MINUTES OF THE 8th MEETING OF RECONSTITUTED EXPERT APPRAISAL COMMITTEE ON ENVIRONMENTAL IMPACT ASSESSMENT OF THERMAL POWER AND COAL MINE PROJECTS
The 8th Meeting of the reconstituted Expert Appraisal Committee (Thermal) was held during October 18-19, 2010 at Scope Convention Centre, Lodhi Road, New Delhi. The Members present were:
1. Shri V.P. Raja - Chairman
2. Dr. C.R. Babu - Member
3. Shri T.K. Dhar - Member
4. Shri J.L. Mehta - Member
5. Dr. G.S. Roonwal - Member
6. Dr. S.D. Attri - Member
7. Shri S. Seshadri - Member
8. Dr. P.L. Ahujarai - Member Secretary
Dr. CBS Dutt, Member; Dr. K.K.S. Bhatia; Dr. V.B. Mathur, Member; and Member Secretary, CPCB could not attend due to their prior commitments.
In attendance: Sh. W. Bharat Singh, Deputy Director, MoEF.
The deliberations held and the decisions taken are as under:
DATE: 18.10.2010.
Item No. 1.1 Presentation by Shri S. Seshadri, Member.
A presentation was made by Shri S. Seshadri, Member on the issues and challenges on thermal power plants in India. Emphasizing the need of capacity addition in tune with the Ministry of Power’s Policy, Shri Seshadri presented the present power scenario in the country. He also deliberated at length the issues involved in selection of a site for thermal power plant and unit size and technological issues. Shri Seshadri also informed the need for carrying studies in critically polluted areas on the following. Such studies also need to be carried out in areas where large number of projects are coming up, so that the cumulative impact can be accessed.
i) Carrying capacity for critically polluted area;
ii) Optimal utilization of river waters;
iii) Effects on fisheries, Mangroves and others due to large number of coastal power projects and associated jetties / ports etc.
The Committee deliberated on the issues highlighted by Shri Seshadri and decided that the Ministry may like to initiate action for carrying out the above mentioned studies at an early date.
Item No. 1.2 Confirmation of the Minutes of 7th Meeting.
The Committee deliberated on the minutes of the 7th meeting held on September 28, 2010 and confirmed the same.
The Committee noted an inadvertent lapse while confirmation of the 5th Meeting during the 7th Meeting with respect to Item No. 2.33 pertaining to amendment of environmental clearance for 1x600 MW Coal Based TPP of M/s Jhabua Power Ltd. at Ghansore Tehsil, in Seoni Distt., in Madhya Pradesh.
It was informed that the condition no. (i), in the environmental clearance to the aforesaid power plant read as “Environmental clearance is subject to submission from the Competent Authority in the State Govt. that the project area does not fall within a notified tribal area” is now irrelevant and need to be deleted since acquisition of 34.92 Ha is involved and condition no. (ii), read as “No tribal land shall be acquired for the power plant” has been agreed to be deleted.
The Committee decided that accordingly the condition no. (i) has no relevance now and recommended that the same may be deleted
ITEM NO. 2: CONSIDERATION OF PROJECTS
2.1 2x600 MW Coal Based TPP of M/s The Singareni Collieries Company Ltd. at village Jaipur, in Mandal Jaipur, in Adilabad Distt., in Andhra Pradesh - reg. environmental clearance.
The proposal was placed for consideration for environmental clearance as per provisions of EIA notification 2006. Environmental clearance for 2x300 MW was accorded on 28.10.2009. Later it was decided to go for 1x600 MW instead of 2x300 MW and the same was agreed by the EAC (T) in its 65th Meeting held during February 12-13, 2010. Later M/s SCCL proposed to add another 1x600 MW within the same location and the matter was placed in the 69th Meeting held during April 30- May 01, 2010. During the 69th Meeting, the Committee discussed the proposal in detail and it was decided that the same attracts the provisions of the circular of the Ministry dated March 22, 2010, wherein it was decided that such expansion can be considered only if the previous proposal is in an advanced stage of implementation.
The project proponent under the circumstances requested that they intent to withdraw their earlier proposal and the environmental clearance accorded on 28.10.2009 may be considered invalid. The Committee agreed to their request and recommended that the present proposal may be considered as fresh proposal for 2x600 MW and TOR can be prescribed. The project proponent was also advised to apply afresh along with Form-1 and pre-feasibility report to the Ministry. It was also decided that the project proponent shall explore possibility of setting up 2x660 MW instead of 2x600 MW, as super critical technology will improve efficiency and reduce the carbon footprint.
On submission of requisite documents, the matter was placed for consideration for environmental clearance. The project proponent also gave a presentation along with its consultant M/s Ramky Enviro Engineers Ltd. and provided the following information:
The proposal is for setting up of 2x600 MW Coal Based thermal power plant at village Jaipur, in Jaipur Mandal, in Adilabad Distt., in Andhra Pradesh. Land requirement will be 743.72 acres, which is under the possession of M/s SCCL. Out of the total land 393.32 acres is unirrigated revenue land; 235.27 acres is single crop agriculture land; 39.84 acres is double crop agriculture land; 3.77 acres is grazing land; 2.56 acres is waste land; 20.84 acres is mango orchard, roads and others. Coal requirement will be 4.784 MTPA, which will be obtained from own mines viz. (i) SRP OC-1; (ii) SRP OC-II; (iii) RKP OC phase-I. Environmental clearances for these mines have been obtained. Quantity of fly ash to be generated will be 1.022 MTPA. MOU has been entered with M/s Kesoram cement and M/s Orient cement industries. Water requirement will be 88.8 MLD, which will be obtained form Pranahita river near Devalawada village through a pipeline over the distance of 40 km. Godavari River through a pipeline over a distance of 9km. Water allocation has been obtained from government of Andhra Pradesh. There are no National park, wild life sanctuary, Biosphere/ tiger /Elephant reserves, Heritage sites etc within 10km of the project boundary. Public hearing was held on 8.9.2010. Cost of the project will be Rs. 5527.33 crores.
The Committee also discussed the issues raised in the public hearing and the responses made by the project proponent. The major issues raised were development of infrastructure facilities such as roads, drainage, drinking water, health care facilities, street lighting etc; employment of locals from surrounding villages; compensation for land losers and marginalized farmers etc. The project proponent also confirmed that no litigation is pending in any Courts pertaining to the project.
Based on the information and clarifications provided, the Committee recommended the project for environmental clearance subject to stipulation of the following specific conditions:
i) Environmental Clearance shall be subject to obtaining concurrence of the Ministry of Coal (MoC) for utilizing coal from own mine for running the power plant. A copy of MoC concurrence shall be submitted to the Ministry.
ii) Vision document specifying prospective plan for the site shall be formulated and submitted to the Ministry within six months.
iii) Mango Orchard in the project area shall not be touched.
iv) The project proponent shall provide space for FGD system for future installation as and when required.
v) It shall be ensured that the area drainage is not disturbed due to the proposed expansion.
vi) DGMS permission shall be obtained for back filling of mined out area. In any case, mine back filling shall be carried out one after detailed likely impact studies and adoption of adequate mitigation measures such as providing adequate layer of clay lining before filling
vii) 100 % fly ash disposal shall be ensured from 4th year of operation of the plant.
viii) Height of stack shall be 275 m each with flue gas velocity not less than 22 m/s.
ix) Hydro geological study of the area shall be reviewed annually and report submitted to the Ministry.
x) Monitoring of surface water quantity and quality shall also be regularly conducted and records maintained. The monitored data shall be submitted to the Ministry regularly. Further, monitoring points shall be located between the plant and drainage in the direction of flow of ground water and records maintained. Monitoring for heavy metals in ground water shall be undertaken.
xi) Green Belt consisting of 3 tiers of plantations of native species around plant and at least 100 m width shall be raised. Wherever 100 m width is not feasible a 50 m width shall be raised and adequate justification shall be submitted to the Ministry.
xii) Waste water generated from the plant shall be treated before discharge to comply limits prescribed by the SPCB.
xiii) A well designed rain water harvesting system shall be put in place within six months, which shall comprise of rain water collection from the built up and open area in the plant premises. Action plan and road map for implementation shall be submitted to the Ministry within six months.
xiv) Well designed acoustic enclosures for the DG sets and noise emitting equipments to achieve the desirable insertion loss viz. 25 dB(A) should be provided.
xv) Additional soil for leveling of the sites should be generated within the site in a way that natural drainage system of the area is protected and improved.
xvi) An amount of Rs. 22.10 Crores as one time investment should be earmarked for activities to be taken up under CSR by the above proponent. Recurring expenditure for CSR shall not be less than Rs. 4.40 Crores per annum till the operation of the plant. Detailed action plan with break-up of activities to be undertaken shall be submitted within six months to the Ministry.
xvii) While identifying CSR activities it shall be ensured that need based assessment for the nearby villages within study area shall be conducted to study economic measures with action plan which can help in upliftment of poorer sections of society. Income generating projects consistent with the traditional skills of the people shall be undertaken. Development of fodder farm, fruit bearing orchards, vocational training etc. can form a part of such programme. Company shall provide separate budget for community development activities and income generating programmes. Vocational training programme for possible self employment shall be imparted to pre identified villagers free of cost.
xviii) It shall be ensured that an in-built monitoring mechanism for the CSR schemes identified is in place and annual social audit shall be got done from a government institute of repute in the region. The project proponent shall also submit the status of implementation of the scheme from time to time.
xix) An Environmental Cell shall be created at the project site itself and shall be headed by qualified officer, who is well versed with the environmental aspects. It shall be ensured that the Head of the Cell shall directly report to the head of the organization.
2.2 Expansion of C0-Generation Power Plant from 40 MW to 62 MW of M/s Nirani Sugars Ltd. at Sy No. 166, Kulali Cross, in Jamakhandi Road, in Mudhol Taluk, in Bagalkot Distt., in Karnataka - reg. Environmental Clearance.
