel melting unit. All the wastes from the pollution control systems or treatment units will be re-used or recycled.

 

          Noise will be generated during construction work due to movement of cranes, bulldozers, trucks, and due to piling job and traffic movement and mainly from Induction furnace. High noise prone areas will be earmarked and necessary care will be taken to minimize the noise. Ear plugs or Ear muffs will be provided to employees working in noise prone areas.

 

Out of 5 acres land area, greenbelt will be developed in 0.75 acres in addition to the existing 0.5 acres. Total green belt area will be 1.25 acres, however, the Committee emphasized to cover 33 % area by the green belt.  Power requirement of 15 MW will be sourced from Durgapur Projects Limited.

 

            PAs informed to the Committee that project is located in the notified industrial area and hence no public hearing is required.  However, Committee asked PAs to submit ‘proof’ in this regard to take further decision regarding public hearing.

 

After deliberating on the facts presented, the Committee recommended the proposal for the preparation of environment management plan (EMP) incorporating the following information which will be internally examined before considering for final environmental clearance:

1.      A copy of the notification issued by the State Govt. indicating location of the project in notified industrial area.

2.      A note on performance of existing plant.

3.      Data on existing ambient air quality, stack emissions and fugitive emissions and pollution control measures proposed to control air emissions.

4.      Total water requirement alongwith source, water balance cycle, treatment methods adopted and disposal, if any.

5.      A note on solid / hazardous waste generation, management, recycle/reuse and disposal.

6.      Action plan to develop green belt development in 33 % area.

4.16     Expansion of Mini Steel Plant by installation of Ferro Alloy Plant (30,000 TPA) and Captive Power Plant (25 MW) at Jharsuguda Road, District Raigarh, Chhattisgarh by M/s R. R. Energy Ltd. (TOR)

The project authorities and their consultant gave a detailed presentation on the salient features of the project and proposed environmental protection measures to be undertaken alongwith the draft Term of References for the preparation of EIA/EMP. All the steel plants are kept under Category ‘A’ and appraised at the Central level.

 

            M/s R. R. Energy Ltd. have proposed for expansion of Mini Steel Plant by installation of Ferro Alloy Plant (10.8 MVA, 30,000 TPA) and Coal/rejects based Captive Power Plant (25 MW) at Jharsuguda Road, District Raigarh, Chhattisgarh. PAs confirmed that proposed area is not banned by the State Govt of Chhattisgarh.  Total existing project area is 17.072 ha and 4 ha. will be acquired for the expansion  project for ash dyke purpose. Gajmer RF (3.5 km, NE), Udanaa RF (9 km N) and Boirdadar RF (9 km. NE) are located within 10 km. area. Total cost of the project is Rs. 93.10 Crores.  Rs. 10.71 Lakhs and Rs. 1.352 Lakhs will be earmarked towards total capital cost and recurring cost/annum for environmental pollution control measures.

 

During expansion, Ferro Alloy Plant (10.8 MVA), Thermal Captive Power Plant (25 MW) and Bio-mass based power plant (14 MW) will be installed.  Following are the details of existing and proposed plants.

 

S.N.

Name of product to be expanded

Proposed Capacity Expansion

Proposed facility :

 

1

Ferro Alloys plant

3x3.6 MVA (Ferro/Silico Manganese; 30,000 TPA)

2

Captive Power Plant

25 MW (Coal/rejects based Thermal Power Plant)

3

Bio-Mass Power Plant (existing 14 MW)

1 MW Additional through efficiency improvement

Existing facility :

4

Biomass Power Plant

14 MW (Rice Husk based Thermal Power Project)

5

Semi Finished Steel Plant under implementation

6x16 T (Induction Furnace with CCM 1,00,000 TPA)

6

Fly Ash Bricks Plant

19,800 TPA

  

            Manganese ore, coke, Dolomite, Limestone and paste will be used as raw materials.  Coal (1,58,400 TPA), washery rejects from the coal washeries, char, dolochar will be used as fuel to generate power (25 MW).

            During expansion, ferro alloy plant (3x3.6 MVA) to produce 30,000 TPA ferro alloy such as ferro Manganese, Silico Manganese, Ferro chrome or Ferro silicon will be installed.   CPP (25 MW) with AFBC route using coal, char, dolochar and coal shales to the existing bio-mass based Power Plant (14 MW) will be carried out to improve the efficiency to produce 25 MW power from bio-mass based power plant.  Capacity of the biomass based CPP will be enhanced from 14 MW to 15 MW by implementing energy efficiency measures in the existing boiler and turbine itself without any change in the equipment or capital investment.  Ingots and Billets (1,00,000 MTPA) from Sponge Iron, Pig iron, mild steel scrap are manufactured presently.  Fly ash brick manufacturing facility (19,800 MTPA) also exists.

 

Gaseous emissions will be generated form CPP and ferro alloy plant.  High efficiency ESP will be provided to CPP to control emissions within 50 mg/Nm3.  Bag filters with conveyor will be provided at conveyors and all the transfer points.  Bag filters will be provided to ferro alloy plant and induction furnace.  Dust extraction system with bag filters will be provided to control fugitive emissions due to unloading and handling of coal and ash.

 

Total ground water requirement is revised to 247 m3/day instead of 400 m3/day proposed earlier, including 100 m3/day for the existing plant and have applied for the  permission for drawl of 300 m3/day to the State Water resources Department. Air-cooled condenser will be installed to minimize water consumption.  R.O. system will be installed for DM Water generation.  Effluent treatment plant will be installed to treat back wash and pond sedimentation.  All the treated wastewater will be neutralized and used for Ferro alloys slag quenching, coal moistening, fly ash brick making and green belt development.  ‘Zero’ discharge will be adopted.  The sewage effluent will be treated in Septic tank followed by soak pit and used for irrigation purpose.

 

Fly ash generation will increase from 22,000 TPA to 1,14,500 TPA whereas slag generation will increase from 10,000 TPA to 24,000 TPA. Fly ash from ESP will be used in existing fly ash brick plant to manufacture bricks and also gives to cement plants for PPC manufacturing.  Slag from ferro alloy plant after granulation and bottom ash will be used for filling low lying areas.  Used / waste oil will be sold to registered recyclers.

 

            Greenbelt is proposed in 5.5 ha out of total 21.071 ha. but committee insisted for 33 % area for the green belt development. Coal and washery rejects from coal washeries, char, dolochar from sponge iron plants located in district will be used as fuel to generate power (25 MW).  15 MW power will be used for ferro alloy plant.

After deliberating on the facts presented before the Expert Appraisal Committee (Industry) recommended the proposal for the preparation of EIA/EMP as per the following TORs:

1.      Present land use based on satellite imagery should be incorporated.

2.      Site-specific micro-meteorological data using temperature, relative humidity, hourly wind speed and direction and rainfall is necessary.

3.      Location of National Park and Wild life sanctuary within 10 Km radius of the project should be included.

4.      Permission and recommendations of the State Forest Department regarding impact of proposed expansion on the surrounding reserve forests viz. Gajmer RF (3.5 km, NE), Udanaa RF (9 km N) and Boirdadar RF (9 km. NE) etc. should be included.

5.      List of raw material required and source should be included.

6.      Design details of Submerged Arc Furnace, Bio-mass based Power Plant and Captive Power Plant and manufacturing process details should be included.

7.      Ambient air quality at 8 locations within the study area of 3 km., aerial coverage from project site should be included. Location of one AAQMS should be in downwind direction.

8.      Ambient air quality modeling for Ferro Alloy plant should be included. 

9.      One season data for gaseous emissions and inclusion of existing emission data should be ensured.

10.  An action plan to control and monitor secondary fugitive emissions as per CPCB guidelines should be included.

11.  Determination of atmospheric inversion level at the project site and assessment of ground level concentration of pollutants from the stack emission based on site-specific meteorological features.

12.  ‘Permission’ for the drawl of 247 m3/day ground water from SGWB / CGWA should be obtained and incorporated. Water balance cycle data including quantity of effluent generated, recycled and reused and discharged should be incorporated.

13.  Ground water monitoring minimum at 8 locations and also near solid waste dump zone should be carried out. Geological features and Geo-hydrological status of the study area and ecological status (Terrestrial and Aquatic) should be included.

14.  Solid waste generation, storage, utilization and disposal should be included particularly related to the slag, R.O. reject and fly ash. 

15.  End use of solid waste and its composition should be covered.  Toxic metal content in the waste material and its composition should also be incorporated particularly of slag.

16.  Provision of Toxic Chemical Leachability Potential (TCLP) test for the slag and its end use should be included.  Proposal for the proper disposal of slag should be mentioned.

17.  Commitment that no Ferro chrome will be manufactured without prior approval of the Ministry.

18.  Risk assessment and damage control should be included.

19.  Occupational health of the workers should be incorporated.

20.  An action plan to develop green belt in 33 % area should be included.

21.  Scheme for rainwater harvesting should be incorporated.

22.  Socio economic development activities should be in place.

23.  Total capital cost and recurring cost/annum for environmental pollution control measures should also be included.

24.  A tabular chart for the issues raised and addressed during public hearing/public consultation should be provided.

25.  Any litigation / court case pending against the proposal should also be included.

26.  Compliance to the recommendations mentioned in the CREP guidelines should be included.

            The Expert Appraisal Committee (Industry) decided that PAs may be communicated the above ‘TORs’ for the preparation of EIA/EMP.  As soon as the draft EIA/EMP report is prepared as per the ‘General Structure of EIA’ given in Appendix III and IIIA in the EIA Notification, 2006, the same may be submitted by the PAs to the Chhattisgarh Environment Conservation Board (CECB) for conducting public hearing as per EIA Notification, 2006.  On finalization of EIA/EMP prepared as per TORs addressing all concerns set out in EIA/EMP should be submitted to the MOEF for prior environmental clearance.

 

 

4.17     Expansion of Steel Plant at Village Marakuta & Pandari Pathar, Tehsil and District Jharsuguda, Orissa by M/s Action Ispat & Power (P) Ltd. (TOR)

 

The project authorities and their consultant gave a detailed presentation on the salient features of the project and proposed environmental protection measures to be undertaken alongwith the draft Term of References for the preparation of EIA/EMP.   All the Integrated Steel Plants are listed S.N. 3(a) under category ‘A’ and appraised at the Central level.

 

            M/s Action Ispat & Power (P) Ltd. have proposed for the expansion of Steel Plant at Village Marakuta & Pandari Pathar, Tehsil and District Jharsuguda, Orissa.  Total existing land is 350 acres and 600 acres adjacent to the existing land will be used for expansion plant. However during presentation, PAs informed that total land required for the proposed expansion will be 20 acres in addition to the existing 350 acres. Therefore, total project area will be 370 acres.  Total cost of the project is Rs. 284.00 Crores.  Rs. 10.00 Crores and Rs. 1.00 Crores will be earmarked towards total capital cost and recurring cost/annum for environmental pollution control measures.  Environmental clearance for the existing plant is accorded by the Ministry in September, 2008.  Following are the details of existing and proposed facilities:

 

S.N.

Plant

Facilities

Production (TPA)

(A)  Existing Phase-I

1

DRI

4x350 TPD

 

2

Blast Furnace

4x100 TPD

 

3

Steel Melting Shop (SMS)

1x350 M3

3,00,000

 

Induction Furnace

4x12T

8,00,000

 

Arc Furnace

1 x 70 T

 

 

LRF

1x100 T

 

 

CCM

1x2 Strand; 2x3 Strand

 

4

Re-rolling Mill

 

5,00,000

5

Coal washery

450 TPH

 

6

Captive Power Plant

 

 

 

WHRB

40 MW

148 MW

 

FBB

108 MW

(B)  Proposed : Phase-II

1

Mini Blast Furnace

1 x 150 m3

1,00,000

2

Coke Oven Plant

--

3,00,000

3

Sinter Plant

1 x 25 m3

4,00,000

4

Ferro Alloy Plant

4x9 MVA

57,000

 

            During presentation, PAs informed that following will be the existing and proposed facilities:

 

Facilities

Existing & Phase-I

Phase-II expansion

Sponge Iron

1,800 TPD

--

Power Plant

WHRB

AFBC

 

40 MW

108 MW

--

 

Blast Furnace

1x350 m3

1x150 m3

SMS

8,00,000 TPA

--

Rolling Mill

5,00,000 TPA

--

Coal washery

450 TPH

--

Coke Oven plant

--

3,00,000 TPA

Annular Sinter Plant

--

4,00,000 TPA (1x25 m3)

Ferro Alloy Plant

--

57,000 TPA (4x9 MVA)

 

 

S.N.

Plant

Facilities

Production (TPA)

(C)  Existing Phase-I

1

DRI

4x350 TPD

 

2

Blast Furnace

4x100 TPD

 

3

Steel Melting Shop (SMS)

1x350 M3

3,00,000

 

Induction Furnace

4x12T

8,00,000

 

Arc Furnace

1 x 70 T

 

 

LRF

1x100 T

 

 

CCM

1x2 Strand; 2x3 Strand

 

4

Re-rolling Mill

 

5,00,000

5

Coal washery

450 TPH

 

6

Captive Power Plant

 

 

 

WHRB

40 MW

148 MW

 

FBB

108 MW

(D)  Proposed : Phase-II

1

Mini Blast Furnace

1 x 150 m3

1,00,000

2

Coke Oven Plant

--

3,00,000

3

Sinter Plant

1 x 25 m3

4,00,000

4

Ferro Alloy Plant

4x9 MVA

57,000

 

Iron ore fines (3,63,800 MT) Limestone (48,400 MT), Dolomite (2,96,000 MT) Coke Breeze (49,700 MT) for the Sinter Plant; Dry coal (3,90,000 TPA) for coke oven plant, iron ore lump (51,500 MT), Sinter (1,14,000 MT), Belt Coke (61000 MT), Quartzite (40,800 MT), Coal dust (21,000 MT); Ferro Alloy (Mn Ore 68,400 MT), Fe-Mn Slag (45,600 MT) Quartz (14,250 MT) Coal Breeze (22,800 MT), Coal (30,210 MT) and Dolomite (2,850 MT)  will be used as raw materials.

In the proposed expansion, Pig iron through Blast Furnace, Coke through coke oven plant, Ferro alloys (Fe-Si & Fe-Mn) through submerged Arc Furnace and Sinter Plant to utilize iron ore fines will be installed.

In coke making process, bituminous coal will be fed to series of oven in absence of O2.  Volatile compounds are driven off and combustible gases and other by-products will be recovered.  Coke oven gas contains tar, ammonia, Pnehol Naphthalene, light oil and sulfur which has to be removed before using coke gas as fuel for heating the ovens.  The solid carbon remaining in the oven will be coke, which is quenched with water or by circulating an inert gas (N2) through dry quenching.  ESP will be provided to coke oven to remove tar.  Ammonia will be separated from the tar decanter and sent to waste water treatment after ammonia recovery.  Nephthlene will be removed in the separator.  Light oil will be removed  from the coke oven gas and will be  fractioned to recover  benzene, toluene and Xylene. Coke breeze will be reused in sinter plant.

 

Bag filters/fume extraction system and chimney will be provided to Coke oven plant. Gas cleaning plant, Dust extraction and suppression system will be provided to Ferro alloy plant. Hot gas from Blast furnace will be taken into WHRB and then passed through ESP/bagfilters for control of dust. ESP and dry fog dust suppression system will be provided to the proposed Sinter plant. Bag filters and cyclone will be provided to control dust emission in Raw material handling areas.

 

Total water requirement from the confluence of IB and Bhedan River will be 581 m3/hr.  Closed-circuit re-circulation system will be installed. Zero discharge will be adopted. Liquid effluent will be treated in ETP for suspended solids, PH and oil and grease and treated wastewater will be recycled / reused for slag quenching, dust suppression and green belt development etc.

 

Coal char (760 TPD) will be used as fuel in FBB. Fly ash (2646 TPD) and BF slag (181 TPD) will be supplied to OCL (India) Ltd. IF/AF Slag, Ferro alloys slag will be used for road repairing/ for filling low lying area. Coal washery rejects /Fines will be directly used in FBB. BF slag will be further used for manufacturing ceramics.  FA slag will be used for road repairing.  Coal tar will be used for making black top road.  Sludge from wastewater treatment plant will be disposed off at designated disposal site.  Coke breeze will be used in sinter plant.

 

Out of 370 acres of entire project area, greenbelt will be developed in 112 acres. Silencers/ Mufflers will be provided to employees working in high noise generating areas. Power requirement of 41 MW for the proposed expansion will be met from Captive generation as well as from State grid. Furnace oil (50 KLPA) will be used as fuel.

 

After deliberations, PAs requested Committee for the exemption from the public hearing due to expansion of the proposal in the same campus.  The Committee informed to the PAs that it is a major expansion involving installation of blast furnace, coke oven, ferro alloy plant, sinter plant etc. and public hearing is necessary.  PAs also requested to consider the proposal for ferro alloy plant only and other items including blast furnace, coke oven and sinter plant separately.  The Committee asked PAs to submit the proposal independently alongwith Form I and Pre-feasibility Report and will be considered in next meeting. The Committee also agreed to use the data collected last year for the existing plant for which environmental clearance was accorded by the Ministry in September, 2008.  The EIA/EMP should include description of all the existing and proposed plants and data on air, water and solid waste should be updated to assess cumulative impact of the existing and proposed units. The proposal is differed till the revised proposal is submitted.

4.18     Steel Plant (Sponge Iron 1,20,000 TPA, Liquid Steel 1,25,000 TPA, Billets 1,20,000 TPA and Captive Power Plant (12 MW) at Village Benipur, District Purulia, West Bengal by M/s AIC Iron Industries Pvt. Ltd. (TOR)

The project authorities and their consultant gave a detailed presentation on the salient features of the project and proposed environmental protection measures to be undertaken alongwith the draft Term of References for the preparation of EIA/EMP. All the Integrated Steel plants are listed S.N. 3(a) under category ‘A’ and appraised at the Central level.

 

            M/s AIC Iron Industries Pvt. Ltd. have proposed for the Steel Plant  (Sponge Iron 1,20,000 TPA, Liquid Steel 1,25,000 TPA, Billets 1,20,000 TPA and Captive Power Plant (12 MW) at Village Benipur, District Purulia, West Bengal. Total land acquired for the proposed project is 21 acres and 29 acres is yet to be acquired. Therefore, total land area is 50 acres. Panchet RF, Bheti RF and Muktipur RF are located within 10 km radius. Total cost of the project is Rs. 110.00 Crores. Rs. 9.0 Crores and Rs. 0.20 Crores will be earmarked towards total capital cost and recurring cost/annum for environmental pollution control measures. Following facilities will be installed.

 

Units

Capacity

DRI Plant

4x100 TPD

Captive Power Plant

12 MW

Induction Furnace

2x15 Tonne

LRF

2x15  Tonne

Continuous casting  for billets

 

 

            Following will be manufactured :

 

Unit

Capacity

DRI Plant

1,20,000 TPA

Power Plant

         WHRB (2x4 MW)

         AFBC  (1x4 MW)

 

8 MW

4 MW

Liquid Steel

1,25,000 TPA

Continuous casting for billets

Finished Billet 1,20,000 TPA

 

DRI Unit, Steel Melting shop (SMS), continuous casting machine (CCM) and Captive Power Plant (CPP) will be installed.  The sponge iron will be manufactured through DRI kilns, which will be used for making steel in Induction furnace.  Waste heat of kiln gases will be used in WHRB – CPP.

 

ESP will be provided to Captive power plant to restrict the particulate matter within 100 mg/Nm3. The waste gases of DRI kiln will be used in WHRB based CPP (2x4 MW).  The gases from DRI kiln will pass through dust settling chamber (DSC) and after burning chamber (ABC) before being used in WHRB.  The fugitive dust emissions due to iron ore fines, coal fines and dolomite fines from the stock piles of raw material will be controlled by dust suppression system by water sprinkling. Primary emissions from the Induction furnace and Ladle furnace will be collected by fume extraction systems and taken through ductwork to a bagfilter. Suitable canopy willl be provided to induction furnace to minimize the fugitive emission. Dust extraction systems comprising of bag filters will be installed at material transfer points.

 

Total water requirement from River Damodar will be 664 m3/day instead of 4,735 m3/d proposed earlier and PAs have applied for permission of the same.  Effluent treatment plant will be installed to remove suspended solids, neutralization of acidic water from DM plant and removal of oil and grease etc. PAs vide letter dated 28th August, 2008 informed that Zero effluent discharge will be maintained.

 

Major quantity of Char from DRI kiln will be used in AFBC based CPP (1x4 MW). Excess char will be disposed for brick manufacturing. Slag will be sent to storage yard where it will be disoosed suitably. Ash, slag, dust, refractory debris, sludge etc. will be generated as solid waste.  Dense phase ash handling system will be adopted.

 

Greenbelt will be developed in 33% of plant area.

           

After deliberating on the facts presented the Expert Appraisal Committee (Industry) recommended the proposal for the preparation of EIA/EMP as per the following TORs :

1.      Present land use should be prepared based on satellite imagery.

2.      Location of national parks / wildlife sanctuary within 10 km. radius should specifically be mentioned.

3.      ‘Proof’ / ‘Notification’ issued by the State Govt. if the project is located in notified industrial area.

4.      Permission and recommendations of the State Forest Department regarding impact of proposed expansion on the surrounding reserve forests viz. Panchet RF, Bheti RF and Muktipur RF should be included.

5.      Actual land requirement, classification of land, acquisition status, rehabilitation and resettlement as per the policy of the Govt. of West Bengal should be incorporated.

6.      Site-specific micro-meteorological data using temperature, relative humidity, hourly wind speed and direction and rainfall should be collected.

7.      A list of industries containing name and type in 25 km. radius should be incorporated.

8.      Residential colony should be located in upwind direction.

9.      List of raw material required and source should be included.

10.  Manufacturing process details for all the plants viz. DRI Plant, Captive Power Plant, Induction Furnace, LRF, CCM  etc. should be included.

11.  Ambient air quality at 8 locations within the study area of 10 km., aerial coverage from project site with one AAQMS in downwind direction should be carried out.

12.  The suspended particulate matter present in the ambient air must be analyzed for the presence of poly-aromatic hydrocarbons (PAH), i.e. Benzene soluble fraction.  Chemical characterization of RSPM and for incorporating of RSPM data.

13.  Impact of the transport of raw material and finished product on the surrounding environment should be assessed and provided

14.  Determination of atmospheric inversion level at the project site and assessment of ground level concentration of pollutants from the stack emission based on site-specific meteorological features. Air quality modeling for steel plant for specific pollutants needs to be done. 

15.  Plant-wise air pollution control measures proposed for the control of gaseous emissions from all the sources should be incorporated.

16.  A note on control of fugitive and secondary emissions from as per CPCB guidelines from all the sources should be incorporated.

17.  One season data for gaseous emissions during winter season is necessary.

18.  Permission for the drawl of 4,735 water from River Damodar from the concerned department and water balance data including quantity of effluent generated, recycled and reused and discharged should be provided. Methods adopted/to be adopted for the water conservation.

19.  Surface water quality of nearby rivers (60 m upstream and downstream) and other surface drains at eight locations must be ascertained. 

20.  Ground water monitoring minimum at 8 locations and near solid waste dump zone, Geological features and Geo-hydrological status of the study area are essential as also.  Ecological status (Terrestrial and Aquatic) is vital.

21.  A note on treatment of wastewater from different plants including coke oven plant, recycle and reuse for different purposes should be included.

22.  Action plan for solid/hazardous waste generation, storage, utilization and disposal particularly char and fly ash. Assurance that 100 % char will be used in the FBC boiler and copies of MOU regarding utilization of fly ash should be included.

23.  Risk assessment and damage control needs to be addressed.

24.  Occupational health of the workers needs elaboration.

25.  Green belt development plan in 33 % area and a scheme for rainwater harvesting have to be put in place.

26.  Socio-economic development activities need to be elaborated upon.

27.  A note on identification and implementation of Carbon Credit project should be included.

28.  An Action Plan for the implementation of the recommendations made for the Steel Plants in the CREP guidelines must be prepared.

29.  Total capital cost and recurring cost/annum for environmental pollution control measures should also be included.

30.  A tabular chart for the issues raised and addressed during public hearing/public consultation should be provided.

31.  Any litigation / court case pending against the proposal should also be included.

 

The Expert Committee (Industry) decided that PAs may be communicated the above ‘TORs’ for the preparation of EIA/EMP.  As soon as the draft EIA/EMP report is prepared as per the ‘General Structure of EIA’ given in Appendix III and IIIA in the EIA Notification, 2006, the same may be submitted by the PAs to the West Bengal Pollution Control Board (WBPCB) for conducting public hearing as per EIA Notification, 2006.  On finalization of EIA/EMP prepared as per TORs addressing all concerns set out EIA/EMP should be submitted to the MOEF for prior environmental clearance.

 

 

4.19        Integrated Steel Plant  [Pig Iron (500 TPD), Sponge Iron (600 TPD), M.S. Bars / Structures (1,200 TPD), Ingots Billets (7,200 TPD)] alongwith Captive Power Plant (50 MW) at Sy. No. 32, 57-60, Village Wadaparthi, Mandal Bhongir, District Nalgonda, Andhra Pradesh by M/s Novus Steels and Infrastructure Pvt. Ltd. (TOR)

The project authorities and their consultant gave a detailed presentation on the salient features of the project and proposed environmental protection measures to be undertaken alongwith the draft Term of References for the preparation of EIA/EMP. All the Integrated Steel plants are listed S.N. 3(a) under category ‘A’ and appraised at the Central level.

 

            M/s Novus Steels and Infrastructure Pvt. Ltd. have proposed for the Integrated Steel plant  Pig Iron (500 TPD), Sponge Iron (600 TPD), M.S. Bars / Structures (1,200 TPD), Ingots Billets (7,200 TPD) alongwith Captive Power Plant (50 MW) at Sy. No. 32, 57-60, Village Wadaparthi, Mandal Bhongir, District Nalgonda, A. P.  Total land acquired is 41.04 acres. Total cost of the project is Rs. 700.00 Crores. Following will be installed and manufactured:

 

S.N.

Units

Capacity

Products

Production (TPD)

1

Blat Furnace

2x125 m3

Pig Iron/Molten metal

500 

2

Sponge Iron

3x100 TPD

Sponge Iron

300 

3

Re-rolling Mill

4x300 TPD

M.S. Bars

1,200 

4

Induction Furnace

6 TPH x 6 with 12 crucibles one as stand-by

Ingot / Billets

7,200 

 

During presentation, PAs informed that following will be installed and manufactured:

 

S.N.

 

Capacity

Products

Production (TPD)

1

Blat Furnace

2x128 m3

Pig Iron/Molten metal

500 

2

Sponge Iron

6x100 TPD

Sponge Iron

600 

3

Re-rolling Mill

4x300 TPD

M.S. Bars

1,200 

4

Induction Furnace

10 TPH x 6 with 12 crucibles one as stand-by

Ingot / Billets

7,200 

5

Captive Power Plant

AFBC   -1x27 TPH

WHRB -1x10 TPH

Power

50 MW

           

Hot metal will be produced in Blast furnace in counter current reactor where solid descends and hot gases ascend.  Iron ore / lumps will be reduced in DRI kiln to produce sponge iron.  In re-rolling mill, raw material will be fed to pre-heating furnace at 1150-11800C to get M.S. Bars / structures.  Sponge iron / scrap, fluxes, and ferro alloys will be used in IF at 16500C to get the molten metal which will be refined in ladle refining furnace (LRF) and then transported to continuous casting machine (CCM) to cast molten metal into ingots / billets.

 

ESP will be provided to Sponge iron plant and FBC boiler to control particulate emission within 100 mg/Nm3.  Bag filters will be provided to product separation/storage house, stock house, cooler discharge building, intermediate bins, coal injection building, coal and Iron ore crusher/screen house, etc. of Sponge iron plant. The hot gases from the IF will be controlled by special de-dusting equipment and then cooled in ventury scrubber and let out to atmosphere through a chimney.

 

Total water requirement from APIIC will be 798 m3/day. Heat exchanger will be provided for cooling.  No sludge or liquid effluent is expected. Total power consumption will be 21.7 KW. Coal (143 TPD) will be used as fuel in FBC alongwith Coal char.

 

After deliberating on the facts presented the Expert Appraisal Committee (Industry) recommended the proposal for the preparation of EIA/EMP as per the following TORs :

 

1.      Present land use should be prepared based on satellite imagery.

2.      Location of national parks / wildlife sanctuary within 10 km. radius should specifically be mentioned.

3.      Permission and recommendations of the State Forest Department regarding impact of proposed expansion on the surrounding reserve forests, if any should be included.

4.      Actual land requirement, classification of land, acquisition status, rehabilitation and resettlement as per the policy of the Govt. of A. P. should be incorporated.

5.      Site-specific micro-meteorological data using temperature, relative humidity, hourly wind speed and direction and rainfall should be collected.

6.      A list of industries containing name and type in 25 km radius should be incorporated.

7.      Residential colony should be located in upwind direction.

8.      List of raw material required and source should be included.

9.      Design details and manufacturing process details for all the plants viz. Blast Furnace, Sponge Iron Plant, Induction Furnace, Re-Rolling Mill and Captive Power Plant (WHRB abd AFBC) etc. should be included.

10.  Break-up of annual capacity of all the plants should be incorporated.

11.  Ambient air quality at 8 locations within the study area of 10 km., aerial coverage from project site with one AAQMS in downwind direction should be carried out.

12.  The suspended particulate matter present in the ambient air must be analyzed for the presence of poly-aromatic hydrocarbons (PAH), i.e. Benzene soluble fraction.  Chemical characterization of RSPM and for incorporating of RSPM data.

13.  Impact of the transport of raw material and finished product on the surrounding environment should be assessed and provided

14.  Determination of atmospheric inversion level at the project site and assessment of ground level concentration of pollutants from the stack emission based on site-specific meteorological features. Air quality modeling for steel plant for specific pollutants needs to be done. 

15.  Plant-wise air pollution control measures proposed for the control of gaseous emissions from all the sources should be incorporated.

16.  A note on control of fugitive and secondary emissions from as per CPCB guidelines from all the sources should be incorporated.

17.  One season data for gaseous emissions during winter season is necessary.

18.  Permission for the drawl of 798 m3/day water from APIIC from the concerned department and water balance data including quantity of effluent generated, recycled and reused and discharged should be provided. Methods adopted/to be adopted for the water conservation.

19.  Surface water quality of nearby rivers (60 m upstream and downstream) and other surface drains at eight locations must be ascertained. 

20.  Ground water monitoring minimum at 8 locations and near solid waste dump zone, Geological features and Geo-hydrological status of the study area are essential as also.  Ecological status (Terrestrial and Aquatic) is vital.

21.  A note on treatment of wastewater from different plants, recycle and reuse for different purposes should be included.

22.  Action plan for solid/hazardous waste generation, storage, utilization and disposal particularly char and fly ash. Assurance that 100 % char will be used in the FBC boiler and copies of MOU regarding utilization of ash should be included.

23.  MOU signed with the Cement manufacturers for utilizing granulated BF slag should be included.

24.  Generation and utilization of waste/fuel gases from DRI and BF plant and their utilization in the CPP have to be set out.

25.  Risk assessment and damage control needs to be addressed.

26.  Occupational health of the workers needs elaboration.

27.  Green belt development plan in 33 % area and a scheme for rainwater harvesting have to be put in place.

28.  Socio-economic development activities need to be elaborated upon.

29.  A note on identification and implementation of Carbon Credit project should be included.

30.  An Action Plan for the implementation of the recommendations made for the Steel Plants in the CREP guidelines must be prepared.

31.  Total capital cost and recurring cost/annum for environmental pollution control measures should also be included.

32.  A tabular chart for the issues raised and addressed during public hearing/public consultation should be provided.

33.  Any litigation / court case pending against the proposal should also be included.

 

The Expert Committee (Industry) decided that PAs may be communicated the above ‘TORs’ for the preparation of EIA/EMP.  As soon as the draft EIA/EMP report is prepared as per the ‘General Structure of EIA’ given in Appendix III and IIIA in the EIA Notification, 2006, the same may be submitted by the PAs to the Andhra Pradesh Pollution Control Board (APPCB) for conducting public hearing as per EIA Notification, 2006.  On finalization of EIA/EMP prepared as per TORs addressing all concerns set out EIA/EMP should be submitted to the MOEF for prior environmental clearance.

4.20     Expansion of Steel Plant at Gopalpur, Bamunara Industrial Estate, Gopalpur, Durgapur, District Burdwan, West Bengal by M/s Shyam Steel Industries Ltd (TOR)

 Project authorities didn’t attend the meeting and it was decided that proposal should be considered afresh whenever requested by the PAs.

4.21     Expansion of Sponge Iron Plant (190 TPD to 290 TPD) and CPP (10 MW) at Angadpur, Durgapur, West Bengal by M/s Shyam Steel Industries Ltd. 

PAs informed vide letter dated 16th October, 2008 that they will not be going ahead with the proposed unit of 100 TPD.  Project authorities didn’t attend the meeting.  In view of the fact mentioned, file may be closed.

 

4.22     Sponge Iron Plant (66,000 TPA) alongwith Captive Power Plant (8 MW) at Survey No. 13, Village Nemakal, Mandal Bommanahal, District Ananthapur, Andhra Pradesh by M/s S.L.V. Steels and Alloys Private Limited (TOR)

 

            The project authorities and their consultant gave a detailed presentation on the salient features of the project and proposed environmental protection measures to be undertaken alongwith the draft Term of References for the preparation of EIA/EMP.  All the Sponge iron Plants with > 200 TPD have been listed at S.N. 3(a) under Category ‘A’ and appraised at the Central level.  Capacity of the proposed sponge iron plant is 200 TPD.

 

M/s S.L.V. Steels and Alloys Private Limited has proposed to set up a Sponge Iron Plant (66,000 TPA) alongwith Captive Power Plant (8 MW) at Survey No. 13, Village Nemakal, Mandal Bommanahal, District Ananthapur, A. P. Total land acquired for the proposed project will be 20.86 acres instead of 26.80 acres proposed earlier. Bellary RF (8.5 km NW), Hirehalu RF (9.8 km SW) and Mincheri RF (2.5 km NE) are located within 10 km radius of the proposed project. Hiredahalu is at a distance of 2.5 km from the proposed site. Interstate boundary of Andhra Pradesh and Karnataka is at a distance of 3 km from the proposed site. Total cost of the project is Rs. 61.60 Crores instead of Rs. 61.90 Crores proposed earlier.

 

Sponge Iron Kiln (2x100 TPD), WHRB (2x10 TPH) and FBC Boiler (1x30 TPH) will be installed. Rotary Kiln will be provided for reduction of Iron ore into Sponge Iron at a temperature of 10000C and 10500C using non-coking coal as reductant. The kiln discharge after cooling will be fed to magnetic separators to separate Sponge Iron from Char. Steam generated from WHRB and FBC boiler will be used to generate power in Power plant.

Iron ore (400 TPD), Coal (200 TPD), and Dolomite (8 TPD) will be the raw materials required for Sponge Iron plant. Coal requirement for power plant will be 90 TPD).

 

Hot gases from the kiln will pass through a Dust settling chamber. Thereafter, the flue gases pass through an After burning chamber (ABC) where any combustibles present will be completely burnt in presence of excess air. The gases will then be led to a WHRB to generate steam for power generation. The gas will be cleaned in an ESP before letting them into the atmosphere through ID fan and a tall common stack. Flue gases from power plant will pass over various heat transfer surfaces to ESP and then finally discharged to chimney by ID fan. Fugitive dust will be collected by bag filters will be collected by bag filters at transfer points and by water sprinkling for transport related dust.  The kiln and boiler stack emissions will be maintained at APPCB standards. Bag filters will be provided to raw material crusher, coal junction point, stock house, cooler discharge and product house to control dust emissions.  Particulate emission from bag filters will be <50 mg/Nm3.

 

Total ground water requirement will be 170 KLD. Water requirement of cooling water circulation for Sponge Iron plant and power plant will be 100 KLD and 50 KLD, respectively. Blow down from the process are sent to ETP. Domestic effluent shall be sent to septic tank followed by soak pit. There will be no effluent from the process.

 

Dolochar (70 TPD) will be consumed in FBC boiler. Iron ore fines (32.5 TPD) will be reused in the process or sold to cement plants. Ash from boilers (83.6 TPD) will be sold to cement plants / fly ash manufacturers.  Sludge from wet scrapper (2.3 TPD), solid waste generated from kiln and dust from bag filters (13.5 TPD) will be sold to brick manufacturers or used for landfill. Construction waste will be reused for filling. Used batteries and waste oil will be sent to authorized dealers. Domestic and commercial solid waste will be collected, segregated and disposed for reuse and to dumping yard.

 

Green belt will be developed in 6.88 acres out of the total plant area of 20.86 acres. Less noise generating equipments will be installed. Power requirement from Captive power plant is revised from 600 KVA to 1.8 MW.

 

            After detailed deliberations, the Expert Appraisal Committee (Industry) recommended the proposal for the preparation of EIA/EMP as per the following TORs:  

 

1.      Present land use should be prepared based on satellite imagery.

2.      Actual land requirement, classification of land, current status of acquisition of land with break-up details (Government / Private / Forest land etc.), rehabilitation and resettlement as per the policy of the Govt. of A. P. should be incorporated.

3.      Current status of construction activities should be included.

4.      Location of national parks / wildlife sanctuary within 10 km. radius should specifically be mentioned.

5.      Permission and recommendations of the State Forest Department regarding impact of proposed expansion on the surrounding reserve forests viz. Bellary RF (8.5 km NW), Hirehalu RF (9.8 km SW) and Mincheri RF (2.5 km NE) should be included.

6.      A list of industries containing name and type in 25 km radius should be incorporated.

7.      List of raw material required and source should be included.

8.      Manufacturing process details of the Sponge Iron Plant should be included.

9.      Site-specific micro-meteorological data using temperature, relative humidity, hourly wind speed and direction and rainfall should be collected.

10.  Ambient air quality at 8 locations within the study area of 10 km., aerial coverage from project site with one AAQMS in downwind direction should be carried out.

11.  The suspended particulate matter present in the ambient air must be analyzed for the presence of poly-aromatic hydrocarbons (PAH), i.e. Benzene soluble fraction.  Chemical characterization of RSPM and incorporating of RSPM data.

12.  Determination of atmospheric inversion level at the project site and assessment of ground level concentration of pollutants from the stack emission based on site-specific meteorological features.

13.  Air quality modeling for Sponge Iron Plant and Captive Power Plant for specific pollutants needs to be done.  APCS for the control of emissions from the kiln and WHRB should also be included.

14.  Impact of the transport of the raw materials and end products on the surrounding environment should be assessed and provided.

15.  An action plan to control secondary fugitive emissions as per latest standards issued by the Ministry in May, 2008 and monitoring should be included.

16.  One season data for gaseous emissions other than monsoon season is necessary.

17.  Permission for the drawl of 170 KLD ground water and water balance data including quantity of effluent generated, recycled and reused and discharged is to be provided. Methods adopted/to be adopted for the water conservation.

18.  Surface water quality of nearby rivers (60 m upstream and downstream) and other surface drains at eight locations must be ascertained. 

19.  Ground water monitoring minimum at 8 locations and near solid waste dump zone, Geological features and Geo-hydrological status of the study area are essential as also.  Ecological status (Terrestrial and Aquatic) is vital.

20.  Action plan for solid/hazardous waste generation, storage, utilization and disposal particularly use of Char in FBC boiler should be included.

21.  A plan for the utilization of gases in the WHRB for generating power should be incorporated.

22.  Energy balance data for Sponge Iron Plant should be included.

23.  Risk assessment and damage control needs to be addressed.

24.  Occupational health of the workers needs elaboration.

25.  Green belt development plan in 33 % area and a scheme for rainwater harvesting have to be put in place.

26.  Socio-economic development activities need to be elaborated upon.

27.  A note on identification and implementation of Carbon Credit project.

28.  Total capital cost and recurring cost/annum for environmental pollution control measures should also be included.

29.  A tabular chart for the issues raised and addressed during public hearing/public consultation should be provided.

30.  Any litigation / court case pending against the proposal should also be included.

31.  Action Plan for the implementation of the recommendations made for the Sponge Plants in the CREP guidelines must be prepared.

 

            The Expert Committee (Industry) recommended that the PAs may be communicated the above ‘TORs’ for the preparation of EIA/EMP.   As soon as the combined draft EIA/EMP report is prepared as per the ‘General Structure of EIA’ given in Appendix III and IIIA in the EIA Notification, 2006, the same may be submitted by the PAs to the Andhra Pradesh Pollution Control Board (APPCB) for conducting public hearing as per EIA Notification, 2006. On finalization of EIA/EMP prepared as per TORs and addressing and incorporating all concerns raised by public hearing / public consultation, the same should be submitted to the MOEF for prior environmental clearance.

4.23     Sponge Iron Plant (66,000 TPA) alongwith Captive Power plant (8 MW) at Survey No. 17A & 17B, Village Nemakal, Mandal Bommanahal, District Ananthapur, Andhra Pradesh by M/s Ramanjaneya Ispat Pvt. Ltd. (TOR)

The project authorities and their consultant gave a detailed presentation on the salient features of the project and proposed environmental protection measures to be undertaken alongwith the draft Term of References for the preparation of EIA/EMP. All the Sponge iron Plants with > 200 TPD have been listed at S.N. 3(a) under Category ‘A’ and appraised at the Central level.  Capacity of the proposed sponge iron plant is 200 TPD.

 

M/s Ramanjaneya Ispat Pvt. Ltd. has proposed to set up a Sponge Iron plant (66000 TPA) alongwith Captive Power plant (8 MW) at Survey No. 17A & 17B, Village Nemakal, Mandal Bommanahal, District Ananthapur, A. P. The land acquired for the proposed project will be 23.26 acres instead of 24.99 acres / 26.8 acres proposed earlier. Bellary RF (8.5 km NW), Hirehalu RF (9.8 km SW) and Mincheri RF (2.5 km NE) are located within 10 km radius of the proposed project. Hiredahalu is at a distance of 2.5 km from the proposed site. Interstate boundary of A. P. and Karnataka is at a distance of 3 km from the proposed site. Total cost of the project will be Rs. 61.60 Crores instead of Rs. 61.90 Crores proposed earlier.

Sponge Iron Kiln (2x100 TPD, 66000 TPA), WHRB (2x10 TPH, 4 MW) and Biomass based FBC Boiler (1x30 TPH, 4 MW) will be installed in the proposed plant.

Rotary Kiln will be provided for reduction of Iron ore in to Sponge Iron at a temperature of 10000C and 10500C using non-coking coal as reductant. The kiln discharge after cooling will be fed to magnetic separators to separate Sponge Iron from Char. Steam generated from WHRB and biomass based FBC boiler will be used to generate power in Power plant.

Iron ore (400 TPD), Coal (200 TPD), and Dolomite (8 TPD) will be the raw materials required for Sponge Iron plant. Coal requirement for power plant will be 90 TPD).

Hot gases from the kiln will pass through a Dust settling chamber and then through After burning chamber (ABC) where any combustibles present will be completely burnt in presence of excess air.  The gases will then be led to a WHRB to generate steam for power generation. The gas will be cleaned in an ESP before letting them into the atmosphere through ID fan and a tall common stack of height 75 m. Flue gases from power plant will pass over various heat transfer surfaces to ESP and then finally discharged to chimney by ID fan. Fugitive Dust will be collected by bag filters will be collected by bag filters at transfer points and by water sprinkling for transport related dust. Exhaust emissions from vehicles and equipment deployed during construction phase will result in marginal increase in the levels of SO2, NOx, SPM and CO. The kiln and boiler stack emissions will be maintained at APPCB standards. Bag filters are attached to raw material crusher, coal junction point, stock house, cooler discharge and product house to control dust emissions. Particulate emission from bag filters will be <50 mg/Nm3.

 

Total ground water requirement will be 170 KLD. Water requirement of cooling water circulation for Sponge Iron plant and power plant will be 100 KLD and 50 KLD, respectively. Blow down from the process are sent to ETP. Domestic effluent shall be sent to septic tank followed by soak pit. There will be no effluent from the process.

 

Sludge from wet scrapper (2.3 TPD), solid waste generated from kiln and dust from bag filters (13.5 TPD) will be sold to brick manufacturers or used for landfill. Construction waste will be reused for filling. Any redundant machinery or equipment will be scrapped and disposed off to scrap dealers. Used batteries and waste oil will be sent to authorized dealers. Dolochar (70 TPD) will be consumed in FBC boiler. Iron ore fines (32.5 TPD) will be reused in the process or sold to cement plants, Ash from boilers (83.6 TPD) will be sold to cement plants / fly ash manufacturers. 

 

Green belt will be developed in 7.70 acres out of the total plant area of 23.26 acres. Less noise generating equipments will be installed.  Power requirement from Captive power plant is revised from 600 KVA to 1.8 MW.

            After detailed deliberations, the Expert Appraisal Committee (Industry) recommended the proposal for the preparation of EIA/EMP as per the following TORs:  

1.      Present land use should be prepared based on satellite imagery.

2.      Actual land requirement, classification of land, current status of acquisition of land with break-up details (Government / Private / Forest land etc.), rehabilitation and resettlement as per the policy of the Govt. of A. P. should be incorporated.

3.      Exact location of the project Survey No. 16 B2 & 17 A or Survey No. 14/15 A/15 B/16 A should be mentioned.

4.      Current status of construction activities should be included.

5.      Location of national parks / wildlife sanctuary within 10 km. radius should specifically be mentioned.

6.      Permission and recommendations of the State Forest Department regarding impact of proposed expansion on the surrounding reserve forests viz. Bellary RF (8.5 km NW), Hirehalu RF (9.8 km SW) and Mincheri RF (2.5 km NE) should be included.

7.      A list of industries containing name and type in 25 km radius should be incorporated.

8.      List of raw material required and source should be included.

9.      Manufacturing process details of the Sponge Iron Plant should be included.

10.  Site-specific micro-meteorological data using temperature, relative humidity, hourly wind speed and direction and rainfall should be collected.

11.  Ambient air quality at 8 locations within the study area of 10 km., aerial coverage from project site with one AAQMS in downwind direction should be carried out.

12.  The suspended particulate matter present in the ambient air must be analyzed for the presence of poly-aromatic hydrocarbons (PAH), i.e. Benzene soluble fraction.  Chemical characterization of RSPM and incorporating of RSPM data.

13.  Determination of atmospheric inversion level at the project site and assessment of ground level concentration of pollutants from the stack emission based on site-specific meteorological features.

14.  Air quality modeling for Sponge Iron Plant and Captive Power Plant for specific pollutants needs to be done.  APCS for the control of emissions from the kiln and WHRB should also be included.

15.  Impact of the transport of the raw materials and end products on the surrounding environment should be assessed and provided.

16.  An action plan to control secondary fugitive emissions as per latest standards issued by the Ministry in May, 2008 and monitoring should be included.

17.  One season data for gaseous emissions other than monsoon season is necessary.

18.  Permission for the drawl of 170 KLD ground water and water balance data including quantity of effluent generated, recycled and reused and discharged is to be provided. Methods adopted/to be adopted for the water conservation.

19.  Surface water quality of nearby rivers (60 m upstream and downstream) and other surface drains at eight locations must be ascertained. 

20.  Ground water monitoring minimum at 8 locations and near solid waste dump zone, Geological features and Geo-hydrological status of the study area are essential as also.  Ecological status (Terrestrial and Aquatic) is vital.

21.  Action plan for solid/hazardous waste generation, storage, utilization and disposal particularly use of Char in FBC boiler should be included.

22.  A plan for the utilization of gases in the WHRB for generating power should be incorporated.

23.  Energy balance data for Sponge Iron Plant should be included.

24.  Risk assessment and damage control needs to be addressed.

25.  Occupational health of the workers needs elaboration.

26.  Green belt development plan in 33 % area and a scheme for rainwater harvesting have to be put in place.

27.  Socio-economic development activities need to be elaborated upon.

28.  A note on identification and implementation of Carbon Credit project.

29.  Total capital cost and recurring cost/annum for environmental pollution control measures should also be included.

30.  A tabular chart for the issues raised and addressed during public hearing/public consultation should be provided.

31.  Any litigation / court case pending against the proposal should also be included.

32.  Action Plan for the implementation of the recommendations made for the Sponge Plants in the CREP guidelines must be prepared.

 

            The Expert Committee (Industry) recommended that the PAs may be communicated the above ‘TORs’ for the preparation of EIA/EMP.   As soon as the combined draft EIA/EMP report is prepared as per the ‘General Structure of EIA’ given in Appendix III and IIIA in the EIA Notification, 2006, the same may be submitted by the PAs to the Andhra Pradesh Pollution Control Board (APPCB) for conducting public hearing as per EIA Notification, 2006. On finalization of EIA/EMP prepared as per TORs and addressing and incorporating all concerns raised by public hearing / public consultation, the same should be submitted to the MOEF for prior environmental clearance.

 

4.24     Sponge Iron plant (66,000 TPA) alongwith Captive Power plant (8 MW) at Survey No. 14/15A/15B/16A, Village Nemakal, Mandal Bommanahal, District Ananthapur, Andhra Pradesh by M/s Venkata Sai Ispat Industries Pvt. Ltd. (TOR) 

The project authorities and their consultant gave a detailed presentation on the salient features of the project and proposed environmental protection measures to be undertaken alongwith the draft Term of References for the preparation of EIA/EMP. All the Sponge iron Plants with > 200 TPD have been listed at S.N. 3(a) under Category ‘A’ and appraised at the Central level.  Capacity of the proposed sponge iron plant is 200 TPD.

 

M/s Venkata Sai Ispat Industries Pvt. Ltd. has proposed to set up a Sponge Iron plant (66000 TPA) alongwith Captive Power plant (8 MW) at Survey No. 16B2, 17A, 18A, 26A, Village Nemakal, Mandal Bommanahal, District Ananthapur, A. P. The land acquired for the proposed project will be 26.28 acres instead of 24.99 acres / 26.8 acres proposed earlier. Bellary RF (8.5 km NW), Hirehalu RF (9.8 km SW) and Mincheri RF (2.5 km NE) are located within 10 km radius of the proposed project. Hiredahalu is at a distance of 2.5 km from the proposed site. Interstate boundary of A. P. and Karnataka is at a distance of 3 km from the proposed site. Total cost of the project is Rs. 61.60 Crores instead of Rs. 61.90 Crores proposed earlier.

Sponge Iron Kiln (2x100 TPD, 66000 TPA), WHRB (2x10 TPH, 4 MW) and Biomass based FBC Boiler (1x30 TPH, 4 MW) will be installed in the proposed plant. Rotary Kiln will be provided for reduction of Iron ore in to Sponge Iron at a temperature of 10000C and 10500C using non-coking coal as reductant. The kiln discharge after cooling will be fed to magnetic separators to separate Sponge Iron from Char. Steam generated from WHRB and biomass based FBC boiler will be used to generate power in Power plant.

 

Iron ore (400 TPD), Coal (200 TPD), and Dolomite (8 TPD) will be the raw materials required for Sponge Iron plant. Coal requirement for power plant will be 90 TPD).

 

Hot gases from the kiln will pass through a Dust settling chamber and then through After burning chamber (ABC) where any combustibles present will be completely burnt in presence of excess air.  The gases will then be led to a WHRB to generate steam for power generation. The gas will be cleaned in an ESP before letting them into the atmosphere through ID fan and a tall common stack of height 75 m. Flue gases from power plant will pass over various heat transfer surfaces to ESP and then finally discharged to chimney by ID fan. Fugitive Dust will be collected by bag filters will be collected by bag filters at transfer points and by water sprinkling for transport related dust. Exhaust emissions from vehicles and equipment deployed during construction phase will result in marginal increase in the levels of SO2, NOx, SPM and CO. The kiln and boiler stack emissions will be maintained at APPCB standards. Bag filters are attached to raw material crusher, coal junction point, stock house, cooler discharge and product house to control dust emissions. Particulate emission from bag filters will be <50 mg/Nm3.

 

Total ground water requirement will be 170 KLD. Water requirement of cooling water circulation for Sponge Iron plant and power plant will be 100 KLD and 50 KLD, respectively. Blow down from the process are sent to ETP. Domestic effluent shall be sent to septic tank followed by soak pit. There will be no effluent from the process.

 

Excavated soil will be used for filling the basement of buildings and unleveled area. Domestic and commercial solid waste will be collected, segregated and disposed for reuse and to dumping yard. Sludge from wet scrapper (2.3 TPD), solid waste generated from kiln and dust from bag filters (13.5 TPD) will be sold to brick manufacturers or used for landfill. Construction waste will be reused for filling. Any redundant machinery or equipment will be scrapped and disposed off to scrap dealers. Used batteries and waste oil will be sent to authorized dealers. Dolochar (70 TPD) will be consumed in FBC boiler. Iron ore fines (32.5 TPD) will be reused in the process or sold to cement plants, Ash from boilers (83.6 TPD) will be sold to cement plants / fly ash manufacturers. 

 

           Greenbelt will be developed in 8.67 acres out of the total plant area of 26.28 acres. Less noise generating equipments will be installed. Power requirement from Captive power plant is revised from 600 KVA to 1.8 MW.

            After detailed deliberations, the Expert Appraisal Committee (Industry) recommended the proposal for the preparation of EIA/EMP as per the following TORs:  

1.      Present land use should be prepared based on satellite imagery.

2.      Actual land requirement, classification of land, current status of acquisition of land with break-up details (Government / Private / Forest land etc.), rehabilitation and resettlement as per the policy of the Govt. of A. P. should be incorporated.

3.      Exact location of the project Survey No. 16 B2 & 17 A or Survey No. 14/15 A/15 B/16 A should be mentioned.

4.      Current status of construction activities should be included.

5.      Location of national parks / wildlife sanctuary within 10 km. radius should specifically be mentioned.

6.      Permission and recommendations of the State Forest Department regarding impact of proposed expansion on the surrounding reserve forests viz. Bellary RF (8.5 km NW), Hirehalu RF (9.8 km SW) and Mincheri RF (2.5 km NE) should be included.

7.      A list of industries containing name and type in 25 km radius should be incorporated.

8.      List of raw material required and source should be included.

9.      Manufacturing process details of the Sponge Iron Plant should be included.

10.  Site-specific micro-meteorological data using temperature, relative humidity, hourly wind speed and direction and rainfall should be collected.

11.  Ambient air quality at 8 locations within the study area of 10 km., aerial coverage from project site with one AAQMS in downwind direction should be carried out.

12.  The suspended particulate matter present in the ambient air must be analyzed for the presence of poly-aromatic hydrocarbons (PAH), i.e. Benzene soluble fraction.  Chemical characterization of RSPM and incorporating of RSPM data.

13.  Determination of atmospheric inversion level at the project site and assessment of ground level concentration of pollutants from the stack emission based on site-specific meteorological features.

14.  Air quality modeling for Sponge Iron Plant and Captive Power Plant for specific pollutants needs to be done.  APCS for the control of emissions from the kiln and WHRB should also be included.

15.  Impact of the transport of the raw materials and end products on the surrounding environment should be assessed and provided.

16.  An action plan to control secondary fugitive emissions as per latest standards issued by the Ministry in May, 2008 and monitoring should be included.

17.  One season data for gaseous emissions other than monsoon season is necessary.

18.  Permission for the drawl of 170 KLD ground water and water balance data including quantity of effluent generated, recycled and reused and discharged is to be provided. Methods adopted/to be adopted for the water conservation.

19.  Surface water quality of nearby rivers (60 m upstream and downstream) and other surface drains at eight locations must be ascertained. 

20.  Ground water monitoring minimum at 8 locations and near solid waste dump zone, Geological features and Geo-hydrological status of the study area are essential as also.  Ecological status (Terrestrial and Aquatic) is vital.

21.  Action plan for solid/hazardous waste generation, storage, utilization and disposal particularly use of Char in FBC boiler should be included.

22.  A plan for the utilization of gases in the WHRB for generating power should be incorporated.

23.  Energy balance data for Sponge Iron Plant should be included.

24.  Risk assessment and damage control needs to be addressed.

25.  Occupational health of the workers needs elaboration.

26.  Green belt development plan in 33 % area and a scheme for rainwater harvesting have to be put in place.

27.  Socio-economic development activities need to be elaborated upon.

28.  A note on identification and implementation of Carbon Credit project.

29.  Total capital cost and recurring cost/annum for environmental pollution control measures should also be included.

30.  A tabular chart for the issues raised and addressed during public hearing/public consultation should be provided.

31.  Any litigation / court case pending against the proposal should also be included.

32.  Action Plan for the implementation of the recommendations made for the Sponge Plants in the CREP guidelines must be prepared.

 

            The Expert Committee (Industry) recommended that the PAs may be communicated the above ‘TORs’ for the preparation of EIA/EMP.   As soon as the combined draft EIA/EMP report is prepared as per the ‘General Structure of EIA’ given in Appendix III and IIIA in the EIA Notification, 2006, the same may be submitted by the PAs to the Andhra Pradesh Pollution Control Board (APPCB) for conducting public hearing as per EIA Notification, 2006. On finalization of EIA/EMP prepared as per TORs and addressing and incorporating all concerns raised by public hearing / public consultation, the same should be submitted to the MOEF for prior environmental clearance.

4.25     Expansion of Sponge Iron Plant into Integrated Mini Steel Plant at Plot No. 202, Kalunga Industrial Esate, Tehsil Kalunga, District Sundergarh, Orissa by M/s Seeta Integrated Steel & Energy Ltd. (TOR)

            The project authorities and their consultant gave a detailed presentation on the salient features of the project and proposed environmental protection measures to be undertaken alongwith the draft Term of References for the preparation of EIA/EMP. All the Integrated Steel Plants are listed at S.N. 3(a) under Primary Metallurgy Industry under Category ‘A’ and are appraised at Central Level.

 

            M/s Seeta Integrated Steel & Energy Ltd. have proposed for the expansion of Sponge Iron Plant into Integrated Mini Steel Plant at Plot No. 202, Kalunga Industrial Industrial Esate, Tehsil Kalunga, District Sundergarh, Orissa.  Total land acquired is 10.62 acres in Kalunga Industrial Estate and expansion will be carried out in 123.81 acre private and Govt. land, which is in the process of acquisition. Thus, total land required will be 134.43 ha. Reserve forests viz. Sagjov RF (5.85 km, SSW), Kumaria RF (4.0 km., SW), Chudla RF (12.0 km SW), Laimura R.F. (7.5 km W), Jharbera R.F. (11.2 km, NW, Jaidega R.F. (14.0 km. NNW, Jugsai R.F. (4.4 km. N, Chadri, R.F. (7.5 km. N), Dassey R.F. (12.4 km. N), Jhitigara R.F. (14.1 km. NNE), Chilangpahar R.F. (11.15 Km. NNE), Harapalli R.F. (12.5 NE), Mudrapahar R.F. (9.3 Km. NE), Bamnipahar R.F. (7.35 Km. NE), Kamarpahar R.F. (5.2 Km. NNE), Patpahar R.F. (11.8 Km. NE), Godharsa R.F. (13.6 Km. NE), Rutkupudi R.F. (4.3 km SE), Hathingbandha R.F. (12.0 km. SE), Durgapur R.F. (6.0 km. ENE), Balanda P.F. (3.8 km. S) are located within 10 km radius. 12 water bodies are located within 15 km radius.  Total cost of the project is revised to 650.00 Crores instead of Rs. 385.00 Crores proposed earlier.  Following will be installed during expansion besides existing sponge iron plant:

 

Project

Production

 

Existing

Proposed

Total

Sponge Iron Plant

45,000 TPA

60,000 TPA

1,05,000 TPA

Captive Power Plant

                   WHRB

                   AFBC

 

--

--

7 MW

63 MW

 

70 MW

Iron ore crusher

1,44,000 TPA

1,92,000 TPA

3,36,000 TPA

Induction furnace

--

3,00,000 TPA

3,00,000 TPA

Coal Washery

--

1,92,000 TPA

1,92,000 TPA

Blast Furnace

--

1,59,000 TPA

1,59,000 TPA

Concast

--

3,00,000 TPA

3,00,000 TPA

Rolling Mill

--

1,50,000 TPA

1,50,000 TPA

 

During presentation, PAs informed that following will be the existing and proposed facilities :

 

Project

Production

 

Existing

Proposed

Total

Sponge Iron Plant

45,000 TPA

(1x50 TPD+1x100 TPD)

1,80,000 TPA

(6x100 TPD)

2,25,000 TPA

Captive Power Plant

                       WHRB

                       AFBC

 

--

--

 

15 MW

55 MW

 

70 MW

Iron ore crusher

1,80,000 TPA

(1x30 TPH)

4,20,000 TPA

(70 TPH)

6,00,000 TPA

Induction furnace

--

3,00,000 TPA

3,00,000 TPA

Coal Washery

2,40,000 TPA

(1x40 TPH)

3,60,000 TPA

6,00,000 TPA

Blast Furnace

--

1,59,000 TPA

1,59,000 TPA

Concast

--

3,00,000 TPA

3,00,000 TPA

Rolling Mill

--

1,50,000 TPA

1,50,000 TPA

 

            Iron Ore (0.6435 MTPA), Coal (0.702 MTPA), Dolomite (0.0042 MTPA), Manganese (0.2385 MTPA) and Quartz (540 TPA) will be used as raw materials.

            During expansion, Rotary kiln (200 TPD), IF, Coal Washery, Iron ore crusher, BF, Concast and Rolling Mill, WHRB (7 MW) and AFBC (63 MW) will be installed DR-IF route will be adopted.  In Iron ore crusher, lumps of iron ore will be crushed in Jaw Crusher and discharged into screen and collected at Stockpile.  Coal washing will be done by dry process by jigging the coal where clean coal i.e. land density coal will flow from the top of the bed through a separate chute and secondary roll crusher will recycle the crushed coal again.  The rejected coal will be disposed off to the rejected coal stockyard.   Sponge Iron manufacturing will involve reduction of iron ore with solid carbonaceous material such as coal in a rotary kiln at high temperature.  The products will be magnetically separated int9o char and sponge iron.  Iron ore and sinter will be melted in BF and liquid hot iron and slag will be collected separately.  Scrap and sponge iron will be melted in IF to manufacture pencil ingots. Billets will be manufactured from the scrap by casting the moulds.  Billets will be reheated in the –reheating furnace to manufacture bars and rods and also rolled products in Rolling Mill.  The flue gas from DRI will be used in waste heat recovery boiler (WHRB).  Char, coal fines, coal middling from coal washery will be used in atmospheric Fluidized Combustion Boiler (AFBC).

 

The flue gases from the DRI will be passed through dust settling chamber (DBC) and After burning Chamber (ABC) and then used in WHRB boiler. Bag house/filter will be provided to coal washery and blast furnace.  Fume extraction system will be provided to IF. Electrostatic precipitator will be provided to WHRB and AFBC boiler to control emissions within 50 mg/Nm3.  Dust Dust extraction with bag filters will be provided to control fugitive emission in work zone environment and Induction furnace. Dry fog system will be provided at all material transfer points.

 Earlier, it was informed that the total water requirement from Brahmani River will be 927 m3/hr. However, during presentation, PAs informed that the water requirement for proposed expansion will be 1000 m3/day which will be met from IDCO supply. Permission for the same has been applied. All the effluent will be abundantly treated and   neutralized inside the plant premises and subsequently used for greenbelt and dust suppression.  No effluent will be discharged and ‘zero’ discharge will be adopted.  The cooling water blow down will be used for dust suppression and horticulture.  Acidic and alkaline water from DM plant will be neutralized in neutralization pit.  Domestic effluent will be treated in sewage treatment plant.

 

Dolochar, Washery rejects and fresh coal will be used in FBB. Iron ore fines will be sold to outside agencies & Cement units. Flue dust, fly ash from AFBC, Bed ash and slag from BF will be used in manufacturing cement.  Waste oil, oil sludge and dry cell batteries will be sold to authorized recyclers / re-processors.

 

Green belt will be developed in 33 % area. Power (52.5 MW) for the proposed expansion will be sourced from CPP (70 MW). This makes the total power requirement after the proposed expansion to be 53.45 MW. HSD (135 KLD) and coal (0.702 MTPA) will be used as fuels.  Excess power will be transferred to M/s Chari of Cement Co.

After deliberating on the facts presented the Expert Appraisal Committee (Industry) recommended the proposal for the preparation of EIA/EMP as per the following TORs :

1.      Present land use should be prepared based on satellite imagery.

2.      Location of national parks / wildlife sanctuary within 10 km. radius should specifically be mentioned.

3.      ‘Proof’ / ‘Notification’ issued by the State Govt., if the project is located in notified industrial area.

4.      Permission and recommendations of the State Forest Department regarding impact of proposed expansion on the surrounding reserve forests viz. Sagjov RF (5.85 km, SSW), Kumaria RF (4.0 km., SW), Chudla RF (12.0 km SW), Laimura R.F. (7.5 km W), Jharbera R.F. (11.2 km, NW, Jaidega R.F. (14.0 km. NNW, Jugsai R.F. (4.4 km. N, Chadri, R.F. (7.5 km. N), Dassey R.F. (12.4 km. N), Jhitigara R.F. (14.1 km. NNE), Chilangpahar R.F. (11.15 Km. NNE), Harapalli R.F. (12.5 NE), Mudrapahar R.F. (9.3 Km. NE), Bamnipahar R.F. (7.35 Km. NE), Kamarpahar R.F. (5.2 Km. NNE), Patpahar R.F. (11.8 Km. NE), Godharsa R.F. (13.6 Km. NE), Rutkupudi R.F. (4.3 km SE), Hathingbandha R.F. (12.0 km. SE), Durgapur R.F. (6.0 km. ENE), Balanda P.F. (3.8 km. S) should be included.

5.      Actual land requirement, classification of land, current status of acquisition of land with break-up details (Government / Private / Forest land etc.), rehabilitation and resettlement as per the policy of the Govt. of Orissa should be incorporated.

6.      Current status of construction activities should be included.

7.      Site-specific micro-meteorological data using temperature, relative humidity, hourly wind speed and direction and rainfall should be collected.

8.      A list of industries containing name and type in 25 km radius should be incorporated.

9.      Residential colony should be located in upwind direction.

10.  List of raw material required and source should be included.

11.  Manufacturing process details for all the plants viz. Sponge Iron Plant, Induction furnace, Iron ore crusher, Coal Washery, Blast Furnace, Coal Washery, Concast, Rolling Mill, Captive Power Plant (WHRB & AFBC) etc. should be included.

12.  Data on existing ambient air, stack emissions and fugitive emissions should be included.

13.  Ambient air quality at 8 locations within the study area of 10 km., aerial coverage from project site with one AAQMS in downwind direction should be carried out.

14.  The suspended particulate matter present in the ambient air must be analyzed for the presence of poly-aromatic hydrocarbons (PAH), i.e. Benzene soluble fraction.  Chemical characterization of RSPM and for incorporating of RSPM data.

15.  Impact of the transport of raw material and finished product on the surrounding environment should be assessed and provided

16.  Determination of atmospheric inversion level at the project site and assessment of ground level concentration of pollutants from the stack emission based on site-specific meteorological features. Air quality modeling for steel plant for specific pollutants needs to be done. 

17.  Plant-wise air pollution control measures proposed for the control of gaseous emissions from all the sources should be incorporated.

18.  A note on control of fugitive and secondary emissions from as per CPCB guidelines from all the sources should be incorporated.

19.  One season data for gaseous emissions during winter season is necessary.

20.  Permission for the drawl of 1000 m3/day water from IDCO supply and no water from Brahmani River or bore wells from the concerned department and water balance data including quantity of effluent generated, recycled and reused and discharged should be provided. Methods adopted/to be adopted for the water conservation.

21.  Surface water quality of nearby rivers (60 m upstream and downstream) and other surface drains at eight locations must be ascertained. 

22.  Ground water monitoring minimum at 8 locations and near solid waste dump zone, Geological features and Geo-hydrological status of the study area are essential as also.  Ecological status (Terrestrial and Aquatic) is vital.

23.  A note on treatment of wastewater from different plants including coke oven plant, recycle and reuse for different purposes should be included.

24.  Action plan for solid/hazardous waste generation, storage, utilization and disposal particularly char and fly ash. Assurance that 100 % char will be used in the FBC boiler and copies of MOU regarding utilization of ash should be included.

25.  MOU signed with the Cement manufacturers for utilizing granulated BF slag should be included.

26.  Generation and utilization of waste/fuel gases from DRI and BF plant and their utilization in the CPP have to be set out.

27.  Risk assessment and damage control needs to be addressed.

28.  Occupational health of the workers needs elaboration.

29.  Green belt development plan in 33 % area and a scheme for rainwater harvesting have to be put in place.

30.  Socio-economic development activities need to be elaborated upon.

31.  A note on identification and implementation of Carbon Credit project should be included.

32.  An Action Plan for the implementation of the recommendations made for the Steel Plants in the CREP guidelines must be prepared.

33.  Total capital cost and recurring cost/annum for environmental pollution control measures should also be included.

34.  A tabular chart for the issues raised and addressed during public hearing/public consultation should be provided.

35.  Any litigation / court case pending against the proposal should also be included.

 

The Expert Committee (Industry) decided that PAs may be communicated the above ‘TORs’ for the preparation of EIA/EMP.  As soon as the draft EIA/EMP report is prepared as per the ‘General Structure of EIA’ given in Appendix III and IIIA in the EIA Notification, 2006, the same may be submitted by the PAs to the Orissa Pollution Control Board (OPCB) for conducting public hearing as per EIA Notification, 2006.  On finalization of EIA/EMP prepared as per TORs addressing all concerns set out EIA/EMP should be submitted to the MOEF for prior environmental clearance.

4.26     Expansion of Sponge Iron Plant (100 TPD to 200 TPD) alongwith Captive Power Plant (8 MW; WHRB, 4 MW; AFBC 4 MW) at Plot No. 84, Industrial Estate, PO. Kalunga, District Sundergarh, Orissa by M/s Maa Vaishnavi Sponge Limited (TOR)

 

The project authorities and their consultant gave a detailed presentation on the salient features of the project and proposed environmental protection measures to be undertaken alongwith the draft Term of References for the preparation of EIA/EMP. Sponge Iron plants (>200 TPD) have been kept at S.N. 3(a)(b) under category ‘B’ but due to non-existent of SEIAA/SEAC in Orissa, proposal is being appraised at Central level.

 

M/s Maa Vaishnavi Sponge Limited has proposed to expand its existing Sponge Iron Plant (100 TPD to 200 TPD) alongwith Captive Power Plant (8 MW; WHRB, 4 MW; AFBC 4 MW) at Plot No. 84, Industrial Estate, P.O. Kalunga, District Sundergarh, Orissa.  Proposed expansion will be done within the existing plant premises of 26.071 acres instead of 21.231 acres proposed earlier. No national parks/wild life sanctuary/reserve forests are located within 10 km radius. Total cost of the proposed expansion will be Rs. 24.90 Crores. Rs. 2.90 Crores and Rs. 0.40 Crores will be earmarked towards total capital cost and recurring cost/annum for environmental pollution control measures. During presentation, PAs were asked to install 4 MW AFBC boiler for which they have agreed and submitted a commitment vide letter dated 20th October, 2008. Therefore, the total project cost was revised to Rs. 40.90 Crores.

 

S.N

Unit

Project Configuration

Total capacity after expansion

Existing capacity

Proposed capacity

1

DRI

30,000 TPA

(2x50 TPD)

30,000 TPA

(1x100 TPD)

60,000 TPA

2

Induction Furnace

8,400 TPA

(3 TPH)

To be commissioned

-

8,400 TPA

3

Rolling mill

72,000 TPA

To be commissioned

-

72,000 TPA

4

Captive Power plant

-

    4 MW (WHRB)

4 MW (AFBC)

8 MW

 

The existing plant has 2x50 TPD DRI kilns, Induction furnace (8,400 TPA) and Rolling mill (7,200 TPA).  DRI plant (1x100 TPD) and Power Plant (WHRB, 4 MW; AFBC 4 MW) will be installed in the proposed expansion. 

Raw materials required for sponge iron production (100 TPD) will be Iron ore (48,000 TPA), Coal (54,000 TPA), Dolomite (2,400 TPA).  Sponge Iron will be manufactured by SL/RN process following typical rotary kiln operations. Iron ore, coal and flux will be charged into rotary kiln which will rapidly heated up by the combustion of coal volatiles released in the charge. Reduction of Iron ore to metallic Iron will take place at about 1000oC. The products will be cooled in a rotary cooler and the cooler discharge will be magnetically separated as Sponge Iron and char.  WHRB will be coupled to the kilns and the steam generated from the boiler will be sent to steam turbine for power generation. 

Off gases from rotary kiln will initially pass through dust settling chamber. Later, combustibles like Carbon particles and CO apart from oxides of Sulphur, fines of Iron ore, coal and dolomite will be completely burnt in After Burning Chamber (ABC) and passed through WHRB before passing through the ESP and finally discharging into the atmosphere via chimney of adequate height. Bag filter will be provided to cooler discharge, product house, intermediate bin, coal circuit, Iron ore circuit, ESP dust handling unit and stock house of DRI plant. Water sprinkling and dry fog suppression system will be provided to raw material handling, stock piling and material transfer points. Hood with swiveling arm for fume extraction, spark arrester, bag filter and stack of adequate height will be provided to Induction furnace. ESP will be provided to WHRB and adequate stack heigght will be provided to oil fired reheating furnace.

 

Total water requirement after proposed expansion from IDCO supply will be 552 m3/day instead of 32 m3/hr proposed earlier. Chemical wastes from laboratory will be neutralized before discharging into the sanitary sewerage treatment system. The treated effluent will be reused / recycled. The cooling tower blowdowns and boiler blowdowns will be treated in settling tanks and utilized for dust suppression and plantation etc. Domestic waste water will be treated in septic tank followed by soak pit. Back wash of soft water plant will be treated in settling cum neutralization tank.

 

Char / Dolochar will be used in Fluidized bed boilers. Coal fines will be used for injection in DRI kilns. ETP sludge will be disposed off in low lying areas. Used oil (600 LPA) and oily cotton waste (200 kg/annum) generated will be disposed as per CPCB guidelines. Sewage sludge will also be utilized as manure. The manure will be used for green belt and green cover. Canteen solid waste (6 TPA) will be dumped in a pit to convert it to manure by vermin-composting. ESP dust alongwith dust from other APC devices will be used in filling low lying areas. Induction furnace slag and Kiln accretions will be used in road making.

 

Green belt will be developed in 33 % area. Noise isolators, Siliencers / Rubber padding will be provided to modulate the noise generated by plant machinery. Ear muffs/ Ear plugs will be provided to employees who are exposed to noise prone areas.

 

           Power requirement for Sponge Iron plant (100 TPD) will be 0.65 MW and will be sourced from WESCO.  4 MW of power will be generated from CPP.  A DG set of adequate capacity will be provided to cater to the emergency power requirement of the plant. LDO will be used in burners of DRI kilns for initial start-up. HSD (16 KLD) will be used as fuel in Vehicles for the proposed project. 

            After detailed deliberations, the Expert Appraisal Committee (Industry) recommended the proposal for the preparation of EIA/EMP as per the following TORs:  

1.      Present land use should be prepared based on satellite imagery.

2.      Actual land requirement, classification of land, current status of acquisition of land with break-up details (Government / Private / Forest land etc.), rehabilitation and resettlement as per the policy of the Govt. of Orissa should be incorporated.

3.      Location of national parks / wildlife sanctuary within 10 km. radius should specifically be mentioned.

4.      Permission and recommendations of the State Forest Department regarding impact of proposed expansion on the surrounding reserve forests, if any, should be included.

5.      A list of industries containing name and type in 25 km radius should be incorporated.

6.      List of raw material required and source should be included.

7.      Manufacturing process details of the Sponge Iron Plant and Captive Power Plant (WHRB and AFBC) should be included.

8.      Data on air emissions, wastewater generation and solid waste management for the existing plant should be incorporated.

9.      Site-specific micro-meteorological data using temperature, relative humidity, hourly wind speed and direction and rainfall should be collected.

10.  Ambient air quality at 8 locations within the study area of 10 km., aerial coverage from project site with one AAQMS in downwind direction should be carried out.

11.  The suspended particulate matter present in the ambient air must be analyzed for the presence of poly-aromatic hydrocarbons (PAH), i.e. Benzene soluble fraction.  Chemical characterization of RSPM and incorporating of RSPM data.

12.  Determination of atmospheric inversion level at the project site and assessment of ground level concentration of pollutants from the stack emission based on site-specific meteorological features.

13.  Air quality modeling for Sponge Plant and Captive Power Plant (WHRB and AFBC) for specific pollutants needs to be done.  APCS for the control of emissions from the kiln and WHRB should also be included.

14.  Impact of the transport of the raw materials and end products on the surrounding environment should be assessed and provided.

15.  An action plan to control secondary fugitive emissions as per latest standards issued by the Ministry in May, 2008 and monitoring should be included.

16.  One season data for gaseous emissions other than monsoon season is necessary.

17.  Permission for the drawl of 552 m3/day water from IDCO supply and water balance data including quantity of effluent generated, recycled and reused and discharged is to be provided. Methods adopted/to be adopted for the water conservation.

18.  Surface water quality of nearby rivers (60 m upstream and downstream) and other surface drains at eight locations must be ascertained. 

19.  Ground water monitoring minimum at 8 locations and near solid waste dump zone, Geological features and Geo-hydrological status of the study area are essential as also.  Ecological status (Terrestrial and Aquatic) is vital.

20.  Action plan for solid/hazardous waste generation, storage, utilization and disposal particularly use of Char in FBC boiler should be included.

21.  A plan for the utilization of gases in the WHRB for generating power should be incorporated.

22.  Energy balance data for Sponge Iron Plant should be included.

23.  Risk assessment and damage control needs to be addressed.

24.  Occupational health of the workers needs elaboration.

25.  Green belt development plan in 33 % area and a scheme for rainwater harvesting have to be put in place.

26.  Socio-economic development activities need to be elaborated upon.

27.  A note on identification and implementation of Carbon Credit project.

28.  Total capital cost and recurring cost/annum for environmental pollution control measures should also be included.

29.  A tabular chart for the issues raised and addressed during public hearing/public consultation should be provided.

30.  Any litigation / court case pending against the proposal should also be included.

31.  Action Plan for the implementation of the recommendations made for the Sponge Plants in the CREP guidelines must be prepared.

 

            The Expert Committee (Industry) recommended that the PAs may be communicated the above ‘TORs’ for the preparation of EIA/EMP.  As soon as the draft EIA/EMP report is prepared as per the ‘General Structure of EIA’ given in Appendix III and IIIA in the EIA Notification, 2006, the same may be submitted by the PAs to the Orissa Pollution Control Board (OPCB) for conducting public hearing as per EIA Notification, 2006. On finalization of EIA/EMP prepared as per TORs and addressing and incorporating all concerns raised by public hearing / public consultation, the same should be submitted to the MOEF for prior environmental clearance.

4.27    Expansion of Sponge Iron Plant (3,00,000 MTPA to 6,00,000 MTPA), Ferro Alloy Plant (72,000 MTPA) at Village Jitusole, District Paschim Medinipore, West Bengal by M/s Rashmi Cement Limited. (TOR)

The project authorities and their consultant gave a detailed presentation on the salient features of the project and proposed environmental protection measures to be undertaken alongwith the draft Term of References for the preparation of EIA/EMP. All the Primary metallurgical industries have been kept at S.N. 3(a) under primary metallurgical industry under category ‘A’ and appraised at Central level.

 

M/s Rashmi Cement Limited has proposed for the expansion of Sponge Iron plant (3,00,000 MTPA to 6,00,000 MTPA), alongwith addition of Ferro Alloy Plant (72,000 MTPA) at Village Jitusole, District Paschim Medinipore, West Bengal. 75 acres of land adjacent to the existing land (45 acres) is under the process of acquisition. Therefore, total land required will be 120 acres. Jhargram township is 10 km away from the proposed site. No national park / wildlife and reserve forest is located within 10 km radius of the project site. Total cost of the project is Rs. 220.00 Crores. Rs. 18.00 Crores and Rs. 0.50 Crores will be earmarked towards total capital cost and recurring cost /annum for environmental pollution control measures.

 

Sponge Iron Plant consisting of Rotary kilns (4x100 TPD & 2x350 TPD) and Submerged Arc furnace (6x9 MVA) for the Ferro Alloy Plant will be installed. Sponge Iron (3,00,000 MTPA) and Ferro Alloy (72,000 MTPA) will be manufactured during expansion.

 

Plant

Exisiting (TPA)

Proposed (TPA)

Total capacity (TPA)

Phase-I

Phase-II

DRI

3,00,000

(10x100 TPD)

1,20,000

(4x100 TPD)

1,80,000

(2x350 TPD)

6,00,000

Submerged Arc Furnace

-

36,000

(3x9 MVA)

36,000

(3x9 MVA)

72,000

Power Plant

25 MW

-

-

25 MW

 

Sponge iron will be produced using reducing Iron ore with coal or lignite. The reduction will be carried out in a Rotary kiln at a pre-determined temperature and controlled atmosphere. Iron ore, Coal and Limestone will be fed into the rotary kiln. The kiln discharge after cooling will be fed to magnetic separators to separate Sponge Iron from Char. Ferro alloys will be produced in a Submerged Electric Arc Furnace.

 Iron ore (50,000 MTPM), Coal (48,000 MTPM), and Dolomite (1,500 MTPM) will be the raw materials required for Sponge Iron plant. Quartz (46,800 TPA), Manganese ore (15,000 MTPM), Dolomite, Coke breeze (3,600 MTPM), Electrode casing (90 MTPM), Quartz etc. will be the raw materials required for Ferro alloy plant.

Bag filters will be installed at material transfer points to control the emissions. Flue gases from Submerged Arc Furnace will successively pass through heat exchanger, bag filter system and then finally vented to atmosphere through a stack of adequate height. Fumes generated from furnace during tapping will be collected by an exhaust hood and then cleaning will be done by passing them through a bag house. Emission level at the outlet of bag house for furnace fumes and tapping fumes will be less than 50 mg/Nm3. Dust settling chambers, After Burning chambers followed by ESPs will be provided to DRI kilns to bring down the SPM blow permissible limit. Bag filters will also be provided to dedusting stacks. Water sprinkling, black topping of internal roads and greenbelt development will be carried out to control the fugitive dust emission due to vehicular movement. Dust suppression and extraction system comprising of Bag filters, spray nozzles dry fog system etc. will be provided to control secondary fugitive emission during raw material handling and preparation.

 

Total water requirement after the proposed expansion from Jhargram Municipality / PHE department is revised from 800 m3/day to 3,180 m3/day (including existing requirement) vide letter dated 17th October, 2008. Effluent treatment plant will be provided to treat the process water.  Zero discharge will be adopted.

 

Solid waste @ 150 MTPD will be generated from the plant. Coal char generated will be used in Power plant (AFBC boiler).  Bag filter dust will be approximately 150 MTPM. Slag will be disposed off to slag dumping area.  However, during presentation PAs informed that Char and ESP dust from DRI Kilns will be disposed in mooram mines or for road making and land filling. Kiln accretion and slag will be used in Cement plant. Iron ore fines and Coal fines will be used in Sinter plant. Stabilized STP sludge will be used as manure in greenbelt development.

 

Green belt will be developed in 21 acres, in addition to the exisiting 15 acre greenbelt covering total area 36 acres (30 %) out of total 120 acres. Noise from the proposed expansion will be within permissible limits. Power requirement of 4 MW earlier proposed is revised to 40 MW and will be met from WBSEB grid and CPP (25 MW).  LDO will be used as fuel for kiln start-up and for intermittent use during operation.

 

            PAs informed to the Committee that environmental clearance for the existing sponge iron plant (10x100 TPD) and captive power plant (25 MW) is accorded by the Ministry on 17th March, 2008 with public hearing held on 17th March, 2008. During proposed expansion, Sponge Iron Plant (4x100 TPD & 2x350 TPD) and Submerged Arc furnace (6x9 MVA) for the Ferro Alloy Plant will be installed. Since the environmental clearance for the existing sponge iron plant is recently accorded, the Committee agreed for the preparation of revised and updated EIA/EMP incorporating following as additional TORs :

 

1.      Actual land requirement, classification of land, current status of acquisition of land with break-up details (Government / Private / Forest land etc.), rehabilitation and resettlement as per the policy of the Govt. of Orissa should be incorporated.

2.      Data on air emissions, wastewater generation and solid waste management for the existing plant should be incorporated.

3.      Point-wise compliance to the specific and general conditions stipulated in the environmental clearance for the existing plant.

4.      Impact of the transport of the raw materials and end products on the surrounding environment after expansion should be assessed and provided.

5.      An action plan to control secondary fugitive emissions after expansion as per latest standards issued by the Ministry in May, 2008 and monitoring should be included.

6.      Permission for the drawl of 3,180 m3/day water from Jhargram Municipality / PHE department and water balance data including quantity of effluent generated, recycled and reused and discharged is to be provided.

7.      Methods adopted/to be adopted for the water conservation should be included.

8.      Action plan for solid/hazardous waste generation, storage, utilization and disposal particularly use of Char in FBC boiler should be included.

9.      A plan for the utilization of gases in the WHRB for generating power should be incorporated.

10.  End use of solid waste and its composition should be covered.  Toxic metal content in the waste material and its composition should also be incorporated particularly of slag.

11.  Provision of Toxic Chemical Leachability Potential (TCLP) test for the Chrome slag and its end use should be included.  Proposal for the recovery of the Ferro chrome from the slag and its proper disposal should be mentioned.

12.  Commitment that no Ferro chrome will be manufactured without prior approval of the Ministry.

13.  Energy balance data for Sponge Iron Plant, Ferro Alloy Plant and Captive Power Plant should be included.

14.  Green belt development plan in 33 % area and a scheme for rainwater harvesting have to be put in place.

15.  A note on identification and implementation of Carbon Credit project.

16.  Total capital cost and recurring cost/annum for environmental pollution control measures should also be included.

17.  Any litigation / court case pending against the proposal should also be included.

18.  Action Plan for the implementation of the recommendations made for the Sponge Plants in the CREP guidelines must be prepared.

 

The Expert Committee (Industry) recommended that the PAs may be communicated the above additional ‘TORs’ for the preparation of EIA/EMP.  As soon as the final EIA/EMP report is prepared as per the ‘General Structure of EIA’ given in Appendix III and IIIA in the EIA Notification, 2006, the same may be submitted by the PAs to the MOEF for prior environmental clearance. Due to expansion of the proposed unit in the same campus, the Committee recommended the proposal as per Section 7 (ii) of EIA Notification, 2006 requiring no public hearing.

4.28     Expansion of Sponge Iron Plant (42,000 TPA to 1,02,000 TPA) and Captive Power Plant (7.5 MW) at Lohamellya, P.O. Montipa Mohanpur, Jhargram, District Paschim Medinipur, West Bengal by M/s Aryavrata Trading Pvt. Ltd. (TOR)

The project authorities and their consultant gave a detailed presentation on the salient features of the project and proposed environmental protection measures to be undertaken alongwith the draft Term of References for the preparation of EIA/EMP. All the Sponge iron Plants with > 200 TPD have been listed at S.N. 3(a) under Category ‘A’ and appraised at the Central level.  Capacity of the proposed sponge iron plant is 300 TPD.

 

M/s Aryavrata Trading Pvt. Ltd. has proposed to expand its Sponge Iron Plant (42,000 TPA to 1,02,000 TPA) finished product by installing 2x100 TPD Rotary kiln and 7.5 MW CPP unit at Lohamellya, P. O. Montipa Mohanpur, Jhargram, District Paschim Medinipur, West Bengal.  During presentation, PAs informed that the capacity of Sponge Iron plant is being enhanced from 42,000 TPA to 1,02,000 TPA. The proposed expansion will be taking place within existing premises covering an area of 20.135 acres. Kangsabati River flows at a distance of 15 km from the site. There are some protected forests around the site. Jhargram village is at a distance 5-6 km away from the site. Proposed site is located in the proximity of Jharkand / Orissa iron ore reserves.  Total cost of the proposed expansion would be Rs. 63.75 Crores. Rs. 5.6873 Crores and Rs. 5.0-6.0 Lakhs will be earmarked towards total capital cost and recurring cost/annum for environmental pollution control measures of the proposed expansion.

 

Existing plant consists of three lines with 40 TPD, 50 TPD and 50 TPD Rotary kilns. Proposed expansion will be carried out in 3 phases continuously by installing one 100 TPD rotary kiln in the Phase-1 and another in Phase-2.  Phase-3 involves setting up of WHRB (2 x 11 TPH, 5 MW) & AFBC (24 TPH, 2.5 MW) based CPP of capacity 7.5 MW. Installation of WHRB and AFBC in Phase 3 is not acceptable to the Committee and asked to install simultaneously.

Main raw materials required are Iron ore (93,000 TPA) and Dolomite (2,400 TPA). Coal (84,000 TPA) will be used as a fuel as well as ore reductant.

Waste gases from the kiln will pass through a dust settling chamber where heavier particles will settle down. Thereafter, the flue gases pass through an After Burning Chamber (ABC) where un-burnt CO will be completely burnt in presence of excess air. Water is sprayed in ABC where the dust particles coagulate and settle in Dust settling tank. After the ABC, the kiln off gases will be carried through a duct to the gas-conditioning tower (GCT), where water will be sprayed to settle the SPM as well as to cool down and then passed through an ESP and finally vented in to atmosphere through a chimney. After the installation of WHRB, the waste gases from ABC will passed through the WHRB to recover the sensible heat and thereby, cool the gases before entering the ESP. Water sprinkler arrangement will be used in the proposed expansion for wetting the dry ash. ESP dust from hoppers will be conveyed through a pug mill where it is sprayed with water. ESP will be provided to WHRB, AFBC and Kilns. Gaseous emissions from AFBC boiler will be passed through ESP and disposed through high stack. Particulate matter will be generated from various sources like rotary kilns, CPP, vehicles and DG sets etc. Dust suppression system comprising of bag filters with cyclones will be installed in raw material handling and product handling sections. Dry fogging/misting system will be installed at all the material transfer points to restrain the fugitive dust from escaping in to surrounding area. All the internal roads will be either asphalted or concreted.

 

Total ground water requirement for the rotary kiln and CPP will be 340 m3/day and 1,320 m3/day respectively for make-up and the required permission is under the process of approval. Thus, total ground water requirement will be 1,660 m3/day.  Wastewater from water treatment plant and cooling tower blow down will be collected and used for dust suppression.  Boiler blow down and backwash from CPP will be neutralized and treated before recycling or use in gardening/ dust suppression. Kiln cooling water will be recirculated. The gas conditioning tower quenching water will also be re-circulated after settling the SPM. The ablution / domestic use water will be discharged through septic tanks and soak pits within the boundary of the plant. A guard drain will be provided around the plant to collect rain water and disposed outside through a single outlet through a holding tank for gravity separation of particulates. 

 

Dolochar will be used as fuel in AFBC alongwith coal fines. Ore fines generated during kiln operation will be sold. Accretion slag will be used as sub-base material for road construction. Ash from CPP will be used for land filling inside the plant premises. Ash handling system envisaged for CPP will be of dense phase pneumatic handling system. ESP dust will be routed through a pug mill for disposal to brick makers. Sludge generated from GCT will be used for brick making/ land filling. PAs vide letter dated 3rd September, 2008 informed that solid waste generated from the existing plant is being used for filling of low land of brick fields and abundant Morum Khadans. PAs have applied for long term lease of Morum Khadans for disposal of solid waste from proposed expansion.

 

PAs also informed that green belt will be developed in 6.65 acres which will be 33% of total plant area. Noise will be generated during operation of DG sets, Kilns, Crushers, Screens etc. and in most cases the noise levels will be below permissible limits of 90 dB(A). The ambient noise levels predicted in the area will range between 55 to 60 dB(A) during operation phase.

 

Total power requirement after the proposed expansion is revised to 1100 KVA instead of 1500 KVA proposed earlier and will be sourced from WBSEB.  280 TPD of coal as fuel will be used in the rotary kiln. In the CPP, WHRB utilizes the waste gases from the kiln, whereas the AFBC will utilize fresh coal (8120 TPA), coal fines (9477 TPA) and Char (9758 TPA) from Sponge Iron plant. DG sets of capacity 500 KVA and 750 KVA will be installed and will run on HSD. 

            After detailed deliberations, the Expert Appraisal Committee (Industry) recommended the proposal for the preparation of EIA/EMP as per the following TORs:  

1.      Present land use should be prepared based on satellite imagery.

2.      Actual land requirement, classification of land, acquisition status should be incorporated.

3.      Location of national parks / wildlife sanctuary / reserve forests within 10 km. radius should specifically be mentioned.

4.      A list of industries containing name and type in 25 km radius should be incorporated.

5.      List of raw material required and source should be included.

6.      Manufacturing process details of the Sponge Iron Plant should be included.

7.      Data on air emissions, wastewater generation and solid waste management for the existing plant should be incorporated.

8.      ‘Consent to Establish’ issued by the WBPCB for the existing plant.

9.      Site-specific micro-meteorological data using temperature, relative humidity, hourly wind speed and direction and rainfall should be collected.

10.  Ambient air quality at 8 locations within the study area of 10 km., aerial coverage from project site with one AAQMS in downwind direction should be carried out.

11.  The suspended particulate matter present in the ambient air must be analyzed for the presence of poly-aromatic hydrocarbons (PAH), i.e. Benzene soluble fraction.  Chemical characterization of RSPM and incorporating of RSPM data.

12.  Determination of atmospheric inversion level at the project site and assessment of ground level concentration of pollutants from the stack emission based on site-specific meteorological features.

13.  Air quality modeling for Sponge Plant, WHRB and AFBC for specific pollutants needs to be done.  APCS for the control of emissions from the kiln, AFBC and WHRB should also be included.

14.  Impact of the transport of the raw materials and end products on the surrounding environment should be assessed and provided.

15.  An action plan to control secondary fugitive emissions as per latest standards issued by the Ministry in May, 2008 and monitoring should be included.

16.  One season data for gaseous emissions other than monsoon season is necessary.

17.  Permission for the drawl of 1,660 m3/day ground water from the SGWB/CGWA and water balance data including quantity of effluent generated, recycled and reused and discharged is to be provided.

18.  Justification for the use of 1,660 m3/day ground water and methods adopted/to be adopted for the water conservation should also be included.

19.  Surface water quality of nearby rivers (60 m upstream and downstream) and other surface drains at eight locations must be ascertained. 

20.  Ground water monitoring minimum at 8 locations and near solid waste dump zone, Geological features and Geo-hydrological status of the study area are essential as also.  Ecological status (Terrestrial and Aquatic) is vital.

21.  A commitment regarding installation of WHRB and AFBC simultaneously and not in Phase 3 as proposed should be included.

22.  Action plan for solid/hazardous waste generation, storage, utilization and disposal particularly use of Char in FBC boiler should be included.

23.  A plan for the utilization of gases in the WHRB for generating power should be incorporated.

24.  Energy balance data for Sponge Iron Plant should be included.

25.  Risk assessment and damage control needs to be addressed.

26.  Occupational health of the workers needs elaboration.

27.  Green belt development plan in 33 % area and a scheme for rainwater harvesting have to be put in place.

28.  Socio-economic development activities need to be elaborated upon.

29.  A note on identification and implementation of Carbon Credit project.

30.  Total capital cost and recurring cost/annum for environmental pollution control measures should also be included.

31.  Any litigation / court case pending against the proposal should also be included.

32.  Action Plan for the implementation of the recommendations made for the Sponge Plants in the CREP guidelines must be prepared.

 

The Expert Committee (Industry) recommended that the PAs may be communicated the above ‘TORs’ for the preparation of final EIA/EMP. As soon as the final EIA/EMP report is prepared as per the ‘General Structure of EIA’ given in Appendix III and IIIA in the EIA Notification, 2006, the same may be submitted by the PAs to the MOEF for prior environmental clearance. The Committee noted that no public hearing is required due to expansion of the proposed unit in the same campus as per Section 7 (ii) of EIA Notification, 2006.

4.29     Expansion of Steel Plant at Topadihi, P.O. Barbil, District Keonjhar, Orissa by M/s Deepak Steel & Power Ltd.  (TOR)

The project authorities and their consultant gave a detailed presentation on the salient features of the project and proposed environmental protection measures to be undertaken alongwith the draft Term of References for the preparation of EIA/EMP. All the steel plants have been listed at S.N. 3(a) under Category ‘A’ and appraised at the Central level. 

 

M/s Deepak Steel & power Ltd. has proposed for Phase-I & Phase-II expansion of Sponge Iron Plant at Topadihi, P.O. Barbil, District Keonjhar, Orissa. The land acquired for the proposed project will be 134 acre of which 68 acres is already acquired and the rest is in the process of acquisition. Phase-I expansion will be taking place within the existing plant premises whereas the Phase-II expansion will be carried out in the additional land to be provided by IDCO.  Total cost of the proposed expansion will be Rs. 223.00 Crores. Rs. 2.2 Crores and Rs. 22.00 Lakhs will be earmarked towards total capital cost and recurring cost for environmental pollution control measures. Following will be the existing and proposed facilities:

 

Facilities

Existing

Phase-I

Phase-II

Combined

Phase-I & II

DRI Plant

2x50 TPD

2x100 TPD

1x350 TPD

--

1x350 TPD

1x350 TPD

Mini Blast Furnace

--

1,50,000 TPA

(262 m3)

--

1,50,000 TPA

(262 m3)

Induction Furnace

--

1x7T; 2x15T

2x20 T

1x7T, 2x15T, 2x20 T

CCM

--

1,10,000 MTPA

(7/11 meter)

--

1,10,000 MTPA

(7/11 meter)

Captive Power Plant

           WHRB

           AFBC

 

4 MW

4 MW

 

--

 

 

8x2 MW

12x2 MW

 

8x2 MW

12x2 MW

 

The existing plant has 2x50 TPD (12,000 TPA capacity each) and 2x100 TPD (24,000 TPA capacity each) sponge Iron kilns. During presentation, PAs informed that another 1x350 TPD Sponge iron plant is under construction. Sponge Iron plant (1x350 TPD), WHRB based power plant (2x8 MW), Concast (7/11 meter, 110000 TPA), Induction furnace (1x7T, 2x15T and 2x20 T) and Mini blast furnace (262 m3, 150000 TPA) will be installed during proposed expansion.

 

Raw materials required will be Iron ore lumps, Coke/coke, Quartzite, Dolomite, Sponge Iron, Pig Iron and hot metal. 

ESP and bag filters will be provided to Sponge iron plant. Bag filters with cyclone will be provided to Mini Blast Furnace. Pulse jet bag filters will be provided to Induction furnace. ESP will be provided to Power plant. Fume extraction system followed by exhaust through stack will be provided to Continuous Casting Machine. Dust will be generated during transportation of raw materials and construction. Coal/iron ore screening zone, raw material stock yards, ground hoppers, converyor belts and solid waste dumpyards will be provided with water sprinklers and water foggers. All internal plant roads will be asphalted and plant surface will be concreted to avoid fugitive emissions.

 

Total water requirement from Topadihi nala, a tributary of Karo river will be 200 m3/hr. No industrial effluent will be generated as the exhaust water is recirculated through cooling tower and water basin. Domestic effluent will be discharged to soakpit via septic tank. STP is also proposed. Domestic wastewater will be used for hardening purposes inside the plant itself. Zero discharge will be adopted.

 

Char, Slag and Flyash will be dumped in a land area of 10 acres. Char will completely used in FBB. Waste refractories, Kiln accretions and other miscellaneous waste will be dumped in low-lying areas. Granulated BF slag will be sold to cement manufacturers. Treatment plant sludges will be disposed by dumping. Bag house dust will be recycled. Fly ash and ESP dust will be utilized in brick making. Iron ore fines and Coal fines from Raw material handling section, Dust from Induction furnace will be recycled to Sinter plant. Usable scrap will be recycled in SMS. ESP dust and bottom ash from AFBC will be sent for dry disposal. Spent oil and lubricants will be sold to SPCB authorized recyclers.

 

Green belt will be developed in 33 % area. Noise generated from Rotary kiln and vehicular movement will be within permissible limits. Adequate measures will be taken to minimize sound pollution below the pollution norms.

 

Power required will be sourced from CPP (WHRB & AFBC) and Grid, respectively. Coal (1,30,000 TPA) for DR plant and Light Diesel oil (2000 LPD) will be used as start-up fuels for DR Kiln and FBB.

After deliberating on the facts presented the Expert Appraisal Committee (Industry) recommended the proposal for the preparation of EIA/EMP as per the following TORs :

1.      Present land use should be prepared based on satellite imagery.

2.      Location of national parks / wildlife sanctuary within 10 km. radius should specifically be mentioned.

3.      Permission and recommendations of the State Forest Department regarding impact of proposed expansion on the surrounding reserve forests, if any, should be included.

4.      Actual land requirement, classification of land, current status of acquisition of land with break-up details (Government / Private / Forest land etc.), rehabilitation and resettlement as per the policy of the Govt. of Orissa should be incorporated.

5.      Current status of construction activities for phase I and phase II should be included.

6.      Site-specific micro-meteorological data using temperature, relative humidity, hourly wind speed and direction and rainfall should be collected.

7.      A list of industries containing name and type in 25 km radius should be incorporated.

8.      Residential colony should be located in upwind direction.

9.      List of raw material required and source should be included.

10.  Manufacturing process details for all the plants viz. DRI Plant, Blast Furnace, Induction Furnace, Continuous Casting Machine, Captive Power Plant (WHRB & AFBC) etc. should be included.

11.  Data on air emissions, wastewater generation and solid waste management for the existing plant should be incorporated.

12.  Ambient air quality at 8 locations within the study area of 10 km., aerial coverage from project site with one AAQMS in downwind direction should be carried out.

13.  The suspended particulate matter present in the ambient air must be analyzed for the presence of poly-aromatic hydrocarbons (PAH), i.e. Benzene soluble fraction.  Chemical characterization of RSPM and for incorporating of RSPM data.

14.  Impact of the transport of raw material and finished product on the surrounding environment should be assessed and provided

15.  Determination of atmospheric inversion level at the project site and assessment of ground level concentration of pollutants from the stack emission based on site-specific meteorological features. Air quality modeling for steel plant for specific pollutants needs to be done. 

16.  Plant-wise air pollution control measures proposed for the control of gaseous emissions from all the sources should be incorporated.

17.  A note on control of fugitive and secondary emissions from as per CPCB guidelines from all the sources should be incorporated.

18.  One season data for gaseous emissions during winter season is necessary.

19.  Permission for the drawl of 200 m3/hr water from Karo river from the concerned department and water balance data including quantity of effluent generated, recycled and reused and discharged should be provided. Methods adopted/to be adopted for the water conservation.

20.  Surface water quality of nearby rivers (60 m upstream and downstream) and other surface drains at eight locations must be ascertained. 

21.  Ground water monitoring minimum at 8 locations and near solid waste dump zone, Geological features and Geo-hydrological status of the study area are essential as also.  Ecological status (Terrestrial and Aquatic) is vital.

22.  A note on treatment of wastewater from different plants including coke oven plant, recycle and reuse for different purposes should be included.

23.  Action plan for solid/hazardous waste generation, storage, utilization and disposal particularly char and fly ash. Assurance that 100 % char will be used in the FBC boiler and copies of MOU regarding utilization of ash should be included.

24.  MOU signed with the Cement manufacturers for utilizing granulated BF slag should be included.

25.  Generation and utilization of waste/fuel gases from BF plant and their utilization in the CPP have to be set out.

26.  Risk assessment and damage control needs to be addressed.

27.  Occupational health of the workers needs elaboration.

28.  Green belt development plan in 33 % area and a scheme for rainwater harvesting have to be put in place.

29.  Socio-economic development activities need to be elaborated upon.

30.  A note on identification and implementation of Carbon Credit project should be included.

31.  An Action Plan for the implementation of the recommendations made for the Steel Plants in the CREP guidelines must be prepared.

32.  Total capital cost and recurring cost/annum for environmental pollution control measures should also be included.

33.  A tabular chart for the issues raised and addressed during public hearing/public consultation should be provided.

34.  Any litigation / court case pending against the proposal should also be included.

 

The Expert Committee (Industry) decided that PAs may be communicated the above ‘TORs’ for the preparation of EIA/EMP.  As soon as the draft EIA/EMP report is prepared as per the ‘General Structure of EIA’ given in Appendix III and IIIA in the EIA Notification, 2006, the same may be submitted by the PAs to the Orissa Pollution Control Board (OPCB) for conducting public hearing as per EIA Notification, 2006.  On finalization of EIA/EMP prepared as per TORs addressing all concerns set out EIA/EMP should be submitted to the MOEF for prior environmental clearance.

4.30     Expansion of Sponge Iron Plant (Phase-II) at Topadhi, P.O. Barbil, District Keonjhar, Orissa by M/s Deepak Steel & power Ltd. (TOR)

The Committee asked PAs to merge proposal for phase II with the phase I so that both the proposal are considered together since both are located in the same campus. Therefore, this file is closed after merging proposal for phase II with phase I. 

4.31     Expansion of Sponge Iron Plant (57,600 TPA) with Captive Power Plant (15 MW), MS ingot (1,72,800 TPA) & Ferro Alloy Plant (23,460 TPA) at Village & Post Barjora, District Bankura, West Bengal by M/s M. B. Ispat Corporation Limited (TOR)

The project authorities and their consultant gave a detailed presentation on the salient features of the project and proposed environmental protection measures to be undertaken alongwith the draft Term of References for the preparation of EIA/EMP. All the Sponge iron Plants (<200 TPD) have been listed at S.N. 3(a) under Category ‘A’ and appraised at the Central level due to non-existent of SEIAA/SEAC at the State level in the State of Orissa.   Capacity of the proposed sponge iron plant is 300 TPD.

 

M/s M. B. Ispat Corporation Limited has proposed to expand its existing Sponge Iron unit at Village & Post Barjora, District Bankura, West Bengal.  The proposed expansion will be within the existing plant premises in 30 acres.  No National park / Wild life sanctuary / Reserve forest is located within 10 km radius of proposed project. Total cost of the proposed expansion will be Rs. 16,964.54 Lakhs. Rs. 1056.74 Lakhs and Rs. 90.00 Lakhs will be earmarked towards total capital cost and recurring cost/annum for environmental pollution control measures.

 

Sponge iron plant (2x100 TPD) exists in the present premises. Proposed expansion involves the setting up of Sponge Iron plant (3x100 TPD, 90,000 TPA), Captive Power Plant (15 MW; AFBC 1x11 MW; WHRB 2x2 MW), Ferro Alloy Plant (2x9 MVA, 23,460 TPA), Induction furnace (4x15T, 1,72,800 TPA), Ladle Refining Furnace  (1x18T), AOD Converter (1x25 T), Continuous Casting Machine (1x3 Strands). Following are the details of the existing and proposed facilities:

 

S.N

Facilities

Existing

Proposed expansion

1

Sponge Iron plant

(2x100 TPD)

(3x100 TPD)

2

Ferro alloys Plant

--

(2x9 MVA)

3

Induction Furnace

--

4x15 T

4

Ladle Refining Furnace

--

1x18 T

5

AOD Converter

--

1x25 T

6

Continuous Casting Machine

--

1x3 Strands

7

Captive Power Plant

             AFBC

             WHRB

--

15 MW

1x11 MW

2x2 MW

 

Following will be the products from the existing and proposed facilities:

 

S.N

Products

Existing

Proposed

1

Sponge Iron

57,600 TPA

90,000 TPA

2

Ferro alloys

--

23,460 TPA

3

Ingots

--

1,72,800 TPA

4

Power

--

15 MW

 

Raw materials required will be Iron ore (1,44,000 TPA), Coal (14,400 TPA), Manganese ore (33385 TPA for the production of Fe-Mn & 17812 TPA for the production of Si-Mn) and Dolomite (4500 TPA).

ESPs will be installed in DRI plant, AFBC boiler to bring down the particulate matter in the exhaust gas to <100 mg/m3 to comply with CREP recommendations.  Bag filters will be provided to control the fugitive emissions from Ferro alloys plant and Raw material handling section. Bag filters will be utilized to control the particulate matter emissions from Induction furnace. Clean BOF gas after primary de-dusting and scrubbing will be used as a gaseous fuel in the steel plant. Centralized vacuum cleaner for cleaning dust depositions in the upper floors of converter where bulk material handling operations take place.  De-dusting units will be connected to After Burning Chamber (ABC) and finally emitted through common stack with kiln off-gas emissions. All the de-dusting units will be connected to a stack having a minimum height of 30m.  Fugitive emission from material handling, conveying and screening operations will be controlled by Fabric filters or ESPs. Water sprinkling arrangement will be provided at raw material heaps and on land around crushing and screening units for dust suppression. Fume extraction system will be provided to the smelting unit. Fumes generated will be sucked through a hood/canopy suitable located above the main furnace and shall be carried by means of a blower through ducting system and bag filter to the chimney for discharging it to the atmosphere. Dry fogging system will be installed to control fugitive emissions.

 

Total water requirement for the unit will be 2,190 KLD and will be sourced from Barjora Panchayet Samity, which receives water from Durgapur barrage maintained by Damodar Valley Corporation. Scrubbing water will be recycled as much as possible after coagulation and sedimentation of suspended solids. Any discharge from BOF complex shall be utilized for internal use or recycling, without letting them to meet any outfalls. Discharges which are not re-used can only meet outfall, only after conforming to the specified effluent standards. 

 

At present, the char generated in the plant is being partly stored and partly sold as briquettes. After installation of AFBC, the Char (36,000 TPA) generated will be used in AFBC boiler for power generation. Ferro Manganese Slag (20,640 TPA) generated will be used in the manufacture of Silico-Manganese. Silico-Manganese slag (25,806 TPA) will be used as boulders for road / land development. Induction furnace slag (16,000 TPA) will be used for land leveling, compacting of roads. Bag filter dust (100 TPA) will be sent to sinter plants. Mill scales (200 TPA) will be used for land development. Steel scarp (2400 TPA) will be re-used in the SMS. Fly ash (25,000 TPA) will be used for cement or brick manufacturing. Collected dusts and/or sludge from IF will be re-cycled. All the wastes from pollution control systems will be re-used or recycled to the extent possible. 

 

Existing green belt sprawls over a 6 acre area. Additionally, green belt will be developed in another 3 acre area. Therefore, total area under green belt after the proposed expansion will be 9 acres.

 

          Noise will be generated from Induction furnace, DRI plant, AFBC, WHRB, Turbo generator and Ferro alloys plant. Ear muffs / ear plugs will be provided to employees working in high noise prone areas. Over exposure of employees to high noise will be avoided. Total power requirement of 25 MW, instead of 15 MW proposed earlier, will be sourced from Captive power plant as well as West Bengal State Electricity Distribution Company Limited. A 1x900 KVA DG set running on Diesel (150 lit/hr) will be installed to provide the necessary power-backup.

 

            After detailed deliberations, the Expert Appraisal Committee (Industry) recommended the proposal for the preparation of EIA/EMP as per the following TORs:  

 

1.      Present land use should be prepared based on satellite imagery.

2.      Actual land requirement, classification of land, acquisition status, rehabilitation and resettlement as per the policy of the Govt. of West Bengal should be incorporated.

3.      Location of national parks / wildlife sanctuary / reserve forests within 10 km. radius should specifically be mentioned.

4.      A list of industries containing name and type in 25 km radius should be incorporated.

5.      List of raw material required and source should be included.

6.      Manufacturing process details of the Sponge Iron plant, Ferro Alloy Plant, Induction Furnace, Ladle Refining Furnace, AOD Converter, Continuous Casting Machine, Captive Power Plant (AFBC & WHRB) etc. should be included.

7.      Data on air emissions, wastewater generation and solid waste management for the existing plant should be incorporated.

8.      Site-specific micro-meteorological data using temperature, relative humidity, hourly wind speed and direction and rainfall should be collected.

9.      Ambient air quality at 8 locations within the study area of 10 km., aerial coverage from project site with one AAQMS in downwind direction should be carried out.

10.  The suspended particulate matter present in the ambient air must be analyzed for the presence of poly-aromatic hydrocarbons (PAH), i.e. Benzene soluble fraction.  Chemical characterization of RSPM and incorporating of RSPM data.

11.  Determination of atmospheric inversion level at the project site and assessment of ground level concentration of pollutants from the stack emission based on site-specific meteorological features.

12.  Air quality modeling for all the plants proposed for specific pollutants needs to be done.  APCS for the control of emissions from the kiln and WHRB should also be included.

13.  Impact of the transport of the raw materials and end products on the surrounding environment should be assessed and provided.

14.  An action plan to control secondary fugitive emissions as per latest standards issued by the Ministry in May, 2008 and monitoring should be included.

15.  One season data for gaseous emissions other than monsoon season is necessary.

16.  Permission / copy of MOU signed with the Samity for the drawl of 2,190 m3/day water from Barjora Panchayet Samity and water balance data including quantity of effluent generated, recycled and reused and discharged is to be provided. Methods adopted/to be adopted for the water conservation should also be included.

17.  Surface water quality of nearby river (60 m upstream and downstream) and other surface drains at eight locations must be ascertained. 

18.  Ground water monitoring minimum at 8 locations and near solid waste dump zone, Geological features and Geo-hydrological status of the study area are essential as also.  Ecological status (Terrestrial and Aquatic) is vital.

19.  Action plan for solid/hazardous waste generation, storage, utilization and disposal particularly use of Char in FBC boiler should be included.

20.  End use of solid waste and its composition should be covered. Toxic metal content in the waste material and its composition should also be incorporated particularly of slag.

21.  Provision of Toxic Chemical Leachability Potential (TCLP) test for the slag and its end use should be included.  Proposal for the recovery of the Ferro chrome from the slag, if proposed to be manufactured, and its proper disposal should be mentioned.

22. Commitment that no Ferro chrome will be manufactured without prior approval of the Ministry.

23.  A plan for the utilization of gases in the WHRB for generating power should be incorporated.

24.  Energy balance data for Sponge Iron Plant, Ferro Alloy Plant and Captive Power Plant should be included.

25.  Risk assessment and damage control needs to be addressed.

26.  Occupational health of the workers needs elaboration.

27.  Green belt development plan in 33 % area and a scheme for rainwater harvesting have to be put in place.

28.  Socio-economic development activities need to be elaborated upon.

29.  A note on identification and implementation of Carbon Credit project.

30.  Total capital cost and recurring cost/annum for environmental pollution control measures should also be included.

31.  A tabular chart for the issues raised and addressed during public hearing/public consultation should be provided.

32.  Any litigation / court case pending against the proposal should also be included.

33.  Action Plan for the implementation of the recommendations made for the Steel Plants in the CREP guidelines must be prepared.

 

            The Expert Committee (Industry) recommended that the PAs may be communicated the above ‘TORs’ for the preparation of EIA/EMP.  As soon as the draft EIA/EMP report is prepared as per the ‘General Structure of EIA’ given in Appendix III and IIIA in the EIA Notification, 2006, the same may be submitted by the PAs to the West Bengal Pollution Control Board (WBPCB) for conducting public hearing as per EIA Notification, 2006. On finalization of EIA/EMP prepared as per TORs and addressing and incorporating all concerns raised by public hearing / public consultation, the same should be submitted to the MOEF for prior environmental clearance.

 

4.32     Ferro Alloy Plant (70,372 TPA) alongwith Iron Ore Screening Plant (1,80,000 TPA) at Village Bamunara, Bamunara Industrial Area, District Burdwan, West Bengal by M/s M. B. Ispat Corporation Limited (TOR)

           

The project authorities and their consultant gave a detailed presentation on the salient features of the project and proposed environmental protection measures to be undertaken alongwith the draft Term of References for the preparation of EIA/EMP. All the Ferro Alloy Plants are kept at S.N. 3(a) under primary metallurgical industry under category ‘A’ and appraised at Central level.

 

M/s M. B. Ispat Corporation Limited has proposed to set up Ferro Alloy Plant (4x9 MVA) alongwith Iron Ore Screening Plant (1x50 TPH; 1,80,000 TPA) at Village Bamunara, Bamunara Industrial Area, District Burdwan, West Bengal. The land acquired for the proposed project will be 11 acres. River Damodar flows at a distance of 2 km from the proposed site. Durgapur is located at a distance of 1 km from the proposed site. No National park / Wild life sanctuary / Reserve forest is located within 10 km radius of proposed project. The area falls in Earthquake Zone-III. Total cost of the proposed project would be Rs. 5,867.42 Lakhs. Rs. 270.00 Lakhs  and Rs. 25.00 Lakhs will be earmarked towards total capital cost and recurring cost/annum for environmental pollution control measures. PAs also informed that project is located in critically polluted area.

 

Ferro Manganese (40,059 TPA), Silico-Manganese (30,313 TPA), Iron ore (>5 mm,; 90,000 TPA, Iron ore (2-5 mm; 90,000 TPA) will be the products from the proposed plants:.  

Main Raw materials required for Ferro Manganese production will be Manganese ore (100148 TPA) and Dolomite (10815.93 TPA). For Silico-Manganese production, the raw materials required will be Manganese ore (1,00,148 TPA) and Dolomite (8,185 TPA). Iron ore lumps required for Screening Plant will be 1,80,000 TPA.

Fugitive emission from material handling, conveying and screening operations will be controlled by Fabric filters or ESPs.  Fugitive emissions will be treated by dampening and / by the use of crust formers.  Fume extraction system will be provided to the smelting unit. Fumes generated will be sucked through a hood/canopy suitable located above the main furnace and shall be carried by means of a blower through ducting system and bag filter to the chimney for discharging it to the atmosphere. Bag filters will be provided to Iron screening plant. During presentation, PAs informed that Dry fogging system will be provided at raw material handling area and material transfer points to control fugitive emissions.

 

Total water requirement of 80 KLD will be met from ADDA/borewell and PAs have applied to the Ground Water Authority for necessary permission. ‘Zero’ discharge will be adopted in the plant.  Domestic effluent will be used in greenbelt and for dust suppression.

 

Ferro Manganese slag (35,252) will be consumed in the production of Silico-Manganese.  Silico-Manganese Slag (33,344 TPA) will be used for road / land development. All efforts will be made to minimize the generation of wastes and maximize utilization of wastes. Wherever it becomes unavoidable, except resorting to option of dumping, in that cases, the wastes will be disposed under controlled conditions.  All the wastes from pollution control systems will be re-used or recycled to the extent possible. 

 

Green belt is proposed in 3.2 acres out of a total area of 11 acres.  Ear muffs /earplugs will be provided to employees working in high noise prone areas. Over exposure of employees to high noise will be avoided. Power requirement for Ferro alloy plant and Iron screening plant 37 MVA and 50.4 MVA respectively and sourced from Damodar Valley Corporation. Coal requirement of the proposed plant will be 28149 TPA. No fuel is required for the project.

 

After deliberating on the facts presented before the Expert Appraisal Committee (Industry) recommended the proposal for the preparation of EIA/EMP as per the following TORs:

1.      ‘Proof’ / ‘Notification’ issued by the State Govt. indicating location of the project in notified Bamunara Industrial Area should be incorporated.

2.      Present land use based on satellite imagery should be incorporated.

3.      Site-specific micro-meteorological data using temperature, relative humidity, hourly wind speed and direction and rainfall is necessary.

4.      Location of National Park and Wild life sanctuary within 10 Km radius of the project should be included.

5.      Permission and recommendations of the State Forest Department regarding impact of proposed expansion on the surrounding reserve forests, if any, should be included.

6.      List of raw material required and source should be included.

7.      Design details of Submerged Arc Furnace and Iron Ore Screening Plant and manufacturing process details should be included. Provision of close type of Iron Ore Screening Plant should be included.

8.      Ambient air quality at 8 locations within the study area of 3 km., aerial coverage from project site should be included. Location of one AAQMS should be in downwind direction.

9.      Ambient air quality modeling for Ferro Alloy Plant and Iron Ore Screening Plant should be included. 

10.  Methods to control emissions from the Submerged Arc Furnace and Iron Ore Screening Plant should be included.

11.  One season data for gaseous emissions and inclusion of existing emission data should be ensured.

12.  An action plan to control and monitor secondary fugitive emissions as per CPCB guidelines should be included.

13.  Determination of atmospheric inversion level at the project site and assessment of ground level concentration of pollutants from the stack emission based on site-specific meteorological features.

14.  ‘Permission’ for the drawl of 80 m3/day water from from ADDA / borewell from the concerned department/SGWB/CGWA should be included.  Water balance cycle data including quantity of effluent generated, recycled and reused and discharged should be incorporated.

15.  Ground water monitoring minimum at 8 locations and also near solid waste dump zone should be carried out. Geological features and Geo-hydrological status of the study area and ecological status (Terrestrial and Aquatic) should be included.

16.  Solid waste generation, storage, utilization and disposal from ferro alloy plant and iron ore screening plant should be included. 

17.  End use of solid waste and its composition should be covered.  Toxic metal content in the waste material and its composition should also be incorporated particularly of slag.

18.  Provision of Toxic Chemical Leachability Potential (TCLP) test for the Chrome slag and its end use should be included.  Proposal for the recovery of the Ferro chrome from the slag and its proper disposal should be mentioned, if applicable.

19.  Commitment that no Ferro chrome will be manufactured without prior approval of the Ministry.

20.  Risk assessment and damage control should be included.

21.  Occupational health of the workers should be incorporated.

22.  An action plan to develop green belt in 33 % area should be included.

23.  Scheme for rainwater harvesting should be incorporated.

24.  Socio economic development activities should be in place.

25.  Total capital cost and recurring cost/annum for environmental pollution control measures should also be included.

26.  Any litigation / court case pending against the proposal should also be included.

27.  Compliance to the recommendations mentioned in the CREP guidelines should be included.

            The Expert Committee (Industry) decided that PAs may be communicated the above ‘TORs’ for the preparation of final EIA/EMP.  As soon as the final EIA/EMP report is prepared as per the ‘General Structure of EIA’ given in Appendix III and IIIA in the EIA Notification, 2006, the same may be submitted by the PAs to the MOEF for prior environmental clearance. It is also noted that no public hearing/consultation is required due to project being located in notified Bamunara Industrial Area as per Section (iii), Stage (3), Para (i)(b) of EIA Notification 2006.

4.33    Setting up of Ferro Alloy Plant (High Carbon Ferro Manganese, 15,224 TPA & Silico Manganese 11,455 TPA) in existing M.S. Ingot Plant at Mouza Nacrajoria, P.S. Salanpur, District Burdwan, West Bengal by M/s Hira Concast (Pvt.) Ltd. (EC)

 

The project authorities and their consultant gave a detailed presentation on the salient features of the project and proposed environmental protection measures to be undertaken. All the Ferro Alloy Plants are kept at S.N. 3(a) (b) under Primary Metallurgical Industry under Category ‘A’ and appraised at the Central level.

 

            M/s Hira Concast (Pvt.) Ltd. have proposed for setting up of Ferro Alloy Plant (High Carbon Ferro Manganese, 15,224 TPA & Silico Manganese 11,455 TPA) in existing M.S. Ingot Plant at Mouza Nacrajoria, P.S. Salanpur, District Burdwan, West Bengal. The proposed expansion by installation of submerged Arc Furnace (7.5 MVA) will be carried out in the existing campus and no additional land will be required.  Total land acquired is 6.68 acres. Total cost of the project is Rs. 1,544.39 Lakhs.  Following will be manufactured:

 

Product

Installed Capacity (TPA)

1st Year

2nd Year

3rd year

High Carbon Ferro Manganese

15,225

12,180

12,941

13,702

Silico Manganese

11,455

9,164

9,737

10,310

Mn ore (42,000 TPA), Coke Coal (15,000 TPA) and Dolomite (5,000 TPA) will be used as raw material. 

One Submerged Arc Furnace (7.5 MVA) will be provided during the expansion to manufacture High Carbon Ferro Manganese. M.S. Ingot manufacturing facility (2x7 MT) Induction Furnace) exist and SAF (7.5 MVA) will be installed to make use of product in ingot manufacturing unit. Metallic ore (Oxides of Fe, Si, Mn) and carbon-source reducing agent (coke, charcoal), a flux material (Limestone) will be fed to SAF.  The carbon source reacts with metal oxides to form CO and to reduce the ores to base metal.  The hot metal liquid will be tapped into a sand bed prepared moulds or cast iron pans. Slag will be collected separately. Silico-Manganese (11,450 MTPA) or Ferro-Manganese (15,225 MTPA) will be manufactured.

Bag filters will be provided to the submerged arc furnace to control gaseous emissions within 150 mg/Nm3.  Smoke hood, heat exchanger, bag filter, inducted dust (ID) fan and stack (30 m height) will be provided.  A water-cooled cover around the furnace and fume collectors hood will be provided. Dust generated by crushing, sizing, drying or other pre-treatment activities will be controlled by providing dust suppression system covered conveyor belts will be provided.

Total ground water requirement will be 6 m3/day.  No water will be discharged from the cooling system due to use for slag cooling, dust suppression etc.  Softener back wash will be neutralized and used for dust suppression.  No industrial waste will be generated due to recycle/reuse of the treated wastewater.  Domestic wastewater will be treated in septic tank followed by soak pit.

 

Slag will be generated as solid waste and disposed by filling low lying area and making roads within the factory premises. Dust collected from bag filter will be collected and recharged in the furnace.

 

Green belt will be developed in 33 % area. Power (8000 KVA) will be sourced from Damodar Valley Corporation (DVC).  1x125 KVA DG sets will be installed.

 

Due to expansion of the proposed unit in the same campus, the Committee recommended the proposal as per Section 7 (ii) of EIA Notification, 2006 requiring no public hearing. The Committee recommended the proposal for environment clearance subject to stipulation of following specific conditions alongwith other environmental conditions:

 

  1. Continuous monitoring facilities for all the stacks and sufficient air pollution control equipments viz. fume extraction system with bag filters, I D fan and stack of adequate height to submerged arc furnace should be provided to control emissions below 100 mg/Nm3. 
  2. Secondary fugitive emissions from all the sources should be controlled within the latest permissible limits issued by the Ministry and regularly monitored. Guidelines / Code of Practice issued by the CPCB should be followed.
  3. Prior permission for the drawl of 6 m3/day ground water should be obtained from State Ground Water Board/Central Ground Water Authority (SGWB/CGWA).
  4. Proper handling, storage, utilization and disposal of all the solid waste shall be ensured and regular report regarding toxic metal content in the waste material and its composition, end use of solid/hazardous waste should be submitted to the Ministry’s Regional Office at Bhuvaneswar, WBPCB and CPCB.
  5. All the ferro alloy slag should be used for land filling inside the plant or used as building material only after passing through Toxic Chemical Leachability Potential (TCLP) test.  Otherwise, hazardous substances should be recovered from the slag and output waste and be disposed in secured landfill as per CPCB guidelines. 
  6. Slag produced in Ferro Manganese (Fe-Mn) production should be used in manufacture Silico Manganese (Si-Mn).
  7. Green belt should be developed in at least 33 % area.
  8. All the recommendations made in the Charter on Corporate Responsibility for Environment Protection (CREP) for the Ferro Alloy Units should be strictly implemented.

 

 

4.34    Expansion of Ferro Alloy Plant (installation of 9 MVA SAF, Ferro Manganese 18,000 MTPA, Silico–Manganese, 13,540 MTPA) at Village Ghutgoria, P.O. Barjora, District Bankura, West Bengal by M/s Cosmic Ferro Alloys Ltd. (EC).

 

The project authorities and their consultant gave a detailed presentation on the salient features of the project and proposed environmental protection measures to be undertaken alongwith the draft Term of References for the preparation of EIA/EMP. All the Ferro Alloy Plants are kept at S.N. 3(a) (b) under Primary Metallurgical Industry under Category ‘A’ and appraised at the Central level.

 

            M/s Cosmic Ferro Alloys Ltd. have proposed for the expansion of Ferro Alloy Plant (installation of 9 MVA SAF, Ferro Manganese 18,000 MTPA, Silico–Manganese, 13,540 MTPA) at Village Ghutgoria, P.O. Barjora, District Bankura, West Bengal.   Proposed expansion will be carried out within the existing campus.  Total project area is 46.62 acres.  Total cost of the project is Rs.  3,371.35 Lakhs.  Four submerged Arc Furnace  (SAFs to produce Silico-Manganese (14,400 MTPA) and Ferro Manganese (30,800 MTPA) are existing and 5th SAF (9 MVA, Ferro Manganese, 18,000 MTPA and Silico – Manganese, 13,540 MTPA) will be installed.  Following will be manufactured.

 

Product

Installed capacity

1st year

2nd year

3rd year

High Carbon Ferro-Manganese

18,000

14,400

15,300

16,200

Silico - Manganese

13,540

10,832

11,509

12,186

 

 

           

 

 

Mn ore (42,000 TPA), Coke Coal (15,000 TPA) and Dolomite (5,000 TPA) will be used as raw material.  Ferro alloy manufacturing will involve melting of Manganese ore and reduction smelting of the ore with coal / coke.  The molten alloy will be poured into mould with the help of ladle.  The mould will be cooled by circulation of cold water with the help of cooling tower.  Hot metal will be tapped in a sand bed prepared moulds or cast iron pans.  The alloy remains in the ladle while slag is skimmed.  The slag will be collected separately.

Gaseous emissions from Submerged Arc Furnace will be controlled by providing smoke hood, heat exchanger, bag filter, inducted draft fan and stacks of adequate height (30 M.)  Dust suppression system will be provided to raw material handling area, storage yards, conveyor belts and bucket elevators.  Covered conveyer belts will be provided.

Total ground water requirement will be 6 m3/day. The water will be used for slag cooling.  The softener back wash will be neutralized and used for dust suppression on.  No liquid effluent will be disposed outside the premises.  Domestic wastewater will be treated in septic tank followed by soak pit.

 

            All the solid waste will be 100% utilized.  The slag will be used as raw material for manufacturing Silico-Manganese. Slag will also be used for land filling and road constructions.  Dust collected from bag filter will be collected and recharged in the furnace.

 

            Out of 46.62 acres, 8.25 acres (33 %) is proposed for the green belt. Power (7.25 MV / 9000 KVA) will be sourced from Damodar Valley Corporation (DVC).  2x125 KVA DG sets will be installed.

 

Due to expansion of the proposed unit in the same campus, the Committee recommended the proposal as per Section 7 (ii) of EIA Notification, 2006 requiring no public hearing. The Committee recommended the proposal for environment clearance subject to stipulation of following specific conditions alongwith other environmental conditions:

 

1.      Continuous monitoring facilities for all the stacks and sufficient air pollution control equipments viz. fume extraction system with bag filters, I D fan and stack of adequate height to submerged arc furnace should be provided to control emissions below 100 mg/Nm3. 

2.      Secondary fugitive emissions from all the sources should be controlled within the latest permissible limits issued by the Ministry and regularly monitored. Guidelines / Code of Practice issued by the CPCB should be followed.

3.      Prior permission for the drawl of 6 m3/day ground water should be obtained from State Ground Water Board/Central Ground Water Authority (SGWB/CGWA).

4.      Proper handling, storage, utilization and disposal of all the solid waste shall be ensured and regular report regarding toxic metal content in the waste material and its composition, end use of solid/hazardous waste should be submitted to the Ministry’s Regional Office at Bhuvaneswar, WBPCB and CPCB.

5.      All the ferro alloy slag should be used for land filling inside the plant or used as building material only after passing through Toxic Chemical Leachability Potential (TCLP) test.  Otherwise, hazardous substances should be recovered from the slag and output waste and be disposed in secured landfill as per CPCB guidelines. 

6.      Slag produced in Ferro Manganese (Fe-Mn) production should be used in manufacture Silico Manganese (Si-Mn).

7.      Green belt should be developed in at least 33 % area.

8.      All the recommendations made in the Charter on Corporate Responsibility for Environment Protection (CREP) for the Ferro Alloy Units should be strictly implemented.

4.35     Expansion of Ferro Alloys manufacturing unit (1,800 TPA) at Sector-II, Falta Special Economic Zone, P. O. Panarhat, PS Falta, District 24-Pargana, West Bengal by M/s DRK metallurgical Pvt. Ltd.- (EC)

The project authorities and their consultant gave a detailed presentation on the salient features of the project and proposed environmental protection measures to be undertaken alongwith the draft Term of References for the preparation of EIA/EMP. All the Ferro Alloy Plants are kept at S.N. 3(a) (b) under Primary Metallurgical Industry under Category ‘A’ and appraised at the Central level.

 

            M/s DRK metallurgical Pvt. Ltd. has proposed to expand the existing Ferro Alloys manufacturing unit (1,800 TPA) at Sector-II, Falta Special Economic Zone, P. O. Panarhat, P.S. Falta, District 24-Pargana, West Bengal. The project is located in the Falta SEZ developed by the Govt. of India. Out of 5,445 m2 of land allotted by Falta SEZ Authority, proposed expansion requires 2000 m2 of land in addition to the existing plant area of 1,753.75 m2. No National Park/Wild life sanctuary/Reserve Forest is located within 10 km radius of the project.  Total cost of the proposed expansion will be Rs. 25.00 lakhs.

The existing unit is manufacturing Ferro Vanadium (450 MTPA), Ferro Molybdenum (300 MTPA), Ferro Tungsten (96 MTPA), Ferro Nickel (70 MTPA) and Cobalt oxide (19.20 MTPA). Out of Ferro Titanium (360 TPA), Ferro Manganese-LCAMC (360 TPA), LC Ferro Chrome (360 TPA), Ferro Nickel (480 TPA), Molybdenum Oxide (240 TPA), any one or two product will be manufactured at a time during proposed expansion.

Raw materials required will be Aluminium powder (700 MTPA), Lime (80 MTPA), Mill scale (800 MTPA), Fluorspar (60 MTPA), Silico Manganese (360 MTPA), Manganese Ore (360 MTPA), Chromites Ore (360 MTPA), Titanium sands (360 MTPA), Spent Nickel catalyst (4800 MTPA), Sodium Nitrate (25 MTPA).

Proposed products will be manufactured by a pyrometallurgical process. Raw materials will be charged into sand pits lined with refractory materials. Reaction is set in with a Magnesium sparkler. Aluminous thermic reaction is highly exothermic and temperature shoots up to 2500oC in the molten condition.  Reaction time is hardly 2 minutes. Slag and metals are separated after cooling and solidification. 

Dust collection system will be provided for arresting dust. Fumes generated during the charging process will be taken to the multi-cyclone through a hood connected with duct line using an ID fan. Particulate matter will be separated in the multi-cyclone and gaseous substance will be scrubbed in the wet scrubber, where water is sprayed and finally the clean gas will be vented to atmosphere through a chimney of height 30 m.

 

Water requirement of 15.34 m3/day (existing) is being supplied by SEZ Authority. No additional water is required for the proposed expansion. Water from the scrubbing system will be recycled. No liquid effluent is discharged in the process. Domestic wastewater will be discharged to septic tank and secondary filter media.  Industrial waste water us recyled in the process.

 

All the product related wastes will be re-used in the process. Only solid slag will be disposed off as per present practice.

 

          Green belt will be developed in 33% of project area. Noise from construction machinery will be in the range of 85-95 dB(A) at source and 70 dB(A) at the factory boundary.  Existing sanctioned power from WBSEB is 48 MW. No additional power/fuel will be required for the proposed expansion. LDO/ FO (500 ltrs/day) is being used for combustion in the furnaces.

 

The Committee (Industry) noted that no public hearing/consultation is required due to project being located in notified Falta Special Economic Zone, P. O. Panarhat, P.S. Falta, District 24-Pargana, West Bengal as per Section (iii), Stage (3), Para (i)(b) of EIA Notification, 2006 and recommended stipulation of following specific conditions alongwith other specific and general conditions :

 

  1. Continuous monitoring facilities for all the stacks and sufficient air pollution control equipments should be provided to control emissions below 100 mg/Nm3.
  2. Fumes generated during the charging process should be taken to the multi-cyclone through a hood connected with duct line using an ID fan. Particulate matter should be separated in the multi-cyclone and gaseous substance should be scrubbed in the wet scrubber and finally the clean gas should be vented to atmosphere through a chimney of adequate height as per CPCB guidelines.
  3. Secondary fugitive emissions from all the sources should be controlled within the latest permissible limits issued by the Ministry and regularly monitored. Guidelines / Code of Practice issued by the CPCB should be followed.
  4. Prior permission for the drawl of 15.34 m3/day water from SEZ Authority should be obtained. As proposed, no additional water should be used during the expansion project.
  5. Proper handling, storage, utilization and disposal of all the solid waste shall be ensured and regular report regarding toxic metal content in the waste material and its composition, end use of solid/hazardous waste should be submitted to the Ministry’s Regional Office at Bhuvaneswar, WBPCB and CPCB.  .
  6. As proposed, all the product related wastes should be re-used in the process.  All the slag should be used for land filling inside the plant or used as building material only after passing through Toxic Chemical Leachability Potential (TCLP) test.  Otherwise, hazardous substances should be recovered from the slag and output waste and be disposed in secured landfill as per CPCB guidelines.
  7. Green belt should be developed in at least 33 % area.
  8. All the recommendations made in the Charter on Corporate Responsibility for Environment Protection (CREP) for the Ferro Alloy Units should be strictly implemented.

 

 

4.36     Cement Plant (2.5 MTPA Clinker Plant, 1.0 MTPA Grinding Plant), Captive Power Plant (25 MW) at Village Lodhava, Tehsil Sutrapda, District Junagarh, Gujarat by M/s Binani Cements Ltd. (TOR)

 

The project authorities and their consultant gave a detailed presentation on the salient features of the project and proposed environmental protection measures to be undertaken alongwith the draft Term of References for the preparation of EIA/EMP. All the cement plants (> 1.0 MTPA) are listed at S.N. 3(b) under Category ‘A’ and appraised at the Central level.

           M/s Binani Cements Ltd. have proposed for the Cement Plant (2.5 MTPA, Clinker Plant, 1.0 MTPA Grinding Plant), Captive Power Plant (25 MW) at Village Lodhava and Captive Limestone Mine (3.75 MTPA, 1528.47 ha.) at Villages Lodhava, Singsar, Barevala and Thordi, Tehsil Sutrapda, District Junagarh, Gujarat.  Total land acquired for the cement plant is 188 ha of which 104 ha of Government land is already allocated and the rest of the private land is under the process of acquisition.  PAs have submitted Integrated proposal for the Cement Plant, (2.5 MTPA, Clinker Plant, 1.0 MTPA Grinding Plant), Captive Power Plant (25 MW) at Village Lodhava and Captive Limestone Mine (3.75 MTPA, 1528.47 ha.) at Village Lodhava (706.68 ha) and Thozdil (670 ha.) in 1528.47 ha.  However, PAs informed vide letter dated 16th October, 2008 that total mine lease area of 1528.47 ha is located in Village Lodhava (706.68 ha), Singsar (614.97 ha), Barevala (164.8 ha) and Thordi (42.02 ha).  Mining lease area is barren wasteland and agricultural land. Proposed site falls in Seismic Zone-III as per IS 1893 (Part-I):2002.  Seashore is at 4.5 km. Total cost of the project is Rs. 694.40 Crores.  Rs. 52.50 Crores are allocated towards total capital cost and recurring cost/annum for environmental pollution control measures.