The proposal was placed for consideration for environmental clearance. A presentation was also made by the project proponent and its consultant M/s Environmental Health and Safety Consultants Pvt. Ltd., Bangalore on the salient features and other details of the project and provided the following information:
The proposal is for setting up for expansion of Co-Generation Power Plant from 40 MW to 62 MW at Sy No. 166, Kulali Cross, in Jamakhandi Road, in Mudhol Taluk, in Bagalkot Distt., in Karnataka. Land requirement will be .22 acres, which is within existing Sugar Plant. A 40 MW Co- Generation Captive Power Plant is under operation. Bagasse is the main fuel and substitute such as Jaggari bagasse and cane trash will be also used. Bagasse requirement will be 46.36 TPH. Imported coal from Indonesia will be used as additional fuel. Coal requirement will be 3.6 TPH. Ash and sulphur contents in coal will be 7% and 0.3 % respectively. Fly ash generated will be utilized for own Cement and Brick manufacturing. Water requirement will be300 KLD, which will be obatained from Ghataprabha river through a pipeline over a distance of 4.25 Km. Water allocation has been obtained from the Govt. of Karnataka. There are no National park, wild life sanctuary, Biosphere/ tiger /Elephant reserves, Heritage sites etc within 10km of the project boundary. Public hearing was conducted on 17.06.2010. Cost of the project will be Rs. 85.0 Crores.
The Committee also discussed the issues raised in the public hearing and noted that the participants were in favour of the proposed expansion and no dissent were recorded in the minutes of the public hearing proceedings. The project proponent also declared that no litigation is pending in any court pertaining to the project.
Based on the information and clarifications provided, the Committee recommended the project for environmental clearance subject to stipulation of the following specific conditions:
i) Vision document specifying prospective plan for the site shall be formulated and submitted to the Ministry within six months.
ii) The project proponent shall ensure that no fugitive fly ash generation takes place at any point of time.
iii) 100 % fly ash disposal shall be ensured from 4th year onwards.
iv) It shall be ensured that the area drainage is not disturbed due to the proposed power plant.
v) Monitoring of surface water quantity and quality shall also be regularly conducted and records maintained. The monitored data shall be submitted to the Ministry regularly. Further, monitoring points shall be located between the plant and drainage in the direction of flow of ground water and records maintained. Monitoring for heavy metals in ground water shall be undertaken.
vi) Green Belt consisting of 3 tiers of plantations of native species around plant and at least 100 m width shall be raised. Wherever 100 m width is not feasible a 50 m width shall be raised and adequate justification shall be submitted to the Ministry.
vii) Waste water generated from the plant shall be treated before discharge to comply limits prescribed by the SPCB.
viii) A well designed rain water harvesting system shall be put in place within six months, which shall comprise of rain water collection from the built up and open area in the plant premises. Action plan and road map for implementation shall be submitted to the Ministry within six months.
ix) Well designed acoustic enclosures for the DG sets and noise emitting equipments to achieve the desirable insertion loss viz. 25 dB (A) should be provided.
x) Additional soil for leveling of the sites should be generated within the site in a way that natural drainage system of the area is protected and improved.
xi) An amount of Rs. 0.34 Crores as one time investment should be earmarked for activities to be taken up under CSR by the above proponent. Recurring expenditure for CSR shall not be less than Rs.0.06 Crores per annum till the operation of the plant. Detailed action plan with break-up of activities shall be submitted within six months to the Ministry.
xii) The project proponent shall also adequately contribute in the development of other neighbouring villages. Special package with implementation schedule for providing potable drinking water supply in the near by villages and schools shall be undertaken in a time bound manner.
xiii) While identifying CSR activities it shall be ensured that need based assessment for the nearby villages within study area shall be conducted to study economic measures with action plan which can help in upliftment of poorer sections of society. Income generating projects consistent with the traditional skills of the people shall be undertaken. Development of fodder farm, fruit bearing orchards, vocational training etc. can form a part of such programme. Company shall provide separate budget for community development activities and income generating programmes. Vocational training programme for possible self employment shall be imparted to pre identified villagers free of cost.
xiv) It shall be ensured that an in-built monitoring mechanism for the CSR schemes identified is in place and annual social audit shall be got done from a government institute of repute in the region. The project proponent shall also submit the status of implementation of the scheme from time to time.
xv) An Environmental Cell shall be created at the project site itself and shall be headed by an officer of appropriate seniority and qualification. It shall be ensured that the head of the Cell shall directly report to the head of the organization.
2.3 2x150 MW Imported Coal Based Merchant Power Plant of M/s Accord Energy Corporation Pvt. Ltd. at village Sirupulalpettai, in Gummidipoondi, in Thiruvallur, in Tamil Nadu - reg. Environmental Clearance.
The proposal is for consideration for environmental clearance. The proposal is an inter-state boundary case and hence is being taken up at the Centre as per general provisions of EIA Notification, 2006. The project proponent made a presentation along with its consultant viz. M/s Environment System Consultants & Ambiente Lab Solutions Pvt. Ltd., Chennai and provided the following information:
The proposal is for setting up of 2x150 MW Imported Coal Based Merchant Power Plant at village Sirupulalpettai, in Gummidipoondi, in Thiruvallur, in Tamil Nadu. Land requirement will be 160.0 acres, which is a single crop agricultural land. Co-ordinates of the site are at Latitude 13025’01.581” N to 13025’27.664” N and Longitude 8004’06.948” E to 8004’45.307” E. Imported coal requirement will be 1.12 MTPA, which will be obtained from Indonesia. Ash and Sulphur contents in imported coal will be 9% and 1.12% respectively. About 0.081 MTPA of Fly Ash will be generated, which will be supplied to cement manufacturer viz. M/s India Cement Ltd. A stack of 220 m will be installed. Harvested rain water will be used as source of water requirement. Air cooled condenser will be used for main condensate cooling. Water requirement will be 802 KLD. There are no National parks, Wildlife sanctuaries, Heritage sites, Tiger/Biosphere reserves etc. within 10 km of the site. Public hearing was conducted on 28.05.2010. Cost of the project will be Rs 1950.0 Crores.
The Committee noted that the project proponent has not firmed up any proposal for transportation of coal by rail and that instead about 60 to 70 trucks of 40T capacity each - is proposed for transportation of coal over a very long distance (about 23 Kms) from the Port, which can be a major environmental concern. The Committee also noted that the proposal for using harvested rain water only is not convincing considering that the area is water starved and does not have very high rainfall. The Committee informed the project proponent that withdrawal of ground water for power plant shall not be permitted. The Committee also noted that no concrete fly ash utitlisation agreements / MoU with prospective users have been submitted.
The Committee therefore decided that the project proponent shall first submit the following before their case is considered for environmental clearance:
i) Point wise compliance of TORs prescribed shall be submitted;
ii) A firm proposal of coal transportation by rail along with requisite documents to indicate advance stage of concurrence of the Ministry of Railways or proposal of closed conveyor system all along from the nearest point of coal source at Port;
iii) In case road transportation is the only option left adequate justification with documents to substantiate denial from the Ministry of Railways for rail transportation option shall be submitted. In that case, impact on ambient air quality along the route of transportation with details of vehicular density along the route from authentic source (Transport Dept.) and other requisite information shall be submitted;
iv) Ambient air quality data shall be re-assessed and cumulative impact of ambient air quality predictions accounting all possible sources of emissions shall be re-done using appropriate wind rose diagram;
v) Action plan with time bound implementation schedule for development of three tier green belt all around Ash Dyke (avoiding non feasible areas with justification) shall be submitted;
vi) Source of water sustainability study in the event of failure of rain water harvesting system during dry spell or less rainfall;
vii) Alternative proposal of water requirement by way of setting up of de-salination plant or NIOT technology;
viii) CSR action plan with time bound implementation schedule and budgetry allocation activity wise shall be submitted;
ix) Action plan for time bound implementation on issues raised in public hearing and others shall be prepared and submitted along with firm commitment;
x) Proposal for fly ash utilization alongwith copy of agreements/MoUs firmed up with prospective fly ash users shall be submitted.
The Committee also decided that the above information / documents shall be submitted along with an undertaking in a notorised stamp paper of appropriate amount and duly signed by the Head of the Organisation or an officer of appropriate superiority (authorized to sign).
Accordingly the proposal was deferred for reconsideration at a later stage. The Committee also decided that since the above may take some time the proposal may be de-listed from the pending list for the time being.
2.4 220 MW Renewable Energy Dual Fuel Based Combined Cycle Power Plant of M/s SIAA Energy Pvt. Ltd. at village Vakalpudi in APIIC notified Industrial area, in Kakinada Rural Taluk, in East Godavari Distt., in Andhra Pradesh - reg. TOR.
The proposal was considered for determination of terms of reference for undertaking EIA/EMP study as per the provisions of EIA notification 2006. The project proponent along with its consultant viz. M/s Vimta Labs Ltd., Hyderabad gave a presentation and provided the following information:
The proposal is for setting of 220 MW Renewable Energy Dual Fuel Based Combined Cycle Power Plant at village Vakalpudi in APIIC Notified Industrial Area, in Kakinada rural Taluk, in East Godavari Distt., in Andhra Pradesh. Fuel for the power plant will be Bio-Diesel and Natural Gas. The power plant is proposed within existing Bio-Diesel Plant (M/s Naturol Bio-Energy Ltd.). Land requirement will be 6.5 ha, which is in notified industrial area. Co-ordinates of the site are at Latitude 170 01’13”N and Longitude 82016’38” E. Natural gas will be obtained from KG Basin from the gas pipeline nearby at about 1.0 km from project site. The Bio-Diesel plant will be the source of Biodiesel. Bio-Diesel requirement will be 1,70,000 TPA and natural gas requirement will be 150 MMSCM. Water requirement will be obtained from Bay of Bengal. There are no National parks, Wildlife sanctuaries, Heritage sites, Tiger/Biosphere reserves etc. within 10 km of the site. Cost of the project will be Rs. 960.0 Crores.
The Committee noted that the proposal is for setting up of unit capacities 2x55 MW each in two phases viz. Phase-I 2x55 MW and Phase-II 2x55 MW. The Committee informed the project proponent that the desirable unit configurations may be 110 MW each and they may like to explore the same configuration, to which the project proponent confirmed its intention. The Committee therefore decided that the project proponent shall submit revised Form-I to the Ministry with the changed configuration of 2x110 MW in lieu of 4x55 MW.
Based on the information provided and presentation made the Committee prescribed the following specific TORs for undertaking detailed EIA study and preparation of EMP.
i) Vision document specifying prospective long term plan of the site shall be formulated and submitted.
ii) Copy of Gazette Notification of APIIC notified industrial area along with environmental clearance for the industrial area/estate shall be submitted.
iii) Executive summary of the project indicating relevant details along with photograph of site shall be provided and issues raised in public hearing along with action plan to address the same shall be provided in tabular form including requisite allocation of funds.
iv) Conformity of the site with the prescribed guidelines in terms of distance of 500 m from HFL of the river, highways, railway line shall be shown on the study area map.
v) The project proponent shall provide confirmed GPS readings of plant boundary.
vi) The project proponent shall examine in detail the possibility to adopt NIOT technology of desalination system through Low Temperature Thermal Desalination (LTTD) process instead of installing De-Salination plant. In case the same is not feasible detailed explanation shall be submitted.
vii) water body/nallah (if any) shall be touched. It shall also be ensured that atleast 100 m distance is kept away from the HFL of the nallah/ river (if any) passing in and around the proposed site.
viii) Hydro-geological study of the area shall be conducted from an institute/ organisation of repute to assess impact of on ground and surface water regime. Specific mitigation measures shall be spelt out and action plan for implementation of the same shall be provided.
ix) Study on the impact on river/reservoir/marine ecology (as applicable) due to the proposed discharge of treated wastewater into the river/creek shall be carried out and submitted alongwith the EIA Report.
x) Action plan for identification of local employable youth for training in skills relevant to the project for eventual employment in the project itself shall be formulated.
xi) Layout of the plant indicating break-up of plant, green belt, infrastructure, roads etc. shall be provided.
xii) Land requirement for the project shall be optimized. Item wise break up of land requirement and its availability to be furnished. It should also include land to be acquired, if any, for fuel transportation system as well as for laying of pipeline including ROW. It may clearly be confirmed that the land including ROW is free of all encumbrances. The issues relating to land acquisition and R&R should be clearly discussed in the EIA report.
xiii) Land use based on satellite imagery or authenticated map indicating drainage, cropping pattern, water bodies (rivers, nallahs, ponds etc.), location of nearest villages, creeks, rivers, reservoirs, national parks, wildlife sanctuaries, tiger reserves, biosphere reserves, heritage sites etc in the study area shall be provided. Location of any National Park, Sanctuary, Elephant/Tiger Reserve (existing as well as proposed), migratory routes, if any, within 10 km of the project site shall be specified and marked on the map duly authenticated by the concerned Department.
xiv) Study on land-use pattern in the study area shall be carried out, including identification of common property resources available for conversion into productive land and action plan for abatement and compensation for damage to agricultural land/ common property land (if any) in the nearby villages, due to proposed project shall be prepared.
xv) Detailed socio-economic study shall be carried out for the study area comprising of 10 km from the plant site.
xvi) A detailed R&R action plan (as applicable) with time schedule for implementation and also consisting of an in-built monitoring mechanism by an independent third party shall be prepared.
xvii) CSR component shall be prepared based on need based assessment study to be carried out in the study area. Income generating measures which can help in upliftment of poor section of society which is consistent with the traditional skills of the people shall be identified. The programme can include activities such as development of fodder farm, fruit bearing orchards, vocational training etc. In addition, vocational training for individuals shall be imparted so that poor section of society can take up self employment and jobs. Separate budget for community development activities and income generating programmes shall be specified. Financial allocation to be taken up under CSR shall be specified.
xviii) While formulating CSR schemes it shall be ensured that an in-built monitoring mechanism for the schemes identified is in place and mechanism for conducting annual social audit from the nearest government institute of repute in the region shall be prepared. The project proponent shall also provide plan for the status of implementation of the scheme from time to time.
xix) Location of intake and outfall points (with coordinates) of water source should be given. These locations should be selected based on detailed modeling studies (as applicable in case of marine environment). Details of modeling and the results obtained there from should be furnished. It may be kept in view that the intake and outfall points are away from the mangroves or other eco sensitive areas.
xx) Demarcation of CRZ lines by any of the authorized agency shall be carried out and submitted.
xxi) Marine impact assessment study (Marine EIA) from a reputed organization shall be carried out.
xxii) Topography of the area should be given clearly indicating whether the site requires any filling. If so, details of filling, quantity of fill material required, its source, transportation etc. should be given.
xxiii) One complete season AAQ data (except monsoon) to be given along with the dates of monitoring. The parameters to be covered shall include SPM, RSPM (PM10,PM2.5), SO2, NOx, Hg and Ozone (ground level). The location of the monitoring stations should be so decided so as to take into consideration the pre-dominant downwind direction, population zone and sensitive receptors including reserved forests. There should be at least one monitoring station each in the upwind and in the pre dominant downwind direction at a location where maximum ground level concentration is likely to occur.
xxiv) Cumulative impact assessment on ambient air quality due to proposed plant and others (including existing as well as other proposed source of emission) shall be carried out and result submitted in the EIA Report. Mitigative measures as necessary shall be clearly spelt out.
xxv) Impact of the project on the AAQ of the area. Details of the model used and the input data used for modelling should also be provided. The air quality contours may be plotted on a location map showing the location of project site, habitation nearby, sensitive receptors, if any. The wind roses should also be shown on this map.
xxvi) Fuel analysis shall be provided. Details of auxillary fuel, if any including its quantity, quality, storage etc should also be given.
xxvii) Quantity of fuel required, its source and transportation route and mode and a confirmed fuel linkage documents shall be provided.
xxviii) Detailed plan for carrying out rainwater harvesting and proposed utilisation in the plant shall be provided.
xxix) Feasibility of zero discharge shall be examined and detailed justification shall be submitted if in case the same is not possible. Proposed discharge (if any), its quantity, quality and point of discharge, users downstream etc. shall be provided.
xxx) Optimization of COC for water conservation. Other water conservation measures proposed in the project should also be given. Quantity of water requirement for the project should be optimized.
xxxi) Details of water balance taking into account reuse and re-circulation of effluents.
xxxii) Detailed plan for conducting monitoring of ambient air and water quality regularly and mechanism for maintenance of records shall be formulated. Details of methodology and identification of water quality assessment monitoring points (between the plant and drainage in the direction of flow of surface / ground water) shall be submitted. It shall be ensured that parameter to be monitored also include heavy metals in surface and ground water.
xxxiii) Details regarding infrastructure facilities such as sanitation, fuel, restroom, medical facilities, safety during construction phase etc. to be provided to the labour force during construction as well as to the casual workers including truck drivers during operation phase.
xxxiv) EMP to mitigate the adverse impacts due to the project along with item wise cost of its implementation.
xxxv) A Disaster Management Plan along with risk assessment study including fire and explosion issues due to storage and use of fuel should be carried out. It should take into account the maximum inventory of storage at site at any point in time. The risk contours should be plotted on the plant layout map clearly showing which of the proposed activities would be affected in case of an accident taking place. Based on the same, proposed safeguard measures should be provided. Measures to guard against fire hazards should also be provided.
xxxvi) Detailed plan for raising Green belt of 100 m width and consisting of at least 3 tiers around plant boundary with tree density not less than 2500 trees per ha and survival rate atleast 75% shall be submitted.
xxxvii) Details of litigation pending or otherwise with respect to project in any courts, tribunal etc. shall be provided.
Further, the following shall be strictly followed (as applicable):
a) The land requirement for the projects should be limited to barest minimum. If the site includes or is located close to marshy areas and backwaters, these areas must be excluded from the site and the project boundary should be atleast 500 away from the ecologically sensitive areas. If backwaters form a part of the site, CRZ clearance is a must.
b) The soil levelling should be minimum with no or minimal disturbance to the natural drainage of the area. If the minor canals (if any) have to be diverted, the design for diversion should be such that the diverted canals not only drains the plant area but also collect the volume of flood water from the surrounding areas and discharge into marshy areas/major canals that enter into creek. Major canals should not be altered but their bunds should be strengthened and desilted.
c) Additional soil for leveling of the sites should be generated within the sites in a way that natural drainage system of the area is protected and improved
d) The marshy areas (if any) which hold large quantities of water should not be disturbed.
e) No waste should be discharged into canal systems, backwaters, marshy areas and seas without treatment. The outfall should be first treated in guard pond and then discharged into deep sea (12 to 15 m depth). Similarly, the intake should be from deep sea to avoid aggregation of fish. The brine that comes out from desalinization plants (if any) should not be discharged into sea but it should be recycled.
f) To absorb the ground level pollutants, to act as buffer against strong winds arising out of tropical cyclones/ storms, to reduce heat load and ameliorate environment, there is a need for shelterbelts / greenbelts / tree cover along the coastline, bunds around marshy areas, roadsides, around the project boundaries, around village boundaries, ash dykes, railway lines, around protected monuments, forts, waste places, School Campuses and other vacant lots. Coconut plantations can be developed along the coastline and near villages, Schools and forts. Stands of Casuariana should also be developed on some dunes and along coasts. Bamboos, neem and other native trees should be planted in and around at the villages.
g) To meet the expenditure of these plantations and their management, a common Green Endowment Fund should be created by the project proponents out of EMP budgets. The interest earned out of it should be used for the development and management of green cover of the area.
h) The villages bordering the sites may be predominantly inhabitated by fishermen and the TPP may have impacts on their livelihood, even though most of the fishing activity is confined to deep seas. An endowment of Fishermen Welfare Fund should be created out of CSR grants not only to enhance their quality of life through creation of facilities for fish landing platforms / fishing harbour / cold storage, but also to provide relief in case of emergency situations such as missing of fishermen on duty due to rough seas, tropical cyclones and storms etc.
i) There should not be any contamination of soil, ground and surface waters (canals & village pond) with sea water in and around the project sites. In other wards necessary preventive measures for spillage from pipelines, such as lining of guard pond used for the treatment of outfall before discharging into the sea and surface RCC channels along the pipelines of outfall and intake should be adopted. This is just because the areas around the projects boundaries is fertile agricultural land used for paddy cultivation.