           Limestone (3.75 MTP) from Captive mining lease, imported coal (1150 TPD)/ or lignite (600 TPD) from Gujarat Lignite Mines, gypsum (0.07 MTPA), Sand stone, Laterite clay, iron ore, fly ash etc. will be used as raw materials. OPC (35-40%) and PPC (60-65%) will be manufactured.

A satellite grinding unit (1.0 MTPA) is proposed near Bharuch, Gujarat.  The clinker (2.5 MTPA) will be used at the grinding units at Sutrapada and Bharuch.  CPP (25 MW) will be installed at Sutrapata.  A Vertical Raw Mill (VRM) will be provided.  Dry process, rotary kiln system with 6 stage pre-heater and pre-calciner process will be used for clinker production.

 

Particulate matter will be generated from cement plant and CPP.  High efficiency bag filters and ESP will be provided to clinker cooler and CPP to control particulate matter.  Adequate stack height will be provided to disperse pollutants. Fugitive emissions will be generated from material handling and transportation areas.  Dust emissions will be controlled by water spraying Bag house will be provided to raw mill.  ESP will be provided to clinker cooler, coal mill, cement mill and CPP.  Bag filters will be provided at all unloading, Storage & transfer points.  Water sprinkling systems will be provided in raw material storage areas and haul roads and dust generating areas. On-line dust monitors will be provided. Dust collectors will be provided for control of Kiln and Cooler emission.

 

Total ground water requirement will be 1,500 m3/day and the necessary approval is under processing.  No wastewater will be generated from the cement plant.  Domestic effluent will be treated in sewage treatment plant (STP) followed by soak pits. Water treatment plant effluent will be utilized for greenbelt development. PAs vide letter dated 23rd July, 2008 informed that hydro geological studies will be carried out to inspect the effect of limestone mining on ground water and will be reported in the EIA report.

 

No solid waste will be generated from the process.  Fly ash generated from CPP will be used in cement plant for manufacturing Pozzolana Portland Cement (PPC).  Bed ash will be used in the raw mix for clinker production. Used oil will be sent to registered recyclers.  Material from ESP and bag filter will be stored in cement storage silo.

 

Green belt will be developed in 33% of plant area. Power (30 MW) will be required from cement plant and mine.  A CPP (25 MW) will be installed and 5 MW power will be sourced from state grid.  Coal and lignite will be used as fuel.

During the discussion, PAs informed to the Committee that they have yet to prepare mine plan.  Mine lease is also yet to be approved by the Indian Bureau of Mines. Therefore, Committee decided to exclude mine from the proposed proposal and consider only for the Cement Plant (2.5 MTPA, Clinker Plant, 1.0 MTPA Grinding Plant) and Captive Power Plant (25 MW). Proposal for Lime stone mine may be considered seperately by the Mining Committee as and when mining plan is prepared and approved by the PAs.

After deliberations and considering the facts mentioned above, the Expert Appraisal Committee (Industry) recommended the proposal for the preparation of revised EIA/EMP excluding limestone mine as per the following TORs :

1.      Revised Form I and Pre-feasibility Report for the Cement plant and captive power plant with all the necessary annexures.

2.      Present land use based on satellite imagery should be included.

3.      Information on National Park/Sanctuary/Reserve Forests within 10 KM radius of the project site, if any, should be included.

4.      Actual land requirement, classification of land and acquisition status should be included.

5.      Rehabilitation and resettlement as per the policy of the Govt. of Gujarat incorporating all relevant aspects should be incorporated.

6.      Total cost of the cement plant and captive power plant; capital cost and recurring cost/annum for environmental pollution control measures.

7.      A list of industries containing name and type in 25 km radius should be incorporated.

8.      List of raw material required and source should be included.

9.      Process and manufacturing details for the cement plant and captive power plant should be included.

10.  Site specific micro-meteorological data including inversion height and mixing height should be incorporated.

11.  Air quality modeling for the cement plant and captive power plant should be incorporated.

12.  Sources of secondary emissions, its control and monitoring as per the CPCB guidelines should be included.

13.  Impact of the transport of the raw materials and end products on the surrounding environment including agricultural land.

14.  A write up on use of high calorific hazardous wastes in kiln and commitment regarding use of hazardous waste should be included. 

15.  Chemical characterization of RSPM and incorporation of RSPM data. Location of one AAQMS in downwind direction should be included.

16.  One-month data for gaseous emissions other than monsoon season should be included.

17.  Permission for the drawl of 1,500 m3/day ground water from SGWB/CGWA should be incorporated. Water balance cycle data including quantity of effluent generated, recycled and reused and discharged should be included.

18.  Efforts made to minimize use of ground water should be included.  A chapter on hydrology study by the State Govt. should be included. Ground water monitoring minimum at 8 locations should be included.

19.  Surface as well as roof top rain water harvesting and ground water recharge should be included.

20.  Scheme of proper storage of fly ash, gypsum, clinker should be included.

21.  Risk assessment and damage control should be incorporated.

22.  Occupational health of the workers should be incorporated.

23.  Green belt development plan for 33 % as per CPCB guidelines should be incorporated.

24.  Socio-economic development activities should be included.

25.  Compliance to the recommendations mentioned in the CREP guidelines should be included.

26.  A tabular chart of the issues raised and addressed during public hearing/public consultation should be provided.

27.  Any litigation / court case pending against the proposal should also be included.

 

            The Expert Committee (Industry) decided that PAs may be communicated the above ‘TORs’ for the preparation of EIA/EMP for the cement plant and captive power plant.  As soon as the draft EIA/EMP report is prepared, the same may be submitted by the PAs to the Gujarat Pollution Control Board (GPCB) for conducting public hearing as per EIA Notification, 2006. On finalization of EIA/EMP prepared as per TORs addressing all concerns set out in EIA/EMP should be submitted to the MOEF for prior environmental clearance.

 

            The Committee also decided to exclude Lime stone mine proposal from the proposed proposal and consider only for the Cement Plant (2.5 MTPA, Clinker Plant, 1.0 MTPA Grinding Plant) and Captive Power Plant (25 MW) due to mining plan still under preparation and yet to be approved by the concerned authorities.

 

 

4.37     Expansion of Cement Plant (Cement 0.30 MTPA to 0.90 MTPA; Clinker 0.60 MTPA to 1.60 MTPA) and Limestone Mine (0.90 MTPA to 2.55 MTPA) at Village Mattapally Mandal Mattampally, District Nalgonda, A. P. by M/s NCL Industries Ltd. (TOR)

           

The project authorities and their consultant gave a detailed presentation on the salient features of the project and proposed environmental protection measures to be undertaken alongwith the draft Term of References for the preparation of EIA/EMP. All the cement plants with > 1.0 MTPA and limestone mine projects > 50 ha mining lease area are listed at S.N. and 1 (a) respectively 3(b) under Category ‘A’ and appraised at the Central level.

 

            M/s NCL Industries Ltd. have proposed for the expansion of Cement Plant (cement 0.30 MTPA to 0.90 MTPA; Clinker 0.60 MTPA to 1.60 MTPA) and Limestone Mine (0.90 MTPA to 2.55 MTPA) at Village Mattapally Mandal Mattampally, District Nalgonda, Andhra Pradesh.  Increase in limestone (0.90 to 2.55 MTPA) in captive lime stone mines will involve increase in lime production capacity in following 3 mining leases :

 

1.       Mining lease I at Mettapalli                  – 0.78 to 1.5 MTPA

2.       Mining lease II at Sultanpur Thanda    – 0.02 to 0.05 MTPA

3.       Mining lease III at Gundlapalli – 0.10 to 1.0 MTPA

Total project area for cement plant is 120 acres and no land will be acquired for the expansion.  Total cost of the project is Rs. 320.00 Crores. Rs. 1.405 Crores will be earmarked towards total capital cost and recurring cost/annum for environmental pollution control measures. Mine lease area for mine I, II & III is 114.5 acres, 105.32 acres and 322.06 acres respectively.  After expansion, there will be no change in mine lease area.  Captive limestone mines are located adjacent to plant.  Sultanpur RF (adjacent), Tangeda RF (1.6 km.), Regulagand RF (3.1 km.) and Gurrambodu RF (2.8 km.) are located within 10 km radius of the project site.  Nearest village is located at 1.5 km in Mettapalli village. No National Park/Wild life sanctuary is located within 10 km radius of the project.

Limestone (2.55 MTPA) will be sourced from Captive limestone mines located at Mettapalli, Sultanpur, Thanda and Gundlapalli village.  Laterite 10.048 MTPA), Gypsum (0.045 MTPA) and coal (0.32 MTPA) will be used as raw material

Cement manufacturing process will involve limestone crushing, raw mix preparation, homogenization, coal preparation, calcinations and clinkerization, cement grinding and packing etc.  Production capacity of cement plant will incease by 0.6 MTPA and clinker by 1.0 MTPA.  Ordinary Pot Land (95% clinker, 5% Gypsum) and Portland Pozzolana (70% Clinker, 5 % Gypsum and 25 % fly ash) will be used to produce cement.

 

Mining :

Sultanpur RF (adjacent), Tangeda RF (1.0 km.), Regulagand RF (4.2 km.) and Gurrambodu RF (3.3 km.) are located within 10 km radius of the project site.  Out of 114.5 acres, 105.32 acres and 322.06 acres mine area, 103 acres, 95 acres and 290 acres will be converted into water respectively. Fully mechanized open cast mining by drilling and blasting will be carried out.  Top soil will be stacked separately and used for plantation.  Total mine lease area will be 541.88 acres.  The in-situ mine reserves are estimated to be 132 million tones.  Out of which mineable reserves are estimated to be about 1,000 million tones.  At the planned limestone production rate of 2.55 MTPA, life of the deposit will be 40 years.  The limestone excavated will be transported to the cement plant site by dumpers.

 

Dust emissions will be generated from various units of cement plant and mining activities.  SO2 and NOx emissions from the kiln of cement plant will also be generated.  All the pollution control equipments will be designed to control emissions less than 50 mg/Nm3.  Bag filters will be provided to Raw mill, Coal mill, Cement mill, LS Crushers, Fine coal Bins and Silos, Preheater top dedusting equipment, Kiln feed extraction equipment and packing plant. ESP will be provided to Clinker cooler and Preheater waste gas equipment. Bag house and ESP will be provided to Kiln and cooler.

 

Total water requirement after expansion will be 670 m3/d instead of 1,7000 m3/d proposed earlier and sourced from River Krishna. Permission for drawl of above quantity of water is awaited. No wastewater will be generated from the cement plant.  Domestic wastewater is presently treated in septic tanks followed by soak pits but STP will be provided after expansion. In mine workshop area, an oil separation tank will be provided to segregate oil and grease from the outlet water of source camp.  Treated wastewater will be used for plantation etc.  The water from mine pits will be used for dust suppression at faces, on haul roads, cleaning and washing HEMM and plantation etc.

 

No solid waste will be generated from cement plant. All the dust collected from the process or pollution control equipments will be recycled / reused in the process itself.

 

            Out of 120 acres, 54 acres is earmarked for the green belt development in cement plant area.  Greenbelt will be developed in 10 ha in addition to the existing 40 ha of total mine lease area of 3 mines. DG set (2.5 MW) exists for emergency use.  Power (17 MW) will be sourced from the State Grid.  

 

After deliberations and considering the facts mentioned above, the Expert Appraisal Committee (Industry) recommended the proposal for the preparation of revised EIA/EMP as per the following TORs:

TORs for Cement Plant:

1         Revised form-1 alongwith the earlier questionnaire for including cement and mining sectors should be submitted while submitting EIA/EMP.

2         Present land use based on satellite imagery. Study area should be 10Km radius.

3         Site-specific micro-meteorological data including inversion height and mixing height.

4         Data on existing air, water, soil & noise etc.

5         Ambient air quality monitoring modeling for cement plant and CPP (If any).

6         Sources of secondary emissions, its control and monitoring as per the CPCB guidelines.

7         A write up on use of high calorific hazardous wastes including BF slag in kiln and commitment regarding use of hazardous waste.

8         Chemical characterization of RSPM and incorporation of RSPM data. Location of one AAQMS in downwind direction.

9         One-month data for gaseous emissions for winter season.

10     Water balance cycle data including quantity of effluent to be generated, recycled and reused and discharged.

11     Efforts made to minimize use of ground water. A chapter on hydrology study by the State Govt. may be included. Ground water monitoring minimum at 8 locations.

12     Surface as well as roof top rainwater harvesting and ground water recharge.

13     Scheme of proper storage of fly ash, gypsum, clinker, coal.

14     Impact of transportation of raw materials

15     Risk assessment and damage control.

16     Occupational health of the workers.

17     Green belt (33%) development plan as per CPCB guidelines.

16     Socio-economic development activities.

17     Compliance to the recommendations mentioned in the CREP guidelines.

18     Details of location of wildlife sanctuary and national parks within 10 km radius of the plant.

19     Detailed Environment management Plant (EMP) with specific reference to air pollution control system, water management, monitoring frequency, responsibility and time bound implementation plan.

20     EMP should include the concept of waste minimization, recycle / reuse / recover techniques, energy conservation, and natural resource conservation.

21     EMP should include a clear map for plantation/green belt.

 

TORs for Mines:

 

1.       The study area should comprise of 10 km zone around the mine lease from lease periphery. 

2.       Land use of the study area delineating forest area, agricultural land, grazing land, wildlife sanctuary and national park, migratory routes of fauna, water bodies, human settlements and other ecological features.

3.       Land use plan of the mine lease area should be prepared to encompass pre-operational, operational and post operational phases.

4.       A copy of the approval of the mine lease area and approved mine plan should be included.

5.       Location of National Parks, Sanctuaries, Biosphere Reserves, Reserve Forest, Wildlife corridors, within 10 km of the mine lease should be clearly indicated.  A location map duly authenticated by Chief Wildlife Warden should also be provided in this regard. Necessary clearance, if any, as may be applicable to such projects due to proximity of the ecologically sensitive areas as mentioned above should be obtained from the State Wildlife Department/ Chief Wildlife Warden under the Wildlife (Protection) Act, 1972 and copy furnished.

6.       A detailed biological study for the study area [core zone and buffer zone (10 km radius of the periphery of the mine lease)] shall be carried out. Details of flora and fauna, duly authenticated, separately for core and buffer zone should be furnished based on field survey clearly indicating the Schedule of the fauna present. In case of any scheduled-I fauna found in the study area, the necessary plan for their conservation should be prepared in consultation with State Forest and Wildlife Department and details furnished. Necessary allocation of funds for implementing the same should be made as part of the project cost. 

7.       Impact of change of land use particularly agriculture land and gaucher / grazing land, if any. 

8.       R & R plan / compensation details for the project affected people, if any. 

9.       Collection of one season (non-monsoon) primary baseline data on ambient air quality, water quality, noise level, soil and flora and fauna. Site-specific meteorological data should also be collected.  The location of the monitoring stations should be justified.

10.   Air quality modeling should be carried out for prediction of impact of the project on the air quality of the area. It should also take into account the impact of movement of vehicles for transportation of mineral. The details of the model used and input parameters used for modeling should be provided. The air quality contours may be shown on a location map clearly indicating the location of the site, location of sensitive receptors, if any and the habitation. The wind roses showing pre-dominant wind direction may also be indicated on the map.

11.   The water requirement for the project, its availability and source to be furnished. A detailed water balance should also be provided.  Fresh water requirement for the project should also be indicated. 

12.   Necessary clearance from the Competent Authority for drawl of 1,700 m3/day water from River Krishna for the project should be provided. 

13.   Details of water conservation measures proposed to be adopted in the project.

14.   Impact of the project on the water quality both surface and groundwater should be assessed and necessary safeguard measures, if any required should be provided.

15.   Action plan for the protection of River Krishna flowing at 400 meters including construction of high dyke around the mine due to high flood area and other safety measures should be included.

16.   A chapter on the impact of mining activities on the River Krishna and proposed remedial measures should be included.

17.   Monitoring of heavy metals and fluoride levels in the ground water should be incorporated.

18.   Details of rainwater harvesting proposed, if any, in the project area to be provided. 

19.   Information on site elevation, working depth, ground water table should be provided both in AMSL and BGL.  A schematic diagram may also be provided for the same.  In case the working will intersect groundwater table, a detailed hydro-geological study should be undertaken and report furnished. 

20.   Quantity of solid waste generation to be estimated and details for its disposal and management be provided.

21.   The reclamation plan, post mine land use and progressive greenbelt development plan should be prepared in tabular form (prescribed format) and submitted.  

22.   Impact on local transport infrastructure due to the project. Projected increase in truck traffic as a result of the project in the present road network (including those outside the project area) and whether it is capable of handling the increased load.  Arrangement for improving the infrastructure, if contemplated including action to be taken by other agencies such as State Government, if any, should be covered.

23.   Details of the infrastructure facilities to be provided for the mine workers.

24.   Conceptual post mine land use and Reclamation and Rehabilitation of mined out area (with plans and with adequate number of sections).

25.   Phase-wise plan of green belt development, plantation and compensatory afforestation clearly indicating the area to be covered under plantation and the species to be planted. The details of plantation already done should be given. 

26.   Occupational health impact of the project should be provided. 

27.   Measures of socio economic influence to the local community proposed to be provided by project proponent.  As far as possible, quantitative dimension to be given. 

28.   Detailed environmental management plan to mitigate the environmental impacts, which, should inter-alia also include the impact due to change of land use, due to loss of agricultural land and grazing land, if any, besides other impacts of the projects should be provided. 

29.   Public hearing issues/public consultation raised and commitment of the project proponent on the same alongwith time bound action plan to implement the same should be provided. 

30.   Any litigation pending against the project and /or any direction /order passed by any Court of Law against the project, if so, details thereof should be provided. 

 

            The Expert Committee (Industry) decided that PAs may be communicated the above ‘TORs’ for the preparation of EIA/EMP for the cement plant and captive power plant.  As soon as the draft EIA/EMP report is prepared, the same may be submitted by the PAs to the A.P. Pollution Control Board (APPCB) for conducting public hearing as per EIA Notification, 2006. On finalization of EIA/EMP prepared as per TORs addressing all concerns set out in EIA/EMP should be submitted to the MOEF for prior environmental clearance.

4.38     Expansion of the Cement Plant (1.80 MTPA to 2.40 MTPA) at BharataparaVillage Rawan Tehsil Baloda Bazar, District Raipur, Chhattisgarh by M/s Ambuja Cements Ltd. (EC)

The project authorities and their consultant gave a detailed presentation on the salient features of the project and proposed environmental protection measures to be undertaken alongwith the draft Term of References for the preparation of EIA/EMP. All the cement plant with > 1.0 MTPA production capacity have been kept at S.N. 3(b) under Category ‘A’.  In the instant case, total capacity of the cement plant after expansion will be 2.40 MTPA and is appraised by the central Govt.

 

            M/s Ambuja Cements Ltd. have proposed for the capacity enhance of Cement Plant (1.80 MTPA to 2.40 MTPA) by installing a pre-grinder before cement mill within the existing premises at Village Rawan, Tehsil Baloda Bazar, District Raipur, Chhattisgarh. Existing cement mill area is 1512 m2.   Vertical Roller Pre-grinding Mill (VRPM) (175 TPH) and grinding mill will be installed in 200 m2 area besides chain bucket Elevator of 500 TPM capacity.  No additional land will be required. Total cost of the project is Rs. 45.00 Crores.  Rs. 2.02 Crores and Rs. 0.20 Crores will be earmarked towards total capital cost and recurring cost/annum for environmental pollution control measures.

Clinker (0.384 MTPA) from existing cement plant, fly ash (0.192 MTPA) from NTPC, Korba and Gypsum (0.024 MTPA) from Jodhpur will be used as raw material.

It is proposed to use clinker produced at the existing unit.  Fly ash and gypsum will also be available from the existing source.  Existing plant is of 1.80 of cement grinding and 1.20 clinker production capacity and capacity will be enhanced by 0.60 MTPA by adding fly ash grinding.

Ambient air quality was monitored during July, 2007 to December, 2007 at 4 locations and data submitted indicated SPM (172-308 ug/Nm3), RPM (43-85 ug/Nm3), SO2 (10–18 ug/Nm3) and NOx levels (9-17 ug/Nm3) and are within the permissible limit. ESPs have been installed to kiln stack, cooler stack and cement mills of existing plant. It is proposed to install glass bag house to kiln.  Bag filters will be provided to coal mill to control gaseous emissions from the stack within 50 mg/Nm3. Fugitive emissions will be generated from material handling and transportation areas due to vehicular movement.  Cement and ash will be stored in silos. PAs vide letter dated 20th August, 2008 informed that existing ESPs will be replaced by glass bag house in December, 2009.

 

Total water requirement will be 50 m3/day and sourced from the water stored in mines pit.  No surface or ground water will be tapped for the purpose. No liquid effluent will be generated from the cement plant due to use of dry process.  Sewage water will be treated in sewage water Reclamation Plant (SWRP) and treated waste water will be 100% used for greener development, spraying on haul road and also for plant cooling make up.

 

No solid waste will be generated.  All solid materials collected through bag filters will be recycled to the process. SWRP sludge will be used as manure for plantation. Fly ash will be used for making PPC.  Waste oil will be disposed off as per Hazardous Waste  (Management & Handling) Rules.

 

Green belt will be developed in 32 ha, total area of plant and colony being 238.97 ha. but committee emphasized to develop green belt in 33 % area.  Power (2 MW) will be required and sourced from existing CPP.

 

            After detailed deliberations, the Committee recommended the proposal for environmental clearance subject to stipulation of following specific conditions alongwith other environmental conditions  :

 

1.      Continuous stack monitoring facilities to monitor gaseous emissions from all the stacks should be provided.  After expansion, limit of SPM should be controlled within 50 mg/Nm3 by installing adequate air pollution control system viz. glass bag house and bag filters etc. Data on ambient air, fugitive and stack emissions should be submitted to the Ministry’s Regional Office at Bhopal, CECB and CPCB regularly.

2.      Secondary fugitive emissions shall be controlled and should be within the prescribed limits and regularly monitored. Guidelines / Code of Practice issued by the CPCB in this regard shall be followed.

  1. Efforts should be made to reduce impact of the transport of the raw materials and end products on the surrounding environment including agricultural land. All the raw materials including fly ash should be transported in the closed containers only and should not be overloaded.  Vehicular emissions should be regularly monitored.   
  2. As proposed, total water requirement for cement plant (50 m3/day) should be met from mine pit only and no surface or ground water should be used.  All the treated wastewater should be recycled and reused in the process and/or for ash quenching, dust suppression, green belt development and other plant related activities etc. No process wastewater should be discharged outside the factory premises and ‘zero’ discharge should be adopted. 
  3. Sewage Water Reclamation Plant (SWRP) should be used for the treatment of sewage from the colony and treated domestic effluent should be used for green belt development within the plant premises.  Domestic waste from colony and SWRP should be segregated into bio-degradable and non-biodegradable. Bio-degradable waste should be composted and non-biodegradable waste should be land filled at identified sites.  Effluent treatment plant (ETP) should also be provided for workshop.
  4. All the bag filter dust, raw meal dust, coal dust, clinker dust and cement dust from pollution control devices should be recycled and reused in the process and used for cement manufacturing. Spent oil and batteries should be sold to authorized recyclers / reprocessors only.
  5. All the fly ash should be utilized as per Fly Ash Notification, 1999 subsequently amended in 2003. Efforts should be made to use fly ash maximum in making Pozollona Portland Cement (PPC).
  6. Efforts should be made to use low grade lime, more fly ash and solid waste in the cement manufacturing.
  7. An effort should be made to use high calorific hazardous waste in the cement kiln and necessary provision shall be made accordingly.
  8. As proposed, green belt should be developed in at least 33 % area in and around the cement plant as per the CPCB guidelines to mitigate the effects of air emissions in consultation with local DFO.
  9. All the recommendations made in the Charter on Corporate Responsibility for Environment Protection (CREP) for the Cement plants shall be implemented.

 

 

5.0       Reconsideration :

 

5.1       Asbestos Cement Products (1,50,000 MTPA) and Fiber Reinforced Plastic Products (FRP 3,60,000 Metre, FRP Pipes and/other products) at Village Akbarpur Urd, Tehsil Laksar, District Haridwar, Uttranchal by M/s Aqua Infra Projects Ltd. (EC)

 

The proposal was discussed at length with the PAs, Consultants and Representative of the State Government at the 83rd EAC (I) meeting held during 14th-16th July, 2008 and the committee decided to deliberate further on the matter at the next meeting to satisfy itself that all aspects are duly addressed having regard to the apparent gravity and number of representations received and developments reported at the public hearing.

 

The matter was further discussed in the 84th EAC (I) meeting held during 19th-21st August, 2008.  The committee was unanimous that proposed plant is technically sound and pollution control measures proposed are adequate. The Committee was informed that the Ministry has sought comments of the State Government on a number of representations received from various sources and on the public hearing and that the response of the State Government is awaited.  The Committee, therefore, decided to make its final recommendation after the response of the State Government is received and placed before it.

 

            The State Govt. has submitted his comments vide letter dated 4th September, 2008 and were placed before the Committee for further consideration of the matter. The Committee perused the comments on public hearing sent by the State Govt. and having regard to the views expressed in the previous meetings and as appraised in the previous meeting, the Committee was of the view that there is no ground to withhold approval to the projedt and decided to recommend the proposal for the grant of environmental clearance subject to following specific conditions alongwith other environmental conditions :

 

1.      The project proponent should adhere to the prescribed BIS standards and laws regarding use and handling of asbestos, safety of employees etc. Raw materials like asbestos fibre and cement should be transported in closed containers. Asbestos fibre should be brought in palletized form in impermeable bags and under compressed condition.

2.      Only Chrysotile white asbestos fibre should be used. Blue asbestos should not be utilized as raw material in the manufacturing process. A written commitment in this regard should be furnished within a period of one month.

3.      There should be no manual handling/opening of asbestos fiber bags. The company should install fully automatic asbestos fiber debagging system before commissioning the unit.

4.      Fugitive emissions should be controlled by bringing cement in closed tankers, fly ash in covered trucks and asbestos in impervious bags opening inside a closed mixer. Bag filters should be provided at bag opening, bag shredder, fibre mill and to cement silo. Fugitive emissions generated from hopper of Jaw crusher and Pulverizer should be channelized through hood with proper suction arrangement, bag filter and stack. Proper air pollution control system should be installed to control fugitive and air emissions at cement, fly ash, and asbestos fibre handling area.

5.      The Company should comply with total dust emission limit of 2 mg/Nm3 as notified under the Environment (Protection) Act, 1986. Adequate measures should be adopted to control the process emission and ensure that the stack emission of asbestos fibre should not exceed the emission limit of 0.2 fiber/cc.  Asbestos fibre in work zone environment should be maintained within 0.1 fibre/cc.

6.      Bags containing asbestos fibre should be stored in enclosed area to avoid fugitive emissions of asbestos fibre from damaged bags, if any. The cut and damaged fibre bags should immediately be repaired.

7.      Proper house keeping should be maintained within the plant premises. Process machinery, exhaust and ventilation systems should be laid in accordance with Factories Act. Better house keeping practices should be adopted for improvement of the environment within the work environment also. These include:

 (a)    All monitoring transfer points should be connected to dust extraction system.

(b)     Leakages or dust from machines and ducts should be plugged.

(c)      Floor should be cleaned by vacuum cleaner only.

(d)      Enclosed belt conveyer should be used instead of manual transportation of  

         asbestos within the premises.

(e)    Cement and fly ash should be stored in silos.

 

8.      Regular measurement of pollutants (SPM, asbestos fibre count) in the work zone area and stack(s) should be undertaken by the Project proponents. In addition, the asbestos fibre count in the work zone area should be monitored by an Independent monitoring agency like NIOH / ITRC / NCB or any other approved agency and reports submitted to the Ministry’s Regional Office at Lucknow / UEP & PCB and CPCB.

9.      Total water requirement from ground water should not exceed 140 m3/day as per the permission accorded by the Central Ground Water Authority (CGWA). All the recommendations of the CGWA should be implemented in time bound manner. All the treated effluent should be recycled and reused in the process. No process water should be discharged outside the premises and ‘zero’ discharge should be maintained. All the domestic wastewater should be treated in the Sewage Treatment Plant (STP) and used for green belt development.

10.  The Company should ensure that the entire solid waste generated including process rejects, cement, fly ash, dust from bag filters and empty asbestos bag should be recycled in the manufacturing process. Process sludge should be 100% recycled and reused in the process.  Hazardous waste should be ground in dust proof pulverizer with integrated bag filter and recycled back to the process.  Asbestos fibres which can not be further recycled due to contamination of iron dust should be stored in HDPE lined secured landfill. The disposal facilities for asbestos waste should be in accordance with the Bureau of Indian Standard Code.

11.  Regular medical examination of the workers and health monitoring of all the employees should be carried out and if cases of asbestosis are detected, necessary compensation should be arranged under the existing laws. A competent occupational health physician should be appointed to carry out medical surveillance. Occupational health of all the workers should be monitored for lung function test, chest x-ray, sputum for acid-fast-bacilli (AFC) and asbestos body (AB), urine for sugar and albumen, bloat tests for TLC, DLC, ESR, Hb and records maintained for at least 40 years from the beginning of the employment or 15 years after the retirement or cessation of employment whichever is later. Occupational Health Surveillance should be carried out as per the directives of the Hon’ble Supreme Court.

12.  To educate the workers, all the work places where asbestos dust may cause a hazard should be clearly indicated as a dust exposure area through the use of display signs which identifies the hazard and the associated health effects.

13.  The company should also undertake rain water harvesting measures and plan of action should be submitted to the Ministry of Environment and Forests within three months.

14.  Green belt should be developed in 33 % area with local species in consultation with DFO as per CPCB guidelines.

 

            The Committee was also informed about the vigilance case in pending in the Ministry for which Committee expressed the view that appropriate action may be taken by the Minstry but it has nothing to do with the decision of the Cepert Appraisal Committee (Industry).

 

 

7.0       Any Other Item :

 

7.1       Steel plant (5,00,000 TPA, MBF & SMS) at Shyamraipur, Gokulpur, Kharagpur, Paschim Medinipur, West Bengal by M/s Rashmi Metaliks Ltd. (Change in location).

 

PAs vide their letter dated 14th October, 2008 have informed to the Ministry that they could not procure 188 acre land at the proposed location at Mouza Medinipur, J.L. No. 139, Shyamraipur, Gokulpur, Kharagpur, Paschim Medinipur, West Bengal. Instead, they have procured 188 acre land at Mouza Kismatpur, J.L. No. 114, Shyamraipur, Gokulpur, Kharagpur, Paschim Medinipur, West Bengal located at a distance of 1.5 km.  At the same time, W. B. Pollution Control Board vide their letter dated 1st October, 2008 has also informed to the Ministry that the project is coming up at new location due to non-procurement of 188 acre land at the site mentioned in environmental clearance letter and have asked PAs to stop the work at the site and refused to issue ‘Consent to Establish’ due to change in location.

 

The Committee examined the matter and discussed at length. It is noted that proposed steel plant will be located at Mouza Kismatpur, J.L. No. 114, Shyamraipur, Gokulpur, Kharagpur, Paschim Medinipur, W. B. which is 1.5 km from the site proposed earlier.

 

Since the PAs have carried out Environment Impact Assessment within 10 km radius of the earlier proposed site at Mouza Medinipur, J. L. No. 139, Shyamraipur, Gokulpur, Kharagpur, Paschim Medinipur, W. B. as communicated to PAs vide Terms of References (TORs) awarded by the Ministry vide letter dated 6th June, 2007, the Committee had no objection if the proposed plant is set up at Mouza Kismatpur, J.L. No. 114, Shyamraipur, Gokulpur, Kharagpur, Paschim Medinipur, West Bengal since adequate pollution control measures are proposed in Environment Management Plan submitted to the Ministry.

 

 

7.2       Mini Steel Plant (1.5 LTPA), Sponge Iron Plant (1.2 LTPA), Iron Ore Pelletisation Plant (6.0 LTPA) and Captive Power Plant (25 MW) at Village Yerrabanahalli, Taluk Sandur, District Bellary, Karnataka by M/s KMMI Steel Pvt. Ltd. (Change in specific condition)

 

PAs vide their letter dated 10th October, 2008 have represented to the Ministry that they are unable to get finances from different financial institutions for implementation of specific condition no. (viii) since time requirement for the commissioning of sponge Iron plant and AFBC is 6 months and 18 months respectively.  Due to difference in time requirement, sponge iron plant can not be installed one year in advance or otherwise commissioning of sponge iron plant will be withheld (for almost one year) till the AFBC plant is installed viz:

 

AFBC Plant shall be installed before installation of Sponge Iron Plant so that utilization of char in the AFBC boiler is ensured.  All the char from DRI plant shall be utilized in AFBC boiler of power plant after its commissioning and no char shall be disposed off anywhere else. Kiln accretions and SMS slag shall also be properly utilized. Mill scales/cuttings/scrap from Re-rolling mill shall be used as raw material in induction furnace (IF). Dust from bag filters shall be recycled into DRI Plant.  Pellet plant dust shall be reused in the pellet plant itself. All the other solid waste including broken refractory mass shall be properly disposed off in environment-friendly manner”. 

 

The Committee examined the matter and agreed to amend the specific condition no. (viii) as follows:

 

“Construction of sponge iron plant and AFBC plant shall be started simultaneously so that char generated from the sponge iron plant is used in the AFBC boiler directly, or otherwise, char generated from the sponge iron plant shall be provided to char processing industries as proposed or stored properly at the project site as per CPCB guidelines till the AFBC boiler is commissioned.  All the char from DRI plant shall be utilized in AFBC boiler of power plant after its commissioning and no char shall be disposed off anywhere else. Kiln accretions and SMS slag shall also be properly utilized. Mill scales/cuttings/scrap from Re-rolling mill shall be used as raw material in induction furnace (IF). Dust from bag filters shall be recycled into DRI Plant.  Pellet plant dust shall be reused in the pellet plant itself. All the other solid waste including broken refractory mass shall be properly disposed off in environment-friendly manner”.

 

 

7.3       Expansion of Integrated Steel Complex [Pig Iron Plant (1,75,000 to 5,25,000 TPA), Ductile Iron Spun Pipes Plant (1,20,000 to 4,00,000 TPA), Slag Cement (90,000 to 3,90,000 TPA), Coke Oven Plant (1,62,000 to 4,62,000 TPA) and Captive Power Plant (14.5 MW to 40.5 MW)] at Village Rachagunneri, Mandal Srikalaharti, District Chitoor, A. P. by M/s Lanco Industries Ltd. (Amendment).

 

Environmental clearance has been accorded to above mentioned project vide letter dated 25th July, 2008. Now, PAs vide their letter dated 22nd August, 2008 have requested for the following amendments mentioned in the following Specific Conditions :

 

i)   The hot exhaust gas shall be diverted to WHRB to generate 20 MW power instead of 12 MW mentioned in the environmental clearance letter.

vii)   PAs want to use 7,750 m3/day primary treated sewage water of Tirupati Municipal Corporation for the proposed expansion project instead of 11,130 m3/day water from Kandaleru reservoir.

viii)  Prior permission for the drawl of 7,750 m3/day water from the primary treated sewage of Tirupati Municipal Corporation for the expansion shall be obtained from the concerned department instead of for the drawl of 11,130 m3/day water from Kandaleru reservoir.

The Committee noted that use of exhaust gases in WHRB for generation of 20 MW instead of 12 MW is for the betterment of environment and utilization of 7,750 m3/day water from the primary treated sewage of Tirupati Municipal Corporation instead of 11,130 m3/day water from Kandaleru reservoir will save precious fresh water from the reservoir and at the same time ensure utilization of treated wastewater in the process.

Therefore, Committee has no objection for the use of hot exhaust gas in WHRB to generate 20 MW power instead of 12 MW and utilization of 7,750 m3/day water from the primary treated sewage of Tirupati Municipal Corporation for the expansion project instead of drawl of 11,130 m3/day water from Kandaleru reservoir.

 

 

 

21st October, 2008

 

8.0      New Proposals

 

8.1       Exploratory Drilling of Hydrocarbons in Namsai, PEL Block in Lohit District in Arunachal Pradesh by M/s Oil India Ltd.- Environmental Clearance

 

 

The above proposals was considered by the Expert Appraisal Committee in its 77th meeting held on 21st to 24th January, 2008. The Committee prescribed the. TORs for incorporation in the EIA/EMP report and advised the project proponent to submit the EIA/EMP report to the State Pollution Control Board for conducting public hearing. The issues emerged during the PH/PC shall be incorporated in the EIA/EMP report and the report submitted to the Ministry for obtaining environmental clearance. 

 

Public hearing for the project was conducted on 23rd July, 2008.The issues raised were regarding, drilling at safe distance from the villages or human habitation including their farm lands so as to avoid the adverse impacts. Adequate compensation for the rehabilitation to the affected people should be provided. The liquid effluent and solid waste should not be discharged in to the nearby streams, rivers and water bodies. Such waste should be treated and discharged properly. Cutting of trees should be avoided as far as possible. Abandoned or dead wells should be properly capped and sealed. Employment  should be provided to the local people and socio- economic development of the area should be undertaken.Oil refinery  be set up at the Namsai, if oil is found.   All the above issues were addressed by the project proponent.

 

M/s Oil India Ltd have proposed for exploratory Drilling in Namsai, PEL Block, location- NSA, in Lohit District of Arunachal Pradesh in an area of 370 sq. Km. An area of 2.675 ha (175mx140m) will be required by drilling purpose. It is proposed to drill only one exploratory well up to the depth of the 4200-5500 m. Estimated original oil in place (OOIP) is 11.80 MMT and gross ultimate recovery (GUR) will be 3.54 MMT. No eco-sensitive area, National Park, Wildlife Sanctuary etc. in the vicinity of the area. However, the drilling locationis in the forest area in Piyong Reserve Forest. Water based mud will be used as drilling fluid. Power requirement will be met from the DG sets. Approximately 3-5 KLPD of HSD will be used for the DG Set. The cost of the project is Rs. 35 Crores.

 

 

Water requirement of 30-40 m3/day will be sourced from the ground water . Sources of liquid effluents during drilling and production testing will be waste drilling fluids-WBM, drainage discharges, recovered formation water and domestic wastewater. Waste drilling fluids and WBM, drainage discharges will be stored in HDPE lined shallow pits. Formation water (if any) will be treated in the  water clarification system to meet onshore discharge standards . Domestic effluent will be disposed through septic tank and soak pits. 

 

The main air emission source will be  the DG set at well site. Flaring of gases during the drilling testing phase will contribute to additional air pollution. Adequate stack height will be provided  for DG set and flaring of gases. Air quality monitoring was carried at 8 locations for the parameters RSPM, SPM, SO2, NOx, Total HC (CH4). The values for all the parameters were well below the stipulated standards.

 

Solid waste generation will be Drill cutting (170-200 m3l), which will be retained in the retainer pit.

 

After detailed deliberations, the EAC (I) satisfied with the proposed pollution control measures undertaken and recommended the proposal for grant of environmental clearance subject to stipulation of following specific conditions:

 

               I.      Forest clearance  under the forest ( Conservation ) Act, 1980 to carry out during operation in the forest area.

 

             II.      Hydrocarbon Monitoring shall be carried and data  submitted to the Ministry.

 

 

8.2.      Expansion of drilling & production in two wells  one each in NELP – II & NELP – III and one well in NELP – IV at district Bikaner, Rajasthan by M/s Oil India Ltd. – EC/TOR

 

The project authorities and their consultant gave a detailed presentation on the salient features of the project and proposed environmental protection measures to be undertaken. All the projects related to offshore and onshore Oil and Gas exploration, development and production are listed in para 1(b) of schedule of EIA Notification, 2006 covered under category “A”  and appraised at centre level.

 

M/s Oil India Limited (OIL) ventured out of North East in the early Eighties after its transition from a Joint venture Company to a National Oil Company. The Company expanded its operations from the Eastern to Western frontier of the Country. OIL began to explorate on hydrocarbon in the deserts of Rajasthan and OIL discovered Natural Gas in Jaisalmer basin of Tanot fields, which is being supplied to Rajasthan Rajyik Vidyut Utpadan Limited at Ramagarh in Jaisamer District of Rajasthan. M/s Oil India Limited (OIL) proposes for:

 

A.         Drilling & Production in one well in Bikaner district, Rajasthan in the area of 1072.5 Sq.Km in block acquired in NELP IV (RJ-ONN-2002/1) by M/S Oil India Limited-TOR

 

M/S Oil India Limited Rajasthan proposes for drilling & production of one well in Bikaner district, Rajasthan in NELP IV (RJ-ONN-2002/1). The area of block is 1072.5 Sq.Km . The OIL has decided to drill one well in this block for exploration of hydrocarbonsand  plan to undertake EIA study in area as as per the provision of Environmental Impact Assessment Notification dated 14.09.2006.

 

The Expert Appraisal Committee (I) prescribed the following TORs for undertaking detailed EIA Study:

 

1.                  Executive summery of the project.

2.                  Project Description and Project Benefits

3.                  Site details including satellite imagery for 10 km area. Confirmation that there is no National Park/ Wild life Sanctuary/ Eco sensitive area.

4.                  Land use along with maps & cropping pattern, vegetation Ecology,  Flora & Fauna

5.                  Demography & Socio-economics of the area.

6.                  Process details for survey and drilling.

7.                  Baseline data collection for air, water and soil for 5 weeks leaving the monsoon season in an area of 10 Km radius with centre of Oil Field as its centre covering the area proposed drilling well. 

 

·                     Ambient Air Quality monitoring at 8 locations for SPM, RPM, SO2, NOx

·                     Background levels of hydrocarbons (HC) and VOCs (5 samples)

·                     Soil sample analysis at 10 locations

·                     Base line underground and surface water quality in the vicinity of 10 km area.

·                     Climatology & Meteorology including wind speed, wind direction, temperature, rainfall etc.

·                     Measurement of Noise levels at 10 locations in the block

 

8.                  Detailed water balance, waste water generation and discharge.

9.                  Treatment and utilization of produced water.

10.              Detailed solid waste generation, collection, segregations, its recycling and reuse, treatment and disposal

11.              Estimation and computation of air emissions resulting out of drilling operations

12.              Assessment of impact on air , water, soil, solid/hazardous waste and noise levels

13.              Evaluation of the adequacy of the proposed pollution control measures to meet the air quality emission standards, water discharge norms, solid/hazardous waste generation and disposal

14.              Estimation of Noise level due to operation of drilling , its associated equipments and vehicular movement & prediction and evaluation of impacts due to increase in noise levels arising out of the proposed activities on the surrounding environment. Proposed mitigation measures for noise pollution

15.              Storage of chemicals at the site, proposed preventive measures for spillage and   accident.

16.              Environmental Management Plan

17.              Risk Assessment & Disaster Management Plan

 

·                     Identification of hazards

·                     Consequence Analysis

·                     Risk Presentation & proposed measures  for Risk Reduction

·                     Disaster Management Plan (DMP)

·                     Oil Spill Contingency Plan and Emergency Response Plan

 

18.              Measures for decommissioning of the rigs and projects

19.              Post project closure and monitoring programme for minimum 10 years

20.              Documentary proofs for Memberships of common disposal facilities, if any.

21.              Details of proposed occupational Health Surveillance program for the employees and other labour.

22.              Environmental Monitoring program while survey and drilling is undertaken.

23.              Information as per the Questionnaire on industrial projects as earlier devised by the Ministry.

 

The Committee decided that after preparing the EIA/EMP covering the above mentioned TORs, the report will be submitted to the Ministry along with requisite documents for consideration by the Expert Appraisal Committee (I) for obtaining environmental clearance in accordance with procedure laid in the Environmental Impact Assessment Notification, 2006. The Committee exempted the proposal from public hearing/public consultation as per para 7(i) of the EIA Notification, 2006.

 

B.        Drilling & Production in NELP III (RJ-ONN-2001/1) by one well at Bikaner district, Rajasthan by M/S Oil India Limited – EC/TOR

 

M/S Oil India Limited proposed for expansion of  Drilling & Production in NELP III (RJ-ONN-2001/1) for one well at Bikaner district, Rajasthan. The area of the block is 255.43 sq. km. The project area in falls in the same area of NELP-III Block (RJ-ONN-2001/1) for which environmental clearance has been accorded for drilling of one well in above block vide letter No. J-11011/58/2007-IA(I) dated 01.08.2007. M/S Oil India Limited have also obtained NOC’s from Rajasthan State Pollution Control Board for drilling of three wells falling in the same area. The EIA study for these locations was already carried out in 2006-07. The area of NELP-III block falls in great Thar Desert near the international border of Pakistan and has very thin/sparse human habitation and vegetation. The details of the project is as given below:

 

Location / site alternatives under consideration:

Block RJ-ONN-2001/1 Exploratory Block under NELP-III, District: Bikaner, State: Rajasthan

Size of the Project

Oil & Gas Exploration Block RJ-ONN-2001/1, covering an area of  255.43 sq. km.

Total Number of Exploratory & Appraisal Wells

1 (one)

Depth of  Well

Approx. range from 1600 m - 1800 m below mean sea level

Total Estimated Drilling Period for each well

45 days

Total Estimated Testing Period for each well

15 days

Type of hydrocarbon expected

Oil/Gas

Proposed Drilling Fluid for each well

Water Based KCL Polymer System

Anticipated Volume of  Drill Cuttings (without oil)for each well

250-500 cu. metres (approximately)

Expected Cost of the Project

Approximately Rs. 420 lakhs per well

 

The Committee found the presentproposal as an extension of existing activity and recommended the proposal for grant of environmental clearance in accordance with  para 7(ii) of the EIA Notification 2006 dispensing with requirement of EIA/EMP and public hearing subject to general and specific conditions and submission of compliance of the environmental stipulations made in the environmental clearance issued by the Ministry vide letter No. J-11011/58/2007-IA(I) dated 01.08.2007.

 

C.        Drilling & Production in NELP II (RJ-ONN-2000/1) for one well in District Jaisalmer, Rajasthan by M/S Oil India Limited – EC/TOR

 

M/S Oil India Limited proposed for expansion of  Drilling & Production in NELP II (RJ-ONN-2001/1) by one well at Jaisalmer district, Rajasthan. The area of the block is 390.6 sq. km. The project area in falls in the same area of NELP-II Block (RJ-ONN-2001/1) in which Environmental Clearance has been accorded for drilling of one well in above block vide letter No. J-11011/57/2007-IA(I) dated 07.08.2007. M/S Oil India Limited have also obtained NOC’s from Rajasthan State Pollution Control Board for drilling of three wells falling in the same area. The EIA study for these locations was already carried out in 2006-07. The area of NELP-III block falls in great Thar Desert near the international border of Pakistan and has very thin/sparse human habitation and vegetation. The details of the project is as given below:

 

Location / site alternatives under consideration:

Block RJ-ONN-2000/1 Exploratory Block under NELP-II District: Jaisalmer, State: Rajasthan

Size of the Project

Oil & Gas Exploration Block RJ-ONN-2000/1, covering an area of 390.6 sq. km.

Total Number of Exploratory & Appraisal Wells

1 (one)

Depth of each  Well

Approx. range from 1600 m - 1800 m below mean sea level

Total Estimated Drilling Period for each well

45 days

Total Estimated Testing Period for each well

15 days

Type of hydrocarbon expected

Oil/Gas

Proposed Drilling Fluid for each well

Water Based KCL Polymer System (Environmental friendly system)

Anticipated Volume of  Drill Cuttings (without oil)for each well

250-500 cu. metres (approximately)

Expected Cost of the Project

Approximately Rs. 420 lakhs per well

 

The Committee found that proposal is an extension of existing activity and recommended the proposal for grant of environmental clearance in accordance with the  para 7(ii) of the EIA Notification 2006 dispensing with requirement of EIA/EMP and public hearing subject to general and specific conditions and submission of compliance of the environmental stipulations in the environmental clearance issued by the Ministry vide letter No. J-11011/58/2007-IA(I) dated 01.08.2007.

 

C.        Drilling of two wells at Location RJBD and RJBE in Tanot, Dandewala and Bagitibba Mining Lease Area (250 Sq Km) in Jaisalmer District in Rajasthan by M/s Oil India Limited – EC/TOR

 

M/s Oil India Limited have proposed for drilling of two wells at location RJBD and RJBE in Tanot, Dandewala and Bagitibba Mining Lease Area (250 Sq Km) in Jaisalmer district in Rajasthan. M/s Oil have granted environmental clearance for Six drilling locations (Location- RJAZ, RJBA, RJAS, RJAR, RJAT & RJAQ) in Tanot, Dandewala and Bagitibba Mining Lease Area (250 Sq Km) in Jaisalmer district located in great Thar desert and is near International Boarder of India and Pakistan vide letter No –J-11011/252/2007-IAII(I) dated 7th August 2007 and letter No –J-11011/252/2007-IAII(I) dated 1st February 2008. There is no human habitation with in 35 Km radius.

 

The drilling locations were proposed in the  above mining lease area to sustain gas production and supply to Rajasthan Rajyik Vidyut Utpadan Nigam Limited (RRVUNL), a State owned thermal power plant at Ramagrh which generate electricity for the State of Rajasthan. For effective operation of the plant, continuous supply of desired quantity of gas is required as the shortage of gas supply to the plant may affect power generation.

 

At present few wells in the above mining lease area have stopped producing gas. Therefore, to sustain the gas production and supply of gas to RRVUNL M/s OIL have proposed to drill two new wells as an extension to the existing project. These new wells will be located in the same ML area where drilling of six wells is in progress against which OIL have obtained the Environmental Clearance.

 

The Committee found the proposal as an extension of existing activity and recommended the proposal for grant of environmental clearance in accordance with the  para 7(ii) of the EIA Notification 2006 dispensing with requirement of  EIA/EMP and public hearing subject to general and specific conditions and submission of compliance of the environmental stipulations in the environmental clearance issued by the Ministry vide letter No –J-11011/252/2007-IAII(I) dated 7th August 2007 and letter No –J-11011/252/2007-IAII(I) dated 1st February 2008.

 

8.3       Expansion of Exploratory Drilling (Phase-II) for coal bed methane in North Karanpura       CBM block (NK-CBM-2001/1) in Jharkhand by M/s ONGC - Environmental Clearance

 

The above proposal was considered by the Expert Appraisal Committee in its 76th   meeting held on 26th – 28th December, 2007. The Committee noted that EIA/EMP  report was prepared earlier in 2003 for the existing activity. NOC was obtained from the Jharkhand State Pollution Control Board on 10th January, 2004. Since the proposed activity is an expansion of existing activity, the Committee exempted the proposal for preparation of EIA/EMP report and from conducting public hearing as per Para 7(ii) of the Environmental Impact Assessment Notification, 2006. The Committee however, suggested that the EIA/EMP report should be updated based on monitoring of one-month data and report  be submitted to the Ministry for obtaining environmental clearance.

 

M/s ONGC Limited have proposed for expansion of exploratory Drilling for coal bed methane in north Karanpura, CBM block (NK-CBM-2001/1) in Jharkhand. The area of the block is 340.54 km2. M/s ONGC have earlier drilled 9 bore wells and 2 exploratory wells. It is proposed to drill 5 pilot wells (1successful well from Phase-I Carried forward to phase-II as pilot well). The wells will be drilled up to the depth of 1000m-1500 m. Water based low solid polymer mud (3% Bentonite, 2% KCL & 1% PHPA) will be used as a drilling fluid. 127m3 of drilling fluid per well will be used.

 

About 800m3/day of water per well will be  used. The source of water is usually bore well or tanker from the nearby river. Two DG set will be installed for supply of power at the drilling location. The waste water generated during drilling operations will be 5-10 m3/day which will be collected in lined waste pit and solar evaporated. Produced water may vary from 3-5 m3/day and will be used for inland application. However,   disposal  of Produced water will be reviewed on regular intervals as its  quality may change during the life of the CBM well.

 

Air quality monitoring was carried out in winter season for 9 locations for RSPM, SPM, SO2, NOx, MHC & NMHC. The arithmetic mean and 98th percentile values of 24 hourly SPM at all the stations ranged between 45-364 ug/m3 & 240-456 ug/m3 respectively. The arithmetic mean and 98th percentile values of 24 hourly RSPM at all the locations ranged between 24-308 ug/m3 and 93-407 ug/m3 respectively. The arithmetic mean and 98th percentile values of 24 hourly SO2 are observed to be 3 ug/m3 and 3 ug/m3 respectively. The arithmetic mean and 98th percentile values of 24 hourly NOx was ranged between 6-7 & 7 ug/m3 respectively. The non methane hydrocarbon concentration close to the project site were observed to be varying in the range of 2.6-4.8 ppm & methane hydrocarbon concentration varied in the range of 1.7-2.8 ppm. Adequate stack height is proposed to control air emissions from DG set and during test flare in event of gas discovery.

 

The drill cuttings (45 m3 ) generated at drill site will  be  used for road making  or for land filling. Other solid waste generation during the drilling activities will be paper, wood, plastic, metal canes, glass jars, organic kitchen refuse, paints, solvents, lubricating oil, batteries and incinerator ash etc.

 

After detailed deliberations, the EAC (I) recommended the proposal for grant of environmental clearance subject to stipulation of specific condition that monitoring of Hydrocarbon shall be carried and data submitted to the Ministry.

 

8.4 & 8.43       Environmental Clearance for Redevelopment of Baramura, Agartala Dome & Konaban in Tripura  and development of Sonamura field in Tripura by M/s ONGC.(EC)

 

The project authorities and their consultant gave a detailed presentation on the salient features of the project and proposed environmental protection measures to be undertaken. All the projects related to offshore and onshore Oil and Gas exploration, development and production are listed in para 1(b) of schedule of EIA Notification, 2006 and are covered under category “A”  and appraised at centre level.

 

Proposals regarding redevelopment of Baramura, Agartala Dome & Konaban in Tripura  and development of Sonamura field in Tripura by M/s ONGC were placed before the Expert Appraisal Committee (I)in its 76th meeting held during 28th – 30th December 2007 to prescribe the TORs for undertaking detailed EIA study. For this purpose, M/s ONGC submitted form -1 and pre-feasibility reports for each of the project. It was noted that in total six development wells will be drilled of which 2 each in Baramura field, 2 in Agartala dome and 2 in Konaban field. The area of drilling location of Baramura is 2.408 km2 which is a forest land. In Agartala dome, there will be two drilling locations of 15.75 km2 and 32.58km2 which is private and government land respectively. The area of Konaban is 10.3km2 which is private as well as government land. Land acquisition for all development locations is completed. All the three fields are producing gas fields. It is also proposed to upgrade Konaban gas gathering station for which an area of 17.48 ha has been acquired. In the Sonamura field, It is proposed to drill one new development well, which will be connected to group gathering stations alongwith 10km associated flow line.  It is also proposed to develop gas gathering station of 0.8 MMSCMD capacity at Sonamura field for which an area of 45.36 acres has already been acquired. Out of 45.36 acres, 0.83 acres is government land and 43.53 acres is private land. Compensation for acquisition of private land for GGS has already been paid.

 

Since the proposed activity is envisaged in the existing area already developed through exploratory drilling, M/s ONGC authorities requested the Committee to exempt them from public hearing and preparation of EIA/EMP report. In case of proposal regarding redevelopment of Baramula, Agratala dome and Konabona fields, committee exempted the proposal from preparation of EIA/EMP report and conducting public hearing. However, it was decided that the proponent may submit detailed appraisal report  for record  and recommended the project for environmental clearance. In case of Sonamura field in Tripura, Committee decided that EIA/EMP report  and risk assessment report based on the standards TORs shall be submitted to the Ministry for consideration of Expert  Appraisal Committee . The report will be placed before the Expert  Appraisal Committee without inviting the proponent. The proposal was exempted from public hearing.

 

The project authorities have submitted the desired appraisal report to the Ministry with respect to proposal regarding redevelopment of Baramula, Agratala dome and Konabona fields and circulated among the Expert appraisal Committee (Industry).

 

The discovery of gas in Tripura region in 1970s raised the hope for development of this remotely located State, which received further fillip in 1986-87 when gas production commenced in Tripura. Out of existing 60 gas wells (as on 01.01.07), only 22 to 25 are kept on regular production while others are either temporarily abandoned or closed due to lack of consumers. The current gas production stands at 1.4-1.5 MMSCMD is mainly utilized in power sector within the State of Tripura.

 

With a view to monetize the idle gas reserves and improve the poor power scenario of the North-East, ONGC took the lead to set up a power plant of 740 MW at Palatana in Tripura State. Palatana is located at a distance of about 60 km from Agartala City. The required gas for the plant will be made available by ONGC for 15 years.

 

One of the activities planned to produce and supply additional 3.0 MMSCMD gas for the proposed power plant is to redevelop the existing Gas producing fields of Baramura, Agartala Dome and Konaban.

 

Redevelopment of Baramura field: The Asset had initiated the work of Baramura GGS up-gradation from existing handling capacity of 0.2 MMSCMD to 0.5 MMSCMD for technology up-gradation and enhancement of safety system as per latest OISD guidelines. Two new wells are planned to be drilled in Baramura field, which will be connected to this upgraded GGS through flow lines, to be laid upon well drilling and completion(around 10 km per well  of flow line).

 

Redevelopment of Agartala Dome Field: The up-gradation of Agartala Dome field is being done to transport gas from this field to the proposed Power plant at Palatana. This  includes drilling of 5 development wells, ( 3 drilled and 2 wells to be drilled), up-gradation of gas processing facility in Gas Group gathering station from existing 0.4 MMSCMD to 2.2 MMSCMD and dispatch through future gas grid. Drilling of 3 new wells completed. 

 

 

Agartala Dome Field

Facilities

Wells

Flow lines

(KM)

GGS Handling facility

Consumers/consent

Gas

(MMSCMD)

Condensate

(M3/Day)

water(M3/Day)

Land

(Acres)

Existing

13 (9 connected)

52.17

0.40

1.7

3.3

8.23

NEEPCO

TNGC

Under upgraddation( by Oct 2007)

 

 

2.20

20

20

  9.91

Consent to establish obtained before  14th sep2006

Present proposal

2

20

-

-

-

-

OTPC

Total

15

72.17

2.2

20

20

9.91

 

Redevelopment of  Konaban  Field: Redevelopment of Konaban   field is being done to transport gas from this field to the proposed Power plant at Palatana. This  includes drilling of 3 development wells, (2 wells to be drilled),  up-gradation of gas processing facility in Gas Group gathering station from present 0.5 to 1.5 MMSCMD and dispatch through future gas grid. Drilling of 1 new well completed and up gradation of GGS work is  being proposed.   

Konaban  Field

Facilities

Wells

Flow lines

(KM)

GGS Handling facility

Consumers/ consent

Gas

(MMSCMD)

Condensate

(M3/Day)

water(M3/Day)

Land

(Acres)

Existing

16

51.31

0.5

5

4.0

17.48

NEEPCO

Present Proposal 

2

8

1.0

8

30 (add)

Nil

(use existing land)

NEEPCO

OTPC

Total

18

59.31

1.5

13

34

17.48

 

 

Agartala Dome, Konaban and Sonamura GGSs are planned to be connected to Palatana power plant by laying approximately 91 km. grid line before December 2010.

 

Based on   gas profile ,  additional gas producers as brought out above  are required to be drilled to produce established as well as projected reserves.   At present 4 development wells have already been drilled, and 6 balance wells are to be completed by Dec 2010 in these three fields as indicated below:   

Sl. No.

Name of  Field

Required  Number of wells

to be drilled

Balance  Number of wells to be drilled

Expected During

(Year)

1

Baramura

2

2

Before Dec 2010

2

Agartala Dome

5

2

Before Dec 2010 

3

Konaban

3

2

Before Dec 2010

 

Total

10

6

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

The environmental impact and safety issues of the proposed projects and facilities are as detailed below: :

§         Gathering and processing of produced well fluid.

§         Utilities requirement

§         Disposal of waste product

The produced water will be treated to make it suitable for disposal. The air pollutants emitted are suspended particulate matter (SPM), sulphur Dioxide (SO2), Nitrogen Oxides (NOx), Hydrogen Sulfide (H2S), Carbon Monoxide (CO) and Hydrocarbons (HC) emitted from diesel generators at Rigs (during drilling period) and flue gas/gas flares at gas processing installations. Flare header will be provided to transport the flare gas to flare system of gas processing installations. All designs will be made to ensure zero/technical gas flaring. All kinds of gas vents will be taken into process system for their utilization/evacuations.   There will be drill cuttings at rigs and domestic wastes from galley and laundries and sanitary wastes. Various methods for corrosion mitigation have been studied Cathodic protection for the pipeline will be provided for design life of 25 years. All piping material shall be carbon steel suitable grade for hydrocarbon system.

 

The toxicity of water-based drilling fluids used in ONGC operations is low. Concentration of drilling fluid and drill cuttings in the water column decline rapidly due to dilution and dispersion. Bioassy tests for toxicity of produced water carried out by NEERI, Nagpur for other project of ONGC reveal that produced water is less toxic. Further, effluent will be treated before disposal to ensure adherence to norms.

 

Safety is built into the installation design on the basis of risk analysis and standards laid down by various agencies. Life saving appliances are provided on installations as per OISD requirements. Personal protective equipments like hard hats, safety shoes, safety goggles, breathing apparatus and ear muffs etc. are provided. Safety operating procedures have been established. Safety training of personnel is mandatory. 

 

The proponent informed the Committee that there is no ecological sensitive area and National Parks/Wildlife sacnturies within these areas. After detailed deliberations, the Committee noted the details of the appraisal report with respect to proposal regarding redevelopment of Baramula, Agratala dome and Konabona fields and EIA/EMP & RA for Sonamura field in Tripura and found EIA/EMP complete and adequate and recommended the proposal for grant of environmental clearance subject to specific and general conditions.Public hearing was exempted during TOR presentation during 76th Meeting of the EAC(I) under para 7(ii) of the EIA Notification 2006.

 

8.5       Exploratory drilling and seismic survey in GV-ONN-67/1 block in Jhirna Hoshangabad M.P. under PEL block by M/s ONGC Frontier Basin –EC after TOR

 

The project authorities and their consultant gave a detailed presentation on the salient features of the project and proposed environmental protection measures to be undertaken. All the projects related to offshore and onshore Oil and Gas exploration, development and production are listed in para 1(b) of schedule of EIA Notification, 2006 covered under category “A”  and appraised at centre level.

 

M/s ONGC proposes for exploratory drilling and seismic survey in GV-ONN-67/1 block in Jhirna Hoshangabad M.P. under PEL block in Frontier Basin. Drilling of one exploratory well of 4500 Meters , well named as Jhirna #1, located under Village Pipalpura , Tehsil -Itasi, Distt. Hoshingabad,(M P). If hydrocarbons are found, ONGC may go for second well in Satpura Basin-Rampur-Panchmari-Nhoni Block. The cost of drilling operation of one well is Rs. 50 Crores. Duration of Project will be 175 Days.

Electrical Drilling rig comprising of 4 Power Gen-sets of 1200bhp through AC/SCR system, Top drive, Mud pumps, Draw-works, Rig Mast with accessories, LMSS, LMMC, Mud agitators, Desander, Desilter, Mud logging unit, Air compressor, ETP, BOP and cementing unit etc.. The rig is proposed to be taken through Contractor. The rig crew 50 Nos, will be on 14 Days ON/OFF duty with 12 hours shift.

 

Modeling – test flare (2000 m3) gas could be flared in the event of a gas discovery. It has been estimated that maximum of 60 mg/m3 of NOx would result as GLC during 30 minutes of flaring. The impacts due to NOx and HC will be negligible. Background noise level increase is  3-4 dBA and 2-3 dBA during day and night time respectively. It is estimated that approximately 700 m3 of drilling fluid will be required for one exploration well. No significant impacts on water quality are envisaged as the wastewater will be contained in a lined waste pit and will not be discharged from the drill site. Quantity of rejected fine sand, silt and mud is expected to be 200-250 kg/day and on an average 25 m3/day wastewater will be generated. It is anticipated that approximately @ 3 m3/day of drill cuttings will be generated during drilling operation. Drill cuttings after washing dispose it into lined waste pit and covered by native soil.

 

Public hearing meeting was conducted by Madhya Pradesh Pollution Control Board on  8th June, 2008 at village Pipalpura, Itarsi in District Hoshangabad (Madhya Pradesh). The Committee took note of the concerns raised by the public and response given by the Project Authorities. The same have been incorporated in the EIA/EMP report.             

 

After detailed deliberations, the Committee satisfied with the environmental measures taken and found EIA/EMP complete and adequate and recommended the proposal for grant of environmental clearance subject to specific and general conditions.

 

8.6       Expansion of Gas field Development in Tengakhat - Naharkatiya Jorajan,  Dumduma-Pengri, Moran-Sapekhati, Khowang-Shalmari Assam and  Arunachal area in Arunachal Pradesh by M/s Oil India Ltd. – TOR

 

The project authorities and their consultant gave a detailed presentation on the salient features of the project and proposed environmental protection measures to be undertaken. All the projects related to offshore and onshore Oil and Gas exploration, development and production are listed in para 1(b) of schedule of EIA Notification, 2006 covered under category “A”  and appraised at centre level.

 

M/s Oil India Ltd have proposed for expansion of Gas field Development in Tengakhat–Naharkatiya-Jorajan,  Tinsukia-Dhola, Dumduma-Pengri, Moran-Sapekhati, Khowang-Shalmari areas in Assam and  Arunachal area in Arunachal Pradesh. The details of locations are as given below:

 

1. Tengakhat-Naharkatia-Jorajan Area :

        In Dibrugarh & Tinsukia Districts of Assam

        Lies between 94º54´e & 95º35´e longitude

                         and 27º17´n & 27º32´n latitude

        Discovery well nhk-1 was drilled in the year 1953

 

2. Tinsukia-Dhola area :

            In tinsukia district of Assam

            Lies between 94º55´e & 95º48´e longitude

                         and 27º28´n & 27º50´n latitude

        Discovery well hapjan-29 was drilled in the year 1998

3. Dumduma-Pengeri area :

        In tinsukia districts of Assam

        Lies between 95º28´e & 95º55´e longitude

                        and 27º16´n & 27º40´n latitude

        Discovery well Pengeri-1 was drilled in the year 1999

 

4. Khowang-Shalmari area :

            In Dibrugarh District of Assam

            Lies between 94º48´e & 95º23´e Lngitude

                        and 27º04´n & 27º24´n latitude

        Discovery well shalmari-1 was drilled in the year 1986

5. Moran-Sapekhati area :

        In Dibrugarh & tinsukia districts of assam

        Lies between 94º42´e & 95º15´e longitude

                         and 26º55´n & 27º19´n latitude

        Discovery well maoran-1 was drilled in the year 1956

 

6. Arunachal area :

            In arunachal pradesh

            Lies between 95º47´e & 96º19´e longitude

                        and 27º22´n & 27º47´n latitude

        Discovery well kharsang-1 was drilled in the year 1968

 

The project extends in two states of the North East India. The details of the each project area as given below: 

 

1.         Gas Field Development in Tengakhat-Naharkatia- Jorajan Area : The project comprises of :

 

A.         Gas Compressor Stations (GCS) :

                                    a) Tengakhat b) Bhogpara

 

The objective of these are to utilize the associated gas produced at Tengakhat / Bhogpara  Region for distribution and artificial lifting.Each of the GCSs will have the following capacities –

         a) Gas Boosting Capacity       : 280,000 SCMD

         b) Gas Lifting Capacity            : 230,000 SCMD

         c) Gas Dehydration Capacity  : 280,000 SCMD

             

The cost of the project will be approx  Rs   9,000.00 Lakhs and land area will be 6.8 ha ie Tengakhat GCS :  3.40 ha and Bhogpara GCS : 3.40 ha. The facilities will be for natural gas compression, separation (of liquids/solids) and dehydration etc.

 

B.         Field Gathering Station :

a) Jorajan b) OCS-4 c) Kathaloni d) Hapjan e) Ushapur

 

            Objective of these facilities will be to produce NA Gas from Jorajan, OCS-4, Kathaloni, Hapjan and Ushapur region. The Capacity of each FGS will be 0.75 MMSCMD and total cost will be approx Rs 12,500.00 Lakhs. The land requirement will be 1.5 ha for Jorajan, OCS-4, Kathaloni, Hapjan & Ushapur (1 ha each). Each of the FGSs will have facility for separation of liquids/solids from gas, heating, control, pressure reduction of gas etc.

 

C.   GAS TRANSMISSION PIPELINES:

 

Description of the Pipeline(s)

Land (ha)

Estimated Cost

(Rs in Lakhs)

a) W/50 to LPG Off take : 3 nos.        : 600mm X 10Km (2Nos.) : 500mm X 10Km (1No.)

25

5800

b) W/50 to Location NKF : 2 Nos.     : 400mm X 7Km (1No.): 300mm X 7Km (1No.)