Besides all the above, the following general points will be followed:-
a) All documents to be properly referenced with index, page numbers and continuous page numbering.
b) Where data is presented in the report especially in table, the period in which the data was collected and the source should invariably be indicated.
c) Where the documents provided are in a language other than English, an English translation should be provided.
d) The Questionnaire for environmental appraisal of thermal power projects as devised earlier by the Ministry shall also be filled and submitted.
In addition, information on the following may also be incorporated in the EIA report.
1). Is the project intended to have CDM-intent?
i) If not, then reasons thereof?
ii) If yes, then details under mentioned to be provided:
a) Has PIN (Project Idea Note) {or PCN (Project Concept Note)} been submitted to the NCA? (National CDM Authority) in the MoEF?
b) If not, then by when is that expected?
c) Has PDD (Project Design Document) been prepared?
d) What is the Carbon intensity from your electricity generation projected (i.e. CO2 Tons/MWH or Kg/KWH)
e) Amount of CO2 in Tons/year expected to be reduced from the baseline data available on the CEA’s web-site (www.cea.nic.in)
2. Notwithstanding 1(i) above, data on (d) & (e) above to be worked out and reported.
3. The Committee decided that the proposal may be exempted from public hearing in accordance with the provisions of EIA Notification, 2006 (and its amendment) as may be applicable.
4. The Committee informed the project proponent that after preparing the EIA (as per the generic structure prescribed in Appendix-III of the EIA Notification, 2006) covering the above mentioned issues, the same shall be submitted to the Ministry for appraisal by the Expert Appraisal Committee for consideration of awarding environmental clearance under the provisions of Environmental Impact Assessment notification dated September 14, 2006 (and its amendment).
2.5 Expansion by addition of 1x600 MW Coal Based TPP of M/s Korba West Power Co. Ltd. at villages Badde Bhandar, Chote Bhandar, Sarwani and Amali Bhona, in Pussore Tehsil, in Raigarh Distt., in Chhattisgarh - reg. TOR.
The proposal was considered for determination of terms of reference for undertaking EIA/EMP study as per provisions of EIA notification 2006. The project proponent gave a presentation along with its consultant M/s J.M. EnviroNet Pvt. Ltd. and provided the following information:
The proposal is for expansion by addition of 1x600 MW Coal Based TPP at villages Badde Bhandar, Chote Bhandar, Sarwani and Amali Bhona, in Pussore Tehsil, in Raigarh Distt., in Chhattisgarh. Phase-I is in advance stage of implementation and civil works are in progress. Land requirement 398.17 acres. Diversion of 60.17 acres of forests land will be involved. Acquisition of 96.34 acres of tribal land will also be involved. The co-ordinates of the site are at Latitude 21044’0” to 21044’42” N and Longitude 83016’30” to 83017’18” E. Coal requirement will be 3.15 MTPA. Source of water will be from Mahanadi River at a point upstream of proposed Kalma Anicut, 5 Kms away from the site and through a Jack Well. Water requirement will be 16.8 MCM. There are no wildlife sanctuary, national park, biosphere / tiger reserve, heritage sites etc. with 10 km of the proposed site.
Based on the information provided and presentation made the Committee prescribed the following specific TORs for undertaking detailed EIA study and preparation of EMP.
i) Status of compliance to the conditions stipulated in the environmental clearance accorded for Phase-I shall be submitted along with EIA/EMP report.
ii) Status of diversion of forests land involved shall be submitted.
iii) Vision document specifying prospective long term plan of the site shall be formulated and submitted.
iv) Executive summary of the project indicating relevant details along with photograph of site shall be provided and issues raised in public hearing along with action plan to address the same shall be provided in tabular form including requisite allocation of funds.
v) Conformity of the site with the prescribed guidelines in terms of distance of 500 m from HFL of the river, highways, railway line shall be shown on the study area map.
vi) The project proponent shall provide confirmed GPS readings of plant boundary.
vii) Details of acquisition of tribal land and compliance to tribal rights as per existing Central and State legislations as may be applicable shall be submitted.
viii) No water body/nallah (if any) shall be touched. It shall also be ensured that atleast 100 m distance is kept away from the HFL of the nallah (if any) passing in and around the proposed site.
ix) Hydro-geological study of the area shall be conducted from an institute/ organisation of repute to assess impact of on ground and surface water regime. Specific mitigation measures shall be spelt out and action plan for implementation of the same shall be provided.
x) Source sustainability study of water requirement shall be carried out by an institute of repute. The study shall also specify the source of water for meeting the requirement during lean season and proposed plan of action.
xi) Study on the impact on catchment area of the river due to proposed withdrawal of such huge quantity of water for running the power plant shall be carried out and submitted.
xii) Source of water and its availability. Commitment regarding availability of requisite quantity of water from the competent authority shall be provided along with firm linkage.
xiii) Detailed plan for carrying out rainwater harvesting and proposed utilisation in the plant shall be provided.
xiv) Feasibility of zero discharge shall be examined and detailed justification shall be submitted if in case the same is not possible. Proposed discharge (if any), its quantity, quality and point of discharge, users downstream etc. shall be provided.
xv) Optimization of COC for water conservation. Other water conservation measures proposed in the project should also be given. Quantity of water requirement for the project should be optimized.
xvi) Details of water balance taking into account reuse and re-circulation of effluents.
xvii) Detailed plan for conducting monitoring of water quality regularly and mechanism for maintenance of records shall be formulated. Details of methodology and identification of monitoring points (between the plant and drainage in the direction of flow of surface / ground water) shall be submitted. It shall be ensured that parameter to be monitored also include heavy metals in surface and ground water.
xviii) Ash pond shall be shifted away as far as possible from any surface water source. The coordinates of the proposed site including location of ash pond shall be submitted along with topo sheet.
xix) Action plan for identification of local employable youth for training in skills relevant to the project for eventual employment in the project itself shall be formulated.
xx) Layout of the plant indicating break-up of plant, green belt, infrastructure, roads etc. shall be provided.
xxi) Land requirement for the project shall be optimized. Item wise break up of land requirement and its availability to be furnished. It should also include land to be acquired, if any, for coal transportation system as well as for laying of pipeline including ROW. It may clearly be confirmed that the land including ROW is free of all encumbrances. The issues relating to land acquisition and R&R should be clearly discussed in the EIA report.
xxii) Land use based on satellite imagery or authenticated map indicating drainage, cropping pattern, water bodies (rivers, nallahs, ponds etc.), location of nearest villages, creeks, rivers, reservoirs, national parks, wildlife sanctuaries, tiger reserves, biosphere reserves, heritage sites etc in the study area shall be provided. Location of any National Park, Sanctuary, Elephant/Tiger Reserve (existing as well as proposed), migratory routes, if any, within 10 km of the project site shall be specified and marked on the map duly authenticated by the Chief Wildlife Warden.
xxiii) Study on land-use pattern in the study area shall be carried out, including identification of common property resources available for conversion into productive land and action plan for abatement and compensation for damage to agricultural land/ common property land (if any) in the nearby villages, due to proposed project shall be prepared.
xxiv) Detailed socio-economic study shall be carried out for the study area comprising of 10 km from the plant site.
xxv) A detailed R&R action plan (as applicable) with time schedule for implementation and also consisting of an in-built monitoring mechanism by an independent third party shall be prepared.
xxvi) CSR component shall be prepared based on need based assessment study to be carried out in the study area. Income generating measures which can help in upliftment of poor section of society which is consistent with the traditional skills of the people shall be identified. The programme can include activities such as development of fodder farm, fruit bearing orchards, vocational training etc. In addition, vocational training for individuals shall be imparted so that poor section of society can take up self employment and jobs. Separate budget for community development activities and income generating programmes shall be specified. Financial allocation to be taken up under CSR shall be specified.
xxvii) While formulating CSR schemes it shall be ensured that an in-built monitoring mechanism for the schemes identified is in place and mechanism for conducting annual social audit from the nearest government institute of repute in the region shall be prepared. The project proponent shall also provide plan for the status of implementation of the scheme from time to time.
xxviii) Possibility for adopting nearest three villages shall be explored and details of civic amenities such as roads, drinking water, power etc proposed to be provided at the company’s expenses shall be submitted.
xxix) Location of intake and outfall points (with coordinates) should be given and the method of disposal of treated waste water from power plant shall be submitted.
xxx) Topography of the area should be given clearly indicating whether the site requires any filling. If so, details of filling, quantity of fill material required, its source, transportation etc. should be given.
xxxi) One complete season AAQ data (except monsoon) shall be given along with the dates of monitoring. The parameters to be covered shall include SPM, RSPM (PM10,PM2.5), SO2, NOx, Hg and Ozone (ground level). The location of the monitoring stations should be so decided so as to take into consideration the pre-dominant downwind direction, population zone and sensitive receptors including reserved forests. There should be at least one monitoring station each in the upwind and in the pre dominant downwind direction at a location where maximum ground level concentration is likely to occur.
xxxii) Cumulative impact assessment on ambient air quality due to proposed plant and others (including existing as well as other proposed source of emission) shall be carried out and result submitted in the EIA Report. Mitigative measures as necessary shall be clearly spelt out.
xxxiii) Impact of the project on the AAQ of the area. Details of the model used and the input data used for modelling should also be provided. The air quality contours may be plotted on a location map showing the location of project site, habitation nearby, sensitive receptors, if any. The wind roses should also be shown on this map.
xxxiv) Fuel analysis shall be provided. Details of auxillary fuel, if any including its quantity, quality, storage etc should also be given.
xxxv) Quantity of fuel required, its source and transportation route and mode and a confirmed fuel linkage documents shall be provided.
xxxvi) Details regarding infrastructure facilities such as sanitation, fuel, restroom, medical facilities, safety during construction phase etc. to be provided to the labour force during construction as well as to the casual workers including truck drivers during operation phase.
xxxvii) EMP to mitigate the adverse impacts due to the project along with item wise cost of its implementation.
xxxviii) A Disaster Management Plan along with risk assessment study including fire and explosion issues due to storage and use of fuel should be carried out. It should take into account the maximum inventory of storage at site at any point in time. The risk contours should be plotted on the plant layout map clearly showing which of the proposed activities would be affected in case of an accident taking place. Based on the same, proposed safeguard measures should be provided. Measures to guard against fire hazards should also be provided.
xxxix) Detailed plan for raising Green belt of 100 m width and consisting of at least 3 tiers around plant boundary with tree density not less than 2500 trees per ha and survival rate atleast 75% shall be submitted.
xl) Details of litigation pending or otherwise with respect to project in any courts, tribunal etc. shall be provided.