2

1750

c) Location NKF to Shalmari Approach via GCS-2, OCS-8 :   300mm X 33Km

20

3250

d) OCS-3 to W/50 OT : 400mm X 8Km

4.8

1085

e) Tengakhat OCS to Tengakhat Approach : 2 Lines :  300mm X 0.8Km (1No.)                                                          : 100mm X 0.8Km (1No.)

0.5

150

f) Hatiali Scrapper Trap to Wilton :

250mm X 4Km

2.4

350

g) Hatiali Scrapper Trap to W/263 :

100mm X 1Km

0.3

50

h) Hatiali Scrapper Trap to Dikom OCS :

150mm X 5.6Km

3.4

330

i) Tengakhat Approach to Kathloni OCS :

100mm X 4.5Km

1.4

215

j) Wilton  to Tengakhat Approach :

200mm X 0.8Km

0.5

60

k) Bengenabari to Bhekulajan EPS :

150mm X 3.2Km

1.9

201

l) OCS-2 to GCS-7 : 150mm X 3.2Km

1.9

202

m) GCS-7 to OCS-6 : 100mm X 0.8Km

0.25

38

n) LPG OT to OCS/GCS-5 : 250mm X 1Km

0.6

90

o) W/50 OT to  OCS-4 : 150mm X 4Km

2.4

237

p) W/319 to GCS-1 : 150mm X 2.5Km

1.5

159

q) GCS-1 to OCS-1 : 100mm X 1Km.

0.3

59

r) Hapjan OCS to Makum OCS : 150mm X 6.5Km

3.9

395

s) Nagajan OCS to Hapjan OCS : 200mm X 13.5Km

8.1

1020

t) Kathalguri OCS to Nagajan OCS/GCS : 200mm X 7.6Km

4.5

570

u) Jorajan Approach to Jorajan OCS/GCS : 150mm X 0.8Km

0.5

59

v) Extension/Augmentation of Existing Gas Flow P/L Network: 50mm to 250mm : Approx. 50Kms.

15

4000

Total

101.15

20070

 

D.  CENTRAL GAS GATHERING STATION AND OFFTAKE POINT: AT NHK W/50

 

Central gas gathering station will be set up to collect all the natural gas produced at Upper Assam Field of OIL and to distribute the collected gas to the Assam Gas Cracker Plant and other external and internal consumers. The capacity of the plant will be 12.5 MMSCMD. The cost of the unit will be approx. Rs. 14,400.00 Lakhs and land requirement will be 18 ha. The facilities at the CGGS will be collection of natural gas from different field gas production centers, separation of liquid / solid from the collected gas and distribution of this gas to different consumers at required pressure.

 

 

2.   GAS FIELD DEVELOPMENT IN TINSUKIA-DHOLA AREA: The project envisages :

 

A. GAS COMPRESSOR STATION (GCS) :a) Dikom b) Chabua c) Barekuri d) Baghjan  and e) Makum. The objective of the facility will be to utilize the associated gas produced at Dikom / Chabua / Barekuri / Baghjan for distribution and artificial lifting. The  GCSs will have the i)   Gas Boosting Capacity (280,000 SCMD), ii)  Gas Lifting Capacity (230,000 SCMD) and  iii) Gas Dehydration Capacity (280,000 SCMD). The total cost of the project will be  approx  Rs 20,500.00 Lakh. The land area requirement will be 3.4 ha each. Facility will be for natural gas compression, separation (of liquids/solids) and dehydration etc.

 

B. FIELD GATHERING STATION : a) Dikom b) Chabua, c) Baghjan and d) South Chandmari . The objective of the project is to produce NA Gas from Dikom, Chabua, Baghjan and South Chandmari region. The capacity will be             Chabua (1.25 MMSCMD), Baghjan (1.5 MMSCMD) and each of the other FGSs (0.75 MMSCMD). The cost of the project will be about  Rs 17,600.00 Lakh. The land area requirement will be Dikom ( 1 ha), Chabua (2.7 ha),  Baghjan (4.7 ha) and South Chandmari ( 1 ha). Each of the FGSs will have facility for separation of  liquids/solids from gas, heating, control, pressure reduction of  gas etc.

 

C.   GAS TRANSMISSION PIPELINES :

Description of the Pipeline(s)

Land (Ha)

Estimated Cost

(Rs in lakhs)

a) Chabua to W/50 CGGS : 400mm X 20.8Km

31.2

3750

 b) Baghjan to W/50 CGGS : 400mm X 41.5Km

74.2

7850

c) W/263 to Hatiali EPS : 2 nos. : 100mm X 1.5Km each

0.9

165

d) Makum OCS to TF : 100mm X 14Km

4.5

658

e) Hatiali EPS to Hatiali Scrapper Trap : 100mm X 3Km

0.9

159

f) Extension/Augmentation of Existing Gas Flow Pipeline  Network                : 50mm to 250mm : Approx. 50Kms

15

4000

                                                          TOTAL

126.7

16582

 

3.   Gas Field Development in Dumduma-Pengri Area: The project envisages -

 

A.     Field Gathering Station at Borhapjan : The objective of this project is to produce NA Gas from Borhapjan region. The capacity of the unit will be (1.5 MMSCMD). The cost of the project is approx. Rs. 2500.00 Lakhs. The land requirement will be 1 ha. The FGSs will have facility for Separation of liquid/solids from gas, heating, control, pressure reduction of gas etc.

 

B.  GAS TRANSMISSION PIPELINES :

Description of the Pipeline(s)

Land Area (Ha)

Estimated Cost (Rs in Lakhs)

a) Kushijan-2 Approach to DDGG : 200mm X 1Km

0.6

88.00

b) Extension/Augmentation of Existing Gas Flow Pipeline Network : 50mm to 250mm : Approx. 30Kms

9

2500.00

Total

9.6

2588.00

 

4.    Gas Field Development in Moran-Sapekhati Area: The project envisages -

 

A.  FIELD GATHERING STATION at  MORAN. The objective of the project is to produce NA Gas from Moran region. The capacity of the FGS plant will be 0.75 MMSCMD. The cost of the project is approx. Rs. 2500.00 Lakhs. The land required will be 1 ha. The FGSs will have facility for Separation of liquid/solids from gas, heating, control, pressure reduction of gas etc.

 

B. GAS TRANSMISSION PIPELINES :

Description of the Pipeline(s)

Land (Ha)

Estimated Cost (Rs in Lakhs)

a) Extension/Augmentation of Existing Gas Flow Pipeline Network : 50mm to 250mm : Approx. 30Kms

9

2500.00

Total

9

2500.00

 

5. GAS FIELD DEVELOPMENT IN KHOWANG-SHALMARI AREA: The project comprises of only Gas Transmission Pipelines as detailed below: 

 

Description of the Pipeline(s)

Land Area (Ha)

Estimated Cost (Rs in lakhs)

a) Shalmari Approach to Shalmari OCS1/GCS : 150mm X 8.5Km

5.1

515.00

b) Shalmari OCS-1/GCS  to Shalmari OCS-2 : 100mm X 5.7Km

1.75

268.00

c) Extension/Augmentation of Existing Gas Flow Pipeline Network           : 50mm to 250mm : Approx. 30Kms

9

2500.00

Total

9.6

3283.00

 

6. GAS FIELD DEVELOPMENT IN ARUNACHAL AREA:  The project comprise of Gas Transmission Pipelines as detailed:

 

Description of the Pipeline(s)

Land Area (Ha)

Estimated Cost (Rs in lakhs)

a) Kumchai- Doomduma-Hapjan Gas Pipeline: 150mm X 75 km

45

4500.00

b)Extension/Augmentation of Existing Gas Flow Pipeline Network

                                         : 50mm to 250mm : Approx. 5Kms

1.5

350.00

Total

46.5

4850.00

 

 

The committee discussed the projects and the process and decided that the activity attracts the provisions of the EIA Notification, 2006. PAs have informed that in the proposed areas no Eco-sensitive areas/Wild life sanctuaries/National parks are situated within 10 KM radius. The committee noted the project covers a huge area and the pipelines will pass through various rivers, forests and habitat areas. The committee approved the TORs presented along with following:

 

1.      The details of each project site, land area, ownership of land, ROW, status of land, etc should be incorporated.

2.      Monitoring shall be carried out at each site for VOCs, HC (Methane and non Methane)

3.      Certificate from wildlife warden/State Forest Department regarding no ecologically sensitive areas and Wild life sanctuary/National parks within 10 km from the site for each project and each site.

4.      Safety details for the each pipeline

5.      Details of spillage/leakage control

 

The committee decided that the EIA/EMP based on the above and other information as per the generic structure given in the EIA Notification 2006, may be prepared and submitted to the Ministry for consideration for prior environmental clearance. The public hearing issue will be considered after submission of the EIA/EMP based on the above TORs and information.

 

 

8.7       Development of three marginal fields at cluster -7 located on the south west of Mumbai by M/s Prize petroleum company Limited-- Environmental Clearance regd.

 

The above proposal was considered by the Expert Appraisal Committee in its 82nd meeting held on 10th & 12th June, 2008. The Committee prescribed the. TORs for incorporation in the EIA/EMP report and advised the project proponent to submit final EIA/EMP report to the Ministry for obtaining environmental clearance. Public hearing is not applicable to the project, as the project is located in the offshore,

 

 

            M/s Prize petroleum company Limited have proposed for development of three offshore marginal fields ( platforms B-192, B-45 and WO-24 ) under the name of Cluster 7 located at West coast Mumbai offshore. Cluster 7 is located 210 Km on the South West of Mumbai coast. The well will be drilled up to a depth of 2500 m.  It is proposed to drill 13 wells during assessment period of three years from three platforms. Initially the drilling activity is proposed to be carried out in B-192 area. Wellhead platform B-192-1 is located 10 km. from the wellhead and production platform B-192-5. B-192-1 is proposed to have 3 oil production wells with oil production rate of 3,500 standard tank barrels per day. Wellhead platform B-45 is located 20 km. from the wellhead and production platform B-192-5. B-45 has 3 oil production wells and 1 gas production well with an oil production rate of 4,782 b/d and a gas production rate of 12 million standard cubic feet per day (MMscf/d). Wellhead and production platform B-192-5 is located 50 km. from the existing ICP facility. B-192-5 has 6 oil production well with an oil production rate of 15,500 b/d. It also has one gas injection well with an injection rate of 20 MMscf/d. Oil production shall be treated and stabilized in the process platform and then transported to ICP (ONGC installation) through sub-sea pipelines. The transportation of oil and gas through intra field between B-192-1, B-192-5, B-45 and WO-24 and transportation of oil and gas to and from the process platform (located in B-192-5) shall be through sub-sea pipelines. Mundra port is identified as the base station for the project. It is proposed to use KCl-Polymer drilling fluid for the Cluster 7. Cost of the project is 156 million US dollars for drilling of 13 wells.  

 

Water requirement of 50 m3/day will be met from the desalination plant. Domestic wastewater (40 m3/d) generated on drilling rigs will be treated in modular treatment units before releasing to the sea. Produced water (10,000 b/d) will be treated for oil removal and disposed in to the sea. Apart from the flue gases from generators, the flare gases from handling of crude and associated gas contribute to the emission of carbon dioxide, water vapors and traces of oxides of nitrogen. The impact of emissions from flare on marine environment is not  significant.

 

Waste oils (5-10 barrels/month) that cannot be treated onboard the rig , will  be collected and sent to shore base for appropriate reuse/recycle or disposal. Biodegradable wastes will be discharged to the sea.  Non-degradable waste will be properly segregated and brought to shore for on-land disposal. Drill cuttings, thoroughly washed and separated from WBM/SBM, will be brought to shore for disposal in authorized hazardous waste disposal sites.

 

After detailed deliberations, the EAC (I) satisfied with the proposed pollution control measures undertaken recommended the proposal for grant of environmental clearance.

 

8.8  Exploratory drilling in block AA-ONN-2004/4  in Assam by M/s NaftoGaz India Pvt.Ltd. - Environmental Clearance

 

The proposal regarding exploratory drilling in block AA-ONN-2004/4 in Assam by M/s NaftoGaz India Pvt. Ltd. was considered by the Expert Appraisal Committee in its 76st meeting held on 26th – 28th December, 2007.The Committee prescribed the. TORs for undertaking EIA study and  advised the project proponent to submit the EIA/EMP report to the State Pollution Control Board for conducting public hearing. The issues emerged during the PH/PC shall be incorporated in the EIA/EMP report and the report submitted to the Ministry for obtaining environmental clearance. 

 

Public hearing for the project was on 08th August, 2008 and issues raised were regarding,  compensation  for trees cutting in forests, loss of agricultural field, drilling locations from reserved forest, and provision of employment etc.

 

All the above issues were addressed by the project proponent. The project proponent informed that if there be any tree cutting in the local forest they are committed to go for compensatory plantation through forest Department, Govt. of Assam. The drilling location is yet to be finalized. It will be ensured that drilling locations will be away from the sensitive locations. Local people/ vehicles will be hired. Public hearing for the seismic survey is not required.

 

M/s NaftoGaz India Pvt. Ltd. have proposed for exploratory drilling for oil & gas in block AA-ONN-2004/4  in Assam The block is located in District Tinsukia of Assam and covers  an area of 95 m2. No wild life sanctuary or national park exists within the block. Major River Buridihing flows through the block area with tributaries Penari Jan, Manmau Jan and Mugan Pani. The block is surrounded by tea estate gardens like powai and upper Dihing  forest falls in north and Margherita, Lekhajan, Namdang and Ledo forest in South.  It is proposed to drill 6 exploratory wells in the block. The average depth of the wells will be 2500-3000m below ground level and water based drilling fluid will be used. The time required for entire exploratory operation would be 7 years. The cost of Geophysical, Geological and Satellite Survey will be Rs. 24.00 crores and for exploratory drilling will be Rs. 84.00 crores.

 

On completion of activities, the well will be either plugged and suspended or will be killed and permanently abandoned. To suspend the well, it will be filled with a brine solution containing very small quantities of inhibitors to protect the well. The well will be sealed with cement plugs and some of the wellhead equipment will be left on the surface. If the well is abandoned, it will be sealed with a series of cement plugs and all the wellhead equipment will be removed leaving the surface clear of any debris and the site will be restored.

 

Power requirement will be met through the four DG sets of capacity 448 kW each. Three generators will be used at a time and one will be kept as standby   and one DG set of 63 kW is proposed for the residential camp. It is estimated that approx. 15-20 Kl/day of fuel (HSD) will be required during the drilling operation for generation of 7000KW power for     each well.

 

Total water requirement per drilling site will be 1200 -1500 m3, which will be sourced from the local water source. Effluent will be generated in the form of drill cuttings, waste drilling fluid (mud) and drilling wastewater.  Drill cutting (250-550 m3) will be disposed in                                                                                                                                                                                                                                               the  HDPE lined pit. Waste mud and wastewater will be stored in HDPE lined pits of 1mm thick impervious layer. In case of hazardousnature, drilling waste will be disposed as per the Hazardous waste (Management and Handling) Rules, 2003. Domestic effluent will be disposed through septic tanks and soak pits. 

 

The main air emissions will be from the DG set at well site. Flaring of gases during the drilling testing phase will contribute to additional air pollution. However as the flaring will occur only for intermittent phases and will not last for more than a few days, the impact on air quality will not be significant. The air emissions from DG set will be controlled by burning of diesel with low Sulphur content (<0.1%). Air quality monitoring was carried out during December 20 – January 31 for 8 locations for the parameters RSPM, SPM, SO2, NOx , HC and VOCs. Values for RSPM, SO2 and NOx at all the locations were observed within permissible limits. Values for SPM were found to be more at some locations due to vehicular traffic and human activities. VOCs were observed well below the detectable limits. The 8-hourly average. Value varied between 90-198 ug/m3.

 

 After detailed deliberations, the EAC (I) recommended the proposal for grant of environmental clearance subject to stipulation of environmental safeguards.

 

8.9       Exploratory drilling in block CB-ONN-2004/5 at village: Palej, Dist. Bharuch, Gujarat by M/s NaftoGaz India Pvt.Ltd. - Environmental Clearance

 

 

The proposal regarding exploratory drilling in block CB-ONN-2004/5 at village: Palej, Dist. Bharuch, Gujarat by M/s NaftoGaz India Pvt. Ltd. was considered by the Expert Appraisal Committee in its 70th meeting held on 6th – 8th August, 2007.The Committee prescribed the, TORs for undertaking EIA study and advised the project proponent to submit the EIA/EMP report to the State Pollution Control Board for conducting public hearing. The issues emerged during the PH/PC shall be incorporated in the EIA/EMP report and the report submitted to the Ministry for obtaining environmental clearance. 

 

Public hearing for the project was held on  on 18th September 2008 and issues raised were regarding prevention of accidents, impact of blasting and benefit to the local people due to discovery of oil etc.  In general people welcomed the project. 

 

All the above issues were addressed by the project proponent. The project proponent have informed that they will close the  wells after drilling by proper casing and will not leave abandoned wells open. They will provide proper fencing at drill site and security to avoid such accidents. There will be no blasting in the  proposed project drilling. Distribution of oil & gas will be as per the Govt. Policy.

 

M/s NaftoGaz India Pvt. Ltd. have proposed for exploratory drilling for hydrocarbon in block CB-ONN-2004/5 near village: Palej in Dist. Bharuch in  Gujarat. The block covers an area of 75 m2. No wild life sanctuary, national park or reserved forests exist within the block.  It is proposed to drill 15 exploratory wells in the block. The average depth of well will be 2000-4500m. It is  proposed to use water based drilling fluid. The total time required for entire exploratory operation would be 7 years. The total cost in the first phase of the exploratory drilling will be Rs. 90.00 crores.

 

Total water requirement per drilling site will be 1500 KL, which will be sourced from the  nearby local water source. In case need arises ground water will also be used.  The wastewater will be generated because of domestic use and from drilling operations. The wastewater from the domestic sewage (1.5 KLD) will be disposed through soak pit/septic tank system. The wastewater from the waste pit along with fresh water will be used in preparation of drilling fluid. The drilling fluid (mud) after recirculation will be collected in the lined pit at the end of the operation and solar evaporation and solid waste retained will be disposed  to the authorized landfill site. Power requirement will be met through the DG sets of capacity 2250 KW (2 nos.) and 120 KW (1 nos). HSD will be used as fuel for DG set.

 

 

Source of air emission will be the DG sets and test flaring for short period of time and other activities during drilling and well testing. Adequate stack height is proposed for DG sets and test flaring through vertical flare system along with provision of adequate stack height for proper dispersion of pollutants. Air quality monitoring was carried out for a period from 19th March, 2007 to 12th June, 2007, for 10 locations for the parameters SPM, RSPM, SO2, NOx, CO and HC (Toluene and Benzene). Values for SPM, RSPM, SO2 and NOx were observed within the permissible limits. The results of HC were found below detectable limit for all the locations  where as CO   varied from 0.710-0.976 ppm.

 

Solid waste generated in the form of drill cuttings during the drilling phase (20 MT/well) will be collected and covered with native earth and disposed off either in  onsite pits lined with impervious layer or disposed to a approved secured landfill site. Used oil/waste oil will be collected and disposed of to the registered recycler authorized by MoEF.  Construction material waste will be used as a filler material. Kitchen waste will be composted. Sewage sludge will be used as manure. Drilling mud will be disposed of in drilling fluid collection pit. Hydrocarbon waste will be collected in drums and disposed to authorized waste oil recyclers.

 

After detailed deliberations, the EAC (I) satisfied with the proposed pollution control measures to be undertaken recommended the proposal for grant of environmental clearance.

 

 

8.10     Proposed synthetic organic chemical products unit in existing pesticide unit at plot no.  6301-10A, GIDC estate, Ankleshwar, Gujarat  by M/s. Bayer Crop Science- Environmental Clearance reg

 

The project authorities and their consultant gave a detailed presentation on the salient features of the project and proposed environmental protection measures to be undertaken. The project activity is listed at serial no. 5(f) of schedule of EIA Notification, 2006 and categorized under “A” or “B” category depending upon the location of the plant outside or inside the notified industrial area. In instant case the plant is located within the notified industrial area GIDC Ankleshwar and covered under category “B” but the Ankleshwar is an identified critically polluted area hence as per general condition the proposal was appraised at centre. 

 

M/s. Bayer crop science have Proposed for synthetic organic chemical unit in existing pesticide unit at plot no.  6301-10A, GIDC estate, Ankleshwar-393002, Gujarat. The unit is located in GIDC Ankleshwar, which is identified as critically polluted area by CPCB.  No eco-sensitive areas are located within 10 km radius of the plant. River Narmada flows at a distance of 8.25 km and river Amravati at a distance of 3.02 km. The proposed expansion will be carried out  in the existing unit having plot area of 94,364 m2. Cost of the project is Rs. 120 crores.

 

Details of products along with their roduction are given below:

 

Sr. No.

Existing Product

Quantity (T/Annum)

             A.Technical

01

Anilophos

300

02

Triazophos

3000

03

DMTA

255

04

DETA

800

05

Deltamethrin

30

06

Flumethrin

10

07

Benfuresate

80

08

Phenocyanol

18

09

Oxadiargyl

150

10

Ethoprophos

3000

11

Permethrin

20

             B. Formulation

12

Isoproturon

350

13

Diuron

50

14

Carbendazim

150

15

Sevin

550

16

Endosulfan

700

17

Anilophos

300

18

Triazophos

1600

19

Deltamethrin

50

20

Fenoxaporp- Ethyl

50

21

Glufosinate Ammonium

20

22

Monocrotophos

600 (150)*

23

Ethion

100

24

Quintol

150

25

Alliet

50

26

Cypermethrin

800 (80)*

27

Methyl Parathion

1300 KL (900)*

28

Oxydemeton Methyl

630 KL (150)*

29

Quinolphos

630 KL (150)*

30

Ediphenphos

200 KL (100)*

31

Fenthion

300 KL (250)*

32

Propoxur

100 KL (20)*

33

Baytex Gr.

100  (3)*

34

Imidachloropid

400  (85)*

35

Acephete

450 (350)*

  * Equivalent technical quantity has bee mentioned

Proposed Products

1

Desmodur L 75

12000

2

Desmodur N 75

12000

3

Desmodur N 3390

12000

4

Power (CPP)

1.4 MW

                       

        

Power requirement of 4880 KW will be met from the DGVCL. Fuel requirement will be Natural gas (15428 nm3/day) and lube oil (500 lts/month). 

 

Water requirement of  865 m3/d  will be met from GIDC water supply. Effluent generation will be 450 m3/d. Waste water streams will be according to the pollution load.  Process streams will be neutralized and pretreated at plant level, and further treated in existing biological waste water treatment plant. The non process streams would be treated in existing Biological waste water treatment plant. Toxic streams generated from the process will be incinerated in own incinerator. No additional process waste water will be generated due to the proposed expansion.

 

To control the process emissions from the existing unit water, acid, caustic and ventury scrubbers are provided. In the proposed unit  there will be no addition of process stack or vent. Vent gas will be connected to existing incinerator plant. 

Solid/Hazardous waste generated will be  in the form of   used lube oil (2 T/annum) will be sold to MoEF registered reprocessors/incineration within the premises. Oil filter (0.5 T/annum), spent solvent (40 T/annum),waste from containment/clean up of spills (18 T/annum), contaminated cotton waste containers/liners (15 T/annum), distillation waste (33 T/annum), date expired/off specification product (50 KL/annum), used liners (15 T/annum), waste from containment/clean up of spills (2 T/annum) and flue gas cleaning residue/waste carbon (2.5 T/annum) will be incinerated within the premises. Discarded asbestos (5 T/annum), waste from surface preparation for painting (3 T/annum), waste insulation lining material (25 T/annum), ETP sludge (1200 T/annum), used PPE (2 T/annum), broken glass (5 T/annum), incineration ash (40 T/annum) and brick refractory (12 T/annum) will be disposed at BEIL- TSDF. Discarded empty containers (24000 nos/annum) will be sold to GPCB authorized vendors. Ammonium Sulphate (700 T/annum), NaSH (947 T/annum) and sulphuric Acid (350 T/annum) will be sold to end users.

After detailed deliberations, the EAC (I) considering the technical aspects of the project recommended the proposal for grant of environmental clearance subject to stipulation of following additional specific conditions along with specific and general conditions:

 

                                                               i.            The Unit shall carry out VOC  monitoring in the work zone. 

 

                                                             ii.            The unit shall install own ETP and meet the industry specific discharge standards notified under Environment (Protection) Act, 1986.

 

                                                            iii.            GPCB shall not permit any new discharge from new industries or expansion of existing industries in the area that lead to CETP until the said CETP meet the required standards and meet the hydraulic capacity.

 

                                                           iv.            The company shall obtain Authorization for collection, storage and disposal of hazardous waste under the Hazardous Waste (Management and Handling) Rules, 2003 for management of Hazardous wastes and prior permission from GPCB shall be obtained for disposal of solid / hazardous waste in the TSDF. The concerned company shall undertake measures for fire fighting facilities in case of emergency.

 

 Public hearing is not required as the unit is located in the notified industrial estate.

 

 

8.11     Proposed expansion of organic intermediates unit at plot no 27, phase I,   GIDC, industrial estate VAPI , Dist Valsad , Gujarat by M/s  Chemiesynth (Vapi)  Ltd. - Environmental Clearance

 

 

 

The project authorities and their consultant gave a detailed presentation on the salient features of the project and proposed environmental protection measures to be undertaken. The project activity is listed at serial no. 5(f) of schedule of EIA Notification, 2006 and categorized under “A” or “B” category depending upon the location of the plant outside or inside the notified industrial area. In instant case the plant is located within the notified industrial area GIDC Vapi and covered under category “B” but the Vapi is an identified critically polluted area hence as per general condition the proposal was appraised at centre. 

 

M/s Chemiesynth (Vapi)  Ltd.  have Proposed for expansion organic intermediates unit at plot no 27, phase I,   GIDC, industrial estate VAPI , Dist Valsad , Gujarat – 396195  The unit is located in GIDC Vapi, which is identified as critically polluted by CPCB.  No eco-sensitive areas are located within 10 km radius of the plant. The proposed expansion will be with in the existing unit having plot area 13287.75 m2. Green belt will be developed in 1471 m2. Cost of the project will be Rs. 1033.56 lacs. An amount of Rs. 35.00 lacs will be utilized for Environmental Management System.

 

Details of products along with their production capacities are given below:

 

Sr.
No.

Name of the product

Remarks
about
product

Capacity, MT / month

Remarks

 

existing
scenario

proposed

scenario

Diff.

 

 

GROUP A

 

1

Naphthalene 1:8 Dicarboxylic anhydride 4 sulphonic acid  ( 4 SNA )

old

3

3

 

 

 

All the three products shall be alternatively manufactured against their rated capacity only.

 

2

OR 4 - Chloro Anthranilic Acid

new

0

or 1

 

3

OR 4 - Amino -3-methyl Benzoic acid methyl ester.

new

0

or 0.6

 

 

Maximum production capacity of Group A

 

3

3

0

 

 

GROUP B

 

4

DEMAP Aldehyde

old

2

2

 

 

 

All the three products shall be alternatively manufactured against their rated capacity only.

 

5

OR 5 Nitro Indazole (Grade- III )

old

or 1

or 1

 

6

OR BTL  II

new

0

or 1

 

 

Maximum production capacity of Group B

 

2

2

0

 

 

GROUP C

 

7

FEN - 04 OR { 5 - [ 2 - Chloro - 4 - Trifluoromethyl ) - Phenoxy] -2- Nitrobenzoic Acid}

new

40

40

 

no change

 

 

Total production capacity of Group C

 

40

40

0

 

 

Sr.
No.

Name of the product

Remarks
about
product

Capacity, MT / month

Remarks

existing
scenario

proposed

scenario

Diff.

 

GROUP D

8

Meta Systox R or Oxydemeton- methyl,or
5 - 2 ethyl sulfinylethyl 0.0 dimethyl phosphorothiate

new

0

90

 

Both the  products shall be alternatively manufactured against their rated capacity only.

9

OR Ethyl Ptenyl Glyoxylate ( EPG )

new

0

or 60

 

 

maximum  production capacity of Group D

 

0

90

90

 

GROUP E

10

Para Nitro Ortho Toludene

old

10

10

 

All the three products shall be alternatively manufactured against their rated capacity only.

11

OR 2 Methyl 5 Amino Phenol

old

or 4.5

or 4.5

 

12

OR 2:6 Di Chloro P Amino Phenol

new

0

or 6

 

 

maximum production capacity of Group E

 

10

10

0

 

GROUP F

13

4 - nitro Ortho Phenyl Di Amine

new

0

1

 

New product

 

Total production capacity of Group F

 

0

1

1

 

 

GROUP G

14

Puralide

new

0

5

 

New product

 

Total production capacity of Group G

 

0

5

5

 

 

GROUP H

15

DMPAT

new

0

200

 

New product

 

Total production capacity of Group H

 

0

200

200

 

 

Total Net production of all groups

 

55

351

296

 

 

 

 

 

 

 

 

 

And byproduct

 

Sr.
No.

Name of the
 Byproduct

Capacity, MT / month

existing

proposed

Total  after  expansion

1

30% HCl

3.18

3.4

6.58

2

acetic acid

123.5

0.0

123.50

3

Crome Oxide

4.87

0.0

4.87

4

20% Sodium Bisulfite

0

31.7

31.70

5

Spent Acid

37.92

0.0

37.92

6

Hexane

0

0.43

0.43

7

AlCl3 Soln.

0

8.16

8.16

8

Ammonium Chloride

0

75.2

75.20

9

Sodium Chloride

0

248.41

248.41

 

Total

169.47

367.3

536.76

 

 

Power requirement of 475 KVA will be met from DGVCL. DG set, 1 no of 125 KVA is proposed for emergency power back up. Fuel requirement for the boiler will be FO (1600 L/day) and bagasse/coal (400 Kg/hr.). fuel for DG set will be LDO (20 lt/hr.)

 

Water requirement of  251 m3/d  will be met from GIDC water supply. Effluent generation will be 125.435 m3/d. The normal stream will be treated in effluent treatment plant for primary, secondary and tertiary treatment. High TDS effluent will be treated in Tripple Effect Evaporation system. The treated effluent will be sent to CETP for further treatment and disposal.

 

Stack height of 30m for the Boiler. and 11m  for the DG set is proposed. Two stage water and Caustic Scrubber, two stage alkali Scrubber and  two stage water scrubber and single stage water scrubbers are proposed to control process emissions.

Solid/Hazardous waste generation will be, waste/used oil (40 kgs/month)  will be sold to registered recyclers . Discarded containers (4360 nos/month)  will be utilized for packing of HW or sold to authorized recyclers. Sludge from ETP (10 MT/month), evaporated Salt (77.4 MT/month), Calcium phosphate from the process (5.12 MT/month),  Iron Oxide from the process (26.85 MT/month), Calcium Sulphate from the process (10.00 MT/month), magnesium sulphate from the process (0.18 MT/month) and ammonium Sulphate salt from the process (2.15 MT/month) will be disposed off to TSDF, Vapi. Spent carbon (12.16 MT/month) and residue from the process (28.24 MT/month) will be sent to common incineration facility, Vapi. Gypsum from the process (0.3 MT/month) will be disposed of in the TSDF, Vapi or to the cement industries.  

After detailed deliberations, the EAC (I) recommended the proposal for grant of environmental clearance subject to stipulation of following additional specific conditions along with specific and general conditions:

 

I.                     Solvents shall be  stripped before the effluent are sent to Effluent Treatment Plant to control the VOC emissions.

 

II.                   Monitoring of VOCs shall be carried  out in ambient and work zone.

 

III.                  The ETP shall be upgraded and the treated effluent shall meet the required standards specific discharge standards notified under Environment (Protection) Act, 1986..

 

IV.                The unit shall install own ETP and meet the industry specific discharge standards notified under Environment (Protection) Act, 1986.

 

V.                  GPCB shall not permit any new discharge from new industries or expansion of existing industries in the area that lead to CETP until the said CETP meet the required standards and meet the hydraulic capacity.

 

VI.                The company shall obtain Authorization for collection, storage and disposal of hazardous waste under the Hazardous Waste (Management and Handling) Rules, 2003 for management of Hazardous wastes and prior permission from GPCB shall be obtained for disposal of solid / hazardous waste in the TSDF. The concerned company shall undertake measures for fire fighting facilities in case of emergency.

 

 

Public hearing is not required as the unit is located in the notified industrial estate

 

8.12     Proposed specialty oils & chemicals manufacturing unit at plot no 3113, GIDC, industrial estate, Panoli in  Dist. Bharuch in Gujarat by M/s  Prime Chemicals  - Environmental Clearance.

 

 

The project authorities and their consultant gave a detailed presentation on the salient features of the project and proposed environmental protection measures to be undertaken. The project activity is listed at serial no. 5(f) of schedule of EIA Notification, 2006 and categorized under “A” or “B” category depending upon the location of the plant outside or inside the notified industrial area. In the instant case, the plant is located within the notified industrial area, GIDC Panoli and covered under category “B” . But the Panoli is an identified critically polluted area, hence as per general condition the proposal was appraised at centre. 

 

M/s Prime Chemicals have proposed for a specialty oils & chemicals unit at plot no 3113, GIDC, industrial estate, Panoli,  Dist. Bharuch  , Gujarat. The unit will be located in notified industrial   area, GIDC Panoli. As per CPCB, Panoli has been identified as critically polluted area. No protected forests/eco-sensitive areas are located within the 10 km radius of the proposed unit and   area for the proposed unit is 1500 m2   of which, 86.99 m2 will be developed as green belt. The cost of the project is Rs. 25.0 Lacs. of which Rs. 0.5 Lacs will be utilized for the environmental protection measures.

Sr. No

Name of Products

Capacity, (MT/Month)

 

Primex-001

I

Printing Ink Based Process Oil

200

II.

Thinner Based Products

150

2.

Primex-002

I

Speciality Oil

250

II

Rubber Process Oil

260

III

Aromatic Pesticides Solvent

150

3.

Primex-003

I

Alumini. um Rolling Oils

150

II.

Textile Oils

150

4.

Primex – 004

400

Total

1710

 

Details of products along with their production capacities are given below:

 

The power requirement of 20 Hp will be met from the Daxin Gujrat Vij Company Limited. No DG set will be provided in the proposed unit. Natural gas @ 120.0 M3/day will be used for Thermic Fluid Heater.

 

Fresh water requirement of1.015 m3/d will be met from the GIDC water supply. No process effluent will be generated.  The domestic wastewater generation will be 0.4 m3/day, which will be discharged into soak pit through Septic Tank.

Stack height of 15 m will be provided to thermic fluid heater for  dispersion of gaseous emissions. To control the fugitive emissions vaccume distillation with brine circulation will be adopted. The entire manufacturing activities will be carried out in theclosed system. All the pumps would be provided with mechanical seals and adequate ventilation system will be provided.

 25 Nos. /Annum of discarded drums from raw material storage and handling will be decontaminated and reused or sold to approve vendors. 5 Lit/Annum of spent oil from the plant and machinery will be sold to MoEF Approved Recycler.

After detailed deliberations, the EAC (I) satisfied with the proposed pollution control measure to be undertaken recommended the proposal for grant of environmental clearance subject to stipulation of following additional specific conditions along with specific and general conditions:

i.                     The company shall obtain Authorization for collection, storage and disposal of hazardous waste under the Hazardous Waste (Management and Handling) Rules, 2003 for management of Hazardous wastes and prior permission from GPCB shall be obtained for disposal of solid / hazardous waste in the TSDF. The concerned company shall undertake measures for fire fighting facilities in case of emergency.

 

Public hearing is not required as the unit is located in the notified industrial estate.

 

 

8.13     Proposed  Dyes intermediates unit  at plot no 285,  286/1, a-1-322/1 and 2 II phase ,  GIDC Vapi,  dist. Valsad, Gujarat  by M/s  Aarti  industries  Ltd. reg Environmental Clearance

 

The project authorities and their consultant gave a detailed presentation on the salient features of the project and proposed environmental protection measures to be undertaken. The project activity is listed at serial no. 5(f) and 5(b) of schedule of EIA Notification, 2006 and categorized under “A” category and was appraised at centre 

 

 

M/s Aarti industries Ltd. (Amine Division) have Proposed for a dyes intermediates  unit at plot no 285, 286/1, a-1-322/1 and 2, II phase, GIDC Vapi, Dist. Valsad, Gujarat-396195. The unit is located in GIDC Vapi, which is identified as critically polluted area by CPCB. No eco-sensitive areas are located within 10 km radius of the plant. River Damanganga flows at a distance of 3.5 kms.  Total land area will be 12009 m2. Cost of the project will be Rs. 1.80 crores.

 

Details of products and their  production capacities are given below:

 

Sr. No.

Product

Present  capacity  (MTPM)

 Proposed capacity (MTPM)

Total capacity (MTPM)

            GROUP –A : AMMONOLYSIS PRODUCTS

1

4-Nitro Aniline (PNA)

125

545

1100

2

2-Nitro Aniline (ONA)

170

3

2-Chloro 4-Nitro Aniline (OCPNA)

130

4

Para Chloro Ortho Nitro Aniline (PCONA)

130

AND/OR

5

Di Chloro Ortho Nitro Aniline (DCONA)

--

1100

1100

 

                    TOTAL

555

1100

1100

            GROUP-B : NITRATION PRODUCTS

1

2,5 DCNB

NIL

3500

3500

2

3,4 DCNB

3

2,3,4 TCNB

4

2,4,5 TCNB

5

NCB

6

DNCB

 

                    TOTAL

NIL

3500

3500

            REDUCTION PRODUCTS

1

3,5 DCA

NIL

150

150

2

MCA

3

OPDA

4

PPDA

             BY-PRODUCTS

1

Mixture of 2,3,4 & 2,4,5 TCNB

--

700

700

2

CaCl2 Solution

--

620

620

3

Dilute Sulphuric Acid

--

3857

3857

 

Ammonium Chloride (NH4Cl)

2

--

--

4

Sodium Thiosulphate

--

519

519

 

DG set of 750 KVA is proposed for stand by power supply. Fuel requirement for the boiler will be 834 kg/hr of coal and/or gas 700 m3/hr. Fuel requirement for the DG set will be 120 lts/hr.

Total water requirement of  484 m3/d   will be sourced from the GIDC water supply. Total wastewater generation will be 84 m3/d.  No process effluent will be generated. The other effluent will be treated in existing effluent treatment plant which will be modified to treat the effluent for primary, secondary and tertiary treatment and treated effluent will be sent to CETP for further treatment and disposal. Domestic effluent will be treated through septic tanks/ soak pits. 

Multicyclone dust collector system and stack height of 37m is proposed for the coal/gas fired 10 TPH boiler and stack height of 11m is proposed for the DG set. Three stage  scrubber and two stage scrubber are proposed for ammonia recovery.

Hazardous waste/solid wastes  will be in the form of ETP waste (110 MT/month) which will be disposed off to TSDF, VAPI. Used oil (50 lts/year) will be reused in the plant for lubrication purposes. Process waste (NH4Cl) (2 MT/month) Ammonium Chloride will be treated with Calcium hydroxide to obtain Ammonia & Calcium which will be recycled and sold to actual users. Discarded material plastic bags/drums/liners will be sold to actual users.  

After detailed deliberations, the EAC (I) satisfied with the proposed pollution control measures to be undertaken recommended the proposal for grant of environmental clearance subject to stipulation of following additional specific conditions along with specific and general conditions:

 

i.                     The unit shall install own ETP and meet the industry specific discharge standards notified under Environment (Protection) Act, 1986.

 

ii.                   GPCB shall not permit any  new discharge from new industries or expansion of existing industries in the area that lead to CETP until the said CETP meet the required standards and meet the hydraulic capacity.

 

iii.                  Monitoring of VOC shall be carried in the wourk zone anddata submitted to the Ministry.

 

iv.                 The company shall obtain Authorization for collection, storage and disposal of hazardous waste under the Hazardous Waste (Management and Handling) Rules, 2003 for management of Hazardous wastes and prior permission from GPCB shall be obtained for disposal of solid / hazardous waste in the TSDF. The concerned company shall undertake measures for fire fighting facilities in case of emergency.

 

Public hearing is not required as the unit is located in the notified industrial estate.

 

 

8.14     Proposed  dye & dyes intermediates unit at plot no 902, III phase ,  GIDC Vapi,  dist. Valsad, Gujarat  by M/s  Aarti industries  Ltd (Alchemic Organics Division )  Environmental Clearance

 

 

The project authorities and their consultant gave a detailed presentation on the salient features of the project and proposed environmental protection measures to be undertaken. The project activity is listed at serial no. 5(f) of schedule of EIA Notification, 2006 and categorized under “A” or “B” category depending upon the location of the plant outside or inside the notified industrial area. In  the  instant case, the plant is located within the notified industrial area GIDC Vapi and covered under category “B” . But the Vapi is an identified critically polluted area, hence, as per general condition the proposal was appraised at centre. 

 

 

M/s Aarti industries Ltd. (Alchemic Organics Division) have Proposed for a dye & dyes intermediates unit at  GIDC Vapi in  Dist. Valsad in Gujarat. The unit is located in GIDC Vapi, which is identified as critically polluted area by CPCB. No eco-sensitive areas are located within 10 km radius of the plant. River Damanganga flows at a distance of 3.5 kms.  Total land area will be 25270 m2. Cost of the project will be Rs. 2.00 crores.

 

Details of products and production capacities are given below:

 

Sr. No.

Product

Present  Capacity  (MTPA)

 Proposed Capacity (MTPA)

Total Capacity (MTPA)

1

Dichloro Banzedine Hydro Chloride (DCBH)

1000

3000

4000

2

Dichloro Phenol (DCP)

100

500

600

3A

Para/Ortho Flouro Phenol

0

300

300

3B

Para/Ortho Flouro Bromo Benzene

3C

3,5 Di Flouro Bromo Benzene

3D

3,4 Di Flouro Bromo Benzene

3E

3,4,5 Tri Flouro Bromo Benzene

4A

3,5 Dichloro Nitro Benzene

0

750

750

 

And/Or

4B

Trichloro Benzene

5A

3,5 Dichloro Aniline

0

900

900

 

And/Or

5B

Meta Chloro Aniline

 

And/Or

5C

OCPPDA

6A

Quinalphos 25% EC (Diethyl 2-Hydroxy Thiophosphoryl Chloride)

840

0

840

And/Or

6B

Triazophose 40% EC

0

2250

2250

7A

QP

1500

--

1500

 

And /or

 

 

7B

Triazophose

           --

1500

8

2,3 Dichloro 4 Amino Phenol

0

300

300

9

Ortho Chloro Aniline

0

400

400

 

Total

3440

9900

11000

 

By-Products

 

 

 

1

Dilute Sulphuric Acid

1232

25199

26431

2

NaBr. Solution

--

2004

2004

 

Sodium Thiosulphate

--

7591

7591

 

Fuel requirement for the boiler will be 321 lts/hr. of LDO/FO and/or 31 Ton/day of coal and/or gas 625 m3/hr. fuel requirements for the Thermopack and Incinerators will be LDO/FO (113 lt/hr.)

Total water requirement will be 601 m3/d, which will be sourced from the GIDC water supply. Total wastewater generation will be 371.10 m3/d. The effluent will be treated in the existing effluent treatment plant for primary, secondary and tertiary treatment and treated effluent will be sent to CETP for further treatment and disposal. Domestic effluent will be treated through septic tanks/ soak pits. 

Stack height of 20m is proposed for the boiler and Thermopack heater. Ventury Alkali scrubber are proposed for the incinerator. HCl & Alkali scrubber and Two stage scrubber are proposed to control the process emissions.

Hazardous  solid waste generation will be in the form of ETP waste (19479 Kg/day) and will be disposed off to TSDF, VAPI. Distillation residue (74 Kg/day) will be incinerated in own incineration system. Date expired and off Specification Pesticides (200 Kg/annum) will be incinerated in own incineration system. Spent solvent (1200 Kg/annum) will be reused or incinerated in own incineration system. Spent catalyst (15700 Kg/annum) will be sent to suppliers for regeneration. Spent Filter (700 nos/annum) will be incinerated in own incineration system. Incineration Ash (3248 Kg/day) will be disposed to common TSDF site where it will be used for land filling. Used oil (60 lts/month) will be reused in the plant for lubrication purposes.  Discarded material (34000 nos/month) will be sold to actual users.  

After detailed deliberations, the EAC (I) satisfied with the proposed pollution control measures to be undertaken recommended the proposal for grant of environmental clearance subject to stipulation of following additional specific conditions along with specific and general conditions:

 

i.                     The unit shall carry out monitoring of VOC and data should be submitted to the Ministry.

 

 

ii.                   The unit shall install own ETP and meet the industry specific discharge standards notified under Environment (Protection) Act, 1986.

 

iii.                  GPCB shall not permit any new discharge from new industries or expansion of existing industries in the area that lead to CETP until the said CETP meet the required standards and meet the hydraulic capacity.

 

iv.                 The company shall obtain Authorization for collection, storage and disposal of hazardous waste under the Hazardous Waste (Management and Handling) Rules, 2003 for management of Hazardous wastes and prior permission from GPCB shall be obtained for disposal of solid / hazardous waste in the TSDF. The concerned company shall undertake measures for fire fighting facilities in case of emergency.

 

Public hearing is not required as the unit is located in the notified industrial estate.

 

8.15     Organic Specialty chemicals intermediates unit at plot no 1713, III phase,  GIDC Vapi,  dist. Valsad, Gujarat-396195 by M/s  Yasho industries Pvt.  Ltd (Unit-II) - Environmental Clearance.

 

 

The project authorities and their consultant gave a detailed presentation on the salient features of the project and proposed environmental protection measures to be undertaken. The project activity is listed at serial no. 5(f) of schedule of EIA Notification, 2006 and categorized under “A” or “B” category depending upon the location of the plant outside or inside the notified industrial area. In instant case the plant is located within the notified industrial area GIDC Vapi and covered under category “B” but the Vapi is an identified critically polluted area hence as per general condition the proposal was appraised at centre. 

 

M/s. Yasho Industries PVT. Ltd. have proposed for organic Specialty chemicals intermediates unit at plot no 1713, III phase ,  GIDC Vapi,  Dist. Valsad in Gujarat with production capacity of 410 MTPM. The proposed unit is located in a critically polluted area Vapi. No eco-sensitive areas are located within 10 km radius of the proposed unit.  Total plot area is 5000 m2. Green belt will be developed in 1229 m2. The total cost of the project will be Rs. 17.50 crores .

 

Details of the products to be manufactured and their production capacities include the following:

 

S. no

Products

Quantity

(MTPM)

01

5-Methoxy-2-Mercaptobenzimidazole

 (5-MMBI)

5

02

Tetra Methyl Thiuram Monosulfide (TMTM)

5

03

Diphenyl Guadinidine (DPG)

5

04

Butylated Hydroxy Anisole

(BHA)

15

05

4,4-Dithiodimorpholine (DTDM)

2

06

Copper Dimethyl Dithiocarbamate (CDMC)

1

07

Nickel DiButyl Dithiocarbamate (NDBC)

2

08

Zinc Dibenzyl Dithiocarbamate (ZBEC)

20

09

Copper DiButyl Dithiocarbamate (CDBC)

20

10

2-Mercaptobenzimidazole (2-MBI)

10

11

Tertiary Butyl Hydroquinone (TBHQ)

50

12

4,5 Methyl 2-Mercaptobenzimidazole

 (2-MMB)

40

13

Aromatic Derivative of Diphenylamine (ADA)

20

14

Ethylene Thiourea (ETU)

5

15

Octylated Diphenylamine (OCD)

100

16

Tetra Methyl Thiuram Disulfide (TMT)

5

17

Zinc DiButyl Dithiocarbamate (ZDBC)

20

18

Zinc Diethyl Dithiocarbamate (ZDC)

20

19

Zinc Salt of 4&5, Methyl

2-Mercaptobenzimidazole  (ZMMB)

40

20

Dimethyl Diphenyl Thiuram Disulfide (MPTD)

10

21

Zinc Salt of 2-Mercaptobenzimidazole  (ZMB)

5

22

Caprolactum Di Sulphide (DTDC)

10

 

                                              Total

410.00

 

By-Products

 

01

Sodium Bisulphide

4.40

02

Methyl Hydrogen Sulphide

13.20

03

Hydrochloric acid

11.50

04

Sodium Sulphide

12.35

 

The total power requirement for the proposed unit will be 750 HP which will be sourced from the Dakshin Gujarat Vij. co. Ltd. DG set of 500 KVA is also proposed in case of power failure from DGVCL.  Fuel requirement for the non-IBR boiler and Thermo pack boiler will be FO, 75 lts/day and fuel for DG sets  will be LDO 20 lts/Hr.

 

The total water requirement for the proposed unit will be 148.5 m3/day and will be sourced from the GIDC water supply. The effluent generation will be 101 m3/day (94 m3/day industrial +7 m3/day domestic). The effluent will be treated in ETP and treated effluent will be disposed to  CETP, Vapi.

 

To control process emissions water and alkali Scrubbers in series with stack height  of 11 mts. are proposed. Stack height of 32 m for the boiler and stack height of 15 m is proposed for  DG set.

 

Solid /hazardous waste will be generated in the form of ETP waste (200 kgs/month) stored and finally disposed to CSWD site of VWEMCL, Vapi.   Spent carbon (1.85 MT/month) will be stored and  sent for incineration at GEPIL site, Surat. Used oil (100 lts/month) will be sold to registered reprocessors. Discarded drums (25 nos / month) will be sold to the authorized recyclers. and discarded bags (1000 nos/month sold to the authorized scrap dealers.

 

The committee deliberated in detail regarding the measures of odour control. The proponent informed that odour nuisance is due to the sulphure compound. To control the odour reactions will be carried in the closed reactors and exhaust with proper ducting and odour control filters will be  provided. Ventury scrubber will be installed.

 

As desired by the committee, the proponent also submitted the compliance report for the existing unit manufacturing the similer product. The company has installed solvent recovery system to recover the  solvent and secondary condenser with chilled brine to recover the solvents have been provided. Further, regular monitoring of HCl and VOC’s is being carried out within the plant.

 

The Committee after detailed deliberations, recommended the proposal for grant of environmental clearance subject to stipulation of following specific conditions:

 

i.                     The solvent from the effluent shall be stripped before sending to ETP.

 

ii.                   Measures for odour control shall be taken

 

iii.                  Monitoring of VOC in ambient and work zone.

 

iv.                 The unit shall install own ETP and meet the industry specific discharge standards notified under Environment (Protection) Act, 1986.

 

v.                   GPCB shall not permit any new discharge from new industries or expansion of existing industries in the area that lead to CETP until the said CETP meet the required standards and meet the hydraulic capacity.

 

vi.                 The company shall obtain Authorization for collection, storage and disposal of hazardous waste under the Hazardous Waste (Management and Handling) Rules, 2003 for management of Hazardous wastes and prior permission from GPCB shall be obtained for disposal of solid / hazardous waste in the TSDF. The concerned company shall undertake measures for fire fighting facilities in case of emergency.

 

Public hearing is not required as the unit is located in the notified industrial estate.

 

 

8.16     Proposed diversification of existing unit by introduction of colourformer & developer (pergafast & pergascript range of products) & its intermediates unit at plot no 8001, phase-VI,   GIDC, industrial estate, Ankleshwar-393002 Dist. Bharuch  , Gujarat by M/s  Diamond Dye-Chem Ltd.  (unit-II) - Environmental Clearance

 

 

The project authorities and their consultant gave a detailed presentation on the salient features of the project and proposed environmental protection measures to be undertaken. The project activity is listed at serial no. 5(f) of schedule of EIA Notification, 2006 and categorized under “A” or “B” category depending upon the location of the plant outside or inside the notified industrial area. In the instant case, the plant is located within the notified industrial area, GIDC Ankleshwar and covered under category “B”. But the Ankleshwar is an identified critically polluted area, hence as per general condition the proposal was appraised at centre. 

 

 

M/s Diamond Dye-Chem Ltd.  (unit-II) have proposed for diversification of existing unit by introduction  of colourformer & developer (Pergafast & Pergascript range of products) & its intermediates unit at GIDC, industrial estate, Ankleshwar  in Dist. Bharuch in  Gujarat. The unit will be located in the notified industrial   area, GIDC Ankleshwar. As per CPCB, Ankleshwar has been identified as critically polluted area. No protected forests/eco-sensitive areas are located within 10 km radius of the proposed unit. The proposed expansion will be carried  in the existing unit having land area of 71,040 m2.  Green belt will be developed in 4273 m2 of plant area. The cost of the existing unit is Rs. 66.00 Crores and cost for the proposed expansion will be Rs. 11.00 Crores.

 

Details of Products and their production capacities are given below:

 

Sr. No.

Product

Present Capacity  (MTPA)

 Proposed Capacity  (MTPA)

Total

Capacity

(MTPA)

1

Pergascript Red I-6B

and/or

Pergascript Red MC-30

 

180

-

180

2

Pergascript Blue SRB-P

120

-

120

3

Pergascript Green I-2GN

180

-

180

4

Pergascript Orange I-G

60

-

60

5

Pergascript 201

And/or

Pergascript 201 Dispersion (on 100% Basis)

 

1080

-

1080

6

BB Acid

and/or

 Pergascript Blue-1-2G

60

-

60

7

Optical Whiteners (on 100% Basis)

-

500

500

 

Total

1680

500

2180

By Products

1

Sodium Acetate

(on 100% basis)

125

-

125

2

Sodium Acetate liq.

 (on 100% basis)

75

-

75

 

The existing power requirement of 1524 KW will fulfill the requirement for the proposed expansion. DG set of 1010 KVA as stand for power requirement will be installed.  17280 Nm3/day of natural gas will be utilized as fuel for the boiler and 600 lts/day of LDO will be utilized as fuel for DG set.

 

Existing water requirement of 300 m3/day will be met from GIDC water supply. The wastewater generation will remain the same i.e 250 m3/day. The existing effluent after the primary treatment would be sent to  M/s Environ Technology Ltd. (ETL), Ankleshwar for final treatment and disposal. After the proposed expansion, the same scheme will be followed. The existing treatment facility for primary treatment would be improved. The TDS will besolidified by using isolation method and filteration and then biological treatment would be given. Domestic effluent will be disposed  through septic tank/soak pit.

 

Stack height of 32m is proposed for two steam boilers and stack height of 13.5 m is proposed for the DG set. Caustic Scrubber & Regenerative Thermic Oxidiser are proposed to control HCl emissions from the reactor-I. H2SO4 Scrubber is proposed for the reactor-II stack.  Caustic scrubber is proposed for storage tanks. Bag filter is proposed to control the particulate emissions. The regenerative thermal oxidizer, basically a high temperature gas fired unit to control the VOC. The resultant CO2 andwater will be vented into the atmosphere.

 

 

Process waste (20 MTPA) and Tar waste (12 MTPA) will be sent to Common incineration facility at BEIL. Spent Solvent (5872 MTPA) will be sold to M/s Daxesh Petrochem Pvt. Ltd for Distillation and Spent Solvent (2021 MTPA) will be sent to Common incineration facility at BEIL. Used/Spent oil (2 MTPA) will sold to registered refiners. Discarded containers (160 MTPA) and barrels/liners (10 MTPA) will be collected, stored and decontaminated. Non recyclable plastic waste (20 MTPA), used PP equipments (0.2 MTPA), waste insulation material (1 MTPA), broken glass wares

 

 

 

 

 

 

 

 

 

 

 

 etc. (0.2 MTPA) and ETP sludge (410) will be disposed at TSDF of BEIL.

 

After detailed deliberations, the EAC (I) satisfied with the proposed pollution control measure to be undertaken recommended the proposal for grant of environmental clearance subject to stipulation of following additional specific conditions along with specific and general conditions:

 

i.                     The unit shall install own ETP and meet the industry specific discharge standards notified under Environment (Protection) Act, 1986.

 

 

ii.                   GPCB shall not permit any  new discharge from new industries or expansion of existing industries in the area that lead to CETP until the said CETP meet the required standards and meet the hydraulic capacity.

 

iii.                  The company shall obtain Authorization for collection, storage and disposal of hazardous waste under the Hazardous Waste (Management and Handling) Rules, 2003 for management of Hazardous wastes and prior permission from GPCB shall be obtained for disposal of solid / hazardous waste in the TSDF. The concerned company shall undertake measures for fire fighting facilities in case of emergency.

 

Public hearing is not required as the unit is located in the notified industrial estate.

 

8.17     Proposed expansion of dyes manufacturing unit at plot no 6713, 6714/1   GIDC, industrial estate, Ankleshwar-393002 Dist. Bharuch , Gujarat by M/s  Jay Yogeshwar Chemical Industries reg Environmental Clearance

 

The project authorities and their consultant gave a detailed presentation on the salient features of the project and proposed environmental protection measures to be undertaken. The project activity is listed at serial no. 5(f) of schedule of EIA Notification, 2006 and categorized under “A” or “B” category depending upon the location of the plant outside or inside the notified industrial area. In the instant case, the plant is located within the notified industrial area, GIDC Ankleshwar and covered under category “B”. But the Ankleshwar is an identified critically polluted area, hence, as per general condition the proposal was appraised at centre

 

M/s Jay Yogeshwar Chemical Industries have proposed for expansion of dyes manufacturing unit at plot no 6713, 6714/1   GIDC, industrial estate, Ankleshwar-393002 Dist. Bharuch , Gujarat The unit will be located within the notified industrial   area, GIDC Ankleshwar. As per CPCB, Ankleshwar has been identified as critically polluted area. No protected forests/eco-sensitive areas are located within 10 km radius of the proposed unit. The proposed expansion will be carried within  the existing unit having plot area of 1520 m2. Green belt is proposed in 150 m2 of plant area. The cost of the proposed  project is Rs.30.00 lacs.

 

 

Details of Products and their production capacities are given below:

 

Sr. No.

Product

Present Capacity  (MTPM)

 Proposed Capacity  (MTPM)

Total

Capacity

(MTPM)

1

Auramine ‘O’

(Basic Yellow-2)

12.500

62.500

75.00

By-Product

  1

Mechlor’s Ketone

03.125

15.625

18.75

 

 

Raw Material requirement will be DMA (62.50 MT/M), Formaldehyde (25.00 MT/M), Sulphanilic Acid (00.625 MT/M), Sulphur (22.750 MT/M), Urea (109.50 MT/M), Acetic Acid (37.50 MT/M), Salt (220.00 MT/M) and Sulphamic Acid (28.00 MT/M),

 

The power requirement of 63 KVA will be met through Dakshin Gujarat Vij. Company Limited (DGVCL). DG set will be installed for stand by power requirement.  800 Nm3/day of natural gas will be utilized as fuel for the boiler. Stack height of 10m is proposed for the boiler and thermic fluid heater. Stack height of 9m is proposed for the DG set. Scrubbers (2 nos) are proposed to control process emissions.

 

Water requirement of 411.75 m3/day will be met from the GIDC water supply. The effluent generation will be 30.38 m3/day which will be sent to CETP for treatment and disposal. Domestic effluent will be disposed off through septic tank/soak pit.

 

 

Discarded bags (1600 nos/month) will be reused for packing of finished products and excess, if any will be sold to the authorized scrap vendor. Used lubricating oil (10 lts/annum) will be reused for lubrication, if excess will be sold to MoEF registered recycler.

 

After detailed deliberations, the EAC (I) recommended the proposal for grant of environmental clearance subject to stipulation of following additional specific conditions along with specific and general conditions:

 

i.                     The unit shall install own ETP and meet the industry specific discharge standards notified under Environment (Protection) Act, 1986.

 

ii.                   GPCB shall not permit any new discharge from new industries or expansion of existing industries in the area that lead to CETP until the said CETP meet the required standards and meet the hydraulic capacity.

 

iii.                  The company shall obtain Authorization for collection, storage and disposal of hazardous waste under the Hazardous Waste (Management and Handling) Rules, 2003 for management of Hazardous wastes and prior permission from GPCB shall be obtained for disposal of solid / hazardous waste in the TSDF. The concerned company shall undertake measures for fire fighting facilities in case of emergency.

 

Public hearing is not required as the unit is located in the notified industrial estate.                                                                                    

                                      

 

8.18     Proposed  Resins manufacturing  unit at plot no  13 Survey no. 46/1, Shed No. C&D Daman Ganga Industrial Estate Athal , Silvasa (D. & N.H)   396230  by M/s. Orson Chemicals reg Environmental Clearance

 

The project authorities and their consultant gave a detailed presentation on the salient features of the project and proposed environmental protection measures to be undertaken. The project activity is listed at serial no. 5(f) of schedule of EIA Notification, 2006 and categorized under “A” or “B” category depending upon the location of the plant outside or inside the notified industrial area. In the instant case, the unit is located within the Daman Ganga industrial area, hence it is ‘B’ category project..

 

M/s. Orson Chemicals have proposed for Resins manufacturing unit at  Daman Ganga Industrial Estate Athal , Silvasa. The unit is located in Daman Ganga Industrial Estate. Maharashtra state boundary is at a the distance of 12 kms. River Damanganga flows at a distance of 1 km. The total plot area of the proposed unit is 1710 m2. Green belt will be developed in 100 m2 of plant area. Cost of the project will be Rs. 139.50.00 lacs. of which Rs. 13.00 lacs will be utilized for environmental Management System.

Details of products and their production capacities are given below:

 

Sr. No.

Name of Product

Quantity in

MTPM

1.

Unsaturated Polyester Resin

600

2.

Vinyl Ester Resin

  50

 

                                    Total

650

           

Average water consumption of 3.5 m3/d will be met from the ground water. About 4.108 m3/d of effluent will be generated of which 1.0 m3/d of domestic effluent will be sent to soak pit through septic tank.   The process effluent (3.108 m3/d) will be treated in effluent treatment plant for primary, secondary & tertiary treatment and followed by evaporation system. The condensate from the evaporator and treated effluent  will be utilized for plantation or recycled in cooling tower. Thus there will be no discharge of any industrial effluent out side the factory premises.  Power requirement of 150 KVA will be sourced from the Daman Ganga Industrial Estate, Athal. Fuel for thermopak will be FO (300 kg/day). One D G set of capacity 125 KVA is proposed for standby power supply. Fuel for DG set will be 16 lts/hr of HSD. There will be no process gas emission. Thermopack will be provided with  a stack height of 30 meters. Stack height of 5 meters will be provided for DG set.

The solid /hazardous waste will be generated in the form of ETP (500 kgs/month) and salt from evaporation system (1500 kgs/month) will be sent to TSDF of M/s. GEPIL. Discarded containers (250 Nos/Month) will be sold to authorized recycler. Waste oil/used oil (10 kgs/year) will be sold to registered re-refiner. 

After detailed deliberations, the EAC (I) satisfied with the proposed pollution control measures to be undertaken recommended the proposal for grant of environmental clearance.

 

 

8.19     Proposed expansion synthetic organic chemicals  manufacturing  unit at  Survey no. 677- Mahuvad & Survey no. 494- Ekalbara,  Padra Taluka , Dist: Vadodara in Gujarat  by M/s. Tarak Chemicals Private Limited reg Environmental Clearance

 

The project authorities and their consultant gave a detailed presentation on the salient features of the project and proposed environmental protection measures to be undertaken. The project activity is listed at serial no. 5(f) of schedule of EIA Notification, 2006 and categorized under “A” or “B” category depending upon the location of the plant outside or inside the notified industrial area. In the instant case, the unit is located outside the notified industrial area and covered under category “A”, the proposal was appraised at centre. 

 

 

M/s. Tarak Chemicals Private Limited have proposed for expansion of synthetic organic chemicals unit at Mahuvad and Ekalbara Village, Padra Taluka, Vadodara District, Gujarat. No protected forests/eco-sensitive areas are located within 10 km radius of the proposed unit. Proposed expansion will be carried within the existing unit having plot area 19,610 m2. Green belt will be developed in 6367.7 m2 of plant area.   Cost of the Project is Rs. 8.00 crores. A capital expenditure of Rs. 64.01 Lacs and an annual recurring expenditure of about Rs. 39.02 Lacs, at current prices on environmental matters will be earmarked for environmental protection measures.

 

      Details of Products and their production capacity are given below:

 

 

 

S. No.

List of Product

Quantity  in MT/Month

Existing

Proposed

Total

1.

Oil Field Chemicals

500

-

500

2.

Acid Chlorides

50

-

50

3.

Ultrazol BA

6

-

6

4.

Zinc Benzoate

10

-

10

5.

Phenyl Acetyl Glutamine

-

50

50

6.

 

Acid/Alkyl Chlorides

-

200

200

28% HCl: (By product)

-

250

250

SO2: (By product)

-

100

100

7.

Friedel Craft - Derivatives of Acid Chloride

-

50

50

AlCl3  solution : (By product)

-

600

600

8.

Solvent Reducible Polymer

-

750

750

 

Power requirement will be met from the Madhya Gujarat Vij Company Limited (MGVCL). Present connected load is 165 KVA and additional 200 KVA load will be required for expansion. Existing 150 kVA DG set will be replaced by 500 KVA . D.G set will be used in case of emergency during power failure. Fuel Requirement will be HSD (1,200 Liters/day), LDO (1050 Liters/day) for Thermic Fluid Heaters and FO (2,510  liter/day) for boiler. Stacks height of 15m is proposed for DG set and 35m for Boiler. Process vent and vent attached to distillation unit will be further attached to central scrubbing system to reduce emission in atmosphere.

 

Total water requirement after the proposed expansion will be 156.9 m3/day. Water will be sourced from existing bore well at site. Total Effluent generation after the expansion will be 55.5 m3/day. The Unit proposes to modify its existing effluent treatment plant for primary and secondary treatment. Treated effluent will be sent to CETP for further treatment.

Solid/hazardous waste generation will be in the form of ETP Waste/ Sludge (55.0 kg/month) and  will be disposed of in the Secured Landfill facility (GEPIL). Used oil (27.1 lit/month) will be sent to authorized reprocessors. Discarded container/barrels (1367 Nos./month) and Lined paper/LDPE bags (7600 Nos./month) will be sold to scrap vendors. Filter Cloth (14 m3 /month) will be disposed at TSDF, GEPIL. Organic Residue waste (126 MT/month) will be sent for Incineration at TSDF, GEPIL.

 

The committee noted that the public hearing for the earlier expansion was carried out on 4.4.2008. Public in general welcomed the project. After detailed deliberation, the Expert Appraisal Committee (Industry) satisfied with the safety and environmental protection measures taken by the company recommended the proposal  for grant of environmental clearance under para 7(ii) EIA Notification, 2006 exempting the project from public hearing.

 

 

8.20     Proposed expansion of existing chemicals & bulk drugs unit  at  plot no.  4801/A/12, GIDC estate, Ankleshwar-393002, Gujarat  by M/s. Glindia  Chemicals reg Environmental Clearance

 

 

The project authorities and their consultant gave a detailed presentation on the salient features of the project and proposed environmental protection measures to be undertaken. The project activity is listed at serial no. 5(f) of schedule of EIA Notification, 2006 and categorized under “A” or “B” category depending upon the location of the plant outside or inside the notified industrial area. In the instant case, the plant is located within the notified industrial area, GIDC Ankleshwar and covered under category “B”. But the Ankleshwar is an identified critically polluted area, hence, as per general condition the proposal was appraised at centre

 

 

 

M/s. Glindia  Chemicals  have Proposed for expansion of existing chemicals, pharmaceutical & bulk drugs unit from capacity from 2.75 MTPM to 107.75 MTPM. The unit is located in GIDC Ankleshwar, which is identified as critically polluted area by CPCB.  No eco-sensitive areas are located within 10 km radius of the plant. The proposed expansion will be carried within the existing unit having plot area of 811 m2. Green belt will be developed in 240 m2 of the plant area. Cost of the proposed expansion project will be Rs. 40.00 lacs. Recurring cost for EMP will be Rs. 3.50 lacs/annum.

 

Details of products and their production capacities are given below:

 

Sr. No.

Product

Present capacity (Mt/Month)

 Proposed capacity  (Mt/Month)

Total

capacity  (Mt/Month)

01

Hexa Methyl Disilazone (HMDS)

0.35

50.0

50.35

02

Tri Methyl Chlorosilane (TMCS)

2.4

25.0

27.4

03

Sodium-2 Ethyl Haxonate

Nil

15.0

15.0

04

Isopropyl Alcohol.HCl

Nil

20.0

20.0

05

Methyl Alcohol.HCl

Nil

10.0

10.0

 

Total

2.75

120.0

122.75

                       

        

Power requirement of 75 HP will be met from the Gujarat Electricity Board. Fuel requirement for the boiler will be natural gas (300 m3/day) and LDO (400 lts/year) for the  DG set. 

 

Total Water required of  15 m3/d  will be sourced from the GIDC water supply. Effluent generation will be 2.5 KLD. The effluent will be treated in own ETP for primary treatment and Treated effluent will be sent to CETP for further treatment and disposal. Domestic effluent (.7 KLD) will be treated through septic tanks/ soak pits. 

Stack height of 11m is proposed for the gas fired boiler. Process emissions will be in the form of HCl & Ammonia and will be controlled by HDPE scrubbers.

Solid/Hazardous waste generation will be in the form of ETP sludge (0.8 MT/year) and will be disposed at near by TSDF site. Process residue (1.0 MT/year) will be sent to BEIL for incineration.   Used oil (60 lts/year) will be sold to MoEF authorized agency. Discarded PP bags (25.00 Kg/year) and liners/empty drums (500 nos/year) will be reused & returned back to the actual suppliers for similar use.

After detailed deliberations, the EAC (I) satisfied with the proposed pollution control measure to be undertaken recommended the proposal for grant of environmental clearance subject to stipulation of following additional specific conditions along with specific and general conditions:

 

i.                     The unit shall install own ETP and meet the industry specific discharge standards notified under Environment (Protection) Act, 1986.

 

ii.                   VOC monitoring shall be carried in the work zone and data submitted to the ministry.

 

 

iii.                  GPCB shall not permit any new discharge from new industries or expansion of existing industries in the area that lead to CETP until the said CETP meet the required standards and meet the hydraulic capacity.

 

iv.                 The company shall obtain Authorization for collection, storage and disposal of hazardous waste under the Hazardous Waste (Management and Handling) Rules, 2003 for management of Hazardous wastes and prior permission from GPCB shall be obtained for disposal of solid / hazardous waste in the TSDF. The concerned company shall undertake measures for fire fighting facilities in case of emergency.

 

Public hearing is not required as the unit is located in the notified industrial

 

 

 

8.21     Proposed expansion of synthetic organic Dyes  unit at  plot no.  640,100 Shed area, GIDC industrial estate, Vapi, Dist. Valsad , Gujarat  by M/s. Satya aromatic industries reg Environmental Clearance

 

The project authorities and their consultant gave a detailed presentation on the salient features of the project and proposed environmental protection measures to be undertaken. The project activity is listed at serial no. 5(f) of schedule of EIA Notification, 2006 and categorized under “A” or “B” category depending upon the location of the plant outside or inside the notified industrial area. In the instant case the plant is located within the notified industrial area, GIDC Vapi and covered under category “B”. But the Vapi is an identified critically polluted area, hence, as per the general condition the proposal was appraised at centre. 

 

 

M/s. Satya aromatic industries have proposed for expansion of synthetic organic Dyes  unit at  plot no.  640,100 Shed area, GIDC industrial estate, Dist. Valsad , Gujarat The unit is located in GIDC Vapi which is identified as critically polluted area by CPCB. No eco-sensitive areas are located within 10 km radius of the plant. River Damanganga flows at a  the distance of 3.5 kms from the proposed plant.  The proposed expansion will be  carried within the existing unit having plot area of  853.48 m2. Green belt will be developed in 100 m2 of plant area. Cost of the project will be Rs. 49.55 lacs. An amount of Rs. 7.0 lacs will be spent on Environment Management System.

 

Details of  products and their production capacities are given below:

 

S. No.

Product

Existing

Quantity

(TPM)

Total

After

Expansion

1.

Brown Base Crude

0.5

 

 

 

 

 

 

 

    15.0 TPM

2.

Crysodine Y crude

0.5

3.

Crysodine Y Base Crude

0.2

4.

Acid Scarlet 3R Crude

0

5.

Acid Fast Red A Crude

0

6.

Acid Crystal Orange Crude

0

7.

Acid Crude

0

8.

Acid Tartrazine Crude

0

9.

Acid Black 10 BX Crude

0

10.

Acid Violet 4 BS Crude

0

11.

Acid Violet 5 BN Crude

0

12.

Acid Blue FF Crude

0

13.

Brown G Crude

0

14.

Direct SE Crude

0

15.

Direct Red 12B Crude

0

16.

Direct Scarlet 4 BS Crude

0

 

 

Total

1.2

15.0

 

The raw material used will be CPC Blue Crude (102.08 MTPM), Sodium Hydroxide (6.66 MTPM) and Butyl Alcohol Fresh (1.45 MTPM)

 

Power requirement for the proposed expansion will be 45 KW which will be sourced from the DGVCL. DG set of 45 KVA for stand by power supply.  Fuel requirement will be, wood (115 kgs/hr.) and natural gas (150 m3/hr.) for spray drier, LDO (50 lts/hr.) or natural gas (70 m3/hr.) for the boiler. HSD (5 lt/hr.) will be used for DG set.

Total water requirement after the proposed expansion will be 18.55 m3/day and will be sourced from the  GIDC water supply.  Waste water generation will be 16.044 m3/d. Unit proposes to modify its own existing effluent treatment plant for primary, secondary and tertiary treatment. Treated effluent will be sent to CETP for further treatment. Domestic effluent will be treated through septic tanks/ soak pits. 

There will be no process gas emission from the proposed unit. No solvents will be used. Stack height of 11m is proposed for the boiler and DG set. Spray drier has built in wet scrubber.

Solid /Hazardous waste generation will be in the form of ETP waste (2 MTPA) and Process waste (60 MTPA.)  and will be disposed of in the TSDF, Vapi for final disposal.  Discarded containers (800 Nos/yr.) will be sold to authorized recyclers. Spent oil/used oil (12 kgs/year) will be sold to registered re-refiner.

After detailed deliberations, the EAC (I) recommended the proposal for grant of environmental clearance subject to stipulation of following additional specific conditions along with specific and general conditions:

 

i.                     The unit shall install own ETP and meet the industry specific discharge standards notified under Environment (Protection) Act, 1986.

 

ii.                   GPCB shall not permit any new discharge from new industries or expansion of existing industries in the area that lead to CETP until the said CETP meet the required standards and meet the hydraulic capacity.

 

iii.                  The company shall obtain Authorization for collection, storage and disposal of hazardous waste under the Hazardous Waste (Management and Handling) Rules, 2003 for management of Hazardous wastes and prior permission from GPCB shall be obtained for disposal of solid / hazardous waste in the TSDF. The concerned company shall undertake measures for fire fighting facilities in case of emergency.

 

 

Public hearing is not required as the unit is located in the notified industrial

 

 

8.22     Proposed expansion of pesticide manufacturing unit at  village: Chharodi, Taluka- Sanand, Dist. Ahemdabad, Gujarat by M/s Meghmani industries Limited-TOR

 

The project authorities and their consultant gave a detailed presentation on the salient features of the project and proposed environmental protection measures to be undertaken. The project activity is listed at serial no. 5(b) of schedule of EIA Notification, 2006 and  is  ‘A’ category project and   appraised at the centre.  

 

 

M/s Meghmani industries Limited have proposed to expand its existing pesticide manufacturing unit capacity from 2748 MTPA to 5561 MTPA at  village: Chharodi, Taluka- Sanand, Dist. Ahemdabad, Gujarat. No protected forests/eco-sensitive areas are located within 10 km radius from the proposed unit. Proposed expansion will be carried  within the existing unit having plot area of 50000 m2. The cost of the proposed expansion is Rs. 5.00 Crores.

 

Details of Products and their production capacities are given below:

 

s.no

 

Produc          Product

Existing

(MTPA)

Proposed

(MTPA)

Total

(MTPA)

01

Atrazine Technical

300

-

300

02

OPDA

480

-

480

03

ONA

300

-

300

04

Pendimethalin Technical

-

480

480

05

Hexaconazole Technical

-

60

60

06

Tebuconazole Technical

-

15

15

07

Propiconazole Technical

-

90

90

08

Thiophanate Methyl Technical

-

48

48

09

Tricyclazole Technical

-

48

48

10

Terbutryne Technical

-

144

144

11

Ametryne Technical

-

72

72

 

Total

1080

957

2037

 

Formulation Products

 

 

 

01

Atrazine 50% WP

128.4

231.6

360

02

Tricyclazole 75% WP

15.6

104.4

120

03

Carbendazim 50% WP

300

-

300

04

Sulfur 80% WDG

720

900

1620

05

Hexaconazole 5% EC

216

-

216

06

Hexaconazole 5% SC

-

200

200

07

Pendimethalin 30% EC

264

-

264

08

Propiconazole 25% EC

24

-

24

09

Propanil 36% EC

-

120

120

10

Glyphosate 41% SL

-

240

240

11

Thiophanate Methyl 70% WP

-

60

60

 

Total

1668

1856

3524

 

 

The total power requirement for the proposed expansion will be 500 HP, which will be sourced from the Meghmani Energy Ltd. Two DG sets of 250 KVA will be used for stand–by power supply.

 

The total water requirement after the proposed expansion will be 51 m3/day and which will be sourced from the bore well. The process effluent (25 m3/d) will be collected in collection tanks and incinerated. Domestic effluent will be disposed through Soak pit/Septic tanks.

 

Process emissions will be in the form of NH3, NOx and sodium methyl mercaptant. To control process emissions, water scrubber, alkali scrubber and urea Scrubber are proposed. Alkali Scrubber is proposed for incinerator. Stack height of 33 mts is proposed for the boiler and incinerator.

 

Sludge from ETP/Incinerator ash (2.5 MT/month) will be sent to secured Land Fill site approved by GPCB. Discarded drums (300 Nos./month), liners (3.0 MT/month) and used lubricating oil (1.0 Kl/year) will be reused or sold to registered recyclers.

 

The Committee suggested the following TORs for the preparation of EIA/EMP Report for the project:

A. Project Description

·         Executive summery of the project

·         Compliance status to the conditions stipulated while according environmental clearance to the existing project/NOC granted.

·         A filled in Questionnaire on the Industry sector as devised earlier

·         Justification of the project.

·         Promoters and their back ground

·         Project site location along with site map of 7 km area and site details providing    various industries, surface water bodies, forests etc.

·         Project cost

·         Regulatory framework

·         Project location and Plant layout.

·         Existing infrastructure facilities including power sources.

·         Existing environmental scenario, stack emission data

·         Total cost of the project along with cost for environment protection measures.

·         Water source and utilization including existing and proposed water balance.

·         Product spectrum (Existing and proposed products along with production Capacity) and processes

·         List of hazardous chemicals with their toxicity levels.

·         Storage and Transportation of raw materials and products.

·         Mass balance of each product along with the batch size

·         Pollution potential from the proposed products

·         Detailed scheme for waste water treatment along with characteristics of inlet and outlet waste water. The treatment scheme to meet discharge norms of GPCB. Final discharge point. 

B. Description of the Environment and Baseline Data Collection

·         Demarcation of Impact boundary (10 km from the project site)

·         Micrometeorological data for wind speed, direction, temperature, humidity and rainfall in 10 km area.

·         Study of Data from secondary sources.

·         Topography, drainage and soil characteristics. Local area hydrology, storm water drainage etc.

·         Details of the water source available in the impact area (Depth of ground water table, data from the available secondary sources)

·         Other industries in the impact area

·         Prevailing environment quality standards

·         Existing environmental status vis a vis air, water, noise, soil in 10 km area from the project site for SPM, RSPM, SO2, NOx, NH3 and VOC

·         Periodic monitoring of vents from condensers in the existing plant.

C.        Socio Economic Data

Existing socio-economic status, land use pattern and infrastructure facilities available in the study area were surveyed.

D. Impacts Identification and Mitigatory Measures

·         Identification of impacting activities from the proposed project during construction and operational phase.

·         Impact on air (Organic and inorganic pollutants) and mitigation measures including green belt

·         Impact on water environment and mitigation measures (Details of ETP design will be in EMP). Location of final disposal and downstream usages of disposal point.

·         Soil pollution source and mitigation measures

·         Noise generation and control.

·         Ground water abstraction and its impact on water sources.

·         Solid waste quantification and disposal.

·         Control of fugitive emissions

E. Environmental Management Plan

§         Details of pollution control measures

§         Environment management team

§         Proposed schedule for environmental monitoring including post project monitoring for Air, Water, Soil and Noise.

§         Chillers should be provided for chilled brine circulation to condensate the solvent vapors and reduce solvent losses.

§         Solvent recovery plant should be installed to recover the solvents and solvents generated from the vents and in the work zone environment should be monitored

§         Solvent should be stripped from the effluent before discharging into the evaporation pond for their maximum recovery.

§         Industry should treat the effluent and treated effluent shall comply with the industry specific standards.

F. Risk Assessment

·         Objectives, Philosophy and methodology of risk assessment

·         Details of manufacturing process of proposed products

·         Details on storage facilities

·         Process safety, transportation, fire fighting systems, safety features and emergency capabilities to be adopted.

·         Identification of hazards

·         Compatibility studies and special hazards

·         Consequence analysis through occurrence & evaluation of incidents

·         Selection of incidents and consequence calculations

·         Recommendations on the basis of risk assessment done

·         Disaster Management Plan.

·         Safety precautions for the storage of Chemicals and vapour condensation.

·         Safety precaution for handling and transportation of Bromine.

 

G.  Occupational Health and Safety Program for the Project.

 

H. Information on Rain Water Harvesting

 

I. Green Belt Development plan

 

J. Public Hearing

 

Action plan in the tabular form to the issues/suggestions made during the public hearing along with the implementation plan and allocation of funds.

 

It was decided that the proponent shall prepare EIA/EMP/Risk Assessment Report based on the above TORs and submit the same to the concerned SPCB for conducting Public Consultation. The EIA/EMP Report should be as per the generic structure given in Appendix-III of EIA Notification, 2006. The concerns emerged during the Public Consultation may be incorporated in the EIA/EMP Report and the final EIA/EMP may be submitted to the Ministry for obtaining   environmental clearance.

 

 

8.23     Proposed expansion of chemical unit in  existing  unit  at  plot no. B-1/1/2/3,  GIDC estate, phase II, opp. Dipak oil mill, Naroda, Ahemdabad- 382330, Gujarat  by M/s. Industrial chemical works -EC/ TOR

 

 

The proponent did not attend the meeting. It was decided that proposal will be considered as and when requested by the proponent.

 

8.24     Expansion of existing bulk drugs and drug intermediates unit  by M/s Aventis Pharma Limited at Plot Nos. 3501, 3503-15, 6310B-14, GIDC Ankleshwar in district Bharuch in Gujarat- TOR/EC

 

The project authorities and their consultant gave a detailed presentation on the salient features of the project and proposed environmental protection measures to be undertaken alongwith the proposed Term of References for the preparation of EIA/EMP. The synthetic organic chemical manufacturing units are listed at S.N. 5(f) in Category ‘A’ & ‘B’ of EIA Notification, 2006 depending upon the location in/outside the notified industrial area.  The instant unit is located inside the GIDC notified industrial area and as such fall under Category ‘B’ but due to location within the critically polluted area Ankleshwar  hence as per General Condition of Schedule of EIA Notification 2006, the proposal has been appraised at the centre.

 

M/s Aventis Pharma Limited proposes for expansion of existing bulk drugs and drug intermediates manufacturing at Plot Nos. 3501, 3503-15, 6310B-14, GIDC Ankleshwar in district Bharuch in Gujarat. Total land of the plant is 5.7 Ha out of this 1.3479 ha is earmarked for the green belt development.Details of the existing and proposed products are as given below:

 

Sl. No

Name of product
(Bulk-Drugs & Intermediates)

-

Existing

Capacity

 (TPA)

Proposed

Capacity

(TPA)

Total Capacity (TPA)

1.       

Pentoxifylline

Bulk drug

44

206

250

2.       

Phenaramine Maleate

Bulk drug

72

38

100

3.       

Frusemide

Bulk drug

60

80

140

4.       

Ciclopiroxlamine

Bulk drug

0.167

-0.167

0

5.       

Glibenclamide

Bulk drug

11

14

25

6.       

Ramipril Substance

Bulk drug

0.3

-0.3

0

7.       

Tonophosphan

Bulk drug

1

-1

0

8.       

Articaine HCl

Bulk drug

22

8

30

9.       

ACME (RP II 3)

Intermediate

28

7

35

10.   

Phenoxypiretan

Intermediate

2

8

10

11.   

Hydrochlorothiazide

Bulk drug

5

35

40

12.   

Ketoprofen

Bulk drug

2

13

15

13.   

ABAP

Intermediate

5

75

80

14.   

Acebutolol

Bulk drug

0

25

25

15.   

Buprenorphine HCl

Bulk drug

0

0.5

0.5

16.   

TDPA

Intermediate

0

40

40

17.   

TOTAL (Ton per annum)

Bulk drug & intermediate

252

538

791

18.   

Pharma Formulations (Solid) mio tablets/annum

 

5577

0

5577

 

The company have proposed for change in product mix for future details are as given below: 

Sl.

No.

Name of product
(Bulk-Drugs & Intermediates)


Proposed

Capacity

TPA

2008

2009

2010

2011

2012

2013

1.       

Pentoxifylline

250

44

44

100

150

200

250

2.       

Phenaramine Maleate

100

72

72

85

100

100

100

3.       

Frusemide

140

60

60

100

140

140

140

4.       

Ciclopiroxlamine

0

0

0

0

0

0

0

5.       

Glibenclamide

25

11

11

15

20

25

25

6.       

Ramipril Substance

0

0

0

0

0

0

0

7.       

Tonophosphan

0

0

0

0

0

0

0

8.       

Articaine

30

22

22

25

30

30

30

9.       

ACME (RP II 3)

35

28

28

30

30

35

35

10.   

Phenoxypiretan

10

2

2

4

6

8

10

11.   

Hydrochlorothiazide

40

5

5

15

30

40

40

12.   

Ketoprofen

15

2

2

2

5

10

15

13.   

ABAP

80

5

5

10

10

50

80

14.   

Acebutolol

25

0

0

5

10

20

25

15.   

Buprenorphine

0.5

0

0

0

0.2

0.4

0.5

16.   

TDPA

40

0

0

0

10

20

40

17.   

TOTAL (Ton per annum)

791

251

251

391

541

678

791

18.   

Pharma

Formulation(Solid)

mio tablets/annum

5577

5577

5577

5577

5577

5577

5577

 

The water requirement will be increased from 400 KLD to 800 KLD and will be met from the GIDC water supply. PAs have bore well for additional water supply. The waste water generation will increase from 260 KLD to 560 KLD. The wastewater will be treated in the ETP and treated effluent will be sent to ETL and finally to BAIL for treatment and disposal in sea. The Committee asked the project authorities that they have to comply with the industry specific discharge norms since the CETP/FETP Ankleshwar is not working satisfactorily. The PAs agreed to comply with the industry specific discharge standards. Natural Gas will be used for steam generation, which will be supplied by GGCL. Furnace oil provision has been made in case of short supply of Natural Gas. Power supply will be from State Electricity Board. No air pollution is envisaged from the plant. HSD (630 Ltr) will be used for back-up power generation. Ambient air quality monitoring was carried out the resuls indicated the SPM (136 to 257 mg/m3), RSPM ( 51 to 96 mg/m3), NOx (14 to 32 mg/m3), SO2 (29 to 61 mg/m3), HCl (7 to 17 mg/m3) and NH3 (Below Detectable Level). The air quality was found within prescribed limits.

 

The company has the memberships of BEAIL (Bharch Eco-Aqua Infrastructure Limited) for Polishing plant & conveyance of effluent to deep sea; ETL (Enviro Technology Limited) for treatment of effluent; BEIL (Bharuch Enviro Infrastructure Limited) for Secured land filling & Incineration of Hazardous waste; DPMC (Disaster Prevention & Management Centre) for emergency mitigation and GEPIL (Gujarat Enviro Protection & Infrastructure Limited) for Secured land filling & Incineration of Hazardous waste

 

The hazardous wastes (spent solvent) will increase from 50 T/year - 2400 T/year which will be given to distillation agency for further usage and in second priority for incineration. Other hazardous wastes will be given to Authorized TSDF (BEIL) either for secured land filling or for incineration.

 

After detailed deliberations, the EAC (I) satisfied with the environmental protection measures proposed by the project authorities and recommended the proposal for grant of environmental clearance dispensing with public hearing and EIA/EMP as per para 7(ii) of the EIA Notification, 2006 subject to the following specific conditions along with other specific and general conditions:

 

1.      The company shall install full-fledged ETP to treat the wastewater as per the industry specific discharge norms specified in EPA or stipulated by the GPCB.

2.      The company shall install solvent recovery system for control of fugitive emissions.

 

 

8.25     Proposed expansion  of pigments/dye intermediates manufacturing unit at Plot no.780/1 & 2, 40 shed area, GIDC Vapi, District Valsad, in Gujarat by M/s Hemani Intermediates  Private Limited  -ENVIRONMENTAL CLEARANCE .

 

M/s Hemani Intermediates  Private Limited  have Proposed for expansion  of pigments/dye intermediates manufacturing unit at GIDC Vapi, in District Valsad, in Gujarat. The expansion will be carried out in the existing plant. No additional land is required. The unit is located in GIDC Vapi. Cost of the project will be Rs 2.00 crores.

 

Details of products and their production capacity are given below:

 

Sr. No.

Product

Present capacity (Mt/Month)

 Proposed capacity  (Mt/Month)

Total

capacity  (Mt/Month)

01

3,3 Dichlorobenzidine-

HCl

203

797

1000

02

Quinine Sulphate

5

-

5.0

03

Artesunate

.8

-

0.8

04

Arteether

0.5

-

0.5

05

Artemether

0.5

-

0.5

06

Liquid/solid Alum

-

1000

1000

                       

Fuel used for the boiler will be Bark/Coal (5 MT/day). 2 DG sets of capacity 380 KVA  each . fuel for DG set will be 80 lts/hr.

 

Total water requirement of 949.76 m3/d   will be sourced from the GIDC water supply.

The wastewater generation will be 457.6 m3/d. The effluent will be treated in effluent treatment plant and treated effluent after primary, secondary and tertiary treatment will be sent to GIDC drain. Domestic effluent will be treated through septic tanks/ soak pits.

To control the particulate emissions, multi cyclone dust collector & bag filters are proposed for the coal fired boiler and stack height of 11m for DG set and 20m for boiler for dispersion of gaseous emissions.

The hazardous waste generation will be the ETP Sludge (145.15 MT/month) and will be disposed to Ambuja cement Kodinar or TSDF site, Vapi. Process waste (60 MT/month) will be disposed to TSDF site, Vapi. Used oil (152 lt/year) will be reused for lubricating purpose. Discarded material (1020 nos/month) will be decontaminated and sold to actual users. Boiler ash (32 MT/month) will be given to brick manufacturers. Activated carbon (0.1 MT/month) will be disposed to TSDF site, Vapi

After detailed deliberations, the EAC (I) recommended the proposal for grant of environmental clearance subject to stipulation of following additional specific conditions along with specific and general conditions:

 

i.                     The unit shall install own ETP and meet the industry specific discharge standards notified under Environment (Protection) Act, 1986.

 

ii.                   GPCB shall not permit any new discharge from new industries or expansion of existing industries in the area that lead to CETP until the said CETP meet the required standards and meet the hydraulic capacity.

 

iii.                  The company shall obtain Authorization for collection, storage and disposal of hazardous waste under the Hazardous Waste (Management and Handling) Rules, 2003 for management of Hazardous wastes and prior permission from GPCB shall be obtained for disposal of solid / hazardous waste in the TSDF. The concerned company shall undertake measures for fire fighting facilities in case of emergency.

 

Public hearing is not required as the unit is located in the notified industrial

 

 

8.26     Proposed  expansion of specialty chemical manufacturing unit at plot no. 427/1-2, 429, 430 in GIDC Ankleshwar , Gujarat by M/s Navdeep Chemicals Pvt Limited –Environmental Clearance.

 

The project authorities and their consultant gave a detailed presentation on the salient features of the project and proposed environmental protection measures to be undertaken. The project activity is listed at serial no. 5(f) of schedule of EIA Notification, 2006 and categorized under “A” or “B” category depending upon the location of the plant outside or inside the notified industrial area. In the instant case the plant is located within the notified industrial area, GIDC Ankleshwar and covered under category “B”. But the Ankleshwar is an identified critically polluted area, hence, as per general condition the proposal was appraised at centre

 

M/s Navdeep Chemicals  Private Limited have proposed for expansion of capacity from 240 MT to 1686 MT/month for Speciality Chemicals manufacturing unit at  GIDC Estate Ankleshwar in Dist. Bharuch in Gujarat The unit will be located in the notified industrial   area, GIDC Ankleshwar. As per CPCB, Ankleshwar has been identified as critically polluted area. No protected forests/eco-sensitive areas are located within 10 km radius of the proposed unit. The proposed expansion will be carred within the  existing unit having land area  of 8333 m2. Green belt will be developed in 700 m2 of plant  area. The cost of the existing project is Rs.7.94 crores.

 

s.no

Product

Existing capacity

(MTPM)

Proposed

capacity

(MTPM)

Total

capacity

(MTPM)

1. Textile Chemicals

a.

Cross Linking Agents

(Polymaleate-Resin)

nil

15.00

15.00

b.

Navdeelose-T/Navdeetext-01

nil

5.00

5.00

c.

DMEU (Navdeep EU-1)

nil

5.00

5.00

d.

Sandupress-2

nil

10.00

10.00

e.

Softner

 

 

 

 

(i) Nevamine S/CTK 100

nil

5.00

5.00

 

(ii)Indsoft 170

nil

1.00

1.00

 

(iii)Nevamine S/CTSK 75

nil

5.00

5.00

f.

Flame Retard (Semalfon SDU)

nil

5.00

5.00

g

Navdeefix

nil

5.00

5.00

2.   Alkyl Aryl Sulphonic Acid & Its Derivatives

a.

(1) P.T.S. Acid Monohydrate & its various grade

 

 

 

 

 

 

200

 

 

 

 

 

 

700

 

 

 

 

 

 

900

 

(2) P.T.S. Acid Monohydrate & its conc. Solution

 

(i) PTSA-52 Grade

 

(ii) PTSA-58 Grade

 

(iii) PTSA-70 HS Grade

 

(iv) PTSA-65 Grade

 

(v) PTSA-  70% AN

 

(vi) PTSA-70 Grade

 

(vii) PTSA-75 Grade

 

(viii) PTSA-65 Grade

 

(ix)Navdeeptrope TL/TS

b

Xylene Sulphonic Acid/XSA-701

nil

100

100

c

Navcusol-40

nil

100

100

d

Navcusol-90

nil

30

30

e

Navdeeptrope XL/XS

nil

10

10

f

Methyl Ester or PTSA

nil

20

20

g

Phenol Sulphonic Acid

nil

50

50

3. Biocides

a

Navdeepol 87/97

 

 

 

 

 

 

nil

 

 

 

 

 

 

110

 

 

 

 

 

 

110

b

Navdeepol L/L1

c

Navdeepol 25 G

d

Navdeecide AL5014

e

Navdeecide 91

f

Navdeesan 164

g

Navdeepol SL

h

Navdeecide AM-5014

I

Navdeepol-35TKP

J

Navdeecide-B-1100

k

Navdeecide-B-8515

4.

DMI (1-3dimethyl-1,2-imidazolidinone)

nil

25

25

5

Aklyl Sulphonic Acid (MSA)

nil

40

40

6

Methyl Sulphonyl Methane (MSM)

nil

20

20

7

Ethylene Glycol Diacetate (EGD)

nil

20

20

8

Glysrol Triacetate (Triacitine)

nil

20

20

9

Scale Inhibitors

 

nil

 

20

 

20

 

(i)Navdeescale 12 M

 

(ii)Navdeescale 11

 

(iii)Navdeescale CTW

10

Oil Field Chemicals

 

 

nil

 

 

100

 

 

100

 

(i)Navdemulsifier

 

(ii)Navdeoiler

 

(iii)Navdeewax

 

(iv)Acid demulsifier

11

(i)Navdegreaser

nil

12.5

12.5

 

(ii)Navdeecleaner C-1

nil

12.5

12.5

 

Sodium Formate (by product)

nil

8

8

 

The power requirement of 225 KVA will be met through Dakshin Gujarat Vij. Company Limited (DGVCL). 250 KVA DG set will be installed for stand by power requirement. 

 

Water requirement of 39.8 m3/day  will be met from GIDC water supply.The effluent generation will be 4.1 m3/day which will be treated in own effluent treatment plant  and treated effluent will be sent to CETP managed by Enviro Technology Limited, Ankleshwar for further treatment and or will provide sychometric evaporation system to achieve Zero discharge. Domestic effluent will be disposed of through septic tank/soak pit.

 

Stack height of 12m is proposed for the thermic fluid heater. Alkali Scrubber is proposed to control process emissions in the form of HBr.

 

The solid/ hazardous waste generated in the form of spent activated carbon (3.14 MT/annum) and organic waste (20.04 MT/annum) will be sent for incineration at BEIL, Ankleshwar. Inorganic process waste (NaCl) (4.53 MT/annum) will be sent for to TSDF at BEIL, Ankleshwar. Discarded material and used oil will be reused or sold to authorized dealers.

 

After detailed deliberations, the EAC (I) satisfied with the proposed pollution control measures to be undertaken recommended the proposal for grant of environmental clearance subject to stipulation of following additional specific conditions along with specific and general conditions:

 

i.                     The unit shall install own ETP and meet the industry specific discharge standards notified under Environment (Protection) Act, 1986.

 

 

ii.                   GPCB shall not permit any new discharge from new industries or expansion of existing industries in the area that lead to CETP until the said CETP meet the required standards and meet the hydraulic capacity.

 

iii.                  The company shall obtain Authorization for collection, storage and disposal of hazardous waste under the Hazardous Waste (Management and Handling) Rules, 2003 for management of Hazardous wastes and prior permission from GPCB shall be obtained for disposal of solid / hazardous waste in the TSDF. The concerned company shall undertake measures for fire fighting facilities in case of emergency.

 

Public hearing is not required as the unit is located in the notified industrial.

 

 

8.27        Expansion of Bulk Drug Unit and Captive Power Plant (4.8 MW) at village Sundhara, P.O. Mubarakpur, Tehsil Derabassi, District Mohali, Punjab by M/s Parabolic Drugs Limited- (EC)

 

The above proposal was considered in 77th meeting of the Expert Appraisal Committee (Industry) held during 21-24 January,2008 to prescribe the Terms of Reference.  The project falls in the notified Free Enterprises Zone of Govt. of Punjab and hence was exempted from the process of Public hearing / consultation. The EIA report prepared was submitted to the Ministry for obtaining environmental clearance. 

 

             M/s Parabolic Drugs Ltd. have proposed for expansion of Bulk Drug Unit and Captive Power Plant (4.8 MW) at Village Sundhara, P.O.  Mubarakpur, Tehsil Derabassi, in District Mohali in Punjab. Total project area is 17 acres and no additional land will be required for the expansion project.  Green belt will be developed in 33 % of plant area. Total cost of the project is Rs. 45.00 Crores.  

 

 

Details of the products along with the production capacity are given below.

 

 

S.NO

PRODUCT

KG/DAY

KG/DAY

KG/DAY

KGPM

 

 

NEW

EXISTING

TOTAL

TOTAL

  1. 1

Cefepime Hydrochloride

30

0.00

30.00

750

  1.  

Cefpirome sulphate

20

0.00

20.00

400

  1. 2

Cefpodoxime  proxetil

100

0.00

100.00

2500

  1.  

Cefditoren pivoxil

54

0.00

54.00

540

  1.  

Cefprozil

20

0.00

20.00

520

  1. 3

Cefotaxime Acid

150

0.00

150.00

3750

  1.  

Ceftriaxone sodium

100

0.00

100.00

2500

  1.  

Ceftadizime pentahydrate

24.00

0.00

24.00

200

  1.  

Ceftiofur

10.00

0.00

10.00

100

  1.  

Cefonicid

10.00

0.00

10.00

100

  1. 4

Cefuroxime Axetil Crystaline

440

0.00

440.00

11000

  1.  

Cefuroxime Axetil Amorphous

127

0.00

126.67

3167

  1.  

Cefuroxime Acid for steriles

120

0.00

120.00

3000

  1. 5

Cefixime

80

0.00

80.00

2000

  1.  

cefdinir

10

0.00

10.00

100

  1. 6

Ampicillin Sodium

50

51.28

101.28

2600

  1.  

Amoxycillin Sodium

110

50.84

160.84

2750

  1.  

Cloxacillin Sodium

10

50.00

60.00

1500

  1.  

Amoxy/clav(sterile)

5

0.00

5.00

125

  1.  

Oxacillin sodium(sterile)

8.0

0.00

8.00

200

  1.  

Flucloxacillin sodium(sterile)

20

0.00

20.00

417

  1.  

salbactum Sodium

50

0.00

50.00

600

  1. 7

Ceftriaxone Disodium

0

100.00

100.00

2500

  1.  

Cefotaxime Sodium

0

150.00

150.00

3750

  1.  

Cefepime HCL(sterile)

20

0.00

20.00

440

  1.  

Cefuroxime sodium(sterile)

32

0.00

32.00

800

  1. 8

Ampicillin Trihydrate

663

23.00

686.00

16575

  1.  

Amoxycillin Trihydrate

1000

100.00

1100.00

27500

  1.  

Cloxacillin Sodium

840

40.00

880.00

21000

  1.  

Dicloxacillin sodium

400

0.00

400.00

10000

  1.  

Flucloxacillin sodium

90

0.00

90.00

2200

  1.  

Oxacillin sodium

8

0.00

8.00

200

 

 

            Total water requirement of 705 m3/day will be met from the existing  bore wells. ‘Permission’ for  drawl of ground water  has been obtained from CGWA. About 120 m3/day of effluent will be generated.  The effluent will be nutralized in the equilazation tank and flocculants will added by taking the effluent to the flash mixture. To separate the sludge the effluent will be taken to settler. The clarified effluent will be taken to ORG scrubber where steam will be passed through for effluent for separation of solvents. The separated sludge in the tube settler will be incinerated. The effluent will be evaporated in the multiple effect evaporator. The residue from the evaporator will beincinerated and condensate will be taken for two stage aerobic treatment where domestic effluent would also be mixed at the inlet of the first stage aeration tank. The entire water after treatment shall be used as cooling water makeup (87 m3/d) and for green belt development (30 m3/d).

 

The process emissions will be scrubbed and the scrubber effluent would be sent to equalization tank for treatment. The industry already has 2 x 380 KVA, 1 x 210 KVA and 1 x 500 KVA D.G. Sets. New 4 D.G. Sets of 500 KVA each are proposed for the expansion. To disperse the gaseous emissions, adequate stack height for boiler and D.G. Sets will be provided. Two new rice husk fired boilers of 30 TPH and 6 TPH steam capacity are proposed.  Out of the two boilers, one will be required for Captive power plant and other for steam generation. One 4.8 MW co-generation (Extraction/Condensing) Steam Turbine will be provided for 30 TPH boiler to meet power and steam (extraction) requirement of expansion project. To control the particulate emissions, CPP boiler will be provided with ESPs and 6 TPH boiler with multi-cyclones.

 

            Solid waste including sewage sludge (2.462 TPD) will be incinerated in 2-stage incinerator.  Ash (20 kg / day) will be stored in hazardous waste storage area.

 

         The committee after deliberation decided to defer the project and sought the following information.

 

1.      Design details of incinerator.

2.      Data on monitoring of solvents in the work zone.

3.      Chemical analysis of the rejects.

4.      Monthly consumption of raw material.

 

         The Committee also decided that the Representative of the Ministry or Regional Office of the Ministry at Chandigarh may inspect the unit for performance of incinerator and submit the report to the Ministry. On receipt of information, the proposal will be reconsidered without inviting the project proponent.

          

8.28     Proposed 60 KLPD Distillery Unit at District Ariyalur Tamilnadu by M/s Kothari Sugars and Chemicals Limited. ? (Addl.TOR)

 

The proponent informed that they will not be able to attend the meeting.

 

 

8.29     120 KLPD Molasses Based Distillery unit in Thanjavar Taluk & District Tamilnadu  by M/s King India Chemicals Corporation   Limited ? (TOR)

 

Project authorities didn’t attend the meeting and it was decided that proposal should be considered afresh whenever requested by the proponent.

 

 

8.30        Grain Based 30 KLPD Distillery unit at village Gourgaon, Tehsil Kalamb in District Osmanabad Maharashtra by M/s Adlers Bio-Energy  Limited – (EC)

 

M/s. Adlers Bio-Energy Ltd., has submitted a proposal to set up a grain based 30 KLPD distillery unit at village Gourgaon, Tehsil Kalamb in District Osmanabad in Maharashtra. Out of total area of 42 ha. 20 acres is earmarked for green belt development.  No Wild life Sanctuary/National Park/biosphere reserve etc. is located within 10 km radius of the project. No forest land and R&R is involved.  The distillery will adopt batch fermentation technology considering sufficient availability of grains. The distillery will  operate for 300 days.   Other co-products to be generated are DWGS (Distillers Wet Grains with Solubles) and fusel oil. Kolegaon minor irrigation tank is located at a  distance of 3 km in the South-East from the proposed site.   Total cost of the project is Rs. 18.50 Crores of which Rs. 0.09 Crores have been earmarked towards environmental protection measures.     

The committee noted that the public hearing of the project was held in on 24th August, 2006 based on the EIA Report as per EIA Notification, 1994. The proponent explained that due to financial constraint they could not approach the Ministry for obtaining environmental clearance. The Committee decided that the proponent should follow procedure as per EIA Notification, 2006 for obtaining environmental clearance.

 

The Committee prescribed the following TORs for undertaking detailed EIA study:

 

1.      Executive summary of the project.

2.      Detailed break up of the  project cost.

3.      Present land use based on satellite imagery.

4.      Details of site and information related to environmental setting within 10 km radius of the project site.

5.      Information regarding eco-sensitive area such as national park / wildlife sanctuary / biosphere reserves within 10 km radius of project area.

6.      Source of raw material.

7.      Ambient Air Quality Monitoring for three months except monsoon.

8.      Mathematical modeling for calculating the dispersion of air pollutants and ground level concentration along with emissions from the baggase    fired boiler.

9.      Details of the use of steam from the boiler

10.  Hydrology of the area especially down stream.

11.  Ground water quality around the unit  and spent wash storage lagoon. Detailed water balance indicating the input and output along with measures for water conservation. 

12.  Noise levels monitoring at five locations within the study area.

13.  List of flora and fauna in the study area.

14.  Number of working days of the distillery unit.

15.  Details of the spent wash treatment.

16.  Proposed effluent treatment system and scheme for achieving zero discharge.

17.  Treatment system and scheme for achieving zero discharge. Water drawl permission from the Irrigation Department/State Ground Water Board.

18.  Source of raw material

19.  Details of solid waste management including management of boiler ash.

20.  Green belt development as per the CPCB guidelines.

21.  Environment Management Plan.

22.  Rainwater harvesting measures

23.  Details of occupational health surveillance programme.

24.  Details of socio economic welfare activities.

25.  Post project environmental monitoring.

26.  Water drawls permission from the Irrigation Department/State Ground Water Board.

27.   Action plan in the tabular form to the issues/suggestions made during the public hearing along with the implementation plan and allocation of funds.

 

The Committee decided that after preparing the draft EIA/EMP covering the above mentioned issues, the proponent shall submit the EIA/EMP Report to the State Pollution Control Board for Public hearing. The issues raised during the public hearing along with the response shall be incorporated in the EIA/EMP report. The final report shall be submitted to the Ministry for obtaining environmental clearance .

 

 

8.31     Proposed Expansion of existing  sugar mill capacity from 7500 TCD to 10000 TCD and expansion of Bagasse based Co-generation power from 8 MW to 57 MW/hr. at Dist: Haridwar , Uttarakhand by M/s Rai Bahadur Narain Singh sugar mills Ltd. reg EC/ TOR

 

 

 

Project authorities didn’t attend the meeting and it was decided that proposal should be considered afresh whenever requested by the proponent.

 

 

8.32     Proposed expansion of distillery unit from 30 KLPD to 60 KLPD at PO: Kisanveer nagar, Tal Wai, Dist. Satara, Maharashtra 415530 by M/s  Kisan veer Satara Sah. Sakhar Karkhana Ltd –Environmental Clarance

 

 

The project authorities and their consultant gave a detailed presentation on the salient features of the project and proposed environmental protection measures to be undertaken. The project activity is listed at serial no. 5(g) of schedule of EIA Notification, 2006 and categorized under “A” Category and was appraised at central level.  

    

M/s Kisan veer Satara Sahakari Sakhar Karkhana Ltd. have proposed for expansion of Molasses based Distillery Unit from 30 KLPD to 60 KLPD to manufacture Rectified Spirit in Dist. Satara, in Maharashtra. No protected forests/eco-sensitive areas are located with in 10 Km. radius from the unit. The total cost of the project will be Rs. 12.00 crores. The proposed expansion will be carried within the existing unit. The distillery is attached to sugar unit of Crushing capacity of 806240 MTPA. The unit will operate for 270 days. 

 

The main raw materials will be Molasses (240 MT/d), Super phosphate (0.028 MT/d), Sulfuric Acid (0.1 MT/d) and Turkey Red Oil (TRO) (0.12 MT/d).

 

 

The fresh water requirement will be 961 m3/day and will be met from nearest water reservoir.  The spent wash generation will be 600 m3/day.The spent wash treatment will be by Bio-methanation followed by evaporation. The concentrated spent wash (250 m3/d) will be composted with press mud to achieve zero discharge. Spent wash storage capacity will be 30 days. Press mud to spent wash ratio will be 1:2.5. Annual requirement of press mud will be 27000 MT. An area of 13 acres has been earmarked for compost plant, lagoon, storage of finished products etc. Power requirement of 1 MW will be met through the in house power generation unit.

 

 

CO2 generated in the fermentor will be scrubbed with water. SPM and CO emissions from the boiler will be controlled by providing dampers, ID fans, CO2 meter, Fly ash arrester.  

 

The solid waste generated from this unit will be yeast sludge residue and it will be used  in Bio-composting. 

 

After detailed deliberations, the EAC (I) recommended the proposal for grant of environmental clearance as per para 7(ii) of EIA Notification, 2006 exempting from preparation of EIA and public hearing. The method of treatment of spent wash is as per the CPCB guidelines.                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                              

 

8.33     Sugar (2500 TCD) and Co-generation Power Plant 15 MW at Gat No. 588, 589, 590, 592 & 645  Bhandar Kavathe village, Taluk South Sholapur, District, Sholapur, Maharashtra by M/s Lokmangal Sugar Ethanol and co-generation Industries Ltd.  EC after TOR

 

The project authorities and their consultant gave detailed presentation on the salient features of the project and proposed environment protection measures to be undertaken along with the EIA/EMP prepared based on the TORs awarded during 74th  meeting of the Expert Appraisal Committee (Industry) held on 13th – 14th November 2007. All the sugar units (>5000TCD) are covered at Sr. No. 5(j) of Schedule of EIA Notification 2006 in ‘B’ Category as such instant sugar unit does not attract the provisions of EIA Notification 2006.  The proposed CPP 15MW (less than 50MW) based on bagasse fuel is listed in sr. No. 1(d) in ‘B’ category. But due to location of interstate boundary within 10 km of the plant, as per general condition, the proposal was considered at Central level.

 

M/s Lokmangal Sugar Ethanol and co-generation Industries Limited  have proposed to set up a Sugar (2500 TCD) and Co-generation Power Plant of 15 MW at Gat No. 588, 589, 590, 592 & 645 Bhandar Kavathe village, Taluk South Sholapur, District, Sholapur, Maharashtra. River Bhima is passing at distance of 4 KM form the plant site. Total land acquired for the plant is 100 ha of which 35 ha is earmarked for development of green belt. Total cost of project will be Rs. 130.0 Crores, out of this Rs. 10 Crores is earmarked for environmental protection measures.

 

Sugar cane 75000 Tonnes/Month, Lime 150 Tonnes/Month, Phosphoric acid 1.80 Tonnes/Month lubricants 15tonne/month and other auxiliary raw materials like washing soda, caustic soda and bleaching powder are the raw materials for the project. 

 

Total water requirement of the plant is 444m3/day and will be sourced from the Bhima River. Permission for drawl of water is awaited from Government of Maharashtra.    The waste water generation from sugar plant, Captive power plant and domestic purposes will be 250m3/day, 184m3/day and 10m3/day respectively. The treated waste water will be used for irrigation in agriculture land and for green belt development after compliance of the irrigation standards.  

 

Boiler stack of power plant will be the main source of emission. For proper dispersion of emissions, 71m high stack has been proposed.  Electrostatic precipitator will be installed to control particulate emissions from the boiler. 

 

ETP sludge (2 Tonnes/month), flyash (470MT/M), chemical sludge from waste water treatment (1.5 tonne/month) and press mud (2600 tonne/month) will be generated as solid waste and spent oil 3 tonne/month will be generated as hazardous waste. Fly ash will be given to bricks manufacturing units and cement grinding units. Press mud will be given to Lokmangal group’s distillery about 30km from the plant.

 

Total power requirement of the plant will be 15 MW and will be met from bagasse fired captive power plant.  The fuel required for the power plant for running the 80 TPH boiler will be the bagasse generated as by-product.  Excess power will be transmitted to Maharashtra State Electricity Board. 

 

The Committee deliberated upon the issues raised during the Public Hearing / Public Consultation conducted by the Maharashtra Pollution Control Board on 29th February 2008.  It was noted that all the issues have satisfactorily been addressed and incorporated in the final EIA/EMP report.

 

The Expert Appraisal Committee found EIA/EMP complete and adequate and recommended the proposal for grant of environmental clearance subject to compliance of all the commitments made during public hearing alongwith specific and general conditions.

 

8.34                 Expansion of Dyes intermediate Unit at Plot 193/1, 2nd Phase, GIDC, District  Vapi, Gujarat by M/s Apex Pharma Chem Private Limited – TOR/EC

 

The project authorities and their consultant gave a detailed presentation on the salient features of the project and proposed environmental protection measures to be undertaken. All the dye and dyes intermediate units have been listed at S.N. 5(f)of schedule of EIA Notification, 2006 in Category ‘A’ & ‘B’ depending upon the location in/outside the notified industrial area.  The instant proposed dye and dyes intermediate unit is located inside the GIDC notified industrial area and as such fall under Category ‘B’. But due to location of project within critically polluted area, hence as per General Condition of Schedule of EIA Notification of 2006, the proposal is appraised at central level.

 

M/s Apex Pharma Chem Private Limited have proposed for expansion of Dyes intermediate Unit at Plot 193/1, 2nd Phase, GIDC, District  Vapi, Gujarat. The total cost of the project will be Rs. 0.8 Crores. The total land required for the project will be 5000.0 m2.  No eco-sensitive areas are located within 15 km periphery of the plant. The details of the products and their production capacity are as given below:

 

Sr. No.

Name of Product

Quantity/ Month

(Existing)

Quantity/ Month

(Proposed)

Total Quantity/ Month

Remarks

 

Group A Product

1

2- Chloro 5- Chloro Methyl Thiazole  (MAX)

10.0 M T / Month

-----

10.0 M T / Month

 

2

 

2-Diazo 1-Napthol 5- sulphonic acid sodium salt  (NAS)

 

25.0 M T / Month

-----

25.0 M T / Month

 

 

Group B Product ( Sulphonation )

1

(EBASA)  -- Ethyl Benzyl Aniline Meta Sulphonic Acid

-----

100.0 M T / Month

100.0 M T / Month

Manufacturing of either one product or more than one product as per the requirement,  but total quantity will not exceed 100 MT per month

2

(PCOSA)  -- Para Cresidine Ortho Sulphonic Acid

3

(PNTOSA)  --- Para Nitro Tolyl Ortho Sulphonic Acid

4

(PNCBOSA) -- Para Nitro Chloro benzene Ortho Sulphonic Acid

5

(ONCBPSA) -- Ortho Nitro Chloro benzene Para Sulphonic acid

6

(OPDASA) – Ortho Phenydine Diamine Sulphonic Acid,

 

Group C Product ( Specialty Chemical )

 

1

2, 7 Di Chloro 4- ( (2- di butyl amine ) Ethanol) Fluorene

-----

50.0 M T / Month

50.0 M T / Month

Manufacturing of  either one product or more than one product as per the requirement,  but total quantity will not exceed  50 MT per month.

2

Guaiacol --- 2- Methoxy Phenol

3

Veratrole --- 1,2 Dimethoxy Benzene

5

ONA –Ortho Nitro Anisole

6

PCA/OCA HCL  -- Para Chloro Aniline / Ortho Chloro Aniline Hydrochloride

7

PCD  -- Para Cresidine

 

Total Group A, B & C

35.0 M T / Month

150.0 M T / Month

185.0M T / Month

 

 

Detail on By- Product

 

Sr. No.

Name of By - Product

MT/ Month

(Existing)

Quantity/ Month

(Proposed)

Quantity/ Month (Total)

Remark

1.                   

Dilute Sulphuric Acid

---

661.9 MT

661.9 MT

Sold to actual users

2.                   

HCl

9.17 MT

102 MT

111.17

Reuse in process/ Sold to actual users

3.                   

AlCl3

---

464 MT

464 MT

Sold to actual users

4.                   

Veratrole

---

2.90 MT

2.90 MT

Reuse in Veratrole process

5.                   

Spent Nitric Acid

---

146 MT

146 MT

Sold to actual users

6.                   

Sodium Thio Sulphate

59.80 MT

-----

59.80 MT

Sold to actual users

 

The water consumption of the plant will increase from 45.73 KLD to 188.030 KLD which includes domestic consumption of 5 KLD. The total wastewater generation will increase from 9.963 KLD to 52.163 KLD which will be sent to ETP for treatment. Concentrated effluent 11.65 KLD will be sent to evaporator.  The generation of wastewater will increase hence the capacity of ETP will be augmented accordingly. The treated effluent will be drained through the GIDC underground drainage system and will go to CETP for further treatment. Domestic wastewater will go to soak pit/septic tank.

 

Besides existing non IBR Boiler – (2x600kgs/hr) and  Thermopac 2.0 lakh Kcal only one boiler of 2 MT/hr capacity will be installed. D.G Set of 125 KVA will be used when GEB power supply is failure otherwise it will be in stand by mode. Stacks of suitable height as per the CPCB norms will be provided with boilers, thermopac and D.G. Set. For control of fugitive emissions, 4 stage scrubber system will be installed out of which first and 2nd scrubber will recover HCl and 3rd and 4th stage scrubber will absorb the SO2 gas in alkali media. The fuel (LDO/FO) consumption will be 220Ltr/hr.

 

 

The hazardous wastes generated from the plant are as given below: 

 

Particulars

Existing

Expansion

After

Expansion

Remarks

ETP waste

500 Kg/ Month

1500 Kg/ Month

2000 Kg/ Month

The ETP sludge will be filled up in plastic bags & disposed to TSDF, VAPI

Spent Oil

10 Kg / Month

2.5 Kg / month

12.5 Kg /month

Reused in process plant for lubricating purpose.

Discarded Material

1100 Nos./month

2900 Nos./month

4000 Nos./month

Decontaminate and sold to actual users or will be reused in plant.

Process Waste

 

----

750 Kg /month

750 Kg/month

Process Waste will be filled up in plastic bags & disposed to TSDF, VAPI

Evaporated salt

45325 Kg / month

----

45325 Kg / month

Evaporated salt will be filled up in plastic bags & disposed to TSDF, VAPI

Distillation residue

6525 Kg / month

1240 Kg /month

7765 Kg/month

send to Common Incineration System at BEIL, Ankleshwar

Spent Carbon

25 Kg /month

---

25 Kg / month

Sludge from wet scrubber

2 Kg /month

---

2 Kg / month

Sludge from wet scrubber will be filled up in plastic bags & disposed to TSDF, VAPI

 

 

After detailed deliberations the Committee found the environmental protection measures satisfactory and recommended the proposal for grant of environmental clearance  dispensing with EIA/EMP as per para 7(ii) and Public hearing is not required as per para 7(i)IIIStage(3)(b) of the EIA Notification 2006 subject to specific condition for monitoring of VOCs and compliance of industry specifc discharge standards for treated effluent along with other specific and general conditions.

 

8.35     Expansion of molasses based distillery (from 20 KLD to 60 KLD) at Block No. 459/1, Garag, District Dharwad, Karnataka by M/s Sri Lakshmi Narshimha Distilleries Private Limited – TOR

 

The project authorities and their consultant gave a detailed presentation on the salient features of the project and proposed environmental protection measures to be undertaken alongwith the draft TORs for preparation of EIA/EMP. All molasses based distilleries are listed at Sl. No. 5(g) (i) of schedule of EIA notification under category ‘A’ and will be appraised at central level.

 

M/s Sri Lakshmi Narshimha Distilleries Private Limited has proposed for expansion of molasses based distillery (from 20 KLD to 60 KLD) at Block No. 459/1, Garag, District Dharwad, Karnataka. No eco-sensitive areas are located within 15 km periphery of the plant. The total cost of the project will be Rs. 15 Crores. The total land available for the project is 116 acres. 

 

The water requirement of 1500 KLD will be met from the bore wells.  The major source of water pollution from distilleries is the spent wash. Presently the wastewater is being treated in biodigester, Aeration, Clarifier extended aeration. Sludge drying beds has been provided for bottom sludge from clarifier. The treated wastewater is being used for ferti-irrigation. The wastewater generation will be 600KLD after expansion which will be subject to Evaporation by spray drying and powder will be used as fuel or bio fertilizer. The carbon-di-oxide generated during fermentation reaction will be compressed and sold out for further use. The steam requirement is met from a high pressure boiler (4TPH) and the high pressure (3Kg/cm2) utilized to generate 400 KW of electrical energy for captive consumption. The steam leaving the turbines at 1.5 kg/cm2 back pressure is supplied for further distillation processes which are generally practiced at 300 mm of vacuum.

 

The solid waste will be generated in the form of Yeast sludge (7.5 TPD). ETP sludge (10 TPD) would be reused in compost making process. Sewage sludge will be used as manure fro green belt composted along with other solid wastes.

 

The fuel wood and methane gas (recovered from bio-digester) are used as fuels in the boiler house. The off gases are passed through bag filters for the removal of particulate matter to meet the prescribed standards. 

 

The Committee discussed the wastewater treatment technology. The PAs requested for bio-methanation followed by bio-composting. The committee did not agree as this is a stand alone distillery. The PAs agreed on the spray drying technology to maintain zero discharge. After detailed deliberation, the committee prescribed the following TORs for undertaking detailed EIA/EMP study:

 

1.      Executive summary of the project.

2.      Present land use based on satellite imagery.

3.      Details of site and information related to environmental setting within 10 km radius of the project site.

4.      Details and source of raw materials, manufacturing process.

5.      Information regarding eco-sensitive area such as national park / wildlife sanctuary / biosphere reserves within 10 km radius of project area.

6.      Ambient Air Quality Monitoring for three months except monsoon.

7.      Mathematical modeling for calculating the dispersion of air pollutants and ground level concentration along with emissions from the bagasse / coal fired boiler.

8.      Details of the use of steam from the boiler.

9.      Ground water quality around the unit.

10.  Detailed water balance indicating input and output of waste water.

11.  Noise levels monitoring at five locations within the study area.

12.  List of flora and fauna in the study area.

13.  Number of working days of the distillery unit.

14.  Details of the spent wash treatment.

15.  Proposed effluent treatment system and scheme for achieving zero discharge.

16.  Water (1500 KLD) drawl permission from the State Ground Water Board.

17.  Details of solid waste management including management of boiler ash.

18.  Green belt development as per the CPCB guidelines.

19.  Environment Management Plan.

20.  Post project environmental monitoring.

21.  Plan for prevention of odour neusance.

 

            The Committee decided that after preparing the EIA/EMP covering the above mentioned TORs and as per the generic structure given in the EIA Notification 2006. The proponent shall submit the EIA/EMP Report to the MOEF for consideration for prior environmental clearance. Public hearing/public consultation is exempted as per para 7(ii) of the EIA Notification 2006.

 

 

8.36     Setting up of 100 KLPD distillery & Co-generation Plant in (50 MW) at SF No. 82, 83(part), 84(part), 86(part), 87(part), 113(part), 114(part), 115(part) 116(part), 117(part)  and 118(part), Edaikkal Village, Ambasamudram Taluk, Tirunelveli district, Tamilnadu by M/s. Empee Sugars and Chemicals Ltd., (distillery unit) – TOR

 

 

The project authorities and their consultant gave a detailed presentation on the salient features of the project and proposed environmental protection measures to be undertaken alongwith the draft TORs for preparation of EIA/EMP. All molasses based distilleries are listed at Sl. No. 5(g) (i) of schedule of EIA notification under category ‘A’ and will be appraised at central level.

 

 

M/s.Empee Sugars and Chemicals Ltd., (distillery unit) have proposed for setting up of 100 KLPD distillery & Co-generation Plant in (50 MW) at SF No. 82, 83(part), 84(part), 86(part), 87(part), 113(part), 114(part), 115(part) 116(part), 117(part)  and 118(part), Edaikkal Village, Ambasamudram Taluk, Tirunelveli district, Tamilnadu. The total land required for the Unit will be 72.49 acres.  25 acres has been earmarked for green belt. No eco-sensitive areas are located within 15 km periphery of the plant. The total cost of the project will be Rs.323 Crores.                        

 

Raw Material required for co-gen plant are Bagasse , Biogas, Bio Mass and for distillery is Cane Molasses, Nutrients, Antifoam Oil, Sulfuric Acid. The distillery will run for 330 days in a year.

 

The total water requirement of 1997m3/day (Distillery - 846 KLD + Cogen – 1151 KLD) will be met from bore wells inside the factory.   The effluent from the cogen and domestic will be treated in ETP of sugar plant. The distillery spent wash (1000KLD) will be subjected to evaporation  and concentrated spentwash will be incinerated in boiler. The condensate will be used for process dilution. The effluent from co-gen will be 361 KLD which will be treated in conventional ASP and treated wastewater will be utilised for green belt development. Emissions from the co-gen will be controlled by ESP followed by stack of 90 m height. Emissions from the fomenters will be controlled by 15 m high stack with CO2  scrubber. DG sets of 2X1000 KVA will be attached with stack of 17 m height along with acoustic enclosure.

 

Settled yeast sludge -6 T/day will be collected and used in bio- composting. Fly ash (15 TPD) generated from the boilers will be used as manure in the cane fields. The power generation will be 50 MW during the season. At the proposed production capacity, the average power demand for the sugar plant is 9.4 MW and for the distillery plant 1.0 MW per hour respectively. The balance surplus power of 39.6 MW will be exported to TNEB grid during the season.

 

After detailed deliberation the committee prescribed the following TORs for undertaking detailed EIA/EMP study:

 

1.      Executive summary of the project.

2.      Present land use based on satellite imagery.

3.      Details of site and information related to environmental setting within 10 km radius of the project site.

4.      Source of raw material

5.      Information regarding eco-sensitive area such as national park / wildlife sanctuary / biosphere reserves within 10 km radius of project area.

6.      Ambient Air Quality Monitoring for three months except monsoon.

7.      Mathematical modeling for calculating the dispersion of air pollutants and ground level concentration along with emissions from the bagasse / coal fired boiler.

8.      Details of traffic density vis-à-vis impact on the ambient air.

9.      Details of the use of steam from the boiler.

10.  Ground water quality around the unit.

11.  Detailed water balance indicating input and output of waste water.

12.  Noise levels monitoring at five locations within the study area.

13.  List of flora and fauna in the study area.

14.  Number of working days of the distillery unit.

15.  Details of the spent wash treatment.

16.  Proposed effluent treatment system and scheme for achieving zero discharge.

17.  Water drawl permission from the Irrigation Department/State Ground Water Board.

18.  Details of solid waste management including management of boiler ash.

19.  Green belt development as per the CPCB guidelines.

20.  Environment Management Plan.

21.  Post project environmental monitoring.

22.  Plan for prevention of odour nuisance.

23.  Action plan in the tabular form to the issues/suggestions made during the public hearing along with the implementation plan and allocation of funds.

 

            After preparing the draft EIA/EMP covering the above mentioned issues and as per information in the generic structure given in the EIA Notification 2006 the proponent shall submit the EIA/EMP Report to Tamil Nadu PCB and get the public hearing/public consultation conducted. On finalization of EIA/EMP prepared as per TORs addressing all concerns and incorporating in EIA/EMP should be submitted to the MOEF for consideration of prior environmental clearance. A letter may be written to Tamil Nadu Pollution Control Board for conducting the public hearing as per the procedure laid down in the EIA notification 2006.

 

 

8.37     Expansion of integrated Sugar Complex (5000 TCD Sugar Plant, 24 MW Co-Gen Power Plant, 7 MW Power Plant,  200 KLPD Distillery & 100000 m3 Medium Dense Fibre plants at Alagwadi Village, Raibagh Taluka, Belgaum District, Karnataka by M/s. Alagwadi Bireshwar Sugar Pvt. Ltd.-TOR

 

The project authorities and their consultant gave a detailed presentation on the salient features of the project and proposed environmental protection measures to be undertaken alongwith the draft EIA/EMP already prepared. All molasses based distilleries are listed at Sl. No. 5(g) of schedule of EIA notification, 2006 under category ‘A’ and will be appraised at central level.

 

M/s. Alagwadi Bireshwar Sugar Pvt. Ltd. have proposed for expansion of  of integrated Sugar Complex (5000 TCD Sugar Plant, 24 MW Co-Gen Power Plant, 7 MW Power Plant,  200 KLPD Distillery & 100000 m3 Medium Dense Fibre plants at Alagwadi Village, Raibagh Taluka, Belgaum District, Karnataka. No eco-sensitive areas are located within 10 km periphery of the plant. The total land acquired by the project is 268.53 acres.  The total cost of the project will be Rs. 657.25 Crores. The details of product and production capacity are as given below:

Sugar              -           5000 TCD

Co-Gen Power Plant - 24 MW

Power Plant                - 7 MW, 

Distillery          -           200 KLPD

Medium Dense Fibre-100000 m3

Sugar cane will be procured from nearby farmers and will be transported through trucks. Molasses requirement will be 840 TPD which will met from inhouse 200 TPD and remaining from market. Bagasse (1145 TPD) will be used in Co-gen power plant as fuel. Coal (112 TPD) will be used as fuel for 7 MW Power generations.  Coal will be imported and brought to the site through covered trucks. 450 TPD bagasse will be required for MDF plant.

 

Dust generation near raw material handling and transfer points will be suppressed through water spray.

 

The total water requirement for proposed integrated Sugar Complex will be 10300 KLD and will be met from Krishna River. The effluent from the sugar plant will be treated in ETP and after ensuring compliance with standards of KSPCB/CPCB will be used for irrigation and belt development. The spent wash will be treated in multiple effect evaporators to concentrate the solids to 55% and incinerated in the boiler. Hence zero discharge will be implemented in distillery to ensure compliance with CREP recommendations. Domestic wastewater will be treated in septic tank followed by soak pit.

 

 The fly ash generated from cogen will be used as manure and fly ash generated from power plant will be given to brick manufactures .Sludge from neutralization tank will be used for landfilling.

 

After detailed deliberation,the Committee prescribed the following TORs for undertaking detailed EIA/EMP study:

 

1.      Executive summary of the project.

2.      Present land use based on satellite imagery of study area of 10 km radius.

3.      Details of site and information related to environmental setting within 10 km radius of the project site.

4.      Source of raw material, linkages/agreement for supply of deficit bagasse & molasses should be provided.

5.      Information regarding eco-sensitive area such as national park / wildlife sanctuary / biosphere reserves within 10 km radius of project area.

6.      Ambient Air Quality Monitoring for three months except monsoon.

7.      Mathematical modeling for calculating the dispersion of air pollutants and ground level concentration along with emissions from the bagasse / coal fired boiler.

8.      Details of traffic density vis-à-vis impact on the ambient air.

9.      Details of the use of steam from the boiler.

10.  Ground water quality around the unit.

11.  Detailed water balance indicating input and output of waste water.

12.  Noise levels monitoring at five locations within the study area.

13.  List of flora and fauna in the study area.

14.  Number of working days of the distillery unit.

15.  Details of the spent wash treatment.

16.  Proposed effluent treatment system and scheme for achieving zero discharge.

17.  Water drawl permission from the Irrigation Department/State Ground Water Board.

18.  Details of solid waste management including management of boiler ash.

19.  Green belt development as per the CPCB guidelines.

20.  Environment Management Plan.

21.  Post project environmental monitoring.

22.  Plan for prevention of odour nuisance.

23.  Action plan in the tabular form to the issues/suggestions made during the public hearing along with the implementation plan and allocation of funds.

 

            After preparing the draft EIA/EMP covering the above mentioned issues alongwith the other information as per generic structure given in the draft EIA Notification 2006. The proponent shall submit the Draft EIA/EMP Report to Karnataka PCB and get the public hearing/public consultation conducted. On finalization of EIA/EMP prepared as per TORs addressing all concerns and incorporating in EIA/EMP should be submitted to the MOEF for consideration of prior environmental clearance. A letter may be written to Karnataka Pollution Control Board for conducting the public hearing as per the procedure laid down in the EIA notification 2006.

 

 

8.38     New Pesticide Technical Manufacturing Unit  at GIDC Nandesari Tehsil Vadodara District Vadodara Gujarat   by M/s GSP Crop Science Private Limited  ? (TOR)

 

The proponent informed that they will not be able to attend the meeting.

 

8.39     Grain based 45 KLPD Distillery unit at Sansarpur Terrace, Tehsil Jaswan Kotla District Kangra Himachal Pradesh by M/s Premier Alcobev Pvt. Ltd.– (TOR).

 

 

M/s Premier Alcobev (P) Ltd.  (PAPL) proposes to set up  a 45 KLPD  capacity  grain based distillery unit  at Sansarpur Terrace, Tehsil Jaswan Kotla in  District Kangra, in Himachal Pradesh. Bottling plant consisting of 6 Lines for 5000 IMFL Cases per Day & 6 Lines for 4000 Cases per Day of Country Liquor is also proposed. The distillery unit will run for 330 days in a year.  No R & R is involved. The Company has already acquired 10 Acre of land for the proposed distillery project in the notified industrial area of Sansar Terrace.  The Green belt will be developed in 25% of the plant area.. Total cost of the project is Rs. 37.55 Crores  of which  Rs. 4.0 Crores has been earmarked  environmental protection measures.     

 

The water requirement of 1100 m3/day  will be met from bore well. The total spent wash discharge is estimated to be 479 m3/d which will be first taken to Centrifuge  decanter where the suspended  solids would be removed  as wet cake. A part of the 419 m3/d of thin slop thus separated after decantation will be  recycled back to process and  147 m3/d  and the balance thin slop would be evaporated. The thick syrup, estimated to be 36 m3/d will be dried and sold as cattle feed. The process condensate generated after cooling will be used as cooling tower make up water.

 

            The power requirement of 1300 KW which will be met from  14 TPH boiler and 1.3 MW turbine.  To control the particulate emissions from the rice husk fired boiler, multi-cyclones will be installed.     Ash from the boiler will be used for land filling. Wet cake and thick syrup will be used as cattle feed.  No hazardous waste will be generated.

 

 

 The Committee prescribed the following TORs for undertaking detailed EIA study:

 

1.      Executive summary of the project.

2.      Detailed break up of the  project cost.

3.      Present land use based on satellite imagery.

4.      Details of site and information related to environmental setting within 10 km radius of the project site.

5.      Information regarding eco-sensitive area such as national park / wildlife sanctuary / biosphere reserves within 10 km radius of project area.

6.      Source of raw material.

7.      Ambient Air Quality Monitoring for three months except monsoon.

8.      Mathematical modeling for calculating the dispersion of air pollutants and ground level concentration along with emissions from the rice husk    fired boiler.

9.      Details of the use of steam from the boiler

10.  Hydrology of the area especially down stream.

11.  Ground water quality around the unit  and spent wash storage lagoon. Detailed water balance indicating the input and output along with measures for water conservation. 

12.  Noise levels monitoring at five locations within the study area.

13.  List of flora and fauna in the study area.

14.  Number of working days of the distillery unit.

15.  Details of the spent wash treatment.

16.  Proposed effluent treatment system and scheme for achieving zero discharge.

17.  Treatment system and scheme for achieving zero discharge. Water drawl permission from the Irrigation Department/State Ground Water Board.

18.  Source of raw material

19.  Details of solid waste management including management of boiler ash.

20.  Green belt development as per the CPCB guidelines.

21.  Environment Management Plan.

22.  Rainwater harvesting measures

23.  Details of occupational health surveillance programme.

24.  Details of socio economic welfare activities.

25.  Post project environmental monitoring.

26.  Water drawl permission from the Irrigation Department/State Ground Water Board.

 

 

The Committee decided that after preparing the draft EIA/EMP covering the above mentioned issues, the proponent shall submit the EIA/EMP Report to the Ministry for obtaining environmental clearance in accordance with the procedure prescribed in the EIA Notification. Public hearing is not required in this case as the unit is located in the Notified industrial area.

 

8.40.    Setting up of manufacturing of PU Molded Pads (50 MTPM) for automobile seats Plot No. 52, Near Manjusar GIDC Vadodara - Salvi Road, Manjusar, District Vadodara Gujarat by M/S Spack Automotives Ltd. – TOR

 

The project authorities and their consultant gave a detailed presentation on the salient features of the project and proposed environmental protection measures to be undertaken along with the EIA/EMP already prepared. The project activity  is listed at serial no. 5(f) of schedule of EIA Notification, 2006 under “A” as the plant is located out side the notified industrial area, hence the proposal was appraised at central level.

 

M/s. Spack Automotives ltd. setting up of a plant for manufacturing of PU Molded Pads (50 MTPM) for the Automobile Seats at Plot No. 52, Near Mukut Nagar, Sama-Salvi Road, Manjusar, Taluka Salvi, in distt. Vadodara, Gujarat. The proposed plant will be run in a rented building of M/s Polymechplast Machines Limited. The existing building is having total covered area of 1986.29 m2. The total cost of the project will be Rs. 100 Lakhs. The total land required for the project will be 28834 m2. The total green area provided within the premises is around 2439.71 Sq.m.  No eco-sensitive areas are located within 15 km periphery of the plant.