Besides all the above, the following general points will be followed:-
a) All documents to be properly referenced with index, page numbers and continuous page numbering.
b) Where data is presented in the report especially in table, the period in which the data was collected and the source should invariably be indicated.
c) Where the documents provided are in a language other than English, an English translation should be provided.
d) The Questionnaire for environmental appraisal of thermal power projects as devised earlier by the Ministry shall also be filled and submitted.
In addition, information on the following may also be incorporated in the EIA report.
1). Is the project intended to have CDM-intent?
i) If not, then reasons thereof?
ii) If yes, then details under mentioned to be provided:
a) Has PIN (Project Idea Note) {or PCN (Project Concept Note)} been submitted to the NCA? (National CDM Authority) in the MoEF?
b) If not, then by when is that expected?
c) Has PDD (Project Design Document) been prepared?
d) What is the Carbon intensity from your electricity generation projected (i.e. CO2 Tons/MWH or Kg/KWH)
e) Amount of CO2 in Tons/year expected to be reduced from the baseline data available on the CEA’s web-site (www.cea.nic.in)
2. Notwithstanding 1(i) above, data on (d) & (e) above to be worked out and reported.
The Committee informed the project proponent that after preparing the draft EIA (as per the generic structure prescribed in Appendix-III of the EIA Notification, 2006) covering the above mentioned issues, the same shall be submitted to the SPCB for conducting the public hearing as per procedure of EIA notification 2006. The issues which emerge during public hearing shall be further incorporated in the Draft EIA/EMP report. The final EIA/EMP report along with public hearing report and the requisite documents (including written objections, if any) shall be submitted to the Ministry for appraisal by the Expert Appraisal Committee for consideration of awarding environmental clearance under the provisions of Environmental Impact Assessment notification dated September 14, 2006.
2.6 Expansion by addition of 1x600 MW Coal Based TPP of M/s Jhabua Power Co. Ltd. at villages Barela and Gorakhpur, in Ghansore Tehsil, in Seoni Distt., in Madhya Pradesh - reg. TOR.
The proposal was considered for determination of terms of reference for undertaking EIA/EMP study as per provisions of EIA notification 2006. The project proponent gave a presentation along with its consultant M/s J.M. EnviroNet Pvt. Ltd. and provided the following information:
The proposal is for expansion by addition of 1x600 MW Coal Based TPP at villages Barela and Gorakhpur, in Ghansore Tehsil, in Seoni Distt., in Madhya Pradesh. Phase-I is in advance stage of implementation. Land requirement 406.50 acres. Diversion of 148.0 acres of forests land will be involved. Acquisition of 77.17 acres of tribal land will also be involved. The co-ordinates of the site are at Latitude 22043’28” to 22044’35” N and Longitude 79054’10” to 79055’47” E. Coal requirement will be 3.15 MTPA. Source of water will be from Bargi Reservoir at a point upstream 10 Kms away from the site and through a Jack Well. Water requirement will be 16.8 MCM. There are no wildlife sanctuary, national park, biosphere / tiger reserve, heritage sites etc. with 10 km of the proposed site.
Based on the information provided and presentation made the Committee prescribed the following specific TORs for undertaking detailed EIA study and preparation of EMP.
i) Status of compliance to the conditions stipulated in the environmental clearance accorded for Phase-I shall be submitted along with EIA/EMP report.
ii) Status of diversion of forests land involved shall be submitted.
iii) Vision document specifying prospective long term plan of the site shall be formulated and submitted.
iv) Executive summary of the project indicating relevant details along with photograph of site shall be provided and issues raised in public hearing along with action plan to address the same shall be provided in tabular form including requisite allocation of funds.
v) Conformity of the site with the prescribed guidelines in terms of distance of 500 m from HFL of the river, highways, railway line shall be shown on the study area map.
vi) The project proponent shall provide confirmed GPS readings of plant boundary.
vii) Details of acquisition of tribal land and compliance to tribal rights as per existing Central and State legislations as may be applicable shall be submitted.
viii) No water body/nallah (if any) shall be touched. It shall also be ensured that atleast 100 m distance is kept away from the HFL of the nallah (if any) passing in and around the proposed site.
ix) Hydro-geological study of the area shall be conducted from an institute/ organisation of repute to assess impact of on ground and surface water regime. Specific mitigation measures shall be spelt out and action plan for implementation of the same shall be provided.
x) Source sustainability study of water requirement shall be carried out by an institute of repute. The study shall also specify the source of water for meeting the requirement during lean season and proposed plan of action.
xi) Study on the impact on catchment area of the river due to proposed withdrawal of such huge quantity of water for running the power plant shall be carried out and submitted.
xii) Source of water and its availability. Commitment regarding availability of requisite quantity of water from the competent authority shall be provided along with firm linkage.
xiii) Detailed plan for carrying out rainwater harvesting and proposed utilisation in the plant shall be provided.
xiv) Feasibility of zero discharge shall be examined and detailed justification shall be submitted if in case the same is not possible. Proposed discharge (if any), its quantity, quality and point of discharge, users downstream etc. shall be provided.
xv) Optimization of COC for water conservation. Other water conservation measures proposed in the project should also be given. Quantity of water requirement for the project should be optimized.
xvi) Details of water balance taking into account reuse and re-circulation of effluents.
xvii) Detailed plan for conducting monitoring of water quality regularly and mechanism for maintenance of records shall be formulated. Details of methodology and identification of monitoring points (between the plant and drainage in the direction of flow of surface / ground water) shall be submitted. It shall be ensured that parameter to be monitored also include heavy metals in surface and ground water.
xviii) Ash pond shall be shifted away as far as possible from any surface water source. The coordinates of the proposed site including location of ash pond shall be submitted along with topo sheet.
xix) Action plan for identification of local employable youth for training in skills relevant to the project for eventual employment in the project itself shall be formulated.
xx) Layout of the plant indicating break-up of plant, green belt, infrastructure, roads etc. shall be provided.
xxi) Land requirement for the project shall be optimized. Item wise break up of land requirement and its availability to be furnished. It should also include land to be acquired, if any, for coal transportation system as well as for laying of pipeline including ROW. It may clearly be confirmed that the land including ROW is free of all encumbrances. The issues relating to land acquisition and R&R should be clearly discussed in the EIA report.
xxii) Land use based on satellite imagery or authenticated map indicating drainage, cropping pattern, water bodies (rivers, nallahs, ponds etc.), location of nearest villages, creeks, rivers, reservoirs, national parks, wildlife sanctuaries, tiger reserves, biosphere reserves, heritage sites etc in the study area shall be provided. Location of any National Park, Sanctuary, Elephant/Tiger Reserve (existing as well as proposed), migratory routes, if any, within 10 km of the project site shall be specified and marked on the map duly authenticated by the Chief Wildlife Warden.
xxiii) Study on land-use pattern in the study area shall be carried out, including identification of common property resources available for conversion into productive land and action plan for abatement and compensation for damage to agricultural land/ common property land (if any) in the nearby villages, due to proposed project shall be prepared.
xxiv) Detailed socio-economic study shall be carried out for the study area comprising of 10 km from the plant site.
xxv) A detailed R&R action plan (as applicable) with time schedule for implementation and also consisting of an in-built monitoring mechanism by an independent third party shall be prepared.
xxvi) CSR component shall be prepared based on need based assessment study to be carried out in the study area. Income generating measures which can help in upliftment of poor section of society which is consistent with the traditional skills of the people shall be identified. The programme can include activities such as development of fodder farm, fruit bearing orchards, vocational training etc. In addition, vocational training for individuals shall be imparted so that poor section of society can take up self employment and jobs. Separate budget for community development activities and income generating programmes shall be specified. Financial allocation to be taken up under CSR shall be specified.
xxvii) While formulating CSR schemes it shall be ensured that an in-built monitoring mechanism for the schemes identified is in place and mechanism for conducting annual social audit from the nearest government institute of repute in the region shall be prepared. The project proponent shall also provide plan for the status of implementation of the scheme from time to time.
xxviii) Possibility for adopting nearest three villages shall be explored and details of civic amenities such as roads, drinking water, power etc proposed to be provided at the company’s expenses shall be submitted.
xxix) Location of intake and outfall points (with coordinates) should be given and the method of disposal of treated waste water from power plant shall be submitted.
xxx) Topography of the area should be given clearly indicating whether the site requires any filling. If so, details of filling, quantity of fill material required, its source, transportation etc. should be given.
xxxi) One complete season AAQ data (except monsoon) shall be given along with the dates of monitoring. The parameters to be covered shall include SPM, RSPM (PM10,PM2.5), SO2, NOx, Hg and Ozone (ground level). The location of the monitoring stations should be so decided so as to take into consideration the pre-dominant downwind direction, population zone and sensitive receptors including reserved forests. There should be at least one monitoring station each in the upwind and in the pre dominant downwind direction at a location where maximum ground level concentration is likely to occur.
xxxii) Cumulative impact assessment on ambient air quality due to proposed plant and others (including existing as well as other proposed source of emission) shall be carried out and result submitted in the EIA Report. Mitigative measures as necessary shall be clearly spelt out.
xxxiii) Impact of the project on the AAQ of the area. Details of the model used and the input data used for modelling should also be provided. The air quality contours may be plotted on a location map showing the location of project site, habitation nearby, sensitive receptors, if any. The wind roses should also be shown on this map.
xxxiv) Fuel analysis shall be provided. Details of auxillary fuel, if any including its quantity, quality, storage etc should also be given.
xxxv) Quantity of fuel required, its source and transportation route and mode and a confirmed fuel linkage documents shall be provided.
xxxvi) Details regarding infrastructure facilities such as sanitation, fuel, restroom, medical facilities, safety during construction phase etc. to be provided to the labour force during construction as well as to the casual workers including truck drivers during operation phase.
xxxvii) EMP to mitigate the adverse impacts due to the project along with item wise cost of its implementation.
xxxviii) A Disaster Management Plan along with risk assessment study including fire and explosion issues due to storage and use of fuel should be carried out. It should take into account the maximum inventory of storage at site at any point in time. The risk contours should be plotted on the plant layout map clearly showing which of the proposed activities would be affected in case of an accident taking place. Based on the same, proposed safeguard measures should be provided. Measures to guard against fire hazards should also be provided.
xxxix) Detailed plan for raising Green belt of 100 m width and consisting of at least 3 tiers around plant boundary with tree density not less than 2500 trees per ha and survival rate atleast 75% shall be submitted.
xl) Details of litigation pending or otherwise with respect to project in any courts, tribunal etc. shall be provided.
Besides all the above, the following general points will be followed:-
a) All documents to be properly referenced with index, page numbers and continuous page numbering.
b) Where data is presented in the report especially in table, the period in which the data was collected and the source should invariably be indicated.
c) Where the documents provided are in a language other than English, an English translation should be provided.
d) The Questionnaire for environmental appraisal of thermal power projects as devised earlier by the Ministry shall also be filled and submitted.
In addition, information on the following may also be incorporated in the EIA report.
1). Is the project intended to have CDM-intent?
i) If not, then reasons thereof?
ii) If yes, then details under mentioned to be provided:
a) Has PIN (Project Idea Note) {or PCN (Project Concept Note)} been submitted to the NCA? (National CDM Authority) in the MoEF?
b) If not, then by when is that expected?
c) Has PDD (Project Design Document) been prepared?
d) What is the Carbon intensity from your electricity generation projected (i.e. CO2 Tons/MWH or Kg/KWH)
e) Amount of CO2 in Tons/year expected to be reduced from the baseline data available on the CEA’s web-site (www.cea.nic.in)
2. Notwithstanding 1(i) above, data on (d) & (e) above to be worked out and reported.
The Committee informed the project proponent that after preparing the draft EIA (as per the generic structure prescribed in Appendix-III of the EIA Notification, 2006) covering the above mentioned issues, the same shall be submitted to the SPCB for conducting the public hearing as per procedure of EIA notification 2006. The issues which emerge during public hearing shall be further incorporated in the Draft EIA/EMP report. The final EIA/EMP report along with public hearing report and the requisite documents (including written objections, if any) shall be submitted to the Ministry for appraisal by the Expert Appraisal Committee for consideration of awarding environmental clearance under the provisions of Environmental Impact Assessment notification dated September 14, 2006.
2.7 2400 MW Combined Cycle Gas Based TPP of M/s Rajanagaram Gas Power Pvt. Ltd. at village Mukkinada, in Rajanagaram Mandal, in East Godavari Distt., in Andhra Pradesh - reg. TOR.
The proposal was considered for determination of terms of reference for undertaking EIA/EMP study as per provisions of EIA notification 2006. The project proponent along with its consultant viz. M/s B.S. Envitech Pvt. Ltd., Hyderabad gave a presentation and provided the following information:
The proposal is for setting of 2400 MW Combined Cycle Gas Based Power Plant at village Mukkinada, in Rajanagaram Mandal, in East Godavari Distt., in Andhra Pradesh. Land requirement will be 242 acres, which is a private land. Co-ordinates of the site are at Latitude 160 58’36.76” to 160 59’36.03” N and Longitude 81057’22.04” to 81057’53.67” E. Natural gas will be obtained from KG Basin. Natural gas requirement will be 5.29 MMSCMD. Water requirement will be obtained from Godavari River from a point 18.5 Km from the site. There are no National parks, Wildlife sanctuaries, Heritage sites, Tiger/Biosphere reserves etc. within 10 km of the site.
The Committee noted that the proposal is for setting up of unit capacities 2x1075 MW each in two phases viz. Phase-I 1x1075MW and Phase-II 1x1075 MW. The Committee informed the project proponent that the desirable unit configurations may be 2x1200 MW each and they may like to explore the same configuration, to which the project proponent confirmed its intention. The Committee therefore decided that the project proponent shall submit revised Form-I to the Ministry with the changed configuration of 2x1200 MW in lieu of 2x1075 MW.
The Committee noted that the identified site is a fertile agricultural land and cannot be recommended for setting up of a thermal power plant. The Committee therefore decided that the project proponent shall explore alternative sites and come back again. Accordingly the proposal was deferred for re-consideration at a later stage.
2.8 2x660 MW Coal Based TPP of M/s Madhucon Projects Ltd. at villages Thopgram, Bykuntpur, Narayanpur, Abhirampur, debu & Satyanaranpur, in Barharwa Block, in Sahibganj Distt., in Jharkhand - reg. TOR.
The proposal was considered for determination of terms of reference for undertaking EIA/EMP study as per provisions of EIA notification 2006. The project proponent along with its consultant viz. M/s B.S. Envitech Pvt. Ltd., Hyderabad gave a presentation and provided the following information:
The proposal is for setting of 2x660 MW Super-Critical Coal Coal Based TPP at villages Thopgram, Bykuntpur, Narayanpur, Abhirampur, debu & Satyanaranpur, in Barharwa Block, in Sahibganj Distt., in Jharkhand. Land requirement will be 1127.55 acres, which is a single crop agricultural land. The co-ordinates of the proposed site will be at Latitude 240 51’35” to 240 52’44” N and Longitude 87049’6.5” to 87051’25.3” E. Coal requirement will be 6.42 MTPA at 85% PLF. Water requirement will be 36 MCM, which will be obtained from Ganga river. There are no National parks, Wildlife sanctuaries, Heritage sites, Tiger/Biosphere reserves etc. within 10 km of the site.
The Committee noted that the identified site is a fertile agricultural land and may be in the flood plain of river Ganga. In the absence of detail information of the site and / or other suitable alternative sites the Committee expressed its inability to recommended the site for setting up of a thermal power plant. The Committee therefore decided that the project proponent shall explore alternative sites and come back again. Accordingly the proposal was deferred for re-consideration at a later stage.
2.9 Expansion by addition of 2x660 MW Coal Based TPP of M/s Simhapuri Energy Pvt. Ltd. at villages Tamminapatnam and Mommidi, in Chillakur Taluk, in Nellore Distt., in Andhra Pradesh - reg. TOR.
The proposal was considered for determination of terms of reference for undertaking EIA/EMP study as per provisions of EIA notification 2006. The project proponent along with its consultant viz. M/s B.S. Envitech Pvt. Ltd., Hyderabad gave a presentation and provided the following information:
The proposal is for expansion of exiting Phase-I 2x150 MW and Phase-II 2x150 MW by addition of 2x660 MW Super-Critical Coal Coal Based TPP at villages Tamminapatnam and Mommidi, in Chillakur Taluk, in Nellore Distt., in Andhra Pradesh. Both phases are under advance stages of implementation and civil works are under progress. The first unit is likely to be commissioned by March, 2011. Land requirement for expansion will be 728.57 acres. Total land requirement will be 1130.35 acres, out of which 1072.39 acres is revenue land and 57.96 acres is private patta land. An area of 401.78 acres is already acquired. The co-ordinates of the proposed site will be at Latitude 140 12’6.28” to 140 12’50.79” N and Longitude 80005’36.25” to 80004’58.50” E. Coal requirement will be 4.54 MTPA at 85% PLF. Imported and domestic coal in the ratio 70:30 blending will be used as fuel. Kandaleru Creek is adjacent to the proposed site. Water requirement will be 0.29 MLD, which will be obtained from the Creek. There are no National parks, Wildlife sanctuaries, Heritage sites, Tiger/Biosphere reserves etc. within 10 km of the site.
The Committee noted that the proposed layout of the expansion plan vis-à-vis the existing Phases need a drastic relocation / changes, which was admitted to by the project proponent.
The Committee also informed that in case change in layout of the existing phases need to be carried out, endorsement is required from the Ministry. It was also informed that Ash Dyke needs to be shifted. Accordingly the Committee decided that proposal for expansion is pre-mature at this stage was accordingly deferred for re-consideration at a later stage.
2.10 2x660 MW Coal Based Thermal Power Plant of M/s Mirach Power Pvt. Ltd. at village Pokhrawan, in Surajgarha Taluk, in Lakhisarai Distt., in Bihar - reg. TOR.
The proposal was considered for determination of terms of reference for undertaking EIA/EMP study as per provisions of EIA notification 2006. The project proponent along with its consultant viz. M/s Vimta Labs Pvt. Ltd., Hyderabad gave a presentation and provided the following information:
The proposal is for setting up of 2x660 MW Super-Critical Coal Based TPP at village at village Pokhrawan, in Surajgarha Taluk, in Lakhisarai Distt., in Bihar. Land requirement will be 900 acres, which comprises of 759.18 acres of single crop agricultural land; 135.50 acres of double crop agricultural land; and 5.32 acres of govt. revenue land. The co-ordinates of the proposed site will be within Latitude 250 10’31.22” to 250 11’59.56” N and Longitude 86012’46.49” to 86015’13.43” E. Coal requirement will be 7.5 MTPA. Domestic coal will be used as fuel. Water requirement will be 96 MLD, which will be obtained from River Ganga through an Intake Well, 15 Km from the site. There are no National parks, Wildlife sanctuaries, Heritage sites, Tiger/Biosphere reserves etc. within 10 km of the site.