 

The various raw materials will be used for the proposed plant are Polyol 70 Mt/Month, Isocyanate 30 Mt/Month, Release Agent 2 Mt/Month, Insert Wires 10 T/Month, Non-woven Cloth 5000 Mtr. /Month.

 

To control process emissions, air exhaust system will be provided. The plant will be provided with exhaust fans fitted on vent ducting. The water requirement unit will be 10 KLD. The bore wells will be the source of water supply. There will be no industrial waste water generation from the plant. Around 2.84 KLD of domestic sewage will be generated and will be treated in existing STP of capacity 10 KLD.

 

The solid waste generated from the project after the plant is functional shall mainly be domestic waste and byproduct of the manufacturing process comprising of polyurethane pads reject and trimming of pads at parting line, the estimated quantity of the same will be approx. 80 kg/day. Maximum amount of solid waste will be recyclable and sold of to authorised vendors. The remaining solid waste so generated shall be first segregated as plastic, glass, paper and other waste separately and disposed off as per MSW rule, 2000. Waste other than plastic, paper and glass shall be collected and disposed off at the municipal waste sites. 

 

The total power requirement for proposed plant will be 55 KVA. To cater for power failure one DG set of 100 KVA capacity will be installed. The fuel consumption for the DG set is around 1000 Lt/day.

 

The Committee after detailed deliberation suggested that the draft EIA/EMP should be prepared as per the generic structure given in the EIA Notification, 2006 for TORs presented before the committee for the study area of 5 km radius around the plant and draft EIA/EMP may be submitted to the Gujarat pollution Control Board for conducting the public hearing. A letter may be written to the GPCB to conduct public hearing/consultation within stipulated time frame.  On finalization of EIA/EMP prepared as per after addressing and incorporating all concerns raised during public hearing/public consultation, the same should be submitted to the MOEF for consideration of prior environmental clearance.

 

 

8.41     Expansion of Polyester Film production (5000TPA - 7500 TPA) at Plot No.12  Rampura Ramnagar road District Kashipur Uttrakhand by M/S  SRF Limited – TOR/clarification

 

The project authorities and their consultant gave a brief presentation on the salient features of the project and proposed environmental protection measures to be undertaken.

 

M/S SRF Limited have proposed for expansion of Polyester Film production from 5000TPA to 7500 TPA at Plot No.12 in District Kashipur in Uttarakhand. The total cost of the project will be Rs. 25Lakhs. The total land available with the project is 4.857 ha.  No eco-sensitive areas are located within 15 km periphery of the plant.

 

The raw material required for manufacturing polyester chips commonly called PET. This is a harmless product obtained from petrochemical industry. In order to produce 1000 kg of polyester films about 1004 kg of PET is used. 4 kg accounts for moisture loss. The cutting and trimming of polyester films is recycled back in manufacturing process. The present consumption of PET chips to produce 5000 TPA polyester films is 5020 TPA. The consumption of PET chips will increase to 7530 TPA, when the production capacity will increase to 7500 TPA.

 

The Committee found that the manufacturing process does not involve any chemical reaction or synthesis. The activity does not fall in any of the project activity listed in schedule of EIA Notification 2006, hence the committee decided that the project does not attract the provision of the EIA Notification, 2006 and PAs may be communicated acoordingly. 

 

 

8.42     Setting up of Chlor Alkali  complex at Kona Village, Machilipattinam, Krishna District, Andhra Pradesh by M/s Bharat Salt Refineries Ltd. -TOR

 

PAs did not attend the meeting and requested for postponement of presentation till further request.

 

8.44     KLPD Distillery unit at Udumbiyam Village Veparthattai District Tamilnadu by M/s Dhanlakshmi Srinivasan Sugars Pvt. Ltd. (TOR)

 

The above proposal was considered by the Expert Appraisal Committee in its 81st    meeting held on 12th – 14th May, 2008. The Committee prescribed the TORs for undertaking EIA study and advised the project proponent to submit the EIA/EMP report to the State Pollution Control Board for conducting public hearing. The issues emerged during the PH/PC shall be incorporated in the EIA/EMP report and the report should be submitted to the Ministry for obtaining environmental clearance.

 

Public hearing for the project was held on 07th August 2008 at Veellupuram  in  Tamilnadu.  The issues raised were regarding,  measures for  control of water pollution, air pollution from incinerator and odour problem and availability of  Sewedha Nathi river water to the nearby farmers etc. 

 

All the above issues were addressed by the Project proponent. The Project proponent informed that the spent wash will be concentrated in the Multi Effect Evaporator followed by incineration in boiler and there will be no discharge of waste water from the unit on the land. Due to this technology, potassium rich ash will be obtained and  will be utilized by the farmers as manure. There will not be any odour problem due to the proposed unit. To control air pollution from the boiler, stack height of 55 m. and bag filters are proposed. The unit will utilize water of Sewedha Nathi for the three units. However, 75% of the water will be obtained from water recycling and hence, water drawl will be reduced.

 

M/s Dhanalakshmi Srinivasan Sugars Pvt. Ltd.  have proposed for a 60 KLPD Distillery unit to manufacture, Rectified spirit (RS) (10 KLPD) Extra neutral alcohol (ENA) /Anhydrous Alcohol (40 KLPD) and Ethanol (10 KLPD) at Udumbiyum village, Veppanthattai Taluk, Perambalur Dist. , Tamilnadu No protected forests/eco-sensitive  area located with in 10 Km. radius from the proposed unit. Total area of the plant will be 25.17 acres. Green belt will be developed in 8 acres of the plant area. The unit will operate for 330 days. The total cost of the project will be Rs. 61.00 crores of which 1530.00 lacs will be utilized for Environment Management System.

 

The main raw materials used will be cane molasses (225 MT/d), nutrients (97 kgs/d), Sulphuric Acid (110 kgs/d) and Antifoam Oil (115kgs/day).

 

The power requirement of the plant will be 900 KW/hr. the power requirement will be met from the Co-generation power Plant.

 

The total water requirement of 794 m3/day will be sourced from the Swetha Nathi. The wastewater from the domestic usages (3.2 KLD) will be sent directly to the septic tank of size 3mx2mx2m followed by the dispersion trench of size 5mx2mx2.5m. The spent wash (658.5 KLD) will be concentrated in Multi Effect Evaporator followed by incineration in specially designed boiler to achieve zero discharge.

 

To control the particulate emission  from the boiler, stack height of 55 m and bag filters will be provided . In the fermentor, the evolved traces of CO2 will be scrubbed with water and scrubbed water will be recycled in the plant. Air quality monitoring has been carried out for 8 locations for the parameters RSPM, SPM, SO2, and NOx for the period January to March 2008. The results at all the locations were well with in the limit.

 

The solid waste generation from this unit will be settled yeast sludge (3.0 T/day) and will be burnt in the boiler along with spent wash. Boiler Ash (18 T/day) collected & disposed as fertilizer since it is rich in potash. 

 

After detailed deliberations, the EAC (I) satisfied with the proposed pollution control measures to be undertaken recommended the proposal for grant of environmental clearance. The method of treatment of spent wash is as per the CPCB guidelines.

 

 

8.45     Proposed laminate sheet manufacturing plant of capacity 69000 nos./month at Survey no.148 Part, Rajpar, Khanpar Road, Near Sadguru Cotton Mill, village Rajpar, MORBI Gujarat-363641 M/s Arc Lamicraft Pvt Limited reg TOR

 

The proposal was considered by the Expert Appraisal Committee (Industry) to determine the Terms Of Reference (TOR) for undertaking detailed EIA Study for obtaining environmental clearance in accordance with the provisions of EIA Notification, 2006. For the purpose, the proponent had submitted information in the prescribed format (Form-1) along with the pre-feasibility report. The project activity is listed at serial no. 5(f) of schedule of EIA Notification, 2006 and categorized under “A” or “B” category depending upon the location of the plant outside or inside the notified industrial area. Since the proposed unit is located outside the industrial area  and the proposal appraised at central level. This is a “A’ category project.

 

M/s Arc lamicraft Private Limited have Proposed for laminated sheets manufacturing plant of capacity 69000 nos/month and Resins (Melamine formaldehyde resin and Phenol formaldehyde resin)  at in Dist.: Rajkot in Gujarat. No eco-sensitive areas are located within 10 km radius of the plant. River Demi is flows at a  distance of 6 km. Total land area is 19930.49 m2. Green belt will be developed in 5325 m2 of plant area. Cost of the project will be Rs. 4.75 crores. 

 

Raw material requirement will be Kraft paper (160 MTPM), design paper (20 MTPM), tissue paper (5 MTPM), wrapping paper (7 MTPM), Phenol (45 MTPM), Melamine (30 MTPM), formaldehyde (75 MTPM), Methanol (20 MTPM), BOPP film (1 MTPM), caustic soda (1 MTPM) and HCl (0.5).

                       

Power requirement will be met from the PGVCL. Fuel requirement for the boiler will be coal (15 T/day) and Diesel (40 lts/hr) for DG set.  

 

Total Water required will be 30.70 m3/day and will be sourced from the ground water supply. Rain water harvesting scheme is proposed for recharge of ground water. Total effluent generation will be 3.6m3/day. Waste water from the process (0.2 cu.m/day) having high COD and highly acidic will be sent to Multiple Effect Evaporator. The concentrated effluent will be sent to Common Hazardous Waste Incinerator. Domestic effluent will be treated through septic tanks/ soak pits. 

 

Multi cyclone and stack height of 30m is proposed for the boiler. Stack height of 12m is proposed for the DG set. There will be no process emissions due to the proposed activity.

Solid/Hazardous waste generation will be in the form of process waste (50 lt/day) and  will be sent to BEIL for incineration. Spent oil (50 lts/year) will be sent to authorized recyclers. Empty drums (10 nos/month) will be sent to authorized recyclers or returned back to the actual suppliers. Used plastic bags (25 bags/month) will be sent to authorized recyclers.

The Committee prescribed the following TORs for the preparation of EIA/EMP Report for the project:

A. Project Description

·         Executive summery of the project

·         Compliance status to the conditions stipulated while according environmental clearance to the existing project/NOC granted.

·         A filled in Questionnaire on the Industry sector as devised earlier

·         Justification of project.

·         Promoters and their back ground

·         Project site location along with site map of 05 km area and site details providing    various industries, surface water bodies, forests etc.

·         Project cost

·         Regulatory framework

·         Project location and Plant layout.

·         Existing infrastructure facilities including power sources.

·         Existing environmental scenario, stack emission data

·         Total cost of the project along with cost for environment protection measures.

·         Water source and utilization including existing and proposed water balance.

·         Product spectrum (Existing and proposed products along with production Capacity) and processes

·         List of hazardous chemicals with their toxicity levels.

·         Storage and Transportation of raw materials and products.

·         Mass balance of each product along with the batch size

·         Pollution potential from the proposed products

·         Detailed scheme for waste water treatment along with characteristics of inlet and outlet waste water. The treatment scheme to meet discharge norms of GPCB. Final discharge point. 

B. Description of the Environment and Baseline Data Collection

·         Demarcation of Impact boundary (10 km from the project site)

·         Micrometeorological data for wind speed, direction, temperature, humidity and rainfall in 05 km area.

·         Study of Data from secondary sources.

·         Topography, drainage and soil characteristics. Local area hydrology, storm water drainage etc.

·         Details of the water source available in the impact area (Depth of ground water table, data from the available secondary sources)

·         Other industries in the impact area

·         Prevailing environment quality standards

·         Existing environmental status vis a vis air, water, noise, soil in 10 km area from the project site for SPM, RSPM, SO2, NOx, CO, HCl and NH3,VOC

·         Periodic monitoring of vents from condensers in the existing plant .

C.        Socio Economic Data

·         Existing socio-economic status, land use pattern and infrastructure facilities available in the study area were surveyed.

D. Impacts Identification and Mitigatory Measures

 

·         Identification of impacting activities from the proposed project during construction and operational phase.

·         Impact on air (Organic and inorganic pollutants) and mitigation measures including green belt

·         Impact on water environment and mitigation measures (Details of ETP design will be in EMP). Location of final disposal and downstream usages of disposal point.

·         Soil pollution source and mitigation measures

·         Noise generation and control.

·         Ground water abstraction and its impact on water sources.

·         Solid waste quantification and disposal.

·         Control of fugitive emissions

E. Environmental Management Plan

§         Details of pollution control measures

§         Environment management team

§         Proposed schedule for environmental monitoring including post project monitoring for Air, Water, Soil and Noise.

§         Chillers should be provided for chilled brine circulation to condensate the solvent vapors and reduce solvent losses.

§         Solvent recovery plant should be installed to recover the solvents and solvents generated from the vents and in the work zone environment should be monitored

§         Solvent should be stripped from the effluent before discharging into the evaporation pond for their maximum recovery.

§         Industry should treat the effluent and treated effluent shall comply with the industry specific standards.

F. Risk Assessment

 

·         Objectives, Philosophy and methodology of risk assessment

·         Details of manufacturing process of proposed products

·         Details on storage facilities

·         Process safety, transportation, fire fighting systems, safety features and emergency capabilities to be adopted.

·         Identification of hazards

·         Compatibility studies and special hazards

·         Consequence analysis through occurrence & evaluation of incidents

·         Selection of incidents and consequence calculations

·         Recommendations on the basis of risk assessment done

·         Disaster Management Plan.

·         Safety precautions for the storage of Chemicals and vapour condensation.

 

G.  Occupational Health and Safety Program for the Project.

 

H.  Information on Rain Water Harvesting

 

I.   Green Belt Development plan

 

J.   Public Hearing

 

Action plan in the tabular form to the issues/suggestions made during the public hearing along with the implementation plan and allocation of funds.

 

It was decided that the Proponent should prepare EIA/EMP Report based on the above TORs and submit the same to the Gujarat PCB for conducting Public Consultation. The EIA/EMP Report should be as per the generic structure given in Appendix-III of EIA Notification, 2006. The concerns emerged during the Public Consultation may be incorporated in the EIA/EMP Report and the final EIA/EMP may be submitted to the Ministry for obtaining   environmental clearance.

 

 

8.46     Exploratory drilling in CB-ONN-2004/3 (NELP - VI) in Gujarat by M/s ONGC- EC after TOR

 

 

The above proposal was considered by the Expert Appraisal Committee in its 67th meeting held on 19th – 21st June 2007. The Committee prescribed the TORs for undertaking EIA study  and advised the project proponent to submit the EIA/EMP report to the State Pollution Control Board for conducting public hearing. The issues emerged during the PH/PC shall be incorporated in the EIA/EMP report and the report should be submitted to the Ministry for obtaining environmental clearance. 

 

            Public hearing for the  project was held on 05th September 2008 at Dist: Anand, Gujarat. The issues raised were regarding, employment & wages for the local people, economical development of area, benefit to local people if oil & gas is produced, compensation for the damaged crops due to the vehicular movement and colored water in open wells , expenses involved by ONGC in drilling activities and  repair of roads.

          

The issues were addressed by the project proponent. The proponent have assured about the employment and social development of the area.  If any well get successful and when commercial production of oil and gas starts then royalty will be paid to central /state Govt. as per standard prevailing rules. Wages will be as per the standard prevailing rules. Compensation will be paid for damage of standing crops as per the rules. Regarding the Colored water in the wells, the case will be investigated by GPCB  

 

M/s ONGC Limited have proposed for exploratory drilling in Block CB-ONN-2004/3 (NELP-VI) in Bharuch, Gujarat. The block is located in districts  Anand and Bharuch Dist. of Gujarat. The area of the block is 113 km2. It is proposed to drill 10 exploratory wells. Depth of the well will be 3750 m. 

 

 

The total water requirement of 50 m3/day/ well will be sourced from the nearest available water source. The effluent generated during the drilling operations will be 25 m3/day   from a single well. The effluent generated will be discharged in HDPE lined evaporation pit. Domestic effluent will be disposed through septic tanks and soak pits.  DG set of 380 and 350 KVA will be installed to meet the power requirement. 150 lts/hr of HSD will be consumed for Diesel engines max. for 1 month per well and 20 lts/hr. of HSD will be consumed for lighting purposes.

 

 

The main air emissions will be from the DG set at well site. Flaring of gases during the drilling testing phase will contribute to additional air pollution. Adequate stack height is proposed for DG set and flaring of gases. Air quality monitoring was carried out in summer season for 10 locations for the parameters RSPM, SPM, SO2, NOx, HC and CO. The average concentration for RSPM at all the locations ranged from  45.8 to 72.8 ug/m3. The average concentration for SPM was observed to be 84.6 to 151.6 ug/m3. The values for  SO2 was observed to be in the range of 8.2 to 10.2 ug/m3 and for  NOx ranged between 14-17.7 ug/m3. The values of CO  ranged  from 840.1 to 1020 ug/m3 and the concentration of HC was observed to be varying from 913.1 to 1391.6 ug/m3.

 

Solid waste generation will be drill cutting (30-50 MT/well), Oil Sludge (0.15 MT/well) and drilling mud (250-400 m3/well). Solid waste will be disposed of at TSDF site. Drilling mud  will be sent to central mud plant of ONGC for treatment and reuse.

 

 

After detailed deliberations, the EAC (I) satisfied with the proposed pollution control measures to be undertaken recommended the proposal for grant of environmental clearance.

 

 

8.47     Exploratory drilling in CB-ONN-2004/4  (NELP-VI) in Gujarat by M/s ONGC - EC after TOR

 

 

The above proposal was considered by the Expert Appraisal Committee in its 67th meeting held on 19th – 21st June 2007. The Committee prescribed the TORs for undertaking the EIA study  and advised the project proponent to submit the EIA/EMP report to the State Pollution Control Board for conducting public hearing. The issues emerged during the PH/PC shall be incorporated in the EIA/EMP report and the report   submitted to the Ministry for obtaining environmental clearance. 

 

            Public hearing for the proposed project was held on 29th August 2008 at Dist: Bharuch in Gujarat. The issues raised were regarding,  provision of  drinking water to the nearby villages,  impact on agricultural land, damage to roads due to the heavy vehicles used by ONGC. Unit should give support to Govt. in implementation of Nirmal Gujarat and Kanya Kedavani projects and local development activities etd.c

 

The issues raised were addressed by the project proponent. The company has assured   provision  for the employment, drinking water facilities and social development of the area.

 

M/s ONGC Limited have proposed for exploratory drilling in Block CB-ONN-2004/4 (NELP-VI) in Bharuch Dist., Gujarat. The block falls in the Cambay Basin of south Gujarat. The area of the block is 70 km2. It is proposed to drill 04 exploratory wells. Depth of the wells will be 4650m-4750m

 

DG set will be installed to meet the power requirement. 150 lts/hr of HSD will be consumed for diesel engines max. for 1 month per well and 20 lts/hr. of HSD will be consumed for lighting purposes.

The total water requirement will be 50 m3/day/ well. The water will be sourced from the nearest available water source. The effluent generated during the drilling operations will be 25 m3/day during the drilling operation from a single well. The effluent generated will be discharged in HDPE lined evaporation pit. Domestic effluent will be disposed through septic tanks and soak pits. 

 

The main air emissions will be from the DG set at well site. Flaring of gases  during the drilling testing phase will contribute to additional air pollution. Adequate stack height is proposed for DG set and flaring of gases. Air quality monitoring was carried out in summer season for 10 locations for the parameters RSPM, SPM, SO2 and NOx, All the parameters ware well with in the permissible limits.

 

Solid waste generation will be in the form of drill cutting  (30-50 MT/well), Oil Sludge (0.15 MT/well) and drilling mud (250-400 m3/well). Solid waste will be disposed off at TSDF site. The drilling mud will be sent to central mud plant of ONGC for treatment and reuse.

 

After detailed deliberations, the EAC (I) satisfied with the proposed pollution control measures undertaken and recommended the proposal for grant of environmental clearance.

 

9.0  Reconsideration

 

9.1  Expansion of Dyes Manufacturing Unit along with CPP from 700 MTM to 7500 MTM at Plot No. 390A, 390B, 391A, 391B, 393,394-A2, 394-B1, 394-B2 396, 399, 400A, 400B, 401, 402, 403 and 404A in Village Dudhvada, Padra Taluka, Vadodara District in Gujarat by M/s Kiri Dyes and Chemicals Ltd - EC after TOR - consideration of CPCB visit report reg.

 

The proposal was considered in the 84th meeting of the Expert Apprasal Committee held during 19th – 21st August 2008. The Committee was decided that a subcommittee of following shall visit the Plant for spot inspection and submit detailed report on water, Air and soil pollution from the plant before reconsideration of the proposal:

 

1.         Sh. R.K.Garg- Vice Chairman EAC(I) 

2.         Representative of the Ministry

3.         Zonal officer CPCB Vadodara

 

It was informed by the Member Secretary that a team of scientists from the Zonal office of CPCB Vadodara has visited the plant in September, 2008. The committee decided that the inspection report along with recommendations may be sought from the CPCB to decide the proposal and now visit by the sub committee will not be required. The report of CPCB shall be placed before the committee as and when received.

 

The report of CPCB received and placed before the Committee. The committee noted that as per the observations of the CPCB team, the ETP and incinerator were not functioning satisfactory and not complying the standards. The Committee decided that observations of subcommittee may be communicated to the proponent that the proponent should send performance report to the Ministry for placing in the Committee and deciding the visit to the plant. The proposal will be reconsidered by the Committee after the submission of visit report. 

 

9.2       Proposed  Synthetic Organic Chemicals manufacturing  unit at plot no. 3133 to 3139, 3231 to 3245, 3330 to 3351, 3517 to 3524 , GIDC Panoli, Dist: Bharuch, Gujarat. By M/s P.I . Industries Limited- EC after TOR- consideration of CPCB visit report reg.

 

The proposal regarding Synthetic Organic Chemicals manufacturing  unit at  GIDC Panoli in Dist: Bharuch in Gujarat. By M/s PI Industries Limited was considered by the Expert Appraisal Committee in its 83rd   meeting held during 14-16th July, 2008.  The Committee desired the details of effluent treatment system, emissions data and solvent recovery system for the existing plant located adjacent to the proposed unit. The Committee recommended that a sub-committee from ZO, CPCB should visit the existing unit which is of similar nature and submit the report to the Ministry. The proposal will be reconsidered on the facts of the site visit by the Sub-Committee.

 

A team from the CPCB, ZO- Vadodara inspected the unit on 02.09.2008 and 13.09.2008. The Committee discussed the tour report in detail and agreed to the recommendations made in the site inspection report regarding upgradation of ETP and control the odour from the existing unit.

 

The Committee recommended the proposal for grant of environmental clearance subject to stipulation of following specific conditions.

 

 

1.       The unit shall undertake measures to minimize the leakages of odorous gases so as to minimize odour problem in the plant area  and near by area.

 

2.      The unit shall install own ETP and meet the industry specific discharge standards notified under Environment (Protection) Act, 1986.

 

3.      GPCB shall not permit any new discharge from new industries or expansion of existing industries in the area that lead to CETP until the said CETP meet the required standards and meet the hydraulic capacity.

 

4.      The company shall obtain Authorization for collection, storage and disposal of hazardous waste under the Hazardous Waste (Management and Handling) Rules, 2003 for management of Hazardous wastes and prior permission from GPCB shall be obtained for disposal of solid / hazardous waste in the TSDF. The concerned company shall undertake measures for fire fighting facilities in case of emergency.

 

10.0  Any other item:

 

 

10.1                      Bulk Drug unit at SIPCOT Industrial Area Hosur, Krishnagiri Andhra Pradesh by    M/s Calcitech India Private Limited ? EC condition- continuos monitoring system for Bromine amendment regd.

 

The above projects were granted environmental clearance vide letters No- J-1 No- J-11011/411/2006-IA-II (I) Dated 1st August 2007 to M/s Global Calcium Pvt Ltd and 1011/411/2006-IA-II (I) Dated 18th  July 2007 to M/s Calcitech India Private Limited. Both companies have requested for amendment in EC conditions.

 

1.   M/s Global Calcium Pvt Ltd  have requested for amendment in specific condition No. iv regarding - The ambient air quality monitoring stations will be set up in consultation with the State Pollution Control Board. It will be ensured that at least one monitoring station is set up in up-wind & in down-wind direction along with those in other directions. On-line data for air emissions shall be transferred to the CPCB and SPCB regularly. The instruments used for ambient air quality monitoring shall be calibrated regularly.”

 

The company has requested to delete “On-line data for air emissions shall be transferred to the CPCB and SPCB regularly.” From the above condition.

 

The matter was discussed by the committee and the committee decided that instead of online data transfer, PAs may transfer the data to CPCB and SPCB monthly.

 

2.   M/s Calcitech India Private Limited have requested for amendment in specific condition No. ii “A periodic monitoring of Bromine at salient location within the plant premises as well as out side the plant shall be carried out. A continuous monitoring system for bromine shall be installed.

 

The company has requested to delete “A continuous monitoring system for bromine shall be installed.”

The matter was discussed by the Committee and the committee agreed that it can be deleted.

 

10.2                      Expansion of Nitro-Tolune and Addition of New Product SMIA at GIDC  Chemical Complex, Nandesari Baroda, Gujarat by M/s Deepak Nitrite  Limited ? amendment in product list and emission of NOx regd.

 

The proposal was considered in 67th and reviewed in 78th meeting EAC(I) and as per the recommendation of the Committee environmental clearance was accorded on April 9th 2008.  

 

The PAs have requested for corrections in the environmental clearance for products and emission limits.

 

The committee discussed the issue and found that the product Nitro-xylene and Nitro-cumene may be shifted from list of existing products to proposed products. Regarding emission limit for the nitrogen oxides, the committee suggested that limit should be fixed as 25ppm.

 

 10.3    Setting up of Cement Plant (200 TPD) at Modertoli Village, Doboka Revnue Circle, Hojai Sub Division, Nagaon District, Assam by M/s Mahabali Cement Limited – EC

 

The proposal was considered in 83rd meeting of the Expert Committee (Industry) held during 14th – 16th July 2008. The Committee noted that:

1.      The project is small scale industry.

2.      The project Authorities prepared EIA/EMP

3.      The public hearing was suomoto conducted by the Assam Pollution Control Board under EIA Notification 2006 on 2nd February 2008.

4.      The Penal of public hearing headed by Additional Deputy Commissioner, recommended the proposal for setting up of the plant.

5.      Assam Pollution Control Board has granted NOC on 12th February 2008.

6.      Proceeding of public hearing was forwarded to the Ministry on 12th February 2008.

 

The committee had suggested that State Pollution Control Board may be directed by the Ministry to act as per the provisions and procedure of the EIA Notification 2006 regarding public hearing. However, considering the small scale unit, above facts and recommendation of the public hearing panel, the committee recommended the proposal for grant of environmental clearance subjected to specific and general conditions after submission of Form -1 for record.

While processing the proposal in the Ministry it is noted that the public hearing was not conducted as per the provisions of the EIA Notification 2006 and proposal referred back to the EAC(I) for review.

The Committee discussed the matter at length again and the reiterated the decision however suggested that Ministry may write to the industry to submit the EIA/EMP as approved by the committee to the SPCB for fresh public hearing as for as committee is concerned it is satisfied with the public hearing and EIA/EMP. The committee also suggested that in such case the SPCB may be given instructions accordingly.

10.4     Applicability of Environmental Clearance under EIA Notification, 2006 for manufacturing of Aluminium Alloys Ingots (4800 TPA on three shift basis) through rotary furnace by M/s Shree Balaji Alloys Plot No. 10, Industrial Area, Bai-Attarian,Tehsil Indora, District Kangra, Himachal Pradesh – Clarification reg.

 

The proposal is for manufacturing of Aluminium Alloys Ingots 4800 TPA on three shift basis with use of rotary furnace and raw materials will be non-toxic Aluminium scrap. The plant will be located in industrial area.  The PAs have informed that raw material will be non toxic Aluminium scrap and given the composition of the raw material which contains the heavy metals in minor proportions.  

The committee took the note of the information given by the project authority and decided that the activity will not come under heavy and toxic metallurgical activity. Hence being capacity less than 5000 TPA, the proposal does not attract the provision of EIA Notification 2006.

 

 

22nd October, 2008

 

11.0     New Proposals :

 

11.1     Integrated Aluminium Smelter Complex (3.25 LTPA & Primary Aluminium) alongwith coal based Captive Power Plant (750 MW) at Village Orgari, Bargawan, District Sidhi, Madhya Pradesh by M/s Hindalco Industries Ltd. (EC) 

 

The project authorities and their consultant gave a detailed presentation on the salient features of the project and proposed environmental protection measures to be undertaken as per Draft Terms of References (TORs) awarded during the 67th Meeting of the Expert Appraisal Committee (Industry) held during 4th–6th June, 2007 for preparation of EIA/EMP. All the Aluminium Smelter projects are listed at S.N. 3(a) under Primary Metallurgical Industry under Category ‘A’ and are to be appraised at the Central level.  

 

            PAs informed to the Committee that M/s Hindalco Industries Ltd.  have proposed to set up a green field Integrated Aluminium Smelter Complex (3.25 LTPA) alongwith coal based Captive Power Plant (5x150 MW; 750 MW) at at Village Bargawan, District Sidhi, Madhya Pradesh. Out of 2,025 ha, 18.80 ha of forest land will be surrendered. No forest land will be involved now but project will be located adjacent to forest.  Therefore, the project area will be 2,006.20 ha. PAs informed to the Committee that land acquisition is still in process.  Keeping the size of the proposal in mind, the Committee requested PAs to reassess the land requirement of 2006.20 ha. and efforts should be made to reduce the land requirement to 1,500 ha. in place of 2006.20 ha.

 

Proposal also involves rehabilation and resettlement of 1,750 families. PAs informed to the Committee that R & R Plan is prepared and submitted to the District Authorities. No national park, sanctuary or archeological green monuments exists within 25 Km radius of the site.  Mohanban RF (4 km WSW), Jiwan RF (5.5 km NNE), Muher RF (9.2 km SE), Pokhara RF (6.3 km NE), Orgari PF (0.2 km N), Majhigawan PF (7 km NNE), Teldah PF (4.6 km SE), Pachwar PF (9.9 km NNE), Gidher PF (2.7 km NW), Uska PF (6.3 km E), Lohara PF (4.5 km NNW), Bichhi PF (6.6 km N), Parihasi PF (4.6 km NNE) and Bori PF (7.8 km N) are located within 10 km radius of the proposed project site.  Total cost of the project is Rs. 7,700 Crores. Rs. 405.00 Crores for environmental management plan, Rs. 45.00 Lakhs towards total capital cost and Rs. 21.00 Lakhs are earmaked towards recurring cost/annum for environmental pollution control measures.

 

            Coal (3.5 MTPA) will be sourced from captive Mahan Coal Mines located at 25 km..  Alumina (631, 450 TPA) will be sourced from captive Alumina Refinery of Orissa (located at 200 km.) and U.P. and Utkal Alumina Ltd. C.P. Coke (120, 450 MTPA), Pitch (HSP, 29,200 TPA) and various others chemicals will be used as raw material. Alumina is dissolved in molten cryolite (bath) at 950 – 960OC and DC current is passed through molten electrolyte for the reduction of Alumina to form liquid Aluminium at the Catbode. O2 collects at anode de where it combines with carbon.  The process will be continuous in nature.

 

      Air quality monitoring was carried out at 8 locations and all the parameters like SPM (59.4-143.7 mg/m3), RPM (20.7-47.5 mg/m3), SO2 (6.1-10.2 mg/m3) & NOx (7.2-10.8 mg/m3) are within the permissible limits. Main source of air emissions will be Aluminium smelter and CPP particularly Pot Room, Anode baking furnace, cast house etc. Gas treatment centers (GTC) will be provided to treat the fumes coming out from pot line comprising of 336 pots.  Bag filters will be provided.  ESPs will be provided to CPP to control air emissions to 100 mg/Nm3. Closed Alumina wagon and dense phase conveying for Alumina handling will reduce fugitive emissions. High efficiency collection hoods, flue gas treatment plant and dry scrubbers will be provided to keep the Fluoride emissions below 0.7 kgs/ton from Anode bake oven. Internal roads will be paved/asphalted. Calcined petroleum based dry scrubber, dust suppression and collection system will be provided to Carbon paste plant. De-dusting system will be provided to control fugitive emissions.  Major pollutants will be HF, SO2, Spent pot lining.

 

            Total water requirement from River Gopad will be 4,600 m3/hr instead of 4,500 m3/day proposed earlier for Phase-I and the permission has been accorded by the Energy Department of Govt. of M. P.  Entire process effluent will be recycled after treatment. All the wastewater will be treated in ETP and treated wastewater will be used for dust suppression, green belt development and coal/ash handling. ‘Zero’ discharge will be adopted.  Domestic effluent will be treated in STP.

 

            Ash (1.4 MTPA) will be generated from CPP and will be prepared in high-density slurry from ash dyke. Flyash will be 100% utilized within 10 years from commissioning of operations. Aluminium Fluoride (5,475 TPA) will be used which is hazardous in nature.  Spent pot lining (SPL), Dross, waste oils and Grease will be recycled inhouse after appropriate treatment or disposed off to authorized vendors. All organic waste from plant and township will be composted to manure and used for afforestation. A secured landfill as per CPCB design will be constructed for disposal of SPL. ETP & STP sludge will be used as a soil conditions for green belt development.

 

                        Green belt will be developed in 602 ha out of 2006.20 ha of plant area but Committee asked to develop green belt in 33 % area.  Acoustic enclosures will be provided to control noise. 5 MW power will be sourced from MPSEB.  Total power requirement will be 549 MW. Captive Power Plant (750 MW = 5x150 MW) will be installed. Coal (3.4 MTPA) will be used as fuel in CPP.

 

The Committee deliberated upon the issues raised during the Public Hearing / Public Consultation meeting conducted by the M.P. Pollution Control Board (MPPCB) on 14th March, 2008. The major issues included R & R, electricity, water, medical, education, employment, compliance to pollution control etc. and have satisfactorily been incorporated in the final EIA/EMP report.

           

After discussion, the Committee desired submission of following information:

 

1.      Commitment that total land requirement shall not exceed 1,500 ha. 

2.      Material balance for achieving Fluoride emission as 0.7 kg/ton of Aluminium produced including accountable and nonaccountable Fluoride.

 

While the minutes were under preparation, PAs vide their letter dated 24th October, 2008 have submitted commitment for restricting the land acquisition to 1,500 ha. instead of 2025 ha. earlier proposed.

 

After detailed deliberations, the Committee found the final EIA/EMP report adequate and recommended project for according environmental clearance subject to stipulation of following specific conditions alongwith other environmental conditions after submission of above mentioned information which will be examined internally without calling PAs :

 

1.      Efforts should be made to reduce RSPM levels in the ambient air and a time bound action plan shall be submitted. On-line ambient air monitoring and continuous stack monitoring facilities for all the stacks and sufficient air pollution control devices should be provided to all the stacks including captive power plant to keep the emission levels below 100 mg/Nm3. 

2.      Particulate fluoride emissions should not be more than 0.65 mg/Nm3 and fugitive particulate fluoride emissions from pot room should not be more than 1.85 mg/Nm3.

2.      In plant, control measures for checking fugitive emissions from spillage/raw materials handling should be provided. Fluoride emissions should be monitored from the pot room and in the forage around the smelter complex and the data submitted regularly to the Ministry/ Regional Office at Bhopal and MPPCB.  Further dry scrubbing system to control the emissions from the pot lines should be provided. Total fluoride emissions should not exceed 0.7 kg/ton of Aluminium produced. Further, the pot emissions through fume treatment plant should not exceed 0.30 kg/ton of Aluminium produced. Fugitive fluoride emissions from the pot room should be monitored and report submitted regularly to the Ministry/Regional Office at Bhopal and MPPCB.

3.      The particulate emissions from the bake oven plant should not exceed 50 mg/Nm3.

4.      The company should install fume extraction system and bag filters to control the emissions from all melting and casting units. The emissions shall conform to the standards prescribed by the Ministry/CPCB/MPPCB which ever is more stringent.

5.      The poly-aromatic hydrocarbons (PAH) from the carbon plant (anode bake oven) should not exceed 2 mg/Nm3. The data on PAH should be monitored quarterly and report submitted regularly to the Ministry/Regional Office at Bhopal and MPPCB.

6.      Fluoride consumption shall be less than 10 kg/ton of Aluminium produced as specified by the CREP guidelines.  Accordingly, Fluoride emission load shall be reduced.

7.      Total water requirement should not exceed 4,600 m3/hr and prior permission from the drawl of 4,600 m3/hr water from river Gopad from concerned department should be obtained.  As reflected in the EIA /EMP, all the process effluent should be treated in the effluent treatment plant (ETP) and treated waste water should be recycled and reused to achieve ‘zero’ discharge. Domestic effluent should be treated in sewage treatment plant (STP).

8.      The spent pot lining generated from the smelter should be properly treated by setting up of spent pot lining treatment plant to remove fluoride and cyanide and disposed off in a secured landfill site.  The location and design of the landfill site should be approved by the MPPCB as per Hazardous Wastes (Management and Handling) Rules, 2003 and should be as per CPCB guidelines. The ground water quality around the landfill site should be monitored and data submitted to the Ministry/MPPCB. All the used oil and batteries should be sold to the authorized recyclers/reprocessors.

9.      Efforts should be made to find application and use of spent pot lining generated from the smelter.

10.  Proper utilization of fly ash should be ensured as per Fly ash Notification, 1999 and subsequent amendment in 2003.

11.  Green belt should be developed in 33 % area.

12.  Occupational Health Surveillance of the workers should be done on a regular basis and records maintained as per the Factories Act.

13.  The company should develop rain water structures to harvest the run off water for recharge of ground water in consultation with the Central Ground Water Authority/Board.

14.  Land acuisition for the proposed Integrated Aluminium Smelter Complex (3.25 LTPA & Primary Aluminium) alongwith coal based Captive Power Plant (750 MW) at Village Orgari, Bargawan, District Sidhi, Madhya Pradesh should not exceed 1,500 ha.

15.  As proposed, no forest land should be used.

16.  Rehabilitation and Resettlement should be implemented as per the R & R Policy of the State Govt. of Madhya Pradesh. Suitable employment to all the oustees should be provided. Compensation paid to the land oustees in any case shall not be less than the norms prescribed under the National Resettlement and Rehabilitation Policy, 2007.

17.  All the recommendations made in the Charter on Corporate Responsibility for Environment Protection (CREP) for the Aluminium sector should be strictly implemented.

18.  Recommendations of the State Forest Department regarding impact of the proposed expansion plant on the surrounding reserve forests viz. Mohanban RF (4 km WSW), Jiwan RF (5.5 km NNE), Muher RF (9.2 km SE), Pokhara RF (6.3 km NE), Orgari PF (0.2 km N), Majhigawan PF (7 km NNE), Teldah PF (4.6 km SE), Pachwar PF (9.9 km NNE), Gidher PF (2.7 km NW), Uska PF (6.3 km E), Lohara PF (4.5 km NNW), Bichhi PF (6.6 km N), Parihasi PF (4.6 km NNE) and Bori PF (7.8 km N) should be obtained and implemented.

19.  Measures shall also be taken to prevent impact of particulate emissions / fugitive emissions, if any from the proposed plant on the surrounding forest located within 10 km radius of the project.  Further, Conservation Plan for the conservation of wild fauna of Schedule I located in the forest/reserve forests in consultation with the State Forest Department shall be prepared and implemented.  

 

 

11.2     Expansion of Copper Smelter Plant (Phase–II) at SIPCOT Industrial Complex, Madurai Bypass Road, Tuticorin, Tamil Nadu by M/s Vedanta [Sterlite] Industries (India) Limited. (EC)                                     

 

The project authorities and their consultant gave a detailed presentation on the salient features of the project and proposed environmental protection measures to be undertaken as per Draft Terms of References (TORs) awarded during the 84th Meeting of the Expert Appraisal Committee (Industry) held during 19th-21ST August, 2008 for preparation of EIA/EMP.  All the Primary metallurgical industries have been kept at S.N. 3(a) under Primary metallurgical industry under category ‘A’.   

 

PAs informed to the Committee that M/s. Vedanta (M/s. Sterlite Industries (India) Limited) has proposed to set up a Copper Smelter Plant (Phase–II), SIPCOT Industrial Complex, Madurai Bypass Road, Tuticorin, Tamil Nadu.  The total land acquired from SIPCOT, Govt. of Tamil Nadu is 92.5 ha instead of 124 ha earlier mentioned. Gulf of Mannar National park is at a distance of 12 km in the North-East direction. Bay of Bengal is at a distance of 10 km in North–East and East direction. Thoothukkudi falls within the 15 km periphery of the proposed site.  Total cost of the proposed unit will be Rs. 2,400.00 Crores.  Rs. 465.00 Crores are earmarked for environmental protection measures.

 

The existing plant comprises of Copper smelter (1,200 TPD), Sulphuric acid plant (4200 TPD), Phosphoric acid plant (800 TPD), Refinery (875 TPD), Rod Plant (410 TPD). Another Copper smelter of capacity (1,200 TPD) will be installed in the proposed expansion.

 

PAs have earlier proposed that the main products from the proposed Copper smelter-II will be as follows:

 

S. No

Products

Proposed Production

Capacity (TPD)

I

Main Product

1

Copper anode

1200

2

Copper cathode (from anodes produced)

1200

3

Phosphoric acid

800

II

Intermediate Product

1

Anode slime (refinery)

7.20

III

By-Product

1

Sulphuric acid

4500

2

Ferro sand

3200

3

Gypsum

4000

4

Hydrofluro- Silicic acid

50

 

Now, PAs have informed that the following products will be manufactured from the proposed Copper smelter-II.

S. N.

Products

Proposed Production (TPD)

I

Main Product

1

Copper anode

1,200

2

Copper cathode

1,525

3

Phosphoric acid

800

4

Continuous Copper rod

800

II

Intermediate Product

1

Anode slime

3.0

2

Dore Metal

0.65

3

Selenium

1.2

4

Bismuth Bi-sulphate

1.8

5

Copper Telluride

0.6

6

Nickel Sludge

30

7

Nickel

1.5

III

By-Product

1

Sulphuric acid

4,500

2

Ferro sand

3,200

3

Gypsum

4,000

4

Hydrofluro- Silicic acid

50

 

PAs gave a detailed presentation of existing and proposed production details and is as follows:

 

S. N.

Products

Quantity (TPD)

Existing

Expansion

Total

I

Main Product

1

Copper anode

1,200

1,200

2,400

2

Copper cathode

875

1,525

2,400

3

Phosphoric acid

410

800

1,210

4

Continuous Copper rod

800

800

1,600

II

Intermediate Product

1

Anode slime

1.75

3.0

4.75

2

Dore Anode

--

0.65

0.65

3

Selenium

--

1.2

1.2

4

Bismuth Bi-sulphate

--

1.8

1.8

5

Copper Telluride

--

0.6

0.6

6

Nickel Sludge

--

30

30

7

Nickel

--

1.5

1.5

III

By-Product

1

Sulphuric acid

4,200

4,800

9,000

2

Ferro sand

2,400

3,000

5,400

3

Gypsum

3,200

4,200

7,400

4

Hydrofluro- Silicic acid

25

80

105

 

It is also informed that the environmental clearance has been accorded for all Intermediate products.

 

Main raw material for the production of Cu metal is Sulphidic Copper concentrate containing about 25-35% copper, 28-35% Sulphur, Iron 25-30% and 7-10% moisture. Raw materials required will be Copper concentrate, Furnace oil, Liquid Oxygen, Silica, Quartz, LPG, HSD, Limestone, Coke, Copper Anodes, Hydrochloric acid, Thio-urea, Glue, Lime, Caustic Lye, Ferric sulphate, Sodium sulphide, Flocculent, Sulphuric acid, Rock phosphate, Active Silica, Defoamer, Caustic lye solution.  

 

Copper anodes will be produced from the imported copper concentrates through pyro-metallurigical smelting process. The SO2 generated during the smelting of Cu will be converted into H2SO4 by Double Conversion Double Absorption (DCDA) process. Part of H2SO4 will be used for the production of Phosphoric acid from the imported rock phosphate using a Hemi-hydrate Di-Hydrate process.  The casted Cu anodes will be dispatched to the refinery unit for further electrolytic refining to about 99.99% purity. The major steps in Cu extraction will include:

 

1.      Blending of different grades of concentrates

2.      Smelting of concentrate in ISASMELT furnace to produce an intermediate copper rich product known as ‘matte’ containing 50-65% copper and eliminate Iron silicate (Ferro sand) by adding Silica.

3.      Converting liquid matte to blister copper (98-99% Cu) in a Pierce- Smith Converters (PS Converter).

4.       Fire refining of blister copper to produce anode copper (99.5% Cu) in anode furnace and casting of the anodes

5.      Electrolytic refining of anodes to produce copper cathodes (99.99% Cu)

 

In the process of extraction of Copper metal from Sulphidic concentrates, Sulphuric acid will be recovered as a by-product from smelter & furnace.

 

WHRB will be provided to ISA. ESP will be provided to WHRB. ESP dust will be recycled back into ISA furnace. The primary gas from the ISA smelter and converter will be sent to proposed Sulphuric acid plant. Fugitive emissions from rotary holding furnace, secondary emissions from converter will be connected to the scrubber followed by a stack (175 m) provided to Smelter, Sulphuric acid plant and various other furnaces. Stack of height 60 m will be provided to the Phosphoric acid plant. Multi-stage scrubbing system will be installed to treat the secondary gases from smelter particularly Fluorine.  Existing air emission from the Sulphuric acid plant is 1 kg/T of Sulphuric acid produced.

 

Total water requirement for the existing smelter is 1.7 MGD and for proposed smelter is revised from 1.8 MGD to 2.4 MGD and will be sourced from Tamirabarani River and supplied by TWAD board through dedicated pipelines. In addition, Desalination plant (5,000 m3/day) now revised to 10,000 m3/day capacity will be installed to meet peak demands.  During presentation, PAs informed that existing water requirement of 1.8 MGD will be supplied from TWAD board. Proposed expansion requires 2.25 MGD of water, which will be supplied from Desalination Plant.  Existing water consumption is 5.9 m3/T of product. 

 

 The entire wastewater generated will be treated and reused. The liquid effluent generated from Sulphuric acid plant, Refinery section will be reused in the plant after treatment. The other effluents generated from Phosphoric acid, cooling towers, boiler blow down and ETP raw water does not require any treatment for reuse/recycle. Similarly, the scrubbers bleed off, which is in slurry form and will be filtered for solids only.  Gas cleaning effluent and secondary gas scrubber effluent will be treated in ETP. ‘Zero discharge’ will be adopted. Domestic effluent will be treated in sewage treatment plant (STP) and the treated water will be used for green belt. Leachates are also collected and used in the process. Regarding ground water quality, it is observed that Ph and Fluoride levels are high.

 

Scrap from stores / workshop will be sold to authorized recyclers. Lime grit generated from Milk of Lime preparation plant will be recycled back into ISA furnace in place of flux material. ETP cake, ETP slime, Spent Catalyst, Scrubber cake, Resin from Bismuth plant and toxic metal containing residue from Ion exchange material in water purification will be stored in secured land fills designed as per CPCB guidelines. ESP, WHRB and Gas coolers dust will be recycled back into Smelter. Metal slag from TROF converted of DORE process will be recycled to smelter. Regarding storage of gypsum, PAs informed to the Committee that out of 52 Lakhs, 42 Lakhs gypsum is already dispatched to the concerned organizations and remaining 10Lakhs will be sent in 2009.  Spent oil, oil sludge and non-ferrous scrap will be sold to CPCB registered recyclers.

 

During presentation, PAs informed that 39.35 ha of land will be afforested in addition to existing 33 ha. green belt.  Proper noise, vibration and heat arrester will be provided at the generation point itself. Vibration isolators will be provided to all ID fans and Compressors. Personal Protective equipment will be ensured in high noise areas.  Total power requirement will be 60 MW and sourced from existing CPP (120 MW). Now, PAs informed that an additional cpp (75 MW) will be required for proposed expansion. Fuels required for the proposed unit will be LPG, HSD, Fuel oil and Coke.

 

PAs informed to the Committee that environmental clearance was accorded for the the Copper Smelter Plant (Phase–II) at SIPCOT Industrial Complex, Madurai Bypass Road, Tuticorin, Tamil Nadu and may be kept in abeyance since further expansion will be carried out in the existing and new area acquired in the near vicinity. Part of the new area acquired will be overlapping. PAs have requested for the use of data for EIA/EMP collected in 2006-07 (Winter season) and exemption from public hearing due to location in notified SIPCOT industrial estate.  The Committee agreed for the use of same data as well as exemption for public hearing as per Section (iii), Stage (3), Para (i)(b) of EIA Notification, 2006 due to location of the project in notified SIPCOT.

 

After detailed deliberations, the Committee agreed for the exemption for public hearing as per Section (iii), Stage (3), Para (i)(b) of EIA Notification, 2006 due to location of the project in notified SIPCOT.  The Committee found the final EIA/EMP report inadequate and observed that :

 

1.      Data presented regarding continuous ambient air quality monitoring appears to be improper since minimum value can not be ‘zero’ and suggested to recheck the data.  The committee also desired submission of the existing ambient air, stack emission and fugitive emission data collected by TNPCB, approved laboratory and PAs own data generated in their lab.

2.      SO2 values also momentarily go high which PAs were unable to explain.

3.      NOX values are also high.

4.      Ground water quality monitoring data was also not satisfactory.

 

Based on the unsatisfactory explanation, the Committee desired that PAs should submit the above mentioned data which will be reconsidered by the Committee as and when submitted. The proposal is differed till the above information is submitted.

 

 

11.3     Expansion of Sponge Iron Plant into Steel Plant (2.00 MTPA) alongwith Captive Power Plant (25 MW) at Komando, Sundergarh, Orissa by M/s Rungta Mines Ltd. (EC)                                     

 

The project authorities and their consultant gave a detailed presentation on the salient features of the project and proposed environmental protection measures to be undertaken as per Draft Terms of References (TORs) awarded during the 67th Meeting of the Expert Appraisal Committee (Industry) held during 4th–6th June, 2007 for preparation of EIA/EMP. All the steel plants are listed at S.N. 3(a)(a) under Primary Metallurgical process and is appraised at Central level.   

 

            PAs informed to the Committee that M/s Rungta Mines Ltd. have proposed for the expansion of existing DRI Plant (0.270 MTPA) to expand as per details given below:

 

Plant/facility

Product

Capacity

DRI Plant (3x350 TPD kilns)

Sponge iron

3,15,000 TPA

Mini blast furnace (2x262 m3)

Hot metal

3,82,520 TPA

Steel melting shop, comprising

  • Induction furnace (4x15 T)
  • Ladle furnace (2x15 T)
  • Billet caster (2x2 strand)

 

Steel billets

2,00,000 TPA

WHR based CPP

Electricity

42 MW

Coal based CPP

Electricity

25 MW

 

            Total project area is 154.489 ha. and 72.59 ha land is in the process of acquisition.  Total cost of the project is Rs. 1,119.50 Crores.  Rs. 28.34 Crores and Rs. 12.35 Crores are earmarked towards capital cost and recurring cost/annum for environment pollution control measures.

 

      Iron ore, coal, coke, Dolomite/limestone, Silico-Manganese, Scrap iron, Quartzite, HSD and LDO will be used as raw material.

 

      PAs informed to the Committee that proposed plant will produce mild steel and finished steel through DRI/BF-IF-LRF-CCM route. Iron ore (lumps or pellets) will be reduced by heating with carbonaceous material e.g. coal in a Rotary kiln at 1,0000C.  After reduction, product will be cooled, separated into sponge iron and char by magnetic separation. Scrap/Sponge Iron/pig iron will be melted in SMS in presence of Silico-Manganese. Ferro alloys and additives will be heated in Ladle refining furnace. Billet caster will be produced in continuous casting machine.  Hot metal will be produced in mini blast furnace by converting iron oxides into ingot metal. Only billets will be manufactured and no long structures will be manufactured.  WHRB & FBC based power plant will be installed.

 

      Ambient air quality was monitored during March to May, 2005 at 5 locations  and data submitted indicated SPM (91 - 166 ug/m3), RPM (28 - 50 ug/m3), SO2 (5.6 – 12.8 ug/m3), NOx levels (8.6 – 18.0 ug/m3) and  are within the permissible limit. Flue gas from Rotary kiln will pass through dust settling chamber to settle the dust.  The gas will pass through after Burning Chamber (ABC) and used in WHRB to generate power.  ESPs will be provided to DRI kilns, WHRB and FBC boilers to control air emissions to 100 mg/Nm3.  Dust collected from ESP though hopper will be sent to ash silo by pneumatic conveying system.  Dust collected from ESP through happen will be sent to ash silo by pneumatic conveying system.  Dust extraction system consisting of suction hood, cyclones wet scrubber etc. with dusts will be presided to control fugitive emissions in kiln inlet area, crushing unit, cooling outlet area to suppress SPM level below 50 mg/Nm3 from the induction furnace of SMS.  FE system and cleaning system consisting of bag filters I.D. fans etc.  will be provided to the  Ladle furnace to control dust  less than 50 mg/Nm3.  Wet scrubber will be provided to BF to control emission to 50 mg/Nm3.

 

            Total water requirement from Karo river or bore wells will be 10,345 m3/day instead of 80,780 m3/day earlier proposed.  ‘Permission’ for the drawl of 10,345 m3/day from Karo River & bore wells from the SGWB/CGWA/Concerned Department is yet to be obtained and submitted. Water will be stored in reservoir and subjected to clarification, sludge settling and gravity filtration.  Wastewater from cooling tower blow down, DM Plant wastewater and service water effluent will be used for dust suppression and ash handling.  Wastewater from boiler blow down and pre-treatment wastewater will be utilized for horticulture and green belt development.  Domestic effluent will be treated in septic tanks followed by soak pits.

 

            Fly ash (81,900 TPA) generated by the FBC Power Plant will be used by cement and brick manufacturing.  12 acre area is earmarked for the disposal of solid waste of the integrated steel complex. Waste oil and lubricant (50 KLPA) will be generated as hazardous waste and sold to recyclers.  Dolochar (89,100 TPA) will be used in FBC boiler.  Kiln accretions (3,000 TPA) will be used in FBC boiler.  Kiln accretions (3,000 TPA) will be generated.  MBF slag (74,571 TPA) will be given to cement manufacturers.  EAF & CRF slag (15,000 TPA) will be used for village road construction.  DM plant resin (2 KLPA) will be disposed off in pit.

 

            Out of 47.289 ha. 16.30 ha (34.47%) is earmarked for the green belt development.

 

            Acoustic enclosures and silencers will be provided.  Total power requirement will be 40 MW which will be met from Captive Power Plant.  5 DG sets of 2500 KVA each will also be installed.  SEB will provide 33/11 KV electricity to the plant till CPP is installed.  Coal will be used as fuel for the reduction in the kiln as  well as CPP.  HSD (3450 l/day) will be used as fuel for DG sets.  LDO (10 l/day) will be used for start up CPP.  Char will be used as fuel in FBC-CPP.

 

The Committee deliberated upon the issues raised during the Public Hearing / Public Consultation meeting conducted by the Orissa State Pollution Control Board on 25th June, 2008. The issues like employment, air pollution, health, irrigation, water supply, ITI establishment were discussed and have satisfactorily been incorporated in the final EIA/EMP report. PAs also informed that Rs. 17.46 Lakhs are spent to implement various issues raised and Rs. 15.40 Lakhs are kept for 2008-09.

           

            After detailed deliberations, the Committee found the final EIA/EMP report adequate and suggested to stipulate following specific conditions alongwith other environmental conditions while considering for accord of environmental clearance :

 

  1. Efforts should be made to reduce RSPM levels in the ambient air and a time bound action plan should be submitted. On-line ambient air quality monitoring and continuous stack monitoring facilities for all the stacks and sufficient air pollution control devices should be provided to keep the emission levels below 100 mg/Nm3. 
  2. Hot gases from DRI kiln should be passed through Dust Settling Chamber (DSC) to remove coarse solids and After Burning Chamber (ABC) to burn CO completely and used in waste heat recovery boiler (WHRB).  The gas then should be cleaned in ESP before leaving out into the atmosphere through ID fan and stack.  Electrostatic precipitator (ESP) should be provided to DRI plant, WHRB and ABC boilers to control air emissions. Gas cleaning plant having dust catcher and bag filter should be provided to blast furnace (BF).  
  3. Gaseous emission levels including secondary fugitive emissions from blast furnace and sinter plant should be controlled within the latest permissible limits issued by the Ministry and regularly monitored. Guidelines / Code of Practice issued by the CPCB should be followed. The emission standards issued by the Ministry in May, 2008 for the sponge plants should be followed.
  4. Vehicular pollution due to transportation of raw material and finished product should be controlled.  Proper arrangements should also be made to control dust emissions during loading and unloading of the raw material and finished product.
  5. Prior permission for the drawl of 10,345 m3/day water from Karo River and bore wells from the concerned department should be obtained.
  6. The water consumption should not exceed 16 m3/Ton of Steel as per prescribed standard.
  7. Ground water monitoring around the solid waste disposal site / secured landfill (SLF) should be carried out regularly and report submitted to the Ministry’s Regional Office at Bhuvaneswar, CPCB and OPCB.
  8. All the char and kiln accretions should be used in AFBC based power plant.  All the blast furnace (BF) slag should be granulated and provided to cement manufacturers for further utilization. SMS slag should be properly utilized.  All the other solid wastes including broken refractory mass should be properly disposed off in environment-friendly manner. Oily waste should be provided to authorized recyclers/reprocessors.
  9. AFBC Plant and AFBC boiler should be installed simultaneously so the proper utilization of char in the AFBC boiler is ensured and no char is disposed off anywhere else.
  10. A time bound action plan should be submitted to reduce solid waste, its proper utilization and disposal.
  11. Proper handling, storage, utilization and disposal of all the solid waste shall be ensured and regular report regarding toxic metal content in the waste material and its composition, end use of solid/hazardous waste should be submitted to the Ministry’s Regional Office at Bhuvaneswar, OPCB and CPCB. 
  12. Proper utilization of fly ash should be ensured as per Fly ash Notification, 1999 as amendment in 2003.
  13. As proposed, green belt should be developed in 33 % area.
  14. All the recommendations made in the Charter on Corporate Responsibility for Environment Protection (CREP) for the Steel Sector should be implemented.
  15. As committed during public hearing, Rs. 2.00 Crores shall be earmarked for setting of Industrial Training Institute (ITI) in consultation with the State Govt. and progress should be reported to the Ministry’s Regional Office at Bhuvaneswar.

 

 

11.4     Expansion of Sponge Iron Plant (60,000 TPA to 90,000 TPA) and installation of Captive Power Plant (12 MW; 6MW AFBC & 6 MW WHRB) at Sy. No. 899 & 900, Haraginadoni Road, Veniveerapura Cross, Kudathini Village, Bellary Taluka and District, Karnataka by M/s Agarwal Sponge  & Energy Pvt. Ltd. (EC)

 

The project authorities and their consultant gave a detailed presentation on the salient features of the project and proposed environmental protection measures to be undertaken as per Draft Terms of References (TORs) awarded during the 73rd Meeting of the Expert Appraisal Committee (Industry) held during 24th–26th October, 2007, 2008 for preparation of EIA/EMP.  All the Sponge Iron Plants with > 200 TPD Sponge Iron Plant are kept under Primary Metallurgy Industries under S.N. 3(a) under Category ‘A’.  Since total capacity of the sponge iron plant is 300 TPD, proposal is appraised at Central level.   

 

            PAs informed to the Committee that M/s Agarwal Sponge & Energy Pvt. Ltd. have proposed for the expansion of Sponge Iron Plant (60,000 TPA to 90,000 TPA) and installation of Captive Power Plant (12 MW; 6MW AFBC & 6 MW WHRB) at Sy. No. 899 & 900, Haraginadoni Road, Veniveerapura Cross, Kudathini Village, Bellary Taluka and District, Karnataka.  Total project area is 20 acres. Total cost of the project is Rs. 54.72 Crores.  Rs. 4.00 Crores instead of Rs. 5.00 Crores and Rs. 10-15 Lakhs proposed earlier will be earmarked towards capital cost and recurring expenditure/annum for environment pollution control measures.

 

            Lump Iron ore (51,000 TPA), Coal (40,000 TPA) and limestone (1,500 TPA) will be used as raw materials.  Direct Reduced Iron (DRI) method will be used for the reduction of iron ore or pellets in the solid state i.e. without the material going into the liquid phase which is conventional route for converting iron ore into iron) which contains 90% metal and some amount of unreduced iron vide and the gangue in the ore.  The iron oxide of the ore will be reduced to metallic iron by CO generated inside the kiln at 1000oC. It is mentioned that existing plant was for 3 x 100 TPD kilns and hence virtually no expansion will be carried out.

 

          Air quality monitoring was carried out at 8 locations and data submitted indicated SPM,  RPM,  SO2, NOx & CO within permissible limits.  The off gases from the rotary kiln e.g. LO, SO2, Carbon particles, fines of iron ore, coal and limestone will be burnt in After Burning Chamber (ABC).  Then, gaseous emissions will be treated in gas cleaning Plant, ESP and passed through stack.

 

            Total ground water requirement will be 350 m3/day instead of 30,000 l/day earlier proposed.  CGWA has informed that proposal is not located in the critically polluted area. All the treated wastewater will be used for cooling purpose and no water pollution is anticipated since most of the water will be evaporated.  Domestic wastewater will be treated in Sewerage Treatment Plant and used for green belt development.

 

            Char will be used in fluidized bed combustion boiler (FBC). Fly ash, sludge from wet scrubber and bag filter dust will be sold to cement and brick manufacturers.  

 

Out of 20 acre, 6.6 acre is earmarked for green belt development. Acoustic enclosures will be provided.  11 KV power is presently sourced from KEB and 500 KVA will be required.  One more DG set (750 KVA) will be installed.  Waste heat gases of the kiln will be used in WHRB Plant.  LDO/ HSD will be used as fuel for initial start up.

 

The Committee deliberated upon the issues raised during the Public Hearing / Public Consultation meeting conducted by the Karnataka State Pollution Control Board on 27th June, 2008. The issues raised included providing medical, water, electricity, compensation, employment and improvement in roads etc. have satisfactorily been incorporated in the final EIA/EMP report.

           

            After detailed deliberations, the Committee found the final EIA/EMP report adequate and suggested to stipulate following specific conditions alongwith other environmental conditions while considering for accord of environmental clearance :

 

  1. Efforts should be made to reduce RSPM levels in the ambient air and a time bound action plan should be submitted. On-line ambient air quality monitoring and continuous stack monitoring facilities for all the stacks and sufficient air pollution control devices should be provided to keep the emission levels below 100 mg/Nm3.
  2. Hot gases from DRI kiln should be passed through Dust Settling Chamber (DSC) to remove coarse solids and After Burning Chamber (ABC) to burn CO completely and used in waste heat recovery boiler (WHRB).  The gas then should be cleaned in ESP before leaving out into the atmosphere through ID fan and stack.
  3. Secondary fugitive emissions from blast furnace and sinter plant should be controlled within the latest permissible limits issued by the Ministry and regularly monitored. Guidelines / Code of Practice issued by the CPCB should be followed. The emission standards issued by the Ministry in May, 2008 for the sponge plants should be followed.
  4. Vehicular pollution due to transportation of raw material and finished product should be controlled.  Proper arrangements should also be made to control dust emissions during loading and unloading of the raw material and finished product.
  5. Prior permission for the drawl of from 350 m3/day from the State Ground Water Board /Central Ground Water Authority (SGWB/CGWA) should be obtained.
  6. All the char from existing and proposed DRI plant should be utilized in AFBC boiler of power plant and no char should be disposed off anywhere else. AFBC boiler should be installed simultaneously alongwith the DRI plant to ensure full utilization of char from the begning. All the other solid / hazardous waste generated shall be properly utilized or disposed off in environment friendly manner.
  7. Proper utilization of fly ash should be ensured as per Fly ash Notification, 1999 and subsequent amendment in 2003. All the fly ash should be provided to cement and brick manufacturers for further utilization and bottom ash should be used for land filling. 
  8. Green belt should be developed in 33 % area.
  9. All the recommendations made in the Charter on Corporate Responsibility for Environment Protection (CREP) for the Steel Sector should be implemented.
  10. As committed, a hospital in collaboration with other should be established for the general benefit of the public. A note on the MOU signed with others, their share for the establishment of hospital, facilities to be provided, staff and time required for the establishment of the same etc. should be submitted to the Ministry and its Regional Office at Bangalore.

 

 

11.5     Expansion of Integrated Steel Plant, Coal Washery (1.5 MTPA) and Captive Power Plant (200 MW) at Rengeli, Sambalpur Forest Division, Sambalpur, Orissa by M/s Shyam DRI Power Ltd. (EC)

 

The project authorities and their consultant gave a detailed presentation on the salient features of the project and proposed environmental protection measures to be undertaken as per Draft Terms of References (TORs) awarded during the 64th Meeting of the Expert Appraisal Committee (Industry) held during 28th-30th March, 2007 for preparation of EIA/EMP.  All the Integrated Steel Plants have been kept in Category ‘A’ and appraised at the Central level. 

 

      PAs informed to the Committee that M/s Shyam DRI Power Ltd. have submitted a proposal for the expansion of Integrated Steel Plant at Rangeli, Sambalpur Forest Division, Sambalpur, Orissa. PAs have proposed to install 1.0 MTPA Coal Washery, 0.6 MTPA Sponge Iron, 0.7 MTPA Pig iron, 0.6 MTPA Coke Oven, 0.6 MTPA Pelletization with steel making and ferro-alloy making facilities and 100 MW Captive Power Plant.  Now, it is proposed to revise coal washery to 15,00,000 MTPA and CPP to 200 MW capacity as per details given below:

 

S.N.

 

Existing Production (MTPA)

Proposed Production (MTPA)

1.

Sponge Iron

2,00,000

6,00,000

2.

Billet

2,00,000

-

3.

Bars

60,000

-

4.

Sinter

--

8,82,000

5.

Pig iron

-

7,87,000

6.

Ferro alloy

-

1,05,000

7.

Steel making

-

11,75,000

8

Coke oven

-

6,00,000

9

Pellet

-

3,00,000

10

Coal washery

3,00,000

15,00,000

11

Power (WHRB) (MW)

25

200

 

During presentation, PAs informed that following will be the capacity of the existing and proposed production:

 

S.N.

Shop

Existing Production (TPA)

Proposed Expansion

(TPA)

Ultimate

Capacity

(TPA)

1.

Sponge Iron

2,00,000

6,00,000

8,00,000

2.

Billet Caster

2,00,000

-

2,00,000

3.

Rolling Mill

60,000

6,00,000

6,60,000

4.

Sinter plant

-

8,82,000

8,82,000

5.

Blast furnace

-

7,42,500

7,42,500

6.

Ferro alloy

-

2,50,000

2,50,000

7.

SMS

2,10,000

12,34,286

14,44,286

8

Coke oven

-

5,50,000

5,50,000

9

Pelletization & beneficiation plant

-

3,00,000

3,00,000

10

Coal washery

3,00,000

15,00,000

18,00,000

11

Power (MW)

25

200

225

12

Bloom caster

-

3,53,500

3,53,500

13

Lime plant

-

60,000

60,000

 

            The proposed expansion will be carried out in Sambalpur Forest Division in Gramaya Jungle.  Debrigarh Sanctuary and 22 Reserve Forests are located within 25 km. of the project site. PAs also informed that Stage I clearance for the 38.393 ha forest land is obtained and 12.076 ha forest land is still in the process with the State Govt. of Orissa for the approval of the forest land. A letter from the State Forest Department is also submitted indicating that proposed land does not come under National Park, Wildlife Sanctuary, Elephant corridor etc. Total area of the project is revised from 65.175 ha to 294.84 ha.  Total cost of the project proposed earlier as Rs. 1331.00 Crores has been revised to Rs. 2,026.00 Cr and again revised to Rs. 3,868.00 Crores.

 

      Iron ore DRI grade, Iron ore BF grade, limestone, lime, dolomite, coking coal, non coking coal, Manganese ore, Quartzite, Aluminium, Electrode and refractory will be used as raw material.

 

PAs informed to the Committee that manufacturing of steel will involve reducing iron ore to iron by the use of reductant like coal / coke. The iron will be processed through the EAF/induction furnace to produce steel.  The steel than will be purified to different grades and rolled to various sections/sizes as per the requirement.  Pig Iron will be produced in two blast furnaces.  Coke oven plant, sinter plant and pelletization plant will be installed as ancillaries to charge the Blast furnace and produce 0.7 MTPA hot metal and then transferred to EAF for steel making.  Sponge iron (0.6 MTPA) will be produced in rotary kiln out of which 0.385 MTPA sponge iron will be used in EAF and 0.215 MTPA Sponge iron will be used in EAF and 0.215 MTPA in induction furnace alongwith scrap for the production of stainless steel. Coal washery (0.6 TPA) will be installed to meet the annual requirement of coal of DRI kilns. Ferro alloys like SiMn, FeMn & FeCr will also be manufactured.  FeCr will be used to manufacture stainless  steel.

 

 Gases and solid fuels generated during the process of iron and steel making generated as by products will be used to generate power.  Captive power plant of 4x25 MW (100 MW) will be installed to generate electric power from byproduct gases. 