The Committee noted that the identified preferred site is a fertile agricultural land and may be part of flood plain of river Ganga. In the absence of detail information of the site and / or other suitable alternative sites the Committee expressed its inability to recommended the site for setting up of a thermal power plant. The Committee therefore decided that the project proponent shall explore other alternative sites. In case the preferred site in the instant case is the only option left adequate justification along with details of the land including names of owners etc. may be provided. The information of the preferred site shall be provided by an undertaking in the form of an affidavit on a stamp paper of appropriate amount. Accordingly the proposal was deferred for re-consideration at a later stage.
2.11 2x660 MW Coal Based Thermal Power Plant of M/s Lanco Anpara Power Ltd. at villages Chaperghata, Rasulpur Bhuranda, Kirpalpur, Bhartauli and Sihari, in Bhognipur Taluk, in Ramabai Nagar Distt., in Uttar Pradesh - reg. TOR.
The proposal was placed for determination of terms of reference for undertaking EIA/EMP study as per provisions of EIA notification 2006. The project proponent along with its consultant M/s Vimta Labs Ltd., Hyderabad gave a presentation and provided the following information:
The proposal is for setting up of 2x660 MW Super Critical Coal Based TPP at villages Chaperghata, Rasulpur Bhuranda, Kirpalpur, Bhartauli and Sihari, in Bhognipur Taluk, in Ramabai Nagar Distt., in Uttar Pradesh. Land requirement shall be restricted to 900 acres, which comprises of 760.0 acres of single crop agricultural land; 10 acres of double crop agricultural land; and 230 acres of waste land. The co-ordinates of the proposed site will be within Latitude 26010’45.46” to 260 12’24.18” N and Longitude 79054’19.98 to 79056’39.54” E. Coal requirement will be 7.5 MTPA. Water requirement of 40 MCM, which will be sourced from Yamuna River, downstream of Kalpi Raiway Bridge. There are no wildlife sanctuary, national park, biosphere/tiger reserve, heritage sites etc. with 15 km of the proposed site.
Based on the information provided and presentation made the Committee prescribed the following specific TORs for undertaking detailed EIA study and preparation of EMP.
i) Vision document specifying prospective long term plan of the site shall be formulated and submitted.
ii) Executive summary of the project indicating relevant details along with photograph of site shall be provided and issues raised in public hearing along with action plan to address the same shall be provided in tabular form including requisite allocation of funds.
iii) Conformity of the site with the prescribed guidelines in terms of distance of 500 m from HFL of the river, highways, railway line shall be shown on the study area map.
iv) The project proponent shall provide confirmed GPS readings of plant boundary.
v) No water body/nallah (if any) shall be touched. It shall also be ensured that atleast 100 m distance is kept away from the HFL of the nallah/ river (if any) passing in and around the proposed site.
vi) Detailed hydro-geological study of the area shall be conducted from an institute/ organisation of repute to assess impact of on ground and surface water regime. Specific mitigation measures shall be spelt out and action plan for implementation of the same shall be provided.
vii) Detailed source sustainability study of water requirement shall be carried out by an institute of repute. The study shall also specify the source of water for meeting the requirement during lean season and proposed plan of action.
viii) Study on the impact on river/reservoir/marine ecology (as applicable) due to the proposed discharge of treated wastewater into the river/creek shall be carried out and submitted alongwith the EIA Report.
ix) Ash pond shall be shifted away as far as possible from any surface water source and its location shall be chosen taking into consideration the elevation and water drainage pattern in the area. The coordinates of the proposed site including location of ash pond shall be submitted along with topo sheet.
x) Action plan for identification of local employable youth for training in skills relevant to the project for eventual employment in the project itself shall be formulated and details submitted along with EIA/EMP Report.
xi) Layout of the plant indicating break-up of plant, green belt, infrastructure, roads etc. shall be provided.
xii) Land requirement for the project shall be optimized. Item wise break up of land requirement and its availability to be furnished. It should also include land to be acquired, if any, for coal transportation system as well as for laying of pipeline including ROW. It may clearly be confirmed that the land including ROW is free of all encumbrances. The issues relating to land acquisition and R&R should be clearly discussed in the EIA report.
xiii) Land use based on satellite imagery or authenticated map indicating drainage, cropping pattern, water bodies (rivers, nallahs, ponds etc.), location of nearest villages, creeks, rivers, reservoirs, national parks, wildlife sanctuaries, tiger reserves, biosphere reserves, heritage sites etc in the study area shall be provided. Location of any National Park, Sanctuary, Elephant/Tiger Reserve (existing as well as proposed), migratory routes, if any, within 10 km of the project site shall be specified and marked on the map duly authenticated by the Chief Wildlife Warden.
xiv) Study on land-use pattern in the study area shall be carried out, including identification of common property resources available for conversion into productive land and action plan for abatement and compensation for damage to agricultural land/ common property land (if any) in the nearby villages, due to proposed project shall be prepared.
xv) Detailed socio-economic study shall be carried out for the study area comprising of 10 km from the plant site.
xvi) CSR component shall be prepared based on need based assessment study to be carried out in the study area. Income generating measures which can help in upliftment of poor section of society which is consistent with the traditional skills of the people shall be identified. The programme can include activities such as development of fodder farm, fruit bearing orchards, vocational training etc. In addition, vocational training for individuals shall be imparted so that poor section of society can take up self employment and jobs. Separate budget for community development activities and income generating programmes shall be specified. Financial allocation to be taken up under CSR shall be specified.
xvii) While formulating CSR schemes it shall be ensured that an in-built monitoring mechanism for the schemes identified is in place and mechanism for conducting annual social audit from the nearest government institute of repute in the region shall be prepared. The project proponent shall also provide plan for the status of implementation of the scheme from time to time.
xviii) Possibility for adopting nearest three villages shall be explored and details of civic amenities such as roads, drinking water, power etc proposed to be provided at the company’s expenses shall be submitted.
xix) Location of intake and outfall points (with coordinates) should be given. These locations should be selected based on detailed modeling studies. Details of modeling and the results obtained there from should be furnished. It may be kept in view that the intake and outfall points are away from the mangroves or other eco sensitive areas. A river/marine ecology study (as applicable) should also be done to assess impact on river/marine ecology. River/Marine impact of such activities should be clearly brought out in the EIA report.
xx) Topography of the area should be given clearly indicating whether the site requires any filling. If so, details of filling, quantity of fill material required, its source, transportation etc. should be given.
xxi) One complete season AAQ data (except monsoon) to be given along with the dates of monitoring. The parameters to be covered shall include SPM, RSPM(PM10,PM2.5), SO2, NOx, Hg and Ozone (ground level). The location of the monitoring stations should be so decided so as to take into consideration the pre-dominant downwind direction, population zone and sensitive receptors including reserved forests. There should be at least one monitoring station each in the upwind and in the pre dominant downwind direction at a location where maximum ground level concentration is likely to occur.
xxii) Cumulative impact assessment on ambient air quality due to proposed plant and others (including existing as well as other proposed source of emission) shall be carried out and result submitted in the EIA Report. Mitigative measures as necessary shall be clearly spelt out.
xxiii) Impact of the project on the AAQ of the area. Details of the model used and the input data used for modelling should also be provided. The air quality contours may be plotted on a location map showing the location of project site, habitation nearby, sensitive receptors, if any. The wind roses should also be shown on this map.
xxiv) Fuel analysis shall be provided. Details of auxillary fuel, if any including its quantity, quality, storage etc should also be given.
xxv) Quantity of fuel required, its source and transportation route and mode and a confirmed fuel linkage documents shall be provided.
xxvi) Source of water and its availability. Commitment regarding availability of requisite quantity of water from the competent authority shall be provided along with firm linkage.
xxvii) Detailed plan for carrying out rainwater harvesting and proposed utilisation in the plant shall be provided.
xxviii) Feasibility of zero discharge shall be examined and detailed justification shall be submitted if in case the same is not possible. Proposed discharge (if any), its quantity, quality and point of discharge, users downstream etc. shall be provided.
xxix) Optimization of COC for water conservation. Other water conservation measures proposed in the project should also be given. Quantity of water requirement for the project should be optimized.
xxx) Details of water balance taking into account reuse and re-circulation of effluents.
xxxi) Detailed plan for conducting monitoring of water quality regularly and mechanism for maintenance of records shall be formulated. Details of methodology and identification of monitoring points (between the plant and drainage in the direction of flow of surface / ground water) shall be submitted. It shall be ensured that parameter to be monitored also include heavy metals in surface and ground water.
xxxii) Details regarding infrastructure facilities such as sanitation, fuel, restroom, medical facilities, safety during construction phase etc. to be provided to the labour force during construction as well as to the casual workers including truck drivers during operation phase.
xxxiii) EMP to mitigate the adverse impacts due to the project along with item wise cost of its implementation.
xxxiv) A Disaster Management Plan along with risk assessment study including fire and explosion issues due to storage and use of fuel should be carried out. It should take into account the maximum inventory of storage at site at any point in time. The risk contours should be plotted on the plant layout map clearly showing which of the proposed activities would be affected in case of an accident taking place. Based on the same, proposed safeguard measures should be provided. Measures to guard against fire hazards should also be provided.
xxxv) Detailed plan for raising Green belt of 100 m width and consisting of at least 3 tiers around plant boundary with tree density not less than 2500 trees per ha and survival rate atleast 75% shall be submitted.
xxxvi) Details of litigation pending or otherwise with respect to project in any courts, tribunal etc. shall be provided.