 

      Air quality monitoring was carried out at 8 locations during Nov. 2007-Jan 2008 and the parameters are found to vary in the following range: SPM (79.4-162.1 mg/m3), RSPM (16.31-49.5 mg/m3), SO2 (7-16.5 mg/m3) & NOx (7-18.5 mg/m3). Dust suppression arrangement like dense fog system, water sprinkling system will be provided at raw material handling areas. Ash conditioners will be installed to avoid fugitive ash dust pollution at loading and transport points. Dust collectors at crushers, transfer points of conveyors, raw material and coal yard. Dust extraction system comprising of suction hood, duct, ESP, fan, stack etc. will be provided to DR kiln, Sinter plant and Blast furnace. Dust extraction system comprising of suction hood, duct, bag filters, fan, stack etc. will be provided to Induction Furnace, DRI screening section and coal crushing & screening section. Dust suppression with water sprinkling will be provided to control secondary emissions.

 

Total water requirement from Hirakud reservoir for proposed expansion will be 3,238 m3/hr. instead of 2,050 m3/hr. earlier proposed.  Permission has been accorded by the Upper Mahanadi Basin, Burla for the drawl of 6 MGD water from the Hirakud Reservoir vide letter dated 21st October, 2005. The wastewater from the treatment plant and DM plant will be neutralized and used for pumping ash to ash pond from power plant. Purge water will be used for dust control and gardening. The effluent generated from cooling etc. will be completely recycled and reused and will not be discharged outside the premises.  The effluent generated from the After Burning Chamber (ABC) will be treated in settling tanks and recycled.  Blow down water from clean water circuit will also be used for road sprinkling and gardening.  Close circuit cooling system will be adopted.  Due to adoption of dry quenching, no phenolic treatment of liquid effluent from coke oven plant in BOD plant is required. Zero discharge will be adopted. Domestic effluent will be treated by septic tank followed by soakpit.

 

            All the solid waste generated will be disposed off within the premises or any other designated area after prior approval from the OSPCB.  Slag from blast furnace will be granulated and will be provided to cement manufacturers. Coal washery middlings will be used as a fuel in the boiler. Dust from dedusting plant of Sinter plant and Pellet plant will be recycled to Sinter plant and Blast Furnace respectively. Bag house dust from SMS will be recycled to Sinter plant. Char from Sponge Iron plant will be used in FBC boiler as fuel. Slag from SMS and Ferro alloy plant will be used for road making and land filling, respectively. Dust from Coke oven, rejects from Coal washery will be used for land filling. Fly ash will be provided to Cement and brick manufacturers. Garland drain will be provided around the waste dump area.

 

            Out of 146.61 ha. 43.406 ha. was earlier proposed for the green belt development. During presentation, PAs informed that Out of 294.84 ha, 97.297 ha. will be used for green belt development.           Acoustic enclosures and silencers will be provided to noise generating sources. 25 MW captive power plant is existing and is proposed to install 100 MW CPP during expansion of the project.   2.0 MTPA coal will be used as fuel for generating electricity.

 

                        ‘Consent to Establish has been accorded by the Orissa Pollution Control Board vide letter no. 11175/Ind-II-NOC-2301 dated 16th May, 2006.

 

The Committee deliberated upon the issues raised during the Public Hearing / Public Consultation meeting conducted by the Orissa Pollution Control Board on 21st May, 2008. The major issues included plantation, installation of Air Pollution control system, drinking water supply, no disposal of waste water outside the premises, provision of ambulance, employment, ITI training institute etc. have satisfactorily been incorporated in the final EIA/EMP report.

           

It has been brought to the knowledge of the Ministry by the Regional Office at Bhuvaneshwar that capacity of the coal washery is enhanced from 1.0 to 1.5 MTPA, Captive Power Plant from 100 MW to 200 MW and Ferro Alloy Plant (0.05 MTPA) is also installed changing scope of the project. PAs clarified that all the above mentioned items have been included in the proposed steel plant. Regarding construction of rolling mill, PAs clarified that rolling mill construction is related to the existing plant and no work related to the expansion is started so far.

 

            After detailed deliberations, the Committee found the final EIA/EMP report adequate and suggested to stipulate following specific conditions alongwith other environmental conditions while considering for accord of environmental clearance :

 

  1. Efforts should be made to reduce RSPM levels in the ambient air and a time bound action plan should be submitted. On-line ambient air quality monitoring and continuous stack monitoring facilities for all the stacks for SPM, RSPM, SO2, NOx, CO and B(a)P and sufficient air pollution control devices should be provided to keep the emission levels below 100 mg/Nm3. 
  2. Hot gases from DRI kiln should be passed through Dust Settling Chamber (DSC) to remove coarse solids and After Burning Chamber (ABC) to burn CO completely and used in waste heat recovery boiler (WHRB).  The gas then should be cleaned in ESP before leaving out into the atmosphere through ID fan and stack. Electrostatic precipitator (ESP) should be provided to DRI plant, WHRB and ABC boilers to control air emissions. Pushing emission control system in the coke oven should be adopted. Gas cleaning plant having dust catcher and bag filter should be provided to blast furnace (BF).  
  3. Gaseous emission levels including secondary fugitive emissions from blast furnace and sinter plant should be controlled within the latest permissible limits issued by the Ministry and regularly monitored. Guidelines / Code of Practice issued by the CPCB should be followed. The emission standards issued by the Ministry in May, 2008 for the sponge plants should be followed.
  4. Vehicular pollution due to transportation of raw material and finished product should be controlled.  Proper arrangements should also be made to control dust emissions during loading and unloading of the raw material and finished product.
  5. All the standards prescribed for the coke oven plants should be followed as per the latest guidelines. Proper and full utilization of coke oven gases in power plant using waste heat recovery steam generators should be ensured and no flue gases shall be discharged into the air.
  6. As proposed, dry coke quenching method should be adopted in the proposed non-recovery type of the coke oven.
  7. Prior permission for the drawl of 3,238 m3/hr water from Hirakud reservoir from the concerned department should be obtained.
  8. The water consumption should not exceed 16 m3/Ton of Steel as per prescribed standard.
  9. The wastewater from BF-GCP and coal washery should be treated in thickener and used in the process.  Acidic and Alkaline effluent from DM water plant should be neutralized and reused in the plant through ash pond.  All the wastewater from process and domestic sources should be treated and recycled and reused. No wastewater should be discharged outside the premises and ‘Zero’ effluent discharge should be ensured.
  10. Continuous monitoring of Total Organic Compounds (TOC) should be done at the outlet of ETP. 
  11. Ground water monitoring around the solid waste disposal site / secured landfill (SLF) should be carried out regularly and report submitted to the Ministry’s Regional Office at Bhuvaneswar, CPCB and OPCB.
  12. DRI Fines, Coke breeze, Sinter dust, GCP dust, SMS dust, Scale, Iron ore fines should be used in Sinter Plant.  Char, coal washery rejects and middling should be used in AFBC based power plant.  All the blast furnace (BF) slag should be granulated and provided to cement manufacturers for further utilization. SMS slag should be properly utilized. All the other solid wastes including broken refractory mass should be properly disposed off in environment-friendly manner. Oily waste should be provided to authorized recyclers/ reprocessors.
  13. AFBC Plant and Sponge Iron Plant should be installed simultaneously so that utilization of char in the AFBC boiler is ensured no char should be disposed off anywhere else.
  14. A time bound action plan should be submitted to reduce solid waste, its proper utilization and disposal.
  15. Proper handling, storage, utilization and disposal of all the solid waste shall be ensured and regular report regarding toxic metal content in the waste material and its composition, end use of solid/hazardous waste should be submitted to the Ministry’s Regional Office at Bhuvaneswar, OPCB and CPCB. 
  16. Proper utilization of fly ash should be ensured as per Fly ash Notification, 1999 as amendment in 2003.
  17. As proposed, green belt should be developed in 33 % area.
  18. All the recommendations made in the Charter on Corporate Responsibility for Environment Protection (CREP) for the Steel Sector should be implemented.
  19. Measures shall be taken to prevent impact of particulate emissions / fugitive emissions, if any from the proposed plant on the surrounding reserve forests located within 10 km radius of the project. Further, Conservation Plan for the conservation of wild fauna in consultation with the State Forest Department shall be prepared and implemented.
  20. Prior permission and recommendations of the National Board of Wildlife and Chief Wild Life Warden regarding impact of the existing and proposed plant on the Debrigarh Sanctuary should be obtained and implemented. If at the time of collection of data and assessing the impact, it is observed that the wildlife animals are falling in the downwind direction and there is impact, necessary mitigation measures suggested should be implemented.
  21. No construction work on the forest land should be started before obtaining prior forest clearance under the Forest (Conservation) Act, 1980 and subsequent amendments.
  22. As committed, Rs. 2.00 Crores shall be earmarked for setting up of Industrial Training Institute (ITI) in consultation with the State Govt. and progress should be reported to the Ministry’s Regional Office at Bhuvaneswar.

 

 

11.6     Expansion of Ferro Alloy Plant (18,000 to 36,000 TPA), Bloom & Billet (1,29,000 to 3,09,000 TPA), Captive Power Plant (38 to 61 MW) and installation of Rolling Mill (2,16,000 TPA) at Village Sonkara & Sondra, Siltara Industrial Growth Centre, District Raipur, Chhattisgarh by M/s Vandana Global Ltd. (EC) 

 

The project authorities and their consultant gave a detailed presentation on the salient features of the project and proposed environmental protection measures to be undertaken as per Draft Terms of References (TORs) awarded during the 73rd Meeting of the Expert Appraisal Committee (Industry) held during 24th–26th October, 2007 for preparation of EIA/EMP.  All the structural rolling mill are covered under 3(a) under Category ‘A’ and Ferro Alloy Induction furnace and CPP (33 MW) under category ‘B’ and is to be appraised at the Central level for Category ‘B’ portion also due to absence of SEAC/SEIAA at the State level. 

 

            PAs informed to the Committee that M/s Vandana Global Ltd. have proposed for the expansion of Ferro Alloy Plant (18,000 to 36,000 TPA), Bloom & Billet (1,29,000 to 3,09,000 TPA), Captive Power Plant (38 to 71 MW) and installation of Rolling Mill (2,16,000 TPA) at village Sonkara & Sondra, Siltara Industrial Growth Centre, Siltara, District Raipur, Chhattisgarh as per details given below :

 

S.N.

Details

Capacity (TPA)

Existing

Proposed

Total

1

Induction Furnace

1,29,000

1,80,000

3,09,000

2

Ferro Alloy Plant

18,000

18,000

36,000

3

Rolling Mills

-

2,16,000

2,16,000

4

Captive Thermal Power Plant

38 MW

33 MW

71 MW

5.

Sponge Iron Plant

2,16,000

-

2,16,000

 

However, the Committee noted that no coal based sponge iron plant is proposed but coal based captive power plant is proposed which are banned by the State Govt. in Siltara, C.G. and asked PAs to withdraw coal based CPP from the proposal until and permission is accorded by the Chhattisgarh Govt.  Revised configuration will be as follows after withdrawing CPP :

 

S.N.

Details

Capacity (TPA)

Existing

Proposed

Total

1

Induction Furnace

1,29,000

1,80,000

3,09,000

2

Ferro Alloy Plant

18,000

18,000

36,000

3

Rolling Mills

-

2,16,000

2,16,000

4

Captive Thermal Power Plant

38 MW

-

38 MW

5.

Sponge Iron Plant

2,16,000

-

2,16,000

 

Project is located in 56 acres in CSIDC authorized Siltara Industrial area. Total cost of the project is revised from Rs. 240.00 Crores to Rs. 240.27 Crores.

 

            Manganese ore (30,000 TPA) and coal (2,38,000 TPA) will be used as raw material. Iron ore, coal, dolomite/ limestone will be feed to the rotary kiln for the direct reduction of iron, cooled and separate d for coal ash and coal char.  Sponge Iron will be produced using iron ore (haematite) and non-coking coal.  In rolling mill, red-hot materials (billets or blooms) will pass through rolling mill to out various designs on the rolls.

 

      Air quality monitoring was carried out at 8 locations and the parameters are found to vary in the following range: SPM (139.1-286.6 mg/m3), RSPM (43.0-89.5 mg/m3), SO2 (9.3-13.6 mg/m3) & NOx (12.6-22.5 mg/m3) and are within permissible limit.  ESP to control, de-dusting system, bag filters, dust collectors will be provided to control air emission to 50 mg/Nm3. Total water requirement will be 454 m3/day and sourced from CSIDC / Chhattisgarh Ispat Bhoomi borewell. DM Plant back wash will be treated in ETP. Ash will be used for brick manufacturing. ESP dustwill be sold to cement manufacturers. Slag will be sold to brick manufacturers and also used for road making and land filling.

 

            Green belt will be developed in 18 acres (32 %) out of total 56 acres.  Acoustic enclosures will be provided. Power requirement of 71 MW will be sourced from CPP (1x33 CPP). Coal (2,38,000 TPA) will be used as fuel.

 

            The Committee (Industry) noted that no public hearing/consultation is required due to project being located in notified Siltara industrial area as per Section (iii), Stage (3), Para (i)(b) of EIA Notification, 2006. 

 

            After detailed deliberations, the Committee has recommended the proposal for environmental clearance without coal based captive power plant subject to stipulation of following specific conditions alongwith other environmental conditions

 

1.      No coal based captive power plant should be installed without prior permission from the State Govt.

2.      Efforts should be made to reduce RSPM levels in the ambient air and a time bound action plan should be submitted. Continuous stack monitoring facilities for all the stacks should be provided and sufficient air pollution control devices viz. ESP and bag filters etc. should be provided to keep the emission levels below 100 mg/Nm3.  

3.      Gaseous emission levels including secondary fugitive emissions from all the sources should be controlled within the latest permissible limits issued by the Ministry and regularly monitored. Guidelines / Code of Practice issued by the CPCB should be followed. New standards issued by the Ministry for the sponge iron plant in May, 2008 should be followed.

4.      Hot gases from the existing DRI kiln should be passed through Dust Settling Chamber (DSC) to remove coarse solids and After Burning Chamber (ABC) to burn CO completely and used in waste heat recovery boiler (WHRB).  The gas then should be cleaned in ESP before leaving out into the atmosphere through ID fan and stack.

5.      Vehicular pollution due to transportation of raw material and finished product should be controlled.  Proper arrangements should also be made to control dust emissions during loading and unloading of the raw material and finished product.

6.      Prior ‘Permission’ for the drawl of 454 m3/day water from CSIDC / Chhattisgarh Ispat Bhoomi should be obtained.

7.      ‘Zero’ effluent discharge should be strictly followed and no wastewater should be discharged outside the premises.

8.      All the char from DRI plant should be utilized in AFBC boiler of power plant and no char should be disposed off anywhere else.

  1. All the ferro alloy slag should be used for land filling inside the plant or used as building material only after passing through Toxic Chemical Leachability Potential (TCLP) test.  Toxic slag should be disposed in secured landfill as per CPCB guidelines.  Otherwise, hazardous substances should be recovered from the slag and output waste and be disposed in secured landfill as per CPCB guidelines. 
  2. Slag produced in Ferro Manganese (Fe-Mn) production should be used in manufacture Silico Manganese (Si-Mn). All the other solid waste including broken refractory mass should be properly disposed off in environment-friendly manner.
  3. Proper utilization of fly ash shall be ensured as per Fly ash Notification, 1999 and subsequent amendment in 2003.
  4. Proper handling, storage, utilization and disposal of all the solid waste shall be ensured and regular report regarding toxic metal content in the waste material and its composition, end use of solid/hazardous waste should be submitted to the Ministry’s Regional Office at Bhopal, CECB and CPCB.  .

13.  A time bound action plan should be submitted to reduce solid waste, its proper utilization and disposal.

14.  As proposed, green belt should be developed in 33 % area.

15.  All the recommendations made in the Charter on Corporate Responsibility for Environment Protection (CREP) for the Steel plants should be implemented.

16.  Prior permission from the State Forest Department should be taken regarding likely impact of the expansion of the proposed steel plant on the mangroves located at a distance of 1 km.

 

           

11.7     Ferro Alloy Plant (12,650 MTPA) at Village Nakrajoria, P.O. Salanpur, District Burdwan, West Bengal by M/s Asansol Alloys Pvt. Ltd. (EC)

Project authorities didn’t attend the meeting due to cardiac problem and it was decided that proposal should be considered afresh whenever requested by the PAs.

11.8     Induction Furnace with Continuous Casting Machine (1,00,000 TPA) Rolling Mill (1,00,000 TPA) and Coal Benefication Plant (14,40,000 TPA) at Khasara No. 41/3. 3-5, P.H. No.90 Village Siltara, Siltara Industrial Area, Tehsil and District Raipur, Chhattisgarh by M/s Rashmi Sponge Iron & Power Industries Ltd. (EC)  

 

The project authorities and their consultant gave a detailed presentation on the salient features of the project and proposed environmental protection measures to be undertaken as per Draft Terms of References (TORs) awarded during the 78th Meeting of the Expert Appraisal Committee (Industry) held during 20th to 22nd February, 2008 for preparation of EIA/EMP.  All the coal washeries with >1.0 MTPA through put of coal are kept at S.N. 2(a) in Category ‘A’ and appraised at the Central level.  Since capacity of the proposed coal washery is 41.44 MTPA, proposal is kept under Category ‘A’.  Proposed Induction Furnace with 3x8 TPH capacity and Rolling Mills are covered under S.N. 5(k) and 3(a) under Category ‘B’ but appraised at the Central level due to part of the proposal in Category ‘A’.    

 

            PAs informed to the Committee that M/s Rashmi Sponge Iron & Power Industries Ltd. have proposed for the expansion of Induction Furnace with Continuous Casting Machine (1,00,000 TPA), Rolling Mill (1,00,000 TPA) and Coal Beneficiation Plant (14,40,000 TPA) at Khasara No. 41/3, 3-5, P.H. No. 90 Village Siltara, Near Phase-II, Siltara Industrial Area, Tehsil and District Raipur, Chhattisgarh.  Sponge Iron Plant  (66,000 TPA) and Power Plant (8 MW) is already existing. The Committee noted that no coal based sponge iron plant and captive power plant is proposed which are banned by the Chhattisgarh Govt. in Siltara, C.G.  Following will be installed :

 

S.N.

Details

Existing Capacity

Proposed capacity

Total Capacity

1

Sponge Iron

66,000 TPA

--

66,000 TPA

2

Induction Furnace with CCM

21,000 TPA

 

79,000 TPA

1,00,000 TPA

3

Rolling mill

--

1,00,000 TPA

1,00,000 TPA

4

Power Plant

8 MW

--

8 MW

5

Coal Beneficiation

--

1.44 MTPA

(200 TPH)

1.44 MTPA

(200 TPH)

 

Total land acquired is 30 acres near Phase-II, Siltara Industrial area, Raipur.  PAs have not submitted any proof or copy of the Notification indicating location of the project in notified industrial area since the project is located adjacent to Siltara Industrial Area but not in notified area.  No National Park / Wildlife Sanctuary / Reserve Forest is located within 10 km radius of the project site. Total cost of the project is Rs. 50.00 Crores. Rs. 1.20 Crores and Rs.20 lakhs/ annum are earmarked towards capital cost and recurring cost/annum for environment pollution control measures.

 

            Coal (14,40,000 TPA), Sponge Iron (66,000 TPA) Scrap (25,000 TPA) and Ferro Alloys (790 TPA) will be used as raw material.

 

      Proposed Steel Ingots / Billets will be manufactured by melting sponge iron, scrap and Ferro Alloys in Induction Furnace. The molten metal will be poured in ladle furnace and casted in the form of Billets/Ingots through continuous casting machine.  These Billets/Ingots will be fed to a Rolling Mill to produce Re-rolled products.  Washed coal from coal washery (dry type) will be partly used for manufacturing sponge iron and partly sold to local parties.

 

      Air quality was monitored at 8 locations during November 2007-January 2008  and data submitted indicated SPM (98.8-442.9 mg/m3),  RSPM (30.3-141.7  mg/m3),  SO2 (6.7 – 21.9 mg/m3) & NOx (9.8-28.6 mg/m3).  Fume extraction system with bag filters will be provided to control emissions from IF / SMS.  Dust extraction system and bag filter to coal beneficiation plant will be provided.  Bag filters will also be provided to coal washery. Cleaned gases after passing through APCS will be let out into the atmosphere through stacks of adequate height as per CPCB norms.  Dust suppression system will be provided in unloading areas.  All the internal roads will be asphalted. Coal washery will be of dry type and no wastewater will be generated.  Bag filters will be provided to coal washery.

 

Total water requirement from Chhattisgarh Ispat Bhumi Ltd. will be 250 m3/day and permission has been accorded by the Chhattisgarh State Industrial Corporation (CSIDC) on 9th October, 2007.  During presentation, PAs informed to the commttee that 250 m3/day water will be supplied by Chhatisgarh Ispat Bhumi Ltd.  No effluent will be generated from the SMS and Rolling Mill as closed circuit cooling system will be adopted.  Sanitary wastewater will be treated in Septic tank followed by soak pit.

 

Slag from IF / SMS (24 TPD) will be crushed and Iron content will be recovered and balance material will be used in road construction.  Mill scales (15 TPD) from Rolling Mill will be used as raw material for Induction Furnace.  Washery middlings and rejects (1500 TPD) will be given to units with power plants.  F.O. sludge will be provided to approved vendors. Green belt will be developed in 10 acres (33%) out of total 30 acres. 

 

Total power requirement will be 11 MW out of which 8 MW will be generated in CPP and balance 3 MW will be sourced from CSEB.

 

The Committee deliberated upon the issues raised during the Public Hearing / Public Consultation meeting conducted by the Chhattisgarh Environment Conservation Board on 7th August, 2008. The issues like pollution problem in Siltara area, water availability, employment, land availability etc. were discussed and have satisfactorily been incorporated in the final EIA/EMP report.

           

            After detailed deliberations, the Committee found the final EIA/EMP report adequate and suggested to stipulate following specific conditions alongwith other environmental conditions while considering for accord of environmental clearance :

 

1.      Efforts should be made to reduce RSPM levels in the ambient air and a time bound action plan should be submitted. Continuous stack monitoring facilities for all the stacks should be provided and sufficient air pollution control devices viz. ESP and bag filters etc. should be provided to keep the emission levels below 100 mg/Nm3.  

2.      Gaseous emission levels including secondary fugitive emissions from all the sources should be controlled within the latest permissible limits issued by the Ministry and regularly monitored. Guidelines / Code of Practice issued by the CPCB should be followed. New standards issued by the Ministry for the sponge iron plant in May, 2008 should be followed.

3.      Fume extraction system with bag filters should be provided to control emissions from induction furnace and steel melt shop. Dust extraction system and bag filter should be provided to coal beneficiation plant.  Bag filters shouldalso be provided to coal washery.

4.      Adequate pollution control measures should also be provided to coal beneficiation plant to control fugitive emissions and crushed coal should be properly supplied to the concerned industries.

5.      Vehicular pollution due to transportation of raw material and finished product should be controlled. Proper arrangements should also be made to control dust emissions during loading and unloading of the raw material and finished product.

6.      Prior ‘Permission’ for the drawl of 250 m3/day water water from Chhattisgarh Ispat Bhumi Ltd. should be obtained.

7.      All the char from DRI plant, coal washery rejects and middlings should be utilized in AFBC boiler of power plant and no char should be disposed off anywhere else. All the mill scales from rolling mill should be used in the induction furnace. SMS slag should also be properly utilized. All the other solid waste including broken refractory mass should be properly disposed off in environment-friendly manner.

  1. Proper utilization of fly ash shall be ensured as per Fly ash Notification, 1999 and subsequent amendment in 2003.
  2. Proper handling, storage, utilization and disposal of all the solid waste shall be ensured and regular report regarding toxic metal content in the waste material and its composition, end use of solid/hazardous waste should be submitted to the Ministry’s Regional Office at Bhopal, OPCB and CPCB.  .

10.  A time bound action plan should be submitted to reduce solid waste, its proper utilization and disposal.

11.  As proposed, green belt should be developed in 33 % area.

12.  All the recommendations made in the Charter on Corporate Responsibility for Environment Protection (CREP) for the Steel plants should be implemented.

 

 

11.9     Steel Melting Plant, Rolling Mill & Ferro Alloys Plant at Paipalaiyam and Vasanadu Village, Kuppam Mandal, District Chittoor, Andhra Pradesh by M/s J R Steel Industries (I) Pvt. Ltd. (EC)

 

The project authorities and their consultant gave a detailed presentation on the salient features of the project and proposed environmental protection measures to be undertaken as per Draft Terms of References (TORs) awarded during the 82nd Meeting of the Expert Appraisal Committee (Industry) held during 10th to 12th June, 2008 for preparation of EIA/EMP. All the Primary metallurgical industries have been kept at S.N. 3(a) under primary metallurgical industry under category ‘A’ and appraised at Central level. 

 

PAs informed to the Committee that M/s J R Steel Industries (I) Pvt Ltd. has proposed to set up a Steel melting plant, Rolling mill & Ferro Alloys Plant at Paipalaiyam and Vasanadu Village, Kuppam Mandal, District Chittoor, Andhra Pradesh. The total land area acquired for the proposed plant will be 21.87 acres.  No national parks/wild life sanctuary/reserve forests is located within 10 km radius. Inter-state boundary is 5.5 km from the proposed site.  Total cost of the proposed unit will be Rs. 67.00 Crores. Rs. 3.40 Crores and Rs. 0.50 Crores are earmarked towards capital cost and recurring cost/annum for environmental pollution control measures.

 

S. N.

Proposed units

Phase I

Phase II

Total

1.

Induction furnace for SMS

25 TPH

50 TPH

75 TPH

2.

Rolling mill

250 TPD

500 TPD

750 TPD

3.

Ferro alloys plant

--

50 TPD

50 TPD

 

Following will be manufactured:

 

S. N.

Product

Phase I

Phase II

Total

1.

M.S. Billets

75,000 TPA

1,50,000 TPA

2,25,000 TPA

2.

Long steel products (TMT bars / Structural steel)

75,000 TPA

75,000 TPA

1,50,000 TPA

3.

Producer Gas (By product)

(Lakhs m3/day)

217.5

217.5

435

4.

Ferro alloys

--

15, 000 TPA

15,000 TPA

           

During presentation, PAs informed that following will be manufactured:

 

S. N.

Product

Phase I

Phase II

Total

1.

M.S. Billets

250 TPD

500 TPD

740 TPD

2.

TMT bars / Structural steel

250 TPD

250 TPD

500 TPD

3.

 

Producer Gas

 

72,500 m3/day

72,500 m3/day

1,45,000 m3/day

4.

Ferro alloys

--

50 TPD

50 TPD

 

Manganese ore, Dolomite, Coal/Coke, Sponge Iron, Pig Iron, Quartz and Recovered Steel scrap will be used as raw material.

 

Air quality monitoring was carried out at 8 locations during December 2007-February 2008 and SPM (76.3 - 99.3 mg/m3), RSPM (24.2 - 35.3 mg/m3), SO2 (5.3 - 7.6 mg/m3) & NOx (6.1 – 8.7 mg/m3) have been found to be within the permissible limit. Fume extraction system with cyclones and bag filters will be provided to control the primary and secondary emissions from Induction furnaces & submerged arc furnaces. These emissions will be discharged into the atmosphere through common stacks of height 30 m height.  Flue gas emissions from Rolling mill will be discharged in to atmosphere through stacks of height 38 m for adequate dispersion in to the atmosphere. Dust suppression system will be provided in unloading areas to prevent the fugitive dust emission.  Water spraying will be done to prevent the dust emanation due to vehicular movement.  Dust curtains will be provided all around the work area to prevent the dust emissions due to construction. Water sprinklers will used to control the dust during material handling.

 

Total ground water requirement for the proposed project will be 150 m3/day instead of 300 m3/day proposed earlier and have applied for the permission to the State Ground Water Board. Closed circuit cooling system will be adopted in Ferro Alloys, Steel melting shop & Rolling mill. Hence, no waste generation from process and cooling. Sanitary wastewater generation will be 8 KLD, which will be treated in septic tank followed by soak pit. The entire water treated will be recycled and re-used within the plant.

 

Induction furnace slag and Silico Manganese slag will be used for road construction. Mill scales will be used in the process.  Ash will be used as a base material in the manufacture of construction bricks.  High Carbon Ferro-manganese slag will be used to manufacture Silico-Manganese as it contains high MnO2 and Silicon.  High Carbon Ferro-chrome slag will be used in cast iron foundries. The dug soil during excavation will be used for filling of low-lying areas and to refill the excavated areas after concreting. All the Municipal solid waste will be disposed off as per norms. Furnace oil sludge will be stored in HDPE drums and disposed off to APPCB approved vendors.

 

Out of total 21.87 acres of plant area, green belt is proposed in 7.30 acres. As a part of green belt development plan, native species that are suitable to that soil condition will be developed in consultation with local DFO as per CPCB guidelines.

 

            The sources of noise generation in the plant will be Furnace, generator, rolling mill etc. Ear plugs will be provided to workers working in the noise prone areas. Ambient noise levels will be in accordance with MoEF notification dated 14-02-2000.   The power requirement of the plant will be 47000 KVA supplied by AP Transco / AP Southern power distribution company.  Furnace oil will be used for reheating the furnace as standby fuel. In the rolling mill producer gas, which is environment friendly will be used as a primary fuel. However, furnace oil will be used a stand-by fuel. 

 

The Committee deliberated upon the issues raised during the Public Hearing / Public Consultation meeting conducted by the A. P. Pollution Control Board on 30th August, 2008. The issues like employment and welfare measures were discussed and have satisfactorily been incorporated in the final EIA/EMP report.

           

            After detailed deliberations, the Committee found the final EIA/EMP report adequate and suggested to stipulate following specific conditions alongwith other environmental conditions while considering for accord of environmental clearance :

 

1.      Efforts should be made to reduce RSPM levels in the ambient air and a time bound action plan should be submitted. Continuous stack monitoring facilities for all the stacks should be provided and sufficient air pollution control devices should be provided to keep the emission levels below 100 mg/Nm3.  

2.      Gaseous emission levels including secondary fugitive emissions from all the sources should be controlled within the latest permissible limits issued by the Ministry and regularly monitored. Guidelines / Code of Practice issued by the CPCB should be followed.

3.      Vehicular pollution due to transportation of raw material and finished product should be controlled. Proper arrangements should also be made to control dust emissions during loading and unloading of the raw material and finished product.

4.      Prior ‘Permission’ for the drawl of 150 m3/day ground water from the SGWB/CGWA should be obtained.

5.      All the standards prescribed for the coke oven plants should be followed as per the latest guidelines. Proper and full utilization of coke oven gases in power plant using heat recovery steam generators should be ensured and no flue gases should be discharged into the air.

  1. All the ferro alloy slag should be used for land filling inside the plant or used as building material only after passing through Toxic Chemical Leachability Potential (TCLP) test.  Toxic slag should be disposed in secured landfill as per CPCB guidelines.  Otherwise, hazardous substances should be recovered from the slag and output waste and be disposed in secured landfill as per CPCB guidelines. 
  2. Slag produced in Ferro Manganese (Fe-Mn) production should be used in manufacture Silico Manganese (Si-Mn).
  3. Proper utilization of fly ash shall be ensured as per Fly ash Notification, 1999 and subsequent amendment in 2003.
  4. Proper handling, storage, utilization and disposal of all the solid waste shall be ensured and regular report regarding toxic metal content in the waste material and its composition, end use of solid/hazardous waste should be submitted to the Ministry’s Regional Office at Bhuvaneswar, OSPCB and CPCB.  .

10.  A time bound action plan should be submitted to reduce solid waste, its proper utilization and disposal.

11.  As proposed, green belt should be developed in 33 % area.

12.  All the recommendations made in the Charter on Corporate Responsibility for Environment Protection (CREP) for the Steel plants should be implemented.

 

 

11.10   Expansion of steel plant (150,000 TPA) for manufacturing of rolled products at peria oblapuram village, gummidipoondi Taluk, Tiruvallur District, Tamil Nadu by M/s K.L. Concast Private Ltd. (unit-II) (EC after TOR)

 

Setting up of Iron Ingots plant (150,000 TPA) for manufacturing of rolled products at peria oblapuram village, gummidipoondi Taluk, Tiruvallur District, Tamil Nadu by M/s K.L. Concast Private Ltd. (unit-II) (EC after TOR)

 

The project authorities and their consultant gave a detailed presentation on the salient features of the project and proposed environmental protection measures to be undertaken alongwith the EIA/EMP prepared based on the TORs awarded by the Expert Appraisal Committee (Industry) in its 77th meeting held during 21st to 24th September, 2008. The project activity is listed at 3(a) under Primary Metallurgical Industry and is of ‘A’ Category hence considered at central level.

 

M/s K. L. Concast Private Limited (Unit-II) has proposed to set up of Iron Ingots plant (70,000 TPA) for manufacturing of rolled products at Peria Oblapuram Village, Gummidipoondi Taluk, Tiruvallur District, Tamil Nadu.  The plant is located in S.F. No. 127, 129, 143, 144, 146/1A, 1B, 146/2A1, 146/2A2, 146/2B, 147/1 having a total area of 33.42 acres. Green belt will be developed in 10 acres of land. The products of the project are MS Ingots and re-rolled structural steel and production capacity will be 70,000 Tonnes/year. Total cost of the project is Rs. 30.0 Crores. No eco-sensitive areas are located within 15 km periphery of the plant. The products will be Angles, Channels, Shapes etc (150000 TPA) and intermediate product will be Steel Billets 150000 TPA.

 

The raw material for the project will be Sponge Iron (60,000 T/annum), Melting Scrap (140,000 T/annum),            Ferro Alloys (1000 T/annum) and Coal (4,000 T/annum). Manufacturing process involves induction furnace for steel melting and billet caster. The billets will be used for rolled products.

 

The main Source of Air Pollution will be Melting Furnace and re-heating Furnace. Air Pollution Control Device like collection hood, settling chamber, bag house, cyclone separator, Wet scrubber with ID fan and Chimney of height 30m will be provided with induction furnace and heating furnace as per CPCB norms.      

 

The total water requirement of the project will be 50 KL/day and it will be sourced from ground water. The domestic waste water will be treated in sewage treatment plant and utilize the same for gardening within the premises as per the pollution control norms. Cooling tower blow down water will be reused for further process.

 

The Solid Waste generation from the project will be Slag from Furnace (10.0 T/day) and Sludge (STP – 0.1 T/day). There will be no hazardous waste from the project. Out of 33.42 acres land, 10.0 acres will be allotted for green belt.

 

Total power requirement of the project will be 12.0 MW per day and it will be sourced from State Electricity Board. DG set of 1000 KVA will also be installed in the project. The fuel requirement of the project will be furnace oil (20 lit/Month, Coal (10 Kg/Month) and Diesel (10 lit/hr).   

 

The public meeting held during on 7th August, 2008 at Ambattur industrial Estate, Tamil Nadu. The committee took the note of the public hearing proceeding and found satifactory.

 

The Expert Appraisal Committee (Industry) found the EIA/EMP complete and adequate and complete and recommended the proposal for grant of environmental clearance subject to the following specific conditions along with other specific and general conditions and submission of details of the ETP, disposal details of tarry waste from scrubber, Disposal arrangement of solid waste along with ash from scrubber pit.: 

 

1.      Continuous monitoring facilities for all the stacks and sufficient air pollution control equipments viz. fume extraction system with bag filters, I D fan and stack of adequate height to submerged arc furnace and electrostatic precipitator to captive power plant should be provided to control emissions below 100 mg/Nm3. 

 

2.      Secondary fugitive emissions from all the sources should be controlled within the latest permissible limits issued by the Ministry and regularly monitored. Guidelines / Code of Practice issued by the CPCB should be followed.

 

3.      Proper handling, storage, utilization and disposal of all the solid waste should be ensured and regular report regarding toxic metal content in the waste material and its composition, end use of solid/hazardous waste should be submitted to the Ministry’s Regional Office at Bangalore, APPCB and CPCB. 

 

4.      All the SMS slag should be used for land filling inside the plant or used as building material only after passing through test for hazardous quality.  Otherwise, hazardous substances should be recovered from the slag and output waste should be disposed in secured landfill as per CPCB guidelines. 

 

5.      The company shall obtain permission for drawl of 50 KLD ground water from the CGWA/SGWB.

 

6.      The company shall comply with the commitments made during public hearing held on 7th August 2008.

 

 

11.11   Blast Furnace (0.90MTPA), Sinter Plant (2MTPA), Coke Plant (0.6MTPA) and Waste Heat Recovery Power Plant (60 MW) at Village Navelim, Taluka Bicholim, North Goa Dist, Goa by M/s Sesa Industries Limited (EC after TOR)

 

The project authorities and their consultant gave a detailed presentation on the salient features of the project and proposed environmental protection measures to be undertaken alongwith the draft Term of References for the preparation of EIA/EMP prepared based on the TORs awarded by the Expert Appraisal Committee (Industry) in its 76th  meeting held during 26th to 28th December, 2007. All metallurgical industries (ferrous and non-ferrous) with primary metallurgical process are listed at serial no. 3(a) under category “A” projects in schedule of EIA Notification, 2006. Proposal was appraised at centre level.

 

M/S Sesa Goa Limited have proposed to set up integrated steel plant with Blast Furnace (0.90MTPA), Sinter Plant (2MTPA), Coke Plant (0.6MTPA) and Waste Heat Recovery Power Plant (60 MW) at Village Navelim, Taluka Bicholim, North Goa Dist, Goa. Total Cost of the project is Rs.1104.00 Crores. Capital cost proposed for the Environmental Protection and Social Cost is Rs.22.00 Crores. Total land required by the plant will be 104 Hectares. Out of this 21 Ha is reserved for future and 33 Ha for green belt development.

 

The project is having following Product and  production facilities:

 
  1. Blast Furnace (Pig Iron)          -900,000 TPA
  2. Sinter Plant                             -2,000,000 TPA
  3. Coke Plant                              -600,000 TPA
  4. Waste Heat Recovery Power Plant-60MW

 

The raw materials required for the plant are as given below:

 

S.No

Raw Material Requirement

At Sinter Feed (80%) in MT

Source

1

Sinter

1188000

Own

2

High Grade Iron Ore Lumps

X

 

3

High Grade Low MN Lumps

53910

Karnataka

4

Low Grade Local Lumps

268185

Goa

5

Siliceous Ore Lumps

162058

Goa

6

High Grade Fines

X

 

7

High Grade Low MN Fines

219799

Hospet

8

Siliceous Ore Fines

X

 

9

Low Grade Local Fines

969996

Goa

10

Limestone Lumps

X

 

11

Dolomite Lumps

X

 

12

Limestone Fines

137220

Karnataka

13

Dolomite Fines

138476

Karnataka

14

Coke (20-60 mm size)

448753 MT/ Annum

Own

15

Coke Breeze

98179 MT/Annum

Own

16

Coal for PCI (120 kg/THM)

108000MT/Annum

Imported

 

The project Comprises of 9,00,000 TPA Blast Furnace in Naveli village next to the existing plant of the company. This furnace will be a modern Blast Furnace equipped with Hot Blast Stoves, Bell less top, and Pulverized Coal Injection including O2 enrichment. Sinter plants to produce 2 million tons of sinters to cater the need of companies existing Blast Furnaces and the new Blast Furnace. To cater to the coke requirement of Blast Furnace, Coke making capacity of 600,000 TPA with Sesa’s technology of Heat Recovery, which conforms, to the most stringent environment norms worldwide.

 

The proposed power plant will have capacity of 60 MW which will utilize the waste heat from Coke ovens and the excess gas available from the proposed 900,000 TPA Blast Furnace.  The financial viability of the project takes into consideration the revenue that will accrue from the sale of CER’s that will be realized from the Power plant being a CDM project.

 

Total water requirement for the plant will be 16632 KL/Day. This will be met from Government Water Supply Bhandara (check dam) and Rain Water Harvesting (Fresh water 6,700 KL/day) along with the saline water drawn (10,000 KL/day) from Mandovi estuary. Details of water consumption are as given below:

 

Operations/ Plant

Water Requirement        Quantity in KL/day

Blast Furnace

4,800

Sinter Plant

1,560

Power Plant

9,000

Coke Oven

1,200

Domestic

72

Total

16,632

 

The wastewater generated from the plant will be treated and recycled/reused/consumed within the plant and zero discharge condition will be maintained.

 

Blast furnace, Hot blast stove, coke oven plant, Sinter plant and power plant are the point emission sources besides the fugitive emissions from material handling and preparatory areas. Details of sources of emission and proposed air pollution control arrangements are given below: 

Source

Control Method

Emissions from the Blast Furnace and PCI

Gas cleaning System

Emission from Hot Blast Stove Stacks

Stack of adequate height as per CPCB

Fugitive Dust Emissions from Hot Metal & Raw Material Handling System

Dust Suppression system (Dry Fog type)

Coke Oven Plant

For Fugitive Dust Emissions, Dust Suppression System and stacks will be connected to Waste Heat Recovery Boiler

Sinter Plant

Dust Extraction System and Dust Suppression System and A stack of adequate height as per CPCB norms for proper dispersion of flue gases

Power Plant

Stack of adequate height as per CPCB

 

 

Solid waste will be generated in the form of Blast Furnace slag (770 TPD), Raw Material Fines (245 TPD) and dust/sludge from gas cleaning system (80 TPD).    Slag will be sold off to the cement industry. Raw Material Fines, process dust, dry sludge from Blast Furnace will be used as raw material in Sintering process.

 

Total Power Requirement will be 35 MW and will be met from the Captive Power Plant of capacity 60 MW. DG Set of capacity 10 MW (4x2.5 MW) will be installed. No fuel will be used except 385 Lts /hr/DG set. The other fuels used will be coke and coal which are the raw material in the process.

 

The project authorities presented the compliance of TORs given and during presentation PAs and their consultant could not explain the CO concentration, Material balance for the various products, details of the wastewater and treatment from the coke quenching unit, solid waste management disposal details etc. The Expert Appraisal Committee (Industry) decided the PAs may be ask to submit the above information for reconsideration and deferred the proposal.

 

 

11.12   Manufacture of TMT Bars with installation of 2x15 T Induction Furnace, 240 TPD CCM and 200 TPD Rolling Mill at Sy. No. 147, 80/2, 80/1, 20/2, of Mangaldoddi Village, Vasanadu post, Kuppam Mandal, Chittoor District, Andhra Pradesh. M/s. Dhanya Steel Industries Pvt. Ltd., - (EC after TOR) 

 

The project authorities and their consultant gave a detailed presentation on the salient features of the project and details of environmental protection measures to be undertaken along with the EIA/EMP report already prepared based on the TOrs awarded by the SEIAA. The primary metallurgical processes are kept in 3(a) under ‘A’ category of EIA Notification 2006.

 

M/s. Dhanya Steel Industries Pvt. Ltd proposed to set up plant for manufacturing of TMT Bars with installation of 2x15 T Induction Furnace, 240 TPD CCM and 200 TPD Rolling Mill at Sy. No. 147, 80/2, 80/1, 20/2, of Mangaldoddi Village, Vasanadu post, Kuppam Mandal, Chittoor District, Andhra Pradesh. The Inter state boundary of Tamilnadu and Andhra Pradesh is located at 5.58km distance from the site in Northwest direction. No forest land acquisition and R&R is involved.  The company has already acquired 10 acres of land for the proposed plant of which 3.3 acres of the area will be brought under green belt.  Total cost of the project is Rs. 31.78 Crores. The details of products and production capacity are as given below:

 

S.No

Description

Capacity (TPD)

Capacity (TPA)

1

MS Billets

240

72000

2

TMT Bars

200

60000

 

Raw Material Requirement

S.No

Raw Material

Requirement

TPD

TPA

1

Sponge Iron scrap

60

18000

2

Hot metal  Scrap

108

32400

3

Turnings/Bundles

72

21600

4

Ferroalloy

80

24000

 

The proposed plant will produce steel in the form of billets and rolled products through IF-CCM-RM route. Steel making will be done using induction furnace. The steel formed is molded into billets and rolled products by casting mills and rolling mills.

 

Ambient air quality monitoring has been carried out for SPM, RPM, SO2 and NOx during December 2007 to March 2008 at six locations including the project site. The highest reported value for these parameters are 88 mg/m3, 9mg/m3 and 10mg/m3    respectively. Values conform to the prescribed standards for Ambient Air Quality.  The sources of air pollution from the plant are Induction Furnace, Rolling mill and DG set of 750 KVA capacity. For control of air pollution stacks and nuisance bag filters at various departments will be installed. The total water requirement for the proposed unit is met from bore well located within plant premises.  The net water requirement after implementation of the project will be 90 KLD.  The unit will generate 15.0 m3/day of cooling tower and 12.0 m3/day of domestic effluent during operation. The unit operations are equalization/neutralization tank, clarifier, collection tank and sludge drying beds.   The treated water shall be used for on land irrigation.  Domestic effluents shall be sent to septic tank followed by soak pit.

 

The solid waste generated from the plant is mill scales from CCM & Rolling Mill and slag from Induction Furnace will be sold to cement manufacturers. The total power requirement is 1800 KVA which will be met from APTRANSCO.

The public hearing meeting was held on 25th June 2008. The committee took the note of the public hearing proceeding and found satisfactory. PAs have incorporated the same in the EIA/EMP.

                                                                                                                                                                                                                                                                                                                                                                                 After detailed deliberation the Committee found EIA/EMP report complete and adequate. The Committee recommended the proposal for grant of environmental clearance subject to the specific and general conditions.

 

11.13   Sbmerged Electric Arc Furnace(Phase-I 6 MVA & Phase II-9 MVA), Phase II- Induction Furnace 2X15 TPC,Continuous Casing Machine -240 TPD and Rolling Mill 200TPD) at Survey No. 1301-1305 of Thurupupalli, Ananthrajpeta Panchayat, KOduru Mandal, Distt. Kadapa, Andhra Pradesh by M/s Manishreni Feroalloys Pvt.ltd. (EC after TOR).

 

The project authorities and their consultant gave a detailed presentation on the salient features of the project and proposed environmental protection measures to be undertaken alongwith the EIA/EMP prepared based on the TORs awarded by the Expert Appraisal Committee (Industry) in its 81st  meeting held during 13th May, 2008. The project activity is listed at 3(a) under Primary Metallurgical Industry and is of ‘A’ Category hence considered at central level.

 

The plant has proposed Steel Plant Sbmerged Electric Arc Furnace(Phase-I 6 MVA & Phase II-9 MVA), Phase II- Induction Furnace 2X15 TPC,Continuous Casing Machine -240 TPD and Rolling Mill 200TPD) at Survey No. 1301-1305 of Thurupupalli, Ananthrajpeta Panchayat, KOduru Mandal, Distt. Kadapa, Andhra Pradesh.  No forest land acquisition and R&R is involved.  The company has already acquired 30.56 acres of land for the proposed plant of which 22.56 acres of the area will be brought under green belt.  Total cost of the project is Rs. 85 Crores and Rs. 1.4 Crores have been earmarked towards the capital cost for environmental protection. The proposed manufacturing capacities are as follows:

S.No

Description

Capacity (TPA)

Phase-I

Phase-I

Phase-II

Total

1

Silico Manganese (Si Mn)

9570

14355

23925

2

Ferro Manganese( Fe Mn)

14190

21285

35475

3

Ferro Silicon (Fe Si)

4290

6435

10725

4

MS Ingots

--

72000

72000

5

TMT Bars

--

60000

60000

 

The required raw materials are Managanese ore, Dolomite, manganese slag, reductants, quartz, charcoal, iron scrap, electrode paste in the case of ferro alloys and sponge iron, scrap metal for the induction furnace.  

Ambient air quality monitoring has been carried out for SPM, SO2 and NOx during March 2008 to May 2008 at eight locations including the project site. The highest reported value for these parameters are 114mg/m3, 9mg/m3, and 10mg/m3    respectively. Values conform to the prescribed standards for Ambient Air Quality. The sources of air pollution from the plant are Induction Furnace, Rolling Mill Furnace, 6000 and 9000 KVA submerged EAF and 125 KVA DG Set.   The company has proposed to install stacks and nuisance bag filters at various departments for emissions. The total water requirement for the proposed unit is met from bore well located within plant premises.  The net water requirement after implementation of the project will be 155.5 KLD; 46.5 KLD (Phase-I) & 109 KLD (Phase-II).   The unit will generate 39 KLD (10KLD: Phase –I & 29 KLD: Phase-II)  of Cooling tower blow down and 11.5 KLD((3.5KLD: Phase –I & 8 KLD: Phase-II)   of domestic effluent during operation. The unit operations for ETP will be equalization/neutralization tank, clarifier, collection tank and sludge drying beds.   The treated water shall be used recycled to the cooling tower and also used for green belt development.  Domestic effluents shall be sent to septic tank followed by soak pit.

 The slag generated from the production of Ferro Manganese will be used as a raw material for Silico Manganese and the slag generated from Silico Manganese &  Ferro Silicon will be used as a construction material, base layer for roads laying and for land filling. The mill scales obtained from CCM and Rolling Mill shall be sold to brick manufacturers.

The total power requirement will be 18 MVA and  will be met from APTRANSCO.   

 

The Committee deliberated upon the issues raised during the Public Hearing / Public Consultation meeting conducted by the Andhra Pradesh Pollution Control Board on 6th August, 2008 satisfactorily been incorporated in the final EIA/EMP report. After detailed deliberations, the Committee has recommended the proposal for environmental clearance subject to stipulation of following specific alongwith other specific and general conditions:

 

  1. Continuous monitoring facilities for all the stacks and sufficient air pollution control equipments viz. fume extraction system with bag filters, I D fan and stack of adequate height to submerged arc furnace should be provided to control emissions below 100 mg/Nm3. 

 

  1. Secondary fugitive emissions from all the sources should be controlled within the latest permissible limits issued by the Ministry and regularly monitored. Guidelines / Code of Practice issued by the CPCB should be followed.

 

  1. Proper handling, storage, utilization and disposal of all the solid waste should be ensured and regular report regarding toxic metal content in the waste material and its composition, end use of solid/hazardous waste should be submitted to the Ministry’s Regional Office at Bangalore, APPCB and CPCB. 

 

  1. All the ferro alloy slag should be used for land filling inside the plant or used as building material only after passing through Toxic Chemical Leachability Potential (TCLP) test.  Otherwise, hazardous substances should be recovered from the slag and output waste should be disposed in secured landfill as per CPCB guidelines. 

 

  1. The company shall obtain permission for drawl of 155.50 KLD ground water from the CGWA/SGWB.

 

  1. The company shall comply with the commitments made during public hearing held on 6th August, 2008.

 

11.14   Expansion of the cement plant Capacity by clinker production from 0.40 MTPA to 0.55 MTP, cement grinding from 0.40 MTPA to 1.20 MTPA and limestone production from existing 0.633 MTPA to 1.025 MTPA at Mysore Cement existing unit in Ammasandra, District Tumkur, Karnataka by M/s Mysore Cements Limited (EC after TOR)

 

The project authorities and their consultant gave a detailed presentation on the salient features of the project and proposed environmental protection measures to be undertaken alongwith the EIA/EMP prepared based on the TORs awarded in 75th meeting of the EAC(I) held during 28th – 30th November 2007. All cement plant more than 1.0 MTPA covered under Category ‘A’ as per para 3(b) of the Schedule of the EIA notification 2006. Instant case comes under category ‘A’ and appraised at central level.

 

M/s Mysore Cements Limited have proposed for expansion of the clinker plant capacity from 0.40 MTPA to 0.55 MTPA by internal de-bottlenecking and optimizing equipment usage; expansion of cement plant by expanding the grinding capacity from 0.40 MTPA to 1.20 MTPA and expansion of limestone production from existing 0.633 MTPA to 1.025 MTPA {Yerekatte limestone mine-ML-I(19.38 Ha) from0.033 to 0.2 MTPA and Yerekatte limestone mine – ML-II (305.54 Ha) from 0.60 to 0.825 MTPA}  at Mysore Cements existing unit in Ammasandra, District Tumkur, Karnataka. Plant is having 40 hectares of land with existing cement plant and no additional land is required for expansion. Mines are located at a distance of 18 KM from the plant. Limestone Mining Lease (ML)-I of 19 hectares, complete forest land, no land acquired. Forest clearance yet to be obtained and Mining Lease-II of 305 hectares, the entire land has been acquired. The Cost of the project is Rs. 122 Crores for brown field plant expansion and Rs. 6 Crores towards replacement of mining machineries. Rs 7 Crores for capital and Rs 1.0 Crores for recurring cost have been earmarked towards environmental protection measures.

 

The committee during presentation observed that the plant does not have valid mining lease and proposal of lease is pending since last 8 years for approval from the state government. The project authorities failed to explain the reason. The committee considering the seriousness of the issue rejected the proposal.

 

11.15   Expansion of Clinker manufacturing plant from 1.2 MTPA to 3.1 MTPA and Captive Mines of Narsingarh Limestone mine(1.49 MTPA) and Patharia Limestone(0.75 MTPA to 4.5 MTPA) at Narsingarh, District Damoh, Madhya Pradesh by M/s Diamond Cement Ltd. (Narsingarh Clinkerisation Plant). (EC after TOR) 

 

 

The project authorities and their consultant gave a detailed presentation on the salient features of the project and proposed environmental protection measures to be undertaken alongwith the draft Term of References for the preparation of EIA/EMP. All cement plant more than 1.0 MTPA covered under Category ‘A’ as per para 3(b) of the Schedule of the EIA notification 2006. Instant case comes under category ‘A’ and appraised at central level.

 

M/s Diamond Cement Ltd. have proposed expansion  of Clinker plant from 1.2 MTPA to 3.1 MTPA and Captive  Mines of Narsingarh Limestone mine1302.70 ha-1.49 MTPA(no change in capacity and ML area) and Patharia Limestone0.75 to 4.50 MTPA-1247.267 ha (No change in ML area. Only increase in production rate) at  Narsingarh, District Damoh, Madhya Pradesh. The proposed expansion will be carried out in the existing plant premises and no change of land use is envisaged.   120 ha of land will be acquired for lying railway line connection between Clinker plant and Patharia railway station.  River Sonar is passing through mine lease area in Narsingarh mine lease area and a seasonal stream Sajali Nadi flows 750m North of Patharia Mine lease.  River Bebas is about 3.5 km to the North of Patheria mining area.  Lakharia protected forests lies about 3.5 kms South of Patharia Lime stone area. The total cost of the project is Rs. 832 Crores.

 

The production capacity of proposed expansion includes the following:

1.                  clinker production: 1.2 MTPA to 3.1 MTPA

2.                  Expansion of Patharia Limestone mine 7500 TPD to 15000 TPD(1247.267Ha)

3.                  Narsingarh Mine 6000 TPD(1300.70 Ha)

 

For expansion of clinkerisation a new line for clinker manufacturing capacity of 1.9 MTPA will be installed.  The manufacturing process involves calcinations by State of Art 5 stage pre-heater/precalciner, rotary kiln, great cooler and for control of pollution ESP.  

 

Lime stone consumption will increase from 1.8 MTPA to 4.8 MTPA .  The limestone required for producing clinker shall be sourced from Mysore Cements existing captive limestone quarry at Patharia.  The high grade limestone (if required) for producing clinker shall be sourced from Katni MP, by rails/trucks.  Laterite consumption will increase from 0.04 MTPA to 0,10 MTPA.  Laterite is also proposed to be sourced from Katni MP and shall be transported by trucks to the clinkerisation unit.  Coal consumption will increase from 0.25 MTPA to 0.60 MTPA and the same shall be sourced from coalaries of South Eastern Coal Field.  Facilities will be provided for the storage of explosives and fuel 1x20 Kl capacity fuel tank at Narsingarh and 2x20 Kl capacity tank at Patharia Mining lease area.

 

Clinker manufacturing is an air polluting process.  The source of air pollution are limestone crusher, coal crusher, raw mill, kiln , clinker cooler and other various material transfer points.  For new line following air pollution control equipment have been proposed:

 

1.                  Kiln/raw mill-Bag House.

2.                  Calciner or kiln burner-low NOx technology

3.                  Cooler vent  ESP

4.                  Coal mill Bag filter.

5.                  Storage and transfer points – bag filters

6.                  Limestone crushers – bag house

 

Water consumption for the existing plant is around 2500m3.  Water requirement is proposed to be met from the existing water sources like old mining pits or nearby river water.  Additional pumps & pipes will be installed to meet the additional water requirement, which is estimated to be around 2000m3/day. An application has been sent to Irrigation Department Mahdya Pradesh for additional requirement of water to be drawn from Sonar River.

 

The water requirement for mine operation will be about 300m3 /day and 215 m3/day respectively for Patharia and Narsingarh limestone mines.  It will be sourced from accumulated rain water from the excavated pits.  

 

Electrical  power is presently received from the MPSEB on single circuit 132 KV line grid  with a 132 KV Switchyard at plant premises.  The existing contract demand with MPSEB is 12 MVA.  The existing captive power plant is already generating 12 MW.  Additional power demand due to the installation of the new clinkerisation unit will be around 15 MW and planned to be sourced from the local power grid of MPSEB.

 

3.96 MTPA over burden will be generated and proposed to be back filled after extraction of limestone . 

 

The public hearing meeting was held on 28th June 2008. The committee took the note of the public hearing proceeding. The issue raised during public hearing have been satisfactorily addressed and incorporated in the EIA/EMP.

 

After detailed deliberations, the Committee did not found EIA/EMP complete and adequate and deferred the proposal. The committee desired the following information for reconsideration: 

 

1.      Complete assessment report regarding water sources, water consumption, wastewater generation, rain water harvesting, water table depth etc. with statistical/ analytical calculations.

2.      Water conservation scheme along with zero discharge.

3.      Details of arrangements for safety of water pond in mining area

4.      Detailed design of protection arrangement for river passing through mine area.

5.      The scheme for mitigation of Fluoride in water

6.      The concentration of chlorides required to rechecked and details provided

7.      Details of mining benches and operations.

8.      Mining area reclamation scheme and progress till date

9.      Scheme for OB management

10.  Details of ground vibration study

11.  Dust suppression plan with latest technology

 

 

11.16   Cement Plant (Cement Plant 1.91 MTPA; 1.50 Clinker), Coke Oven Plant (1.5 LTPA) and Captive Power Plant (50 MW) near Village Padhiarka, Taluka Mahuva, District Bhavnagar, Gujarat by M/s Nirma Ltd. (EC)

 

The project authorities and their consultant gave a detailed presentation on the salient features of the project and proposed environmental protection measures to be undertaken as per Draft Terms of References (TORs) awarded during the 77th Meeting of the Expert Appraisal Committee (Industry) held during 21st to 24th January, 2008 for preparation of EIA/EMP.  All the Cement plants are listed S.N. 3(b) under Category ‘A’ and is appraised at the Central level.  

 

            PAs informed to the Committee that M/s Nirma Ltd. has proposed for the cement Plant (Cement Plant 1.91 MTPA; 1.50 Clinker), Coke oven plant (1,50,000 TPA) and Captive Power Plant (50 M) near Village Padhiarka, Taluka Mahuva, District Bhavnagar, Gujarat.  Total project area is revised to 268 ha instead of 280 ha. out of which 170 ha. will be used for cement plant and CPP. No National Park/Wildlife sanctuary/Reserve forest is located within 10 km radius of the project. Total area of the project is 280 ha. Total cost of the project earlier proposed as Rs. 779.50 Crores, revised to Rs. 828.50 Crores is further revised to Rs. 893.52 Crores.  Rs 38.79 Crores and Rs. 4.46 Crores are earmarked towards the capital cost and recurring cost/annum for environmental pollution control measures.

 

            Limestone (6,935 TPD) from captive mine (Padhiarka); Clay (110 TPD) from Goga, Gujarat, Sand 71 (TPD) from Bhavnagar Gujarat, Gypsum (390 TPD) from Barmer, Rajasthan, Coal (300 TPD, Import), Lignite (500 TPD) from Kutch, Fly ash (1,370 TPD) from CPP and Gandhinagar, Gujarat will be used as raw material. Lime will be sourced from captive limestone located at pithead and will be transported through conveyers. PAs also informed that they have already applied for the mining lease and is yet to be approved.

     

Out of 1.91 MTPA Cement, 2,350 TPD OPC and 3,450 TPD PPC will be manufactured. Cement manufacturing will involve raw meal grinding, blending, pre-calcining, clinker burning and cement grinding.  The clinker will be ground with gypsum and / or fly ash to a fine product called cement. Dry process technology will be adopted. Pre-calcination with rotary kiln and 6-stage cyclone pre-heater technology will be adopted for manufacturing OPC/PPC cement.

     

PAs informed to the Committee that coke oven (non-recovery type) of proven technology will be adopted for coke manufacturing which will be used to generate power for the cement plant and also as fuel for lime plant. No solid waste and liquid effluent will be generated from the coke oven plant. No by-products will be generated from the coke oven plant.  Energy will be recovered through WHRB and used for the power generation. Circulating Fluidized Bed Combustion (CFBC) boilers 2x25 MW Turbo-alternators with water-cooled condensers will be installed in CPP.

 

Air quality monitoring was carried out at 5 locations during March-May 2007 indicating SPM (76-166 mg/m3), RPM (31-67 mg/m3), SO2 (5.0-10.4 mg/m3) & NOx (6.5 – 10.7 mg/m3). ESP will be provided to cooler, WHRB and CPP boiler.  Bag house will be provided to kiln/Raw mill and Lignite/Coal mill, cement mill to control emissions within 50 mg/Nm3.  Bag filters will be provided to crusher, coal mill and packing plant to control fugitive dust from the Cement plant.  Dust suppression will be provided at transfer points and coal/lignite handling area. Fly ash and clinker will be stored in silos.

 

Total water requirement from Sea through desalination plant will be 8,500 m3/day for the process and 20,000 m3/hr sea water for the CPP.  PAs also informed to the Committee that 1.50 MGD water will be sourced from Narmada pipeline for which permission has been accorded by Gujarat Water Infrastructure Ltd. vide letter dated 3rd September, 2004. ETP sludge (5 TPD) and STP sludge (10 TPD) will be generated.  Dust (1,072 TPD) collected in various APC equipments will be recycled back to the process.  Refractory bricks (400 TPA) will be replaced once in a year and sold to outside agencies. ETP sludge will be used for land filled.  STP sludge will be used as manure.  Fly ash (12.5 TPD) will be used in manufacturing PPC. Spent transformer oil, waste oil, automobile batteries will be sold to recyclers. No effluent will be generated from the Coke oven since the effluent will be used for quenching. High calorific hazardous waste will be utilized in the kiln as fuel.

 

                        Green belt will be developed in 33 % area. Power (44 M) is required and met from proposed total lignite base CPP (50 MW). Power will be sourced from GSEB too. As a precaution regarding cyclones/storms, specific precautions will be taken by constructing tall buildings to maximum 50 m/sec wind velocity. 

 

The Committee deliberated upon the issues raised during the Public Hearing / Public Consultation meeting conducted by the Gujarat Pollution Control Board on 9th September, 2008. The issues like salinity control, employment, social development, road construction, CRZ clearance, mine clearance etc were discussed and have satisfactorily been incorporated in the final EIA/EMP report.

           

            After detailed deliberations, the Committee found the final EIA/EMP report adequate and suggested to stipulate following specific conditions alongwith other environmental conditions while considering for accord of environmental clearance :

 

1.      Continuous stack monitoring facilities to monitor gaseous emissions from all the stacks should be provided.  After expansion, limit of SPM should be controlled within 50 mg/Nm3 by installing adequate air pollution control system. 

2.      Proper and full utilization of coke oven gases in power plant using heat recovery steam generators (WHRB) should be ensured and no flue gas shall be discharged into the air.

3.      The prescribed emission standards for coke oven plants as notified vide notification no. GSR 46 (E) dated 3rd February, 2006 should be complied with.

4.      Secondary fugitive emissions should be controlled and should be within the prescribed limits and regularly monitored. Guidelines / Code of Practice issued by the CPCB in this regard should be followed.

5.      The company should install adequate dust collection and extraction system to control fugitive dust emissions from different sources. All the raw material stock piles should be covered.  All conveyers should be covered with GI sheets. Covered sheds for storage of raw materials and fully covered conveyers for transportation of materials should be provided besides coal, cement, fly ash and clinker shall be stored in silos.   Pneumatic system should be used for fly ash handling.

6.      Asphalting/concreting of roads and water spray all around the stockyard and loading/ unloading areas in the cement plant should be carried out to control fugitive emissions. Regular water sprinkling should be carried out in critical areas prone to air pollution and having high levels of SPM and RPM such as haul road, loading and unloading points, transfer points and other vulnerable areas. It should be ensured that the ambient air quality parameters conform to the norms prescribed by the Central Pollution Control Board in this regard.

7.      Efforts should be made to reduce impact of the transport of the raw materials and end products on the surrounding environment including agricultural land. All the raw materials including fly ash should be transported in the closed containers only and should not be overloaded.  Vehicular emissions be regularly monitored.   

8.      Total water requirement for cement plant from Gujarat Water Infrastructure Ltd. should not exceed 1,50 MGD as per the permission accorded.  All the treated wastewater should be recycled and reused in the process and/or for ash quenching, dust suppression, green belt development and other plant related activities etc. No process wastewater should be discharged outside the factory premises and ‘zero’ discharge shall be adopted. 

9.      All the bag filter dust, raw meal dust, coal dust, clinker dust and cement dust from pollution control devices should be recycled and reused in the process and used for cement manufacturing. Coal and coke fines should be recycled and reused in the process. The waste oil shall be properly disposed off as per the Hazardous Waste (Management & Handling) Rules, 1989 and subsequent amendments and should be sold to authorized recyclers / reprocessors only.

10.  All the fly ash should be utilized as per Fly ash Notification, 1999 subsequently amended in 2003. Efforts should be made to use fly ash maximum in making Pozollona Portland Cement (PPC).

11.  Efforts should be made to use low grade lime, more fly ash and solid waste in the cement manufacturing.

12.  An effort should be made to use of high calorific hazardous waste in the cement kiln and necessary provision should be made accordingly.

13.  As proposed, green belt should l be developed in at least 33 % area.

14.  All the recommendations made in the Charter on Corporate Responsibility for Environment Protection (CREP) for the Cement and Coke Oven Plants should be implemented.

15.  CRZ clearance for laying the pipeline in coastal area under the CRZ Notification should be obtained from the concerned department/authority.

16.  An impact assessment study should be carried out for the disposal of treated effluent into the seawater and all the recommendations should be implemented.

 

 

11.17   Steel plant (Sponge Iron 3,00,000 TPA; CPP 72 MW; MS Billets 5,00,000 TPA; Coal Washery 2 MTPA) at Village Ukam, Tehsil Rairangpur, Mayarbhanj, District Orissa by M/s. Dagara Minerals & Alloys Limited. (TOR)

 

  

 

The project authorities and their consultant gave a presentation on the features of the project and proposed environmental protection measures to be undertaken alongwith the draft Term of References for the preparation of EIA/EMP. All sponge iron manufacturing units more than 200 TPD capacity are listed at serial no. 3(a) (b) under category “A” projects in schedule of EIA Notification, 2006. Hence the instant case will come under category “A” and will be appraised at centre level.

 

M/s Dagara Minerals and Alloys Limited has proposed for setting up of integrated steel plant Sponge iron (3 lakh TPA), MS billet/Ingots (5 lakh TPA), power (72 MW), coal Washery (20 lakh TPA), pig iron (2.5 lakh TPA), coke oven (2 lakh TPA), sinter plant (32 m. sq. ) at Ukam Village, Rairangpur Tehsil, Mayarbhanj Ditrict, Orissa. The total land required for the project will be 600 acres. No eco-sensitive areas are located within 15 km periphery of the plant. The total cost of the project will be Rs. 998 Crores.

 

The product and production capacity are as given below:

 

S. No.

Details

Capacity

1.                   

Sponge Iron

300000 TPA

2.                   

M.S. Billets/ingots

500000 TPA

3.                   

Power

(I)                  WHRB

(II)                FBC

Total

 

30 MW

42 MW

72 MW

4.                   

Coal washery

2.00 MTPA

5.                   

Pig Iron

250000 TPA

6.                   

Coke oven

200000 TPA

7.                   

Sinter Plant

32 M2

 

The various raw materials will be used in proposed project are Iron Ore 480000 TPA, Coal 2390000 TPA (inclusive of washery), Dolomite-15000 TPA.

 

The emission from SMS will be controlled by providing a Fume Extraction System with bag filters and then let out into the atmosphere through stacks of 30m height. Dust suppression system will be provided in unloading areas. Dust extraction system with bagfilters will be provided in coal crushing and screening, cooler discharge area, product separation areas etc. All conveyors will be covered with GI sheets. All internal roads will be asphalted.

 

The water required for the plant will be met from khadakhi suleipit reservoir. The total water requirement for the proposed project will be 975 cum/hr. No waste water generation from the DRI, SMS, MBF, Sinter Plants as closed circuit cooling system will be adopted. GCP blow down from MBF will be recycled back. DM plant regeneration water & boilers blowdown will be neutralized in a neutralization tank and will be mixed with CT Blowdown in a central monitoring basin and will be used for dust suppression, ash conditioning and for green belt development. Sanitary waste water will be treated in septic tank followed by soak pit.

 

The solid waste generated will be Dolochar -90000 TPA, Accretion slag - 750 TPA, Slag from SMS - 50000 TPA and  Ash/Dust - 100000 TPA.  The entire dolochar generated from sponge iron kilns will be completely utilized in AFBC boiler as fuel. Slag from SMS will be used in road construction/filling of low lying areas. Accretion slag will be used for filling of low lying areas. Ash generated from ESP of FBC Boiler & WHRB will be given to cement plants/brick manufactures in the area. Bag filter dust will be given to brick manufacturers and Agarbathi manufacturers in the area.

 

The committee noted that the project a village is coming in the project area which should excluded from the project area. After deliberating on the facts presented the Expert Appraisal Committee (Industry) recommended the proposal for the preparation of EIA/EMP as per the following TORs :

 

1.      Evaluation of the site vis-à-vis alternate site.

2.      Exclusion of the village area falling within the proposed site

3.      Orientation of the layout to minimize the impact of air polluting units on the nearby village and forests. Complete and final layout should be incorporate

4.      Present land use should be prepared based on satellite imagery for study area of 10 km radius around the site.

5.      Location of national parks / wildlife sanctuary within 10 km. radius should specifically be mentioned.

6.      Site-specific micro-meteorological data using temperature, relative humidity, hourly wind speed and direction and rainfall should be collected.

7.      List of raw material required and source should be included.

8.      Manufacturing process for each products should be included.

9.      Details of land and its utilization breakup with justification.

10.  Fuel analysis, quantity of fuel required, its source and transportation.

11.  One season ambient air quality data (except monsoon) at 8 locations within the study area of 10 km., aerial coverage from project site with one AAQMS in downwind direction should be carried out. The monitoring stations should take into account the pre-dominant wind direction, population zone and sensitive receptors including reserved forests.

12.  The suspended particulate matter present in the ambient air must be analysed for the presence of poly-aromatic hydrocarbons (PAH), i.e. Benzene soluble fraction. Chemical characterization of RSPM and for incorporating of RSPM data.

13.  Determination of atmospheric inversion level at the project site and assessment of ground level concentration of pollutants from the stack emission based on site-specific meteorological features. Air quality modelling for steel and cement plant for specific pollutants needs to be done. 

14.  Plant-wise air pollution control measures proposed for the control of gaseous emissions from all the sources should be incorporated.

15.  A note on control of fugitive and secondary emissions from as per CPCB guidelines from all the sources should be incorporated.

16.  One season data for gaseous emissions during winter season is necessary.

17.  Impact of the transport of the raw materials and end products on the surrounding environment should be assessed and provided. Details of layout plan of railway siding should be provided with EIA.

18.  Permission for the drawl of water from Reservoir from the concerned department of Orissa department and should be provided with the EIA report.

19.  Water balance data including quantity of effluent generated, recycled and reused and discharged should be provided. Details of the Methods to be adopted for the water conservation.

20.  Surface water quality of nearby rivers and dam (60 m upstream and downstream) and other surface drains at eight locations must be ascertained. 

21.  Ground water monitoring minimum at 8 locations and near solid waste dump zone, Geological features and Geo-hydrological status of the study area are essential as also.  Ecological status (Terrestrial and Aquatic) is vital.

22.  A note on treatment of wastewater from different plants including coke oven plant, recycle and reuse for different purposes should be included.

23.  Action plan for solid/hazardous waste generation, storage, utilization and disposal particularly tailings, slag, char and fly ash. Copies of MOU regarding utilization of ash should be included.

24.  Detailed plan of ash utilization / management, evacuation of ash, ash pond impermeability and whether it would be lined, if so, details of the lining etc. and MOU signed with the Cement manufacturers for utilizing granulated BF slag should be included.

25.  Generation and utilization of waste/fuel gases from plant and their utilization in the CPP have to be set out.

26.  Risk assessment and damage control needs to be addressed.

27.  Occupational health of the workers needs elaboration.

28.  Green belt development plan in 33 % area and a scheme for rainwater harvesting have to be put in place.

29.  Socio-economic development activities need to be elaborated upon.

30.  Rehabilitation & Resettlement (R & R) plan as per the policy of the State Govt. and National Rehabilitation & Resettlement Policy, 2007 as applicable in the instant case. All the details including land acquired / to be acquired, number of families affected, provision of land for land; compensation, facilities, employment, training etc. including time bound action plan should be included.

31.  Details of programmes for the establishment of educational, graduate, ITI, Engineering Colleges or any other institution to improve the quality of life for the affected persons.

32.  A note on identification and implementation of Carbon Credit project should be included.

33.  An Action Plan for the implementation of the recommendations made for the Steel and Cement Plants in the CREP guidelines must be prepared.

34.   Conservation plan for the reserve forests within 10 km radius should be included

35.  Total capital cost and recurring cost/annum for environmental pollution control measures should also be included.

36.  A tabular chart for the issues raised and addressed during public hearing/public consultation should be provided.

37.  Any litigation / court case pending against the proposed land/proposal should also be included.

 

The Expert Committee (Industry) decided that PAs may be communicated the above ‘TORs’ for the preparation of EIA/EMP.  As soon as the draft EIA/EMP report is prepared as per the ‘General Structure of EIA’ given in Appendix III and IIIA in the EIA Notification, 2006, the same may be submitted by the PAs to the Orissa Pollution Control Board (OPCB) for conducting public hearing as per EIA Notification, 2006.   On finalization of EIA/EMP prepared as per TORs addressing all concerns set out EIA/EMP should be submitted to the MOEF for prior environmental clearance.

 

 

 

11.18   Expansion of Sponge Iron to Integrated Steel plant at Plot No. 98, Industrial Estate, Kalunga, District Sundergarh, Orissa by M/s. Nixon Steel & Power limited. (TOR)

 

The project authorities and their consultant gave a presentation on the features of the project and proposed environmental protection measures to be undertaken alongwith the draft Term of References for the preparation of EIA/EMP. All sponge iron manufacturing units more than 200 TPD capacity are listed at serial no. 3(a) (b) under category “A” projects in schedule of EIA Notification, 2006. Hence the instant case will come under category “A” and will be appraised at centre level.

 

M/s Nixon Steel and Power Limited has proposed for expansion of sponge iron from (350 TPD to 700 TPD) and setting up of coal Washery (0.35 MMTPA), power plant (36 MW), induction furnace (8 No. X 12 T), Ladle refining furnace (2 No. X30 T), VOD/AOD (2 No. X 30 T), Continuous casting machine (6/11 double strand 2 No.) at plot No. 98, Industrial Estate, Kalunga, District Sundergarh, Orissa. No eco-sensitive areas are located within 10 km periphery of the plant. River Brahmani, Sankha and Koel are located at 4 to 5 KM distance from proposed project site. The total cost of the project will be Rs. 235.20 Crores. The total land required for the project will be 80 acres. 

 

Details of the raw material used for different process including existing 350 TPD DRI Kiln are given below:

Iron ore                        :           3, 69,600 TPA

Coal                             :           3, 50,000 TPA through coal washery and 1, 00,000 ROM

Dolomite                      :           14 TPD

Chrome Ore/

 Manganese Ore         :           24000 TPA/89856 TPA respectively

Briquettes                    :           57000 TPA

Quartzite                     :           6000 TPA

Coke                            :           18000 TPA

Electrode Paste          :           650 TPA         

 

For control of air pollution ESPs, Bag filters and fumes extraction system will be provided. Water requirement will be  210 cum/hr including existing use of 41 cum/hr. The water will be supplied by IDCO. In addition during non availability of IDCO supply surface water from River Sankh / River Brahmani which is at about 4 to 5 km from the project site will be drawn with permission from State Irrigation and water Resource Department. Sewage and all other effluents will be treated as per the norms. Sanitary waste of the plant the provision of septic tank and soak pit are provided.

 

Dolo Char, Fly Ash, Furnace slag and Sludge from water Re-circulation System wil be the solid/hazardous waste. And sludge from water treatment plant is disposed off at designated disposal site.

 

The  power requirement will be 65 MW which will be met from captive generation (36 MW) and 29 MW from State Electricity Grid.

 

After deliberating on the facts presented the Expert Appraisal Committee (Industry) recommended the proposal for the preparation of EIA/EMP as per the following TORs :

 

1.      Present land use should be prepared based on satellite imagery for 10 km radius around the plant.

2.      Location of national parks / wildlife sanctuary within 10 km. radius should specifically be mentioned.

3.      Site-specific micro-meteorological data using temperature, relative humidity, hourly wind speed and direction and rainfall should be collected.

4.      List of raw material required and source should be included.

5.      Details of the manufacturing processes.

6.      Details of the products alloys along with annual production of stainless steel, alloys etc

7.      Details of the specifications of Re-rolling mill, VOD/AOD etc

8.      Fuel analysis, quantity of fuel required, its source and transportation.

9.      One season ambient air quality data (except monsoon) at 8 locations within the study area of 10 km., aerial coverage from project site with one AAQMS in downwind direction should be carried out. The monitoring stations should take into account the pre-dominant wind direction, population zone and sensitive receptors including reserved forests.

10.  The suspended particulate matter present in the ambient air must be analysed for the presence of poly-aromatic hydrocarbons (PAH), i.e. Benzene soluble fraction. Chemical characterization of RSPM and for incorporating of RSPM data.

11.  Determination of atmospheric inversion level at the project site and assessment of ground level concentration of pollutants from the stack emission based on site-specific meteorological features. Air quality modelling for steel and cement plant for specific pollutants needs to be done. 

12.  Plant-wise air pollution control measures proposed for the control of gaseous emissions from all the sources should be incorporated.

13.  A note on control of fugitive and secondary emissions from as per CPCB guidelines from all the sources should be incorporated.

14.  Existing emission data for the ambient air. Stack emissions and fugitive emissions.

15.  One season data for gaseous emissions during winter season is necessary.

16.  Impact of the transport of the raw materials and end products on the surrounding environment should be assessed and provided.

17.  Alternate modes of transportation of coal for the project should be examined and their relative merits and demerits in terms of environmental impacts should be provided.

18.  Permission for the drawl of water from Riverground from the concerned department and permission should provided with EIA report.

19.  Consent of IDCO for supply of additional water for expansion should be incorporated.

20.  Water balance data including quantity of effluent generated, recycled and reused and discharged should be provided. Details of the Methods adopted/to be adopted for the water conservation.

21.  Surface water quality of nearby rivers and dam (60 m upstream and downstream) and other surface drains at eight locations must be ascertained. 

22.  Ground water monitoring minimum at 8 locations and near solid waste dump zone, Geological features and Geo-hydrological status of the study area are essential as also.  Ecological status (Terrestrial and Aquatic) is vital.

23.  A note on treatment of wastewater from different plants including coke oven plant, recycle and reuse for different purposes should be included.

24.  Action plan for solid/hazardous waste generation, storage, utilization and disposal particularly tailings, slag, char and fly ash. Copies of MOU regarding utilization of ash should be included.

25.  Detailed plan of ash utilization / management, evacuation of ash, ash pond impermeability and whether it would be lined, if so, details of the lining etc. and MOU signed with the Cement manufacturers for utilizing granulated BF slag should be included.

26.  Generation and utilization of waste/fuel gases from plant and their utilization in the CPP have to be set out.

27.  Risk assessment and damage control needs to be addressed.

28.  Occupational health of the workers needs elaboration.

29.  Green belt development plan in 33 % area and a scheme for rainwater harvesting have to be put in place.

30.  Socio-economic development activities need to be elaborated upon.

31.  Rehabilitation & Resettlement (R & R) plan as per the policy of the State Govt. and National Rehabilitation & Resettlement Policy, 2007 as applicable in the instant case. All the details including land acquired / to be acquired, number of families affected, provision of land for land; compensation, facilities, employment, training etc. including time bound action plan should be included.

32.  Details of programmes for the establishment of educational, graduate, ITI, Engineering Colleges or any other institution to improve the quality of life for the affected persons.

33.  A note on identification and implementation of Carbon Credit project should be included.

34.  An Action Plan for the implementation of the recommendations made for the Steel and Cement Plants in the CREP guidelines must be prepared.

35.  Total capital cost and recurring cost/annum for environmental pollution control measures should also be included.

36.  A tabular chart for the issues raised and addressed during public hearing/public consultation should be provided.

37.  Any litigation / court case pending against the proposal should also be included.

 

The Expert Committee (Industry) decided that PAs may be communicated the above ‘TORs’ for the preparation of EIA/EMP.  As soon as the EIA/EMP report is prepared as per the ‘General Structure of EIA’ given in Appendix III and IIIA in the EIA Notification, 2006, the same may be submitted by the PAs to the MOEF for prior environmental clearance. Public hearing is not required as per para 7(i)IIIStatege(3)(b) of the EIA Notification 2006.

 

 

11.19   Expansion of Sponge Iron plant (200 TPD to 400 TPD), Induction furnace (2 x 8T) along with CCM (1x2 strands), Captive power Plant (8 MW-WHRB+8MW-AFBC) & Ferro alloy plant (2 x 9 MVA)  at Village Sahebdhi, P.S. Barjora, District Bankura, West Bengal by M/s. Govinda Impex Ltd. (TOR)

 

The project authorities and their consultant gave a detailed presentation on the salient features of the project and proposed environmental protection measures to be undertaken alongwith the draft TORs for preparation of EIA/EMP report. All the Primary metallurgical processing industries are listed at serial no. 3(a) under category “A” project. In instant case the project is covered under category “A” and appraised at the centre.

 

M/s Govinda Impex Ltd. has proposed for expansion of Sponge Iron Plant and setting up of Induction furnace (2 x 8T) along with CCM (1x2 strands), Captive power Plant (8 MW-WHRB+8MW-AFBC) & Ferro alloy plant (2 x 9 MVA) at Distt. Bankura, West Bengal. The total cost of the project will be Rs. 108 Crores. The total land required for the project will be 60.15 acres.  No eco-sensitive areas are located within 15 km periphery of the plant.

 

The main raw materials are required for this plant is Iron Ore, Dolomite, Manganese Ore, Steam Coal, Coke Breeze etc. Iron Ore 96000 TPA, Dolomite 3000 TPA and Manganese Ore 22260 TPA for the production of Ferro Manganese & 11880 TPA for the production of Silico Manganese.

 

For control of air polution ESPs to DRI Plant & AFBC Boiler and Bag filters to Induction Furnace and Ferro Alloys Plant will be provided. The total water requirement for existing plant is 1140 KLD. 100 KLD for Sponge Iron Plant, 1000 KLD for Steel melting Shop & 40 KLD for Ferro Alloys Plant. The source of water will be Barjora Panchayat Samiti.

 

The details of the solid and hazardous wastes are as given below:

 

Waste

Quantity

Utilization

Char

24,000 TPA

Will be utilized in AFBC Boiler & sold to other end users

Slag

20640 TPA (Fe Mn Slag)

Will be used in the production of Si Mn

Slag

25,806 TPA (Si Mn Slag)

Will be used as boulders for road / land development

Slag

4260 TPA (induction furnace Slag)

Land leveling, compacting of roads etc.

Bag filter dust

300 TPA

Will be sent to sinter plants

Mill scale

50 TPA

Land development

Steel scrap

640 TPA

Reused in steel melting shop

 

The power requirement will 8 MW for Induction Furnace, 16 MW for Ferro Alloy Division and 1.6 MW for Sponge Iron Division and will be sourced from CPP and from West Bengal State Electricity Distribution Company Ltd. (WBSEDCL)

 

After deliberating on the facts presented the Expert Appraisal Committee (Industry) recommended the proposal for the preparation of EIA/EMP as per the following TORs :

 

1.      Present land use should be prepared based on satellite imagery.

2.      Location of national parks / wildlife sanctuary within 10 km. radius should specifically be mentioned.

3.      Site-specific micro-meteorological data using temperature, relative humidity, hourly wind speed and direction and rainfall should be collected.

4.      List of raw material required and source should be included.

5.      Fuel analysis, quantity of fuel required, its source and transportation.

6.      One season ambient air quality data (except monsoon) at 8 locations within the study area of 10 km., aerial coverage from project site with one AAQMS in downwind direction should be carried out. The monitoring stations should take into account the pre-dominant wind direction, population zone and sensitive receptors including reserved forests.

7.      The suspended particulate matter present in the ambient air must be analysed for the presence of poly-aromatic hydrocarbons (PAH), i.e. Benzene soluble fraction. Chemical characterization of RSPM and for incorporating of RSPM data.

8.      Determination of atmospheric inversion level at the project site and assessment of ground level concentration of pollutants from the stack emission based on site-specific meteorological features. Air quality modelling for steel and cement plant for specific pollutants needs to be done. 

9.      Plant-wise air pollution control measures proposed for the control of gaseous emissions from all the sources should be incorporated.

10.  A note on control of fugitive and secondary emissions from as per CPCB guidelines from all the sources should be incorporated.

11.  Existing emission data for the ambient air. Stack emissions and fugitive emissions.

12.  One season data for gaseous emissions during winter season is necessary.

13.  Impact of the transport of the raw materials and end products on the surrounding environment should be assessed and provided.

14.  Alternate modes of transportation of coal for the project should be examined and their relative merits and demerits in terms of environmental impacts should be provided.

15.  Permission for the drawl of water from River from the concerned department and water balance data including quantity of effluent generated, recycled and reused and discharged should be provided. Methods adopted/to be adopted for the water conservation.

16.  Surface water quality of nearby rivers and dam (60 m upstream and downstream) and other surface drains at eight locations must be ascertained. 

17.  Ground water monitoring minimum at 8 locations and near solid waste dump zone, Geological features and Geo-hydrological status of the study area are essential as also.  Ecological status (Terrestrial and Aquatic) is vital.

18.  A note on treatment of wastewater from different plants including coke oven plant, recycle and reuse for different purposes should be included.

19.  Action plan for solid/hazardous waste generation, storage, utilization and disposal particularly tailings, slag, char and fly ash. Copies of agreements regarding utilization of ash should be included.

20.  Detailed plan of ash utilization / management, evacuation of ash, ash pond impermeability and whether it would be lined, if so, details of the lining etc. and agreement signed with the Cement manufacturers for utilizing granulated BF slag should be included.

21.  Generation and utilization of waste/fuel gases from plant and their utilization in the CPP have to be set out.

22.  Risk assessment and damage control needs to be addressed.

23.  Occupational health of the workers needs elaboration.

24.  Green belt development plan in 33 % area and a scheme for rainwater harvesting have to be put in place.

25.  Socio-economic development activities need to be elaborated upon.

26.  Rehabilitation & Resettlement (R & R) plan as per the policy of the State Govt. and National Rehabilitation & Resettlement Policy, 2007 as applicable in the instant case. All the details including land acquired / to be acquired, number of families affected, provision of land for land; compensation, facilities, employment, training etc. including time bound action plan should be included.

27.  Details of programmes for the establishment of educational, graduate, ITI, Engineering Colleges or any other institution to improve the quality of life for the affected persons.

28.  A note on identification and implementation of Carbon Credit project should be included.

29.  An Action Plan for the implementation of the recommendations made for the Steel and Cement Plants in the CREP guidelines must be prepared.

30.  Total capital cost and recurring cost/annum for environmental pollution control measures should also be included.

31.  A tabular chart for the issues raised and addressed during public hearing/public consultation should be provided.

32.  Any litigation / court case pending against the proposal should also be included.

 

The Expert Committee (Industry) decided that PAs may be communicated the above ‘TORs’ for the preparation of EIA/EMP.  As soon as the draft EIA/EMP report is prepared as per the ‘General Structure of EIA’ given in Appendix III and IIIA in the EIA Notification, 2006, the same may be submitted by the PAs to the West Bengal Pollution Control Board (WBPCB) for conducting public hearing as per EIA Notification, 2006.   On finalization of EIA/EMP prepared as per TORs addressing all concerns set out EIA/EMP should be submitted to the MOEF for prior environmental clearance.

 

 

11.20   Manufacturing of  Pig Iron (15,000 TPA), Ingots (15,000 TPA), Silico Manganese (9,000 TPA) and Cement grinding unit (18,000 TPA) at Paiki, P.O Marar, District Hazaribagh, Jharkhand by M/s. Radha Casting & Metallic (P) Limited. (TOR)

 

The project authorities and their consultant gave a detailed presentation on the salient features of the project and proposed environmental protection measures to be undertaken alongwith the draft TORs for preparation of EIA/EMP report. All the Primary metallurgical processing industries are listed at serial no. 3(a) under category “A” project. In instant case the project is covered under category “A” and appraised at the centre.

 

M/s. Radha Casting & Metallic (P) Limited has proposed for setting up of Pig Iron plant (15,000 TPA), Ingots (15,000 TPA), Silico Manganese (9,000 TPA) and Cement grinding unit (18,000 TPA) at Paiki, P.O Marar, District Hazaribagh, Jharkhand . The land requirement will be 22 acres. Out of 22 acres 5 acres will be earmarked for the green belt. The cost of the plant will be 17 Crores. The details of the products and production capacity are as given below:

 

-      Pig Iron : 15000 TPA

-      M.S. ingot : 15000 TPA

-      Silico Manganese : 9000 TPA

-      Cement Grinding Unit : 18000 TPA

 

The Gas Cleaning System will be provided with Mini Blast Furnace; Dust Collection System will be provided with MS Ingot Plant; Bag Filters will be provided in Silico Manganese Plant and Cement grinding unit for control of air pollution. Water spraying will be done in all the unloading & dust generation areas for dust suppression. The water requirement will be 130 m3/day. There will not be generation of any process effluent. Only domestic effluent about 2 m3/day will be generated which will be disposed of through septic tank and soak pit.

 

Slag (7500 TPA) generated from Pig Iron Plant will be utilised in cement grinding unit. SMS  Slag (2250 TPA) and slag from ferro alloy (4500 TPA) will be used for road making and land development.

 

The committee observer that the prefeasibility submitted was not up to the mark. The description of manufacturing process, raw materials and other details were not matching with the proposed products. After deliberating on the facts presented the Expert Appraisal Committee (Industry) recommended the proposal for the preparation of EIA/EMP as per the following TORs :

 

1.      Fresh form 1and prefeasibility report should be provided with EIA/EMP

2.      Present land use should be prepared based on satellite imagery.

3.      Location of national parks / wildlife sanctuary within 10 km. radius should specifically be mentioned.

4.      Site-specific micro-meteorological data using temperature, relative humidity, hourly wind speed and direction and rainfall should be collected.

5.      List of raw material required and source should be included.

6.      Fuel analysis, quantity of fuel required, its source and transportation.

7.      One season ambient air quality data (except monsoon) at 8 locations within the study area of 10 km., aerial coverage from project site with one AAQMS in downwind direction should be carried out. The monitoring stations should take into account the pre-dominant wind direction, population zone and sensitive receptors including reserved forests.

8.      The suspended particulate matter present in the ambient air must be analysed for the presence of poly-aromatic hydrocarbons (PAH), i.e. Benzene soluble fraction. Chemical characterization of RSPM and for incorporating of RSPM data.

9.      Determination of atmospheric inversion level at the project site and assessment of ground level concentration of pollutants from the stack emission based on site-specific meteorological features. Air quality modelling for steel and cement plant for specific pollutants needs to be done. 

10.  Plant-wise air pollution control measures proposed for the control of gaseous emissions from all the sources should be incorporated.

11.  A note on control of fugitive and secondary emissions from as per CPCB guidelines from all the sources should be incorporated.

12.  Existing emission data for the ambient air. Stack emissions and fugitive emissions.

13.  One season data for gaseous emissions during winter season is necessary.

14.  Impact of the transport of the raw materials and end products on the surrounding environment should be assessed and provided.

15.  Alternate modes of transportation of coal for the project should be examined and their relative merits and demerits in terms of environmental impacts should be provided.

16.  Permission for the drawl of water from the concerned department and water balance data including quantity of effluent generated, recycled and reused and discharged should be provided. Methods adopted/to be adopted for the water conservation.

17.  Surface water quality of nearby rivers and dam (60 m upstream and downstream) and other surface drains at eight locations must be ascertained. 

18.  Ground water monitoring minimum at 8 locations and near solid waste dump zone, Geological features and Geo-hydrological status of the study area are essential as also.  Ecological status (Terrestrial and Aquatic) is vital.

19.  A note on treatment of wastewater from different plants including coke oven plant, recycle and reuse for different purposes should be included.

20.  Action plan for solid/hazardous waste generation, storage, utilization and disposal particularly tailings, slag, char and fly ash. Copies of agreements regarding utilization of ash should be included.

21.  Detailed plan of ash utilization / management, evacuation of ash, ash pond impermeability and whether it would be lined, if so, details of the lining etc. and agreement signed with the Cement manufacturers for utilizing granulated BF slag should be included.

22.  Generation and utilization of waste/fuel gases from plant and their utilization in the CPP have to be set out.

23.  Risk assessment and damage control needs to be addressed.

24.  Occupational health of the workers needs elaboration.

25.  Green belt development plan in 33 % area and a scheme for rainwater harvesting have to be put in place.

26.  Socio-economic development activities need to be elaborated upon.

27.  Rehabilitation & Resettlement (R & R) plan as per the policy of the State Govt. and National Rehabilitation & Resettlement Policy, 2007 as applicable in the instant case. All the details including land acquired / to be acquired, number of families affected, provision of land for land; compensation, facilities, employment, training etc. including time bound action plan should be included.

28.  Details of programmes for the establishment of educational, graduate, ITI, Engineering Colleges or any other institution to improve the quality of life for the affected persons.

29.  A note on identification and implementation of Carbon Credit project should be included.

30.  An Action Plan for the implementation of the recommendations made for the Steel and Cement Plants in the CREP guidelines must be prepared.

31.  Total capital cost and recurring cost/annum for environmental pollution control measures should also be included.

32.  A tabular chart for the issues raised and addressed during public hearing/public consultation should be provided.

33.  Any litigation / court case pending against the proposal should also be included.

 

The Expert Committee (Industry) decided that PAs may be communicated the above ‘TORs’ for the preparation of EIA/EMP.  As soon as the draft EIA/EMP report is prepared as per the ‘General Structure of EIA’ given in Appendix III and IIIA in the EIA Notification, 2006, the same may be submitted by the PAs to the Jharkhand Pollution Control Board (Jharkhand PCB) for conducting public hearing as per EIA Notification, 2006.   On finalization of EIA/EMP prepared as per TORs addressing all concerns set out EIA/EMP should be submitted to the MOEF for prior environmental clearance.

 

 

 

11.21   Ferro alloys manufacturing unit at Industrial Estate, Sofi Nagar, APIIC, Nirmal, Adilabad District, Andhra Pradesh by M/s. Sushma Ferro alloys India Pvt. Ltd. (TOR)

 

The project authorities and their consultant gave a detailed presentation on the salient features of the project and proposed environmental protection measures to be undertaken alongwith the EIA/EMP report already prepared. All the Primary metallurgical processing industries are listed at serial no. 3(a) under category “A” project. In instant case the project is covered under category “A” and appraised at the centre.

 

M/s. Sushma Ferroalloys Pvt Ltd., proposed Primary metallurgical industry manufacturing Ferroalloys in an area of 3.4 acres at plot no: 6, Industrial Park, Sofi Nagar, APIIC, Nirmal Mandal, Adilabad District, Andhra Pradesh. Swarna River is passing at a distance of 2.5 Km in NW direction. No forest land acquisition and R&R is involved.  The company has already acquired 3.4 acres of land for the proposed plant of which 1.14 acres of the area will be brought under green belt.  Total cost of the project is Rs. 14 Crores. The detailes of the products and production capacity are as given below:

 

S.No

Description

Capacity (TPA)*

Phase-I

Phase-II

Total

1.

Ferro Manganese OR

2370

10350

12720

2.

Ferro Silicon         OR

1100

  3300

4400

3.

Silico Manganese OR

2200

  7500

9700

4.

Pig Iron

2370

10350

12720

*Maximum capacity of each alloy, manufacturing the above alloys on annul campaign basis.

 

The requirement of raw materials forvarious products are as given below:

 Silico Manganese

S.No

Material Consumed

Phase- I

(Approx per day)

Phase- II

(Approx per day)

1

Manganese Ore  

13

39.00

2

Coke/coal

5.0

15.00

3

Quartz  

1.7

5.10

4

Electrode Paste

0.2

0.80

5

Casing Sheet

0.03

0.12

6

M.S. Rod

0.08

0.32

Ferro Manganese

S.No

Material Consumed

Phase- I

(Approx per day)

Phase- II

(Approx per day)

1

Manganese Ore  

18

54.00

2

Coke/coal

5.8

17.00

3

Dolomite  

3.0

9.00

4

Electrode Paste

0.1

0.30

5

Casing Sheet

0.02

0.08

6

M.S. Rod

0.12

0.48

Ferro Silicon

S. No

Raw Material

Requirement

kg/t

TPD

Phase-I

Phase-II

1

Quartz

2000.0

6.7

20.1

2

Charcoal

1500.0

5.0

15.00

3

Iron scrap

350.0

1.2

3.6

4

Electrode paste

60.0

0.2

0.6

5

Casing sheet

5.0

0.017

0.051

6

M. S. Round

25

0.08

0.24

7

Lancing Pipe

5

16.6

49.8

8

Oxygen

5 m3

16.6 m3

49.8 m3

Pig Iron

S. No

Raw Material

Requirement, TPD

kg/t

Phase-I

Phase-II

1

Iron Ore        

2000.0

14.4

43.2

2

Coke

700.0

5.02

15.06

3

Dolomite

700

5.02

15.06

4

Electrode paste

15.0

0.1

0.1

5

Casing sheet

5.0

0.017

0.051

6

M. S. Round

25

0.08

0.24

7

Lancing Pipe

5

16.6

49.8

8

Oxygen

5 m3

16.6 m3

49.8 m3

 

The emission from submerged Electric Arc Furnace will be controlled by pulse jet filter bag house to bring down the particulate emission to less than 100 mg/ Nm3. Fume extraction system with bag filters and then let out into the atmosphere through a stack of 3o m height. Dust suppression system will be provided in unloaded areas. Dust curtains will be provided all round the work area to prevent the dust emissions. Water spraying will be done to prevent the dust emanation due to vehicular movement. Ambient air quality monitoring has been carried out for SPM, SO2 and NOx during March 2008 to May 2008 at six locations including the project site. The highest reported values for these parameters are 124 mg/m3, 9 mg/m3, and 11 mg/m3    respectively. Values conform to the prescribed standards for Ambient Air Quality.  The daily total water requirement for the plant shall be 25 KLD (6 KLD: Phase -I & 19 KLD: Phase-II) which is supplied by APIIC. The unit will generate 3.4 KLD (0.9 KLD: Phase –I & 2.5 KLD: Phase-II) of Cooling tower blow down and 6.7 KLD ((2.5 KLD: Phase –I & 4.2 KLD: Phase-II)   of domestic effluent during operation. The unit operations are equalization/neutralization tank, clarifier, collection tank and sludge drying beds.   The treated water shall be used recycled to the cooling tower and also used for green belt development.  Domestic effluents shall be sent to septic tank followed by soak pit.

 

The Solid/hazardous wastes generated from the plant will be as given below along with  mode of treatment and disposal:

S.No

Description

Quantity

Remarks

Phase-I

Phase-II

1.

Ash from furnace

0.25 TPD

0.75 TPD

Sold to brick manufacturers

2 .(i)

Slag from Si Mn

5.3 TPD

15.9  TPD

Used as construction material, land filling

   (ii)

Slag from Fe Mn

7.2 TPD

21.6 TPD

Used as raw material for SiMn

   (iii)

Slag from Fe Si

0.13 TPD

0.39 TPD

Used as construction material, land filling

3.

Slag from Pig Iron

3.23 TPD

9.69 TPD

Used as construction material, land filling

 

4.

Bag filter dust

21.6 kg/day

64.8 kg/day

Sold to brick manufacturers

5.

Waste oil

65 l /yr

80 l /yr

Sent to Authorized Recyclers

 

The total power requirement is 6.7 MVA which will be met from APTRANSCO.

 

PAs informed to the Committee that they have already prepared EIA/EMP and is circulated to the Committee members.  The committee after detailed deliberations found EIA/EMP complete and adequate and recommended the proposal for grant of environmental clearance subject to specific and general conditions. No public hearing is required due to location of the plant in notified industrial as per para 7(i) III, Statge (3)(b) of EIA Notification 2006. 

 

11.22   Induction furnace (2 x 12 TPH) for manufacturing of MS Ingots (66,000 TPA) at Gopalpur, P.O. Badaposi, District Keonjhar, Orissa by M/s. Kalinga Metallic & power Pvt. Ltd. (TOR)

 

PAs did not attend the meeting. The committee deferred the project.

 

11.23   Expansion of the Man made Fibre-Partially Oriented Yarn (POY) plant at Survey no. 46/1/3/1 and 37, Village Rakholi District Silvassa by M/s Bhilosa Industries Pvt. Ltd. (TOR)

 

 

The project authorities and their consultant gave a detailed presentation on the salient features of the project and proposed environmental protection measures to be undertaken alongwith the TORs for preparation of EIA/EMP. All the man made fiber manufacturing units are listed at serial no. 5 (d) of schedule of EIA Notification, 2006 and all projects other than rayon are categorized as “B” category. In the instant case the plant is located with 10 km inter state boundary hence as per general condition the proposal; is considered and apprised at central level.

 

M/s. Bhilosa Industries private Limited has proposed for expansion of manufacturing of man made fiber-Partially Oriented Yarn (POY) at Survey no. 46/1/3/1 and 37, Village Rakholi Distt. Silvassa, U.T. Total plot area of the project is 93850 m2 . Daman Ganga resevoir is at a distance of 1.12 km and reserve forests are located at the distance of 1.37 km NW, 2.11 km SW and 2.72 km SE from the plant. Information regarding location of national or interstate is not given. Total land available is 93850 m2. No additional land will be required for the project. Expansion will be within the existing premises. Land for green belt will be 5444.50 m2. The total cost of the project will be Rs. 148.8 Crores. The details of the products and production capacity are as given below:

 

Sr. No.

Name of the products

Capacity(MT/Day)

1

Synthetic Texturised yarn (Existing)

66.67

2

Partially Oriented Yarn (Proposed)

350

 

The details of raw-materials for proposed product are as given below:

 

Sr. No.

Name of raw materials

MT/MT

Source of supply

1

Purified terepthalic  acid

0.858

Reliance, MCPI, IOCL, Imports

2

Mono Ethylene glycol

0.328

Reliance, Indian, Glycol, Imports

3

Antimony trioxide

0.003

Chemico, Indian oxides, Imports

4

Titanium Dioxide

0.030

Sachtlben chemie, Fuji, Pretiox

 

There is no fuel consuming utilities installed in the existing plant hence there is no flue gas emission generated. The company proposes to install 1 No. of steam boiler of 4 MT/Hr capacity and 3 Nos of Thermic Fluid Heater each having capacity of 8 M K.cal/Hr for the proposed expansion project out of which one will act as Standby unit. Dual fired Power Engine of 4.8 MW capacity will be attached with chimney of  52 m height to control the utility emissions. The total water requirement of the plant is 937 KLD out of which 463 will be met from recycling and fresh requirement is 474 KLD. The wastewater will be 166 KLD which will be treated in the ETP. Treated wastewater will be utilised for green belt development. Domestic water consumption will be 11 KLD and wastewater generation will be 8KLD. The domestic wastewater will be disposed of through soak pits.

 

Hazardous Waste generation & Disposal Method - After Proposed Expansion as given below:

Types of Waste

Qty

Method of Disposal

ETP Waste

5MT/Month

Will be sent to GEPIL Site, Silvassa for final disposal .

Polymer waste

52.5 MT/ Month

Will be sold to actual users

POY waste

4 MT/ Month

Will be sold to actual users

PTA sweeping waste

4 MT/ Month

Will be sold to actual users

Used Oil

500 lits/month

Will be sold to registered recycler/ repprocessor

Empty bags

1260 Nos/Month

Will be sold to authorized scrap vendor

Empty PP Liners

7370 Kgs/Month

Will be sold to authorized scrap vendor

Empty drums

65 Nos/Month

Will be sold to authorized reconditioner

 

The Power requirement will be 4.2 MW which will be sourced from the State Electricity Board. Fuel requirement will be for Boilers, Thermic fluid heaters and dual fuel fired power engine.

 

The PAs requested the committee to consider the proposal for grant of environmental clearance as per para 7(ii) of the EIA Notification 2006 considering expansion case and backward integration of the plant and there will not be any emission from the plant & wastewater will be treated and recycled back for cooling and cooling tower bleed will be used for green belt development. The members were concerned about the wastewater quality, disposal of the wastewater, details of the new ETP and VOC level. After detailed deliberations, the EAC(I) satisfied with the proposed pollution control measures taken by the project authorities and recommended the proposal for grant of environmental clearance subject to specific and general conditions as per para7(ii) of EIA Notification 2006 requiring no public hearing and EIA/EMP subject submission of following information for record and circulation to the committee members for perusal:

 

1.      The details of the wastewater quality

2.      Detailed disposal plan of the wastewater along with the area in which it will be used. The water holding capacity of the area (duty-KLD/ha/day).

3.      The details of the new ETP

4.      VOC level in the similar plants

 

 

11.24   Expansion of Agro based paper plant from 20 TPD to 150 TPD & 4 MW co-generation plant at A-1 Industrial area, Village: Advenia Grant, Tehsil: Sitapur, Dist: Sitapur, Uttar Pradesh by M/s. J B Daruka Papers Limited (TOR)

 

PAs did not attend the meeting. The committee deferred the project.

 

 

11.25   Cement Plant (OPC/PPC 2.25 MTPA), Clinker (1.50 MTPA) Coal based Captive Thermal Power Plant (1x20 MW) at Village Amilia, Taluk Maihar, District Satna. Madhya Pradesh by M/s KJS Cement Pvt. Ltd. (TOR)

 

The project authorities and their consultant gave a detailed presentation on the salient features of the project and proposed environmental protection measures to be undertaken alongwith the draft TORs for preparation of EIA/EMP. All cement plant more than 1.0 MTPA and mines area more than 50 ha. are covered under Category ‘A’ as per para 3(b) of the Schedule of the EIA notification 2006. Instant case was considered as an integrated cement plant along with mines under category ‘A’ and appraised at central level.

 

M/s KJS Cement Pvt. Ltd.  Cement Plant (OPC/PPC- 2.25 MTPA), Clinker (1.50 MTPA) Coal based Captive Thermal Power Plant (1x20 MW) at Village Amilia, Taluk Maihar, District Satna Madhya Pradesh. The Sharda Temple is located at 6.5 km from the proposed site. The Ghuleti Reserve forest (6 km W), Kaimur R.F. (6 km S) and river Tamas (along the western boundary) are the sorroundinds of the plant. Total land acquired for the plant is 90 Hectare. Total cost of project will be Rs. 869.28 Crores.

 

The various raw materials are required for the proposed plant will be Lime Stone : 1.392.T/T of clinker, Sweetner : 0.16 T/T of clinker, Iron Ore : 0.048 T/T of clinker, Coal: 0.22 T/T of clinker, Gypsum : 0.05 T/T of cement, Power 95 kWh/T of Cement, Flyash 0.25 T/T of cement (PPC), Clinker 0.95 T/T of Cement (PPC), 20% clinker to be used for OPC, 80% clinker to be used for PPC.

 

ESP will be installed with clinker cooler and at other air pollution points bag filters will be provided. Particulate emission from various stacks and material transfer points is the main pollution from a cement plant. Adequate preventive measures to keep the pollution level of particulate emissions within 50 mg/Nm3 shall be provided in the plant. The total water requirement for the proposed plant is 2400 KLD. The water will be obtained by drilling bore wells near to Tamas river bed and harvested rain water in worked out pit of proposed limestone mine as raw material at 1.5 km distance.  Sludge from STP will be disinfected and used as manure. There is no wastewater generation at any stage of plant operation.

 

The total power requirement of  33 MW will be met from Madhya Pradesh Power Transmission Company Ltd. (13 MW) and proposed coal based Captive Power Plant (22 MW). The fuel requirement will be  600 TPD of Coal which will be sourced from SECL.

 

The committee discussed the location of the Sharda temple from the plant, PAs informed that it is at a distance of 6.5 km from the plant site. The member desired that one monitoring station should be at the Temple to assess the baseline data. The committee also discussed the predominent wind direction at the site area. The PAs informed that the Temple is not in the predominant wind direction. The Expert Appraisal Committee (Industry), after detailed deliberations finalised the following TORs for the cement Plant:

 

1         Present land use based on satellite imagery. Study area should be 10Km radius from the boundary of plant and mines.

2         Site-specific micro-meteorological data including inversion height and mixing height.

3         Collection of baseline data on air, water, soil, noise, flora, fauna etc. for one season other than monsoon.

4         Atleast one ambient air monitoring station should be set up near the Sharda temple.

5         Layout plan should be oriented in such a way to keep maximum distance of the plant from the Sharda temple and maximum plantation area should be in the direction the temple.

6         Details of the raw materials and manufacturing process.

7         Ambient air quality monitoring modeling for cement plant and mines. Cumulative impact of cement plant and mines should be assessed and incorporated.

8         Sources of secondary emissions, its control and monitoring as per the CPCB guidelines.

9         Chemical characterization of RSPM and incorporation of RSPM data. Location of one AAQM Station in downwind direction.

10     A full chapter on fugitive emissions and control technologies should be provided.

11     Water balance cycle data including quantity of effluent to be generated, recycled and reused and discharged.

12     Efforts should be made to minimize use of ground water and prior permission for drawl of 2400 KLD water will be obtained & an action plan should be provided. A chapter on hydrology study by the State Govt. may be included. Ground water monitoring minimum at 8 locations.

13     Action plan for surface as well as roof top rainwater harvesting and ground water recharge.

14     Scheme of proper/closed storage of fly ash, gypsum, clinker, coal.

15     A write up on use of high calorific hazardous wastes in kiln and commitment regarding use of hazardous waste.

16     Risk assessment and damage control.

17     Occupational health of the workers.

18     Green belt (33%) development plan as per CPCB guidelines. EMP should include a clear map/layout for plantation/green belt.

19     Socio-economic development activities.

20     Need based assessment study for the villagers.

21     Scheme for compliance to the recommendations mentioned in the CREP guidelines for cement plants.

22     Details of location of wildlife sanctuary and national parks within 10 km radius of the plant and plan for conservation and protection of the same should be included.

23     Detailed Environment management Plan (EMP) with specific reference to details of air pollution control system, water & wastewater management, monitoring frequency, responsibility and time bound implementation plan for mitigation measure should be provided.

24     EMP should include the concept of waste-minimisation, recycle/reuse/recover techniques, Energy conservation, and natural resource conservation.

25     A tabular chart of the issues raised and addressed during public hearing/public consultation should be provided.

 

Besides the above, the general points mentioned below should also to be followed during preparation of EIA/EMP:

 

1.      All documents to be properly referenced with index, page numbers and continuous page numbering.

2.      Where data are presented in the report especially in tables, the period in which the data were collected and the sources should be indicated.

3.      Where the documents provided in a language other than English, an English translation should be provided.

 

The Expert Committee (Industry) decided that PAs may be communicated the above ‘TORs’ for the preparation of EIA/EMP. As soon as the draft EIA/EMP report is prepared, the same may be submitted by the PAs to the M.P. Pollution Control Board (MPPCB) for conducting public hearing/public consultation as per EIA Notification, 2006. A letter may be written to the MPPCB to conduct public hearing/consultation within stipulated time frame.  On finalization of EIA/EMP prepared as per TORs and addressing and incorporating all concerns raised during public hearing / public consultation, the same should be submitted to the MOEF for prior environmental clearance.

 

11.26   Setting up of Iron Ore Beneficiation and Palletisation Plant (1.0 MTPA) at  Village Dharampura, Tehsil, Sihora District Jabalpur, Madhya Pradesh by M/s Eurobond Industries Pvt. Ltd. - (EC after TOR)

 

The project authorities and their consultant gave a detailed presentation on the salient features of the project and proposed environmental protection measures to be undertaken along with the EIA/EMP prepared based on the TORs awarded during 81st meeting of the EAC(I) held on 13th May 2008. Mineral beneficiation (³ 0.1million ton/annum mineral throughput) are listed in para 2(b) of schedule of EIA Notification, 2006 covered under category “A” and appraised at central level.

           

M/s Eurobond Industries Pvt. Ltd. has proposed for setting up an Iron Ore Beneficiation and Palletisation plant (1.0 MTPA) at Gram Panchayat, Dhrampura, Tehsil, Sihora, District Jabalpur, Madhya Pradesh. The Herran River is about 2 km away from the site.  The Bohra reserve forest is located at a distance of 8-8.5 km from the site. No National Parks/Wildlife sanctuaries are located with 10 km radius of the proposed site. The total area of the project will be 12.10 ha. The total cost of the projects will be Rs. 200.09 Crores. Out of this the capital cost will be Rs. 800 Lakhs and recurring cost will be 80 Lakhs.The product and production capacity of the plant will be 1MTPA Pallets.

 

The details of the Annual requirement of raw material and their source are as given below:

 

Sr. No.

Raw material

Quantity in MT

01

Iron Ore

17,40,000

02

Bituminous Coal

42,000

03

Limestone

15,000

04

Coke Bridge

10,000

05

Bentonite

10,000

06

Furnace Oil

As and when needed

 

Iron ore available between 52-57 % Fe content are mixed with water to make slurry and fed into classifier to separate by the size and coarser material below 1.00 mm is fed to spiral launders, and remaining are crushed in closed circuit ball mill, after which they are fed to magnetic separator and then to floatation vessels. Concentrate so obtained is thickened in thickner-ponds and dewatered by ceramic discs filters. Disposable slurry is also put into thickner pond and them to filter press to dewater. Water obtained in both the process is recirculated and concentrated iron ore is used for palletisation whereas the solid disposable leftover is disposed into abandoned mines to reclaimed the land.

 

 Concentrated iron ore are mixed with additive (Bentonite) and other inputs lime and coke breeze and are converted into green balls of required size in Disc Palletizer machines. These green balls are baked by heat first in traveling grate and then in rotary kiln. Baked pallets are cooled in the cooler and the heat is reused into rotary kiln and traveling grate. Rotary kiln has coal firing system for the heat required in the process. Spent hot air from traveling grate is put into ESP (Electrostatic Precipitators) to be cleaned to prescribed standard before being discharged from chimney of required height.

 

Total requirement of water is 35246 KLD and process water requirement will be 1040 KLD. Water will be sourced from Herran River and from 2-3 bore wells. The water used in the beneficiation will be settled and ecycled for reuse. No waste water will be generated from the plant. Crushers, traveling grate kiln, raw coal storage hopper, coal mill etc are the sources of particulate emission. The details of air pollution control arrangements to be provided are as given below:

 

Sr. No.

Area

Control Equipment

1

Crushing Plant

Bag Filter

2

Crusher Transfer Point

Spot Bag Filter

3

Dewatering of Slurry

Press filter

4

Traveling Grate/ Kiln

ESP

5

Raw Coal Storage Hopper

Spot Bag Filter

6

Coal / Petcoke Mill system

Bag Filter

7

Additive Mill System

Bag Filter

 

The solid  waste consisting of impurities of naturally available with iron ore. The solid waste will be used for filling of the abandoned mines in the vicinity. Solid waste is also suitable for brick making and would be delivered to local brick makers. The Process will not generate any hazardous waste, as there is no Hazardous Chemical involved in the process. The collector Katni has asked the PAs to submit application for disposal of 1.5 Lakh tonne/annum slurry in to abandoned mines vide his letter no. 1547/Khanij/2008 dated 24th March 2008.

 

The company has requirement of 15000 KVA of power which will be sourced from M P State Electricity Board for the power availability. Bituminous coal (51000 MT/A) is required as fuel including some quantity of furnace oil for back up DG sets.

 

The Committee deliberated upon the issues raised during the Public Hearing / Public Consultation meeting conducted by the Madhya Pradesh Pollution Control Board on 20th August, 2008 and found same were incorporated in the final EIA/EMP report.

 

The committee after detailed deliberations found the EIA/EMP complete and adequate. The committee recommended the proposal for grant of environmental clearance subject to specific and general conditions.

 

 

11.27               Expansion of Cement Plant – Increase of Clinker Production from 1.485 to 3.3 MTPA, Cement production from 2.25 MTPA to 5.0 MTPA, installation of 2 x 35 MW coal based Captive Power Plant and increase of limestone production from 2.25 to 5.0 MTPA at District Kadapa, Andhra Pradesh by M/s Raghuram Cements Limited (TOR)

 

The project authorities and their consultant gave a detailed presentation on the salient features of the project and proposed environmental protection measures to be undertaken alongwith the EIA/EMP prepared on the basis of the TORs awarded during 81st meeting of the EAC(I) held on 14th May 2008. All the cement manufacturing and clinker grinding units are listed at Sl. No. 3(b) of the Schedule of EIA Notification of 2006.  More than 1.0 MTPA Cement production capacity is kept under category ‘A’.  The instant case also falls under Category ‘A’ and was appraised at the centre.

 

M/s Raghuram Cements Limited have proposed for expansion of Cement Plant – Increase of Clinker Production from 1.485 to 3.3 MTPA, Cement production from 2.25 MTPA to 5.0 MTPA, installation of 2 x 35 MW coal based Captive Power Plant and increase of limestone production from 2.25 to 5.0 MTPA at District Kadapa, Andhra Pradesh. Seasonal river Pageru (1.3 km), Penneru (8.6 km) and Papagni (8.3 km) is away from the plant site.  The total area of the plant is 160 ha. and the proposed expansion will be within the existing premises. Out of this 30 ha. will be earmarked for the greenbelt development. The cost of the expansion will be Rs. 887 Crores.

 

The raw material for the project will be limestone (5 MTPA) and will be sourced from the captive mine.

 

Coal mill, and cement mill will be provided with Bag filter and Kiln/Raw mill will be provided with bag house to control the air emission. Cooler will be provided with ESP. Bag house and bag filter will be installed to control the dust emission from transfer points of belt and bucket conveyors. Fugitive dust generated due to clinker transportation will be controlled by water sprinkling. Electrostatic precipitator will be installed to control the fly ash generated from the boiler of CPP. The total water requirement for the project will be 8500 KLD which will be sourced from Sarvarayasagar reservoir/borewells. The total industrial wastewater of 1800 KLD will be recycled for use in cement plant and green belt development. A full fledge sewage treatment plant will be installed to treat the domestic waste water generated from the plant.

 

The solid waste from the sewage treatment plant will be used as manure in plantation. Spent oil and grease generated from the plant will be disposed off through licensed vendors. Ash (0.177 million tonnes/year) generated from power plant will be used for cement production. The sludge generated from the ETP will be 1.1 tonnes/day. The fly ash collected from ESP will be used in the cement manufacturing process.

 

Power requirement will be met from the captive power plant and from State Electricity Board. Coal (1440 tonnes/day) will be used as fuel for CFBC boilers of 160 TPH capacity.

 

The prject authorities informed that no mining lease area will be increased and cement plant will be installed within existing premises.

 

After detailed deliberations, the Committee found the final EIA/EMP report adequate. The committee recommended the proposal for grant of environmental clearance subject to following specific conditions alongwith other environmental conditions:

 

1.      Continuous stack monitoring facilities to monitor gaseous emissions from all the stacks should be provided and limit of SPM should be controlled within 50 mg/Nm3 from cement plant and captive power plant respectively by installing adequate air pollution control system.

2.      Secondary fugitive emissions should be controlled within the prescribed limits and regularly monitored. Guidelines / Code of Practice issued by the CPCB in this regard should be followed.

3.      Efforts should be made to reduce impact of the transport of the raw materials and end products on the surrounding environment including agricultural land.

4.      All the fly ash should be utilized as per Fly ash Notification, 1999 subsequently amended in 2003.

5.      An effort should be made to use of high calorific hazardous waste in the cement kiln and necessary provisions should be made accordingly.

6.      As proposed, green belt should be developed in 33 % in and around the plant as per the CPCB guidelines.

7.      The company shall make the arrangement for protection of nallah/river passing nearby the mines. Detailed action plan in this regards shall be submitted to the Ministry’s Regional Office at Bangalore.

8.      The project proponent shall modify the mine plan of the project at the time of seeking approval for the next mining scheme from the Indian Bureau of Mines so as to reduce the area for external over burden dump by suitably increasing the height of the dumps with proper terracing. It shall be ensured that the overall slope of the dump does not exceed 280.

9.      Topsoil, if any, shall be stacked with proper slope at earmarked site(s) only with adequate measures and should be used for reclamation and rehabilitation of mined out areas.

10.  The project proponent shall ensure that no natural water course shall be obstructed due to any mining operations.

11.  The inter burden and other waste generated shall be stacked at earmarked dump site(s) only and should not be kept active for long period. The total height of the dumps shall not exceed 30 m in three terraces of 10 m each and the over all slope of the dump shall be maintained to 280. The inter burden dumps should be scientifically vegetated with suitable native species to prevent erosion and surface run off. Monitoring and management of rehabilitated areas should continue until the vegetation becomes self-sustaining. Compliance status should be submitted to the Ministry of Environment & Forests and its Regional Office, Bangalore on six monthly bases.

12.  The void left unfilled shall be converted into water body. The higher benches of excavated void/mining pit shall be terraced and plantation done to stabilize the slopes. The slope of higher benches shall be made gentler for easy accessibility by local people to use the water body. Peripheral fencing shall be carried out along the excavated area.

13.  Catch drains and siltation ponds of appropriate size should be constructed for the working pit, inter burden and mineral dumps to arrest flow of silt and sediment. The water so collected should be utilized for watering the mine area, roads, green belt development etc. The drains should be regularly desilted, particularly after monsoon, and maintained properly.     

14.  Garland drain of appropriate size, gradient and length shall be constructed for both mine pit and inter burden dumps and sump capacity should be designed keeping 50% safety margin over and above peak sudden rainfall (based on 50 years data) and maximum discharge in the area adjoining the mine site. Sump capacity should also provide adequate retention period to allow proper settling of silt material. Sedimentation pits should be constructed at the corners of the garland drains and desilted at regular intervals.

15.  Dimension of the retaining wall at the toe of inter burden dumps and inter burden benches within the mine to check run-off and siltation should be based on the rain fall data.

16.  Regular monitoring of ground water level and quality should be carried out by establishing a network of existing wells and constructing new piezometers at suitable locations by the project proponent in and around project area in consultation with Regional Director, Central Ground Water Board. The frequency of monitoring should be four times a year- pre-monsoon (April / May), monsoon (August), post-monsoon (November), and winter (January). Data thus collected should be sent at regular intervals to Ministry of Environment and Forests and its Regional Office Bangalore, Central Ground Water Authority and Central Ground Water Board.

17.  Suitable conservation measures to augment groundwater resources in the area shall be planned and implemented in consultation with Regional Director, Central Ground Water Board.

18.  Blasting operation should be carried out only during the daytime. Controlled blasting should be practiced. The mitigative measures for control of ground vibrations and to arrest fly rocks and boulders should be implemented.

19.  The project proponent shall adopt wet drilling.

20.  The company shall comply with the commitments made during public hearing.

 

 

 

12.0     Any other item:

 

12.1     Request for Extension of time for implementation of Bio-Methanization in three Distillery units each of capacity of 160 KLPD at Gangnauli (Sahranpur), Khambarkheda (Lakhimpurkheri) and at Rudauli (Basti) in Uttar Pradesh by M/s. Bajaj Hindustan Limited.

 

 

            M/s Bajaj Hindustan Ltd, has sought extension of time from the Ministry for installation of Bio-methanation plant in three Distillery units each of capacity 160 KLPD at Gangnauli (Sahranpur), Khambarkheda (Lakhimpurkheri) and at Rudauli (Basti) in Uttar Pradesh. The request was referred to the Committee by the Ministry for consideration.

 

The company has urged that pursuant to rejection of its plaint to accept the Flubex technology as a substitute and its discussions thereafter with technology providers, it would take 12 months time to install the Bio-methanation plant. As per the pert chart furnished by the company, the activity will start in October, 2008 and plant will start functioning and be stabilized in September, 2009.  Further, they have also committed bank Guarantees of Rs. 5 lakhs for each of the three distillery units for installation of bio-methanation plant as per the project implementation schedule.

 

            The Expert Appraisal Committee (I) recommended  change in treatment technology from concentration of spent wash followed by incineration to bio-methanation and composting. And was of the view that a time limit of one year and no more under any circumstances may be granted for the purpose from the date of accepatance of its recommendation, 20th October 2008. Regarding furnishing of bank guarantee, the committee submits that the mode of securing due assurances from the party is for the government to decide. The State Pollution Control Board must ensure that the milestones for implementation are achieved and should monitor the progress of construction of biomethanation plant. Further, the CPCB being a central agency should keep a close watch on the progress of events as per the project implementation schedule submitted by M/s Bajaj Hindustan Limited.

 

Next meeting

 

It was decided to hold the next meeting on 25-26th  November, 2008.

 

The meeting ended with a vote of thanks to the chair.

 

 

 

 

LIST OF PARTICIPANTS

 

 

Expert Appraisal Committee (Industry) :

 

1.

Dr. T. S. Vijayaraghavan

Chairman

P

2.

Prof. B. Pitchumani

Member

P

3.

Dr. B. Sengupta

Member

P

4.

Dr. Sajid Hussain

Member

A

5.

Prof. S. Mohan

Member

             P

6.

Shri V. Balakrishnan

Member

A

7.

Shri R. K. Garg

Member

P

8.

Prof. N. R. Neelakantan

Member

p

9.

Shri M. A. Vaidyalingam

Member

A

10.

Shri. T. K. S. Elangovan

Member

A

11.

Dr. S. D. Attri             

Member

P

12

Representatives of CPCB

 

P

 

MOEF Officials  :

 

13.      Dr. (Mrs.) P.L. Ahujarai

Member Secretary & Director 

14.      Dr. P. B. Rastogi 

Director

15.      Shri H S Malviya

Joint Director

16.      Shri P. Sakhare

Research Officer

 

 

 

*******

 

Untitled Page
MEETING SCHEDULE AS ON 10,09,2012      |BACK
* To view Minutes Click on Date of Meeting
IDCategoryDates Of Meeting
IND Industrial Projects + Hide Dates
Sno.Date of meeting
1 Jun 14, 2012
2 May 24, 2012
3 Apr 26, 2012
4 Mar 29, 2012
5 Feb 27, 2012
6 Jan 27, 2012
7 Dec 22, 2011
8 Nov 28, 2011
9 Oct 24, 2011
10 Sep 26, 2011
11 Aug 26, 2011
12 Jul 21, 2011
13 Jun 29, 2011
14 May 19, 2011
15 Apr 18, 2011
16 Mar 12, 2011
17 Mar 25, 2011
18 Feb 22, 2011
19 Jan 24, 2011
20 Dec 13, 2010
21 Nov 22, 2010
22 Oct 25, 2010
23 Sep 23, 2010
24 Aug 26, 2010
25 Jul 26, 2010
26 Jun 24, 2010
27 May 17, 2010
28 Apr 07, 2010
29 Mar 02, 2010
30 Feb 02, 2010
31 Nov 24, 2009
32 Oct 26, 2009
33 Sep 23, 2009
34 Aug 17, 2009
35 Jul 20, 2009
36 Jul 21, 2009
37 Jun 16, 2009
38 Jun 17, 2009
39 Jun 15, 2009
40 May 12, 2009
41 Apr 15, 2009
42 Apr 14, 2009
43 Apr 16, 2009
44 Mar 18, 2009
45 Mar 19, 2009
46 Mar 20, 2009
47 Feb 09, 2009
48 Feb 11, 2009
49 Feb 10, 2009
50 Jan 06, 2009
51 Jan 07, 2009
52 Jan 08, 2009
53 Dec 22, 2008
54 Dec 11, 2008
55 Nov 25, 2008
56 Oct 20, 2008
57 Sep 23, 2008
58 Aug 19, 2008
59 Jul 15, 2008
60 Jul 16, 2008
61 Jun 12, 2008
62 Jun 10, 2008
63 Jun 11, 2008
64 May 12, 2008
65 Apr 15, 2008
66 Mar 18, 2008
67 Feb 20, 2008
68 Jan 21, 2008
69 Dec 26, 2007
70 Nov 13, 2007
71 Oct 24, 2007
72 Sep 18, 2007
MIN Mining Projects + Hide Dates
Sno.Date of meeting
1 Jul 25, 2012
2 Jun 20, 2012
3 May 23, 2012
4 Apr 16, 2012
5 Mar 19, 2012
6 Feb 21, 2012
7 Jan 23, 2012
8 Dec 22, 2011
9 Nov 28, 2011
10 Oct 19, 2011
11 Sep 21, 2011
12 Aug 24, 2011
13 Jul 20, 2011
14 Jun 21, 2011
15 May 25, 2011
16 Apr 25, 2011
17 Mar 23, 2011
18 Feb 23, 2011
19 Jan 19, 2011
20 Dec 22, 2010
21 Nov 24, 2010
22 Oct 20, 2010
23 Sep 28, 2010
24 Aug 25, 2010
25 Jul 21, 2010
26 Jul 26, 2010
27 Jun 28, 2010
28 May 24, 2010
29 Apr 28, 2010
30 Mar 17, 2010
31 Feb 17, 2010
32 Jan 20, 2010
33 Dec 21, 2009
34 Nov 23, 2009
35 Oct 29, 2009
36 Sep 17, 2009
37 Aug 25, 2009
38 Jul 16, 2009
39 Jun 18, 2009
40 May 20, 2009
41 Apr 16, 2009
42 Mar 18, 2009
43 Feb 17, 2009
44 Jan 19, 2009
45 Dec 17, 2008
46 Nov 19, 2008
47 Oct 22, 2008
48 Sep 23, 2008
49 Aug 18, 2008
50 Jul 22, 2008
51 Jun 17, 2008
52 May 21, 2008
53 Apr 15, 2008
54 Apr 28, 2008
55 Mar 17, 2008
56 Feb 20, 2008
57 Jan 21, 2008
58 Dec 19, 2007
59 Nov 20, 2007
60 Oct 23, 2007
61 Sep 24, 2007
62 Aug 22, 2007
63 Aug 22, 2007
THE Thermal Projects + Hide Dates
Sno.Date of meeting
1 Jun 11, 2013
2 Aug 06, 2012
3 Jul 16, 2012
4 Jul 02, 2012
5 Jun 25, 2012
6 Mar 05, 2012
7 Feb 06, 2012
8 Jan 09, 2012
9 Dec 12, 2011
10 Nov 14, 2011
11 Oct 10, 2011
12 Sep 12, 2011
13 Aug 08, 2011
14 Jul 04, 2011
15 Jun 06, 2011
16 May 02, 2011
17 Apr 04, 2011
18 Mar 07, 2011
19 Mar 14, 2011
20 Feb 07, 2011
21 Jan 10, 2011
22 Jan 09, 2011
23 Dec 22, 2010
24 Dec 06, 2010
25 Nov 01, 2010
26 Oct 18, 2010
27 Sep 06, 2010
28 Sep 28, 2010
29 Aug 09, 2010
30 Jul 07, 2010
31 Apr 30, 2010
32 Mar 19, 2010
33 Feb 12, 2010
34 Jan 30, 2010
35 Jan 11, 2010
36 Dec 11, 2009
37 Nov 10, 2009
38 Oct 13, 2009
39 Oct 13, 2009
40 Sep 10, 2009
41 Aug 10, 2009
42 Jul 14, 2009
43 Jun 09, 2009
44 May 11, 2009
45 Apr 15, 2009
46 Mar 12, 2009
47 Feb 10, 2009
48 Jan 12, 2009
49 Dec 15, 2008
50 Nov 10, 2008
51 Oct 13, 2008
52 Sep 09, 2008
53 Aug 12, 2008
54 Jul 10, 2008
55 Jun 11, 2008
56 May 13, 2008
57 Apr 08, 2008
58 Mar 11, 2008
59 Feb 11, 2008
60 Jan 07, 2008
61 Dec 10, 2007
62 Nov 14, 2007
63 Oct 15, 2007
64 Sep 26, 2007
RIV River Valley and Hydroelectric Projects + Hide Dates
Sno.Date of meeting
1 Jul 20, 2012
2 Jun 01, 2012
3 Apr 27, 2012
4 Mar 30, 2012
5 Mar 31, 2012
6 Feb 10, 2012
7 Dec 26, 2011
8 Nov 11, 2011
9 Sep 16, 2011
10 Aug 16, 2011
11 Jul 15, 2011
12 Jun 02, 2011
13 May 09, 2011
14 Apr 29, 2011
15 Mar 26, 2011
16 Feb 10, 2011
17 Feb 26, 2011
18 Jan 21, 2011
19 Dec 11, 2010
20 Dec 20, 2010
21 Nov 12, 2010
22 Oct 07, 2010
23 Sep 24, 2010
24 Aug 20, 2010
25 Jul 17, 2010
26 Jun 30, 2010
27 Apr 22, 2010
28 Mar 22, 2010
29 Feb 18, 2010
30 Jan 19, 2010
31 Dec 15, 2009
32 Nov 16, 2009
33 Oct 21, 2009
34 Sep 14, 2009
35 Aug 19, 2009
36 Jul 29, 2009
37 Jun 15, 2009
38 May 14, 2009
39 Apr 21, 2009
40 Mar 19, 2009
41 Feb 16, 2009
42 Jan 22, 2009
43 Dec 15, 2008
44 Nov 20, 2008
45 Oct 15, 2008
46 Sep 18, 2008
47 Aug 21, 2008
48 Jul 16, 2008
49 Jun 18, 2008
50 May 07, 2008
51 Apr 12, 2008
52 Mar 17, 2008
53 Feb 20, 2008
54 Jan 16, 2008
55 Dec 13, 2007
56 Nov 14, 2007
57 Oct 15, 2007
MIS Infrastructure and Miscellaneous Projects & CRZ + Hide Dates
Sno.Date of meeting
1 Aug 16, 2012
2 Jul 09, 2012
3 Jun 04, 2012
4 May 10, 2012
5 Apr 16, 2012
6 Mar 05, 2012
7 Feb 09, 2012
8 Jan 10, 2012
9 Dec 15, 2011
10 Dec 15, 2011
11 Oct 17, 2011
12 Sep 21, 2011
13 Aug 17, 2011
14 Jul 13, 2011
15 Jun 23, 2011
16 May 11, 2011
17 May 31, 2011
18 Apr 05, 2011
19 Mar 03, 2011
20 Feb 14, 2011
21 Jan 25, 2011
22 Jan 18, 2011
23 Nov 09, 2010
24 Nov 30, 2010
25 Oct 20, 2010
26 Sep 21, 2010
27 Aug 18, 2010
28 Jul 21, 2010
29 Jun 28, 2010
30 Apr 19, 2010
31 Mar 25, 2010
32 Feb 25, 2010
33 Jan 27, 2010
34 Dec 21, 2009
35 Nov 23, 2009
36 Oct 29, 2009
37 Sep 17, 2009
38 Aug 27, 2009
39 Jul 20, 2009
40 Jun 25, 2009
41 May 21, 2009
42 Apr 23, 2009
43 Mar 12, 2009
44 Jan 30, 2009
45 Dec 19, 2008
46 Nov 25, 2008
47 Oct 22, 2008
48 Sep 18, 2008
49 Aug 21, 2008
50 Jul 30, 2008
51 Jul 02, 2008
52 May 22, 2008
53 Apr 23, 2008
54 Mar 26, 2008
55 Feb 27, 2008
56 Jan 23, 2008
57 Dec 27, 2007
58 Nov 29, 2007
59 Oct 25, 2007
60 Sep 28, 2007
61 Aug 22, 2007
NUC Nuclear Projects + Hide Dates
NCP New Construction Projects and Industrial Estates + Hide Dates
NCP1 Additional Expert Committee of New Construction Projects + Hide Dates
MIN1 Additional Expert Committee of Mining Projects + Hide Dates
IND1 Industrial Projects - 2 + Hide Dates
CMIN Coal Mining + Hide Dates
Sno.Date of meeting
1 Jul 16, 2012
2 Jun 18, 2012
3 May 14, 2012
4 Apr 23, 2012
5 Mar 19, 2012
6 Feb 21, 2012
7 Jan 03, 2012
8 Jan 23, 2012
9 Nov 28, 2011
10 Oct 17, 2011
11 Sep 26, 2011
12 Aug 29, 2011
13 Jul 18, 2011
14 Jun 20, 2011
15 May 23, 2011
16 May 23, 2011
17 Apr 18, 2011
18 Mar 28, 2011
19 Feb 21, 2011
20 Jan 24, 2011
21 Dec 21, 2010
22 Nov 22, 2010
23 Oct 26, 2010
24 Sep 27, 2010
25 Aug 30, 2010
26 Jul 09, 2010
27 Apr 28, 2010
28 Mar 22, 2010
29 Feb 24, 2010
30 Jan 28, 2010
31 Dec 17, 2009
32 Dec 18, 2009
33 Nov 24, 2009
34 Oct 28, 2009
35 Sep 22, 2009
36 Aug 25, 2009
37 Jul 21, 2009
38 Jun 23, 2009
39 May 25, 2009
40 Apr 22, 2009
41 Apr 23, 2009
42 Mar 23, 2009
43 Feb 23, 2009
44 Jan 28, 2009
45 Dec 17, 2008
46 Nov 26, 2008
47 Oct 20, 2008
48 Sep 22, 2008
49 Aug 27, 2008
50 Jul 28, 2008
51 Jun 24, 2008
52 May 24, 2008
53 May 28, 2008
54 Apr 28, 2008
55 Mar 25, 2008
56 Feb 26, 2008
57 Jan 28, 2008
58 Dec 19, 2007
59 Nov 28, 2007
60 Oct 30, 2007
61 Sep 26, 2007
62 Aug 29, 2007