Besides all the above, the following general points will be followed:-
a) All documents to be properly referenced with index, page numbers and continuous page numbering.
b) Where data is presented in the report especially in table, the period in which the data was collected and the source should invariably be indicated.
c) Where the documents provided are in a language other than English, an English translation should be provided.
d) The Questionnaire for environmental appraisal of thermal power projects as devised earlier by the Ministry shall also be filled and submitted.
In addition, information on the following may also be incorporated in the EIA report.
1). Is the project intended to have CDM-intent?
i) If not, then reasons thereof?
ii) If yes, then details under mentioned to be provided:
a) Has PIN (Project Idea Note) {or PCN (Project Concept Note)} been submitted to the NCA? (National CDM Authority) in the MoEF?
b) If not, then by when is that expected?
c) Has PDD (Project Design Document) been prepared?
d) What is the Carbon intensity from your electricity generation projected (i.e. CO2 Tons/MWH or Kg/KWH)
e) Amount of CO2 in Tons/year expected to be reduced from the baseline data available on the CEA’s web-site (www.cea.nic.in)
2. Notwithstanding 1(i) above, data on (d) & (e) above to be worked out and reported.
The Committee informed the project proponent that after preparing the draft EIA (as per the generic structure prescribed in Appendix-III of the EIA Notification, 2006) covering the above mentioned issues, the same shall be submitted to the SPCB for conducting the public hearing as per procedure of EIA notification 2006. The issues which emerge during public hearing shall be further incorporated in the Draft EIA/EMP report. The final EIA/EMP report along with public hearing report and the requisite documents (including written objections, if any) shall be submitted to the Ministry for appraisal by the Expert Appraisal Committee for consideration of awarding environmental clearance under the provisions of Environmental Impact Assessment notification dated September 14, 2006.
2.12 3x840 MW Coal Based Thermal Power Plant of M/s Torrent Pipavav Generation Ltd. at villages Rampara II and Ucchaiya, in Rajula Taluk, in Amreli Distt., in Gujarat - reg. TOR.
The proposal was placed for determination of terms of reference for undertaking EIA/EMP study as per provisions of EIA notification 2006. The project proponent along with its consultant M/s EMTRC, New Delhi gave a presentation and provided the following information:
The proposal is for setting up of 2x840 MW Super Critical Coal Based TPP at villages Rampara II and Ucchaiya, in Rajula Taluk, in Amreli Distt., in Gujarat. Land requirement shall be restricted to 1200 acres, which comprises of single crop agricultural land. The co-ordinates of the proposed site will be within Latitude 20056’21” to 200 57’6” N and Longitude 71027’32 to 71028’41” E. Coal requirement will be 7.5 MTPA. Domestic and Imported Coal in the ration 70:30 will be used. Water requirement of 186 MCMPA, which will be sourced from Arabian Sea at 6 Km. Mangroves are present at Chanch Creek / Bandar. There are no wildlife sanctuary, national park, biosphere/tiger reserve, heritage sites etc. with 15 km of the proposed site.
Based on the information provided and presentation made the Committee prescribed the following specific TORs for undertaking detailed EIA study and preparation of EMP.
i) Vision document specifying prospective long term plan of the site shall be formulated and submitted.
ii) Executive summary of the project indicating relevant details along with photograph of site shall be provided and issues raised in public hearing along with action plan to address the same shall be provided in tabular form including requisite allocation of funds.
iii) Conformity of the site with the prescribed guidelines in terms of distance of 500 m from HFL of the river, highways, railway line shall be shown on the study area map.
iv) The project proponent shall provide confirmed GPS readings of plant boundary.
v) No water body/nallah (if any) shall be touched. It shall also be ensured that atleast 100 m distance is kept away from the HFL of the nallah/ river (if any) passing in and around the proposed site.
vi) Detailed hydro-geological study of the area shall be conducted from an institute/ organisation of repute to assess impact of on ground and surface water regime. Specific mitigation measures shall be spelt out and action plan for implementation of the same shall be provided.
vii) Demarcation of CRZ lines by any of the authorized agency shall be carried out and submitted.
viii) Marine impact assessment study (Marine EIA) from a reputed organization shall be carried out. The study shall comprise of besides other impact on marine ecology due to the proposed withdrawal of sea water and discharge of treated wastewater into the sea.
ix) Ash pond shall be shifted away as far as possible from any surface water source and its location shall be chosen taking into consideration the elevation and water drainage pattern in the area. The coordinates of the proposed site including location of ash pond shall be submitted along with topo sheet.
x) Action plan for identification of local employable youth for training in skills relevant to the project for eventual employment in the project itself shall be formulated and details submitted along with EIA/EMP Report.
xi) Layout of the plant indicating break-up of plant, green belt, infrastructure, roads etc. shall be provided.
xii) Land requirement for the project shall be optimized. Item wise break up of land requirement and its availability to be furnished. It should also include land to be acquired, if any, for coal transportation system as well as for laying of pipeline including ROW. It may clearly be confirmed that the land including ROW is free of all encumbrances. The issues relating to land acquisition and R&R should be clearly discussed in the EIA report.
xiii) Land use based on satellite imagery or authenticated map indicating drainage, cropping pattern, water bodies (rivers, nallahs, ponds etc.), location of nearest villages, creeks, rivers, reservoirs, national parks, wildlife sanctuaries, tiger reserves, biosphere reserves, heritage sites etc in the study area shall be provided. Location of any National Park, Sanctuary, Elephant/Tiger Reserve (existing as well as proposed), migratory routes, if any, within 10 km of the project site shall be specified and marked on the map duly authenticated by the Chief Wildlife Warden.
xiv) Study on land-use pattern in the study area shall be carried out, including identification of common property resources available for conversion into productive land and action plan for abatement and compensation for damage to agricultural land/ common property land (if any) in the nearby villages, due to proposed project shall be prepared.
xv) Detailed socio-economic study shall be carried out for the study area comprising of 10 km from the plant site.
xvi) CSR component shall be prepared based on need based assessment study to be carried out in the study area. Income generating measures which can help in upliftment of poor section of society which is consistent with the traditional skills of the people shall be identified. The programme can include activities such as development of fodder farm, fruit bearing orchards, vocational training etc. In addition, vocational training for individuals shall be imparted so that poor section of society can take up self employment and jobs. Separate budget for community development activities and income generating programmes shall be specified. Financial allocation to be taken up under CSR shall be specified.
xvii) While formulating CSR schemes it shall be ensured that an in-built monitoring mechanism for the schemes identified is in place and mechanism for conducting annual social audit from the nearest government institute of repute in the region shall be prepared. The project proponent shall also provide plan for the status of implementation of the scheme from time to time.
xviii) Possibility for adopting nearest three villages shall be explored and details of civic amenities such as roads, drinking water, power etc proposed to be provided at the company’s expenses shall be submitted.
xix) Location of intake and outfall points (with coordinates) should be given. These locations should be selected based on detailed modeling studies. Details of modeling and the results obtained there from should be furnished. It may be kept in view that the intake and outfall points are away from the mangroves or other eco sensitive areas. A river/marine ecology study (as applicable) should also be done to assess impact on river/marine ecology. River/Marine impact of such activities should be clearly brought out in the EIA report.
xx) Topography of the area should be given clearly indicating whether the site requires any filling. If so, details of filling, quantity of fill material required, its source, transportation etc. should be given.
xxi) One complete season AAQ data (except monsoon) to be given along with the dates of monitoring. The parameters to be covered shall include SPM, RSPM(PM10,PM2.5), SO2, NOx, Hg and Ozone (ground level). The location of the monitoring stations should be so decided so as to take into consideration the pre-dominant downwind direction, population zone and sensitive receptors including reserved forests. There should be at least one monitoring station each in the upwind and in the pre dominant downwind direction at a location where maximum ground level concentration is likely to occur.
xxii) Cumulative impact assessment on ambient air quality due to proposed plant and others (including existing as well as other proposed source of emission) shall be carried out and result submitted in the EIA Report. Mitigative measures as necessary shall be clearly spelt out.
xxiii) Impact of the project on the AAQ of the area. Details of the model used and the input data used for modelling should also be provided. The air quality contours may be plotted on a location map showing the location of project site, habitation nearby, sensitive receptors, if any. The wind roses should also be shown on this map.
xxiv) Fuel analysis shall be provided. Details of auxillary fuel, if any including its quantity, quality, storage etc should also be given.
xxv) Quantity of fuel required, its source and transportation route and mode and a confirmed fuel linkage documents shall be provided.
xxvi) Source of water and its availability. Commitment regarding availability of requisite quantity of water from the competent authority shall be provided along with firm linkage.
xxvii) Detailed plan for carrying out rainwater harvesting and proposed utilisation in the plant shall be provided.
xxviii) Feasibility of zero discharge shall be examined and detailed justification shall be submitted if in case the same is not possible. Proposed discharge (if any), its quantity, quality and point of discharge, users downstream etc. shall be provided.
xxix) Optimization of COC for water conservation. Other water conservation measures proposed in the project should also be given. Quantity of water requirement for the project should be optimized.
xxx) Details of water balance taking into account reuse and re-circulation of effluents.
xxxi) Detailed plan for conducting monitoring of water quality regularly and mechanism for maintenance of records shall be formulated. Details of methodology and identification of monitoring points (between the plant and drainage in the direction of flow of surface / ground water) shall be submitted. It shall be ensured that parameter to be monitored also include heavy metals in surface and ground water.
xxxii) Details regarding infrastructure facilities such as sanitation, fuel, restroom, medical facilities, safety during construction phase etc. to be provided to the labour force during construction as well as to the casual workers including truck drivers during operation phase.
xxxiii) EMP to mitigate the adverse impacts due to the project along with item wise cost of its implementation.
xxxiv) A Disaster Management Plan along with risk assessment study including fire and explosion issues due to storage and use of fuel should be carried out. It should take into account the maximum inventory of storage at site at any point in time. The risk contours should be plotted on the plant layout map clearly showing which of the proposed activities would be affected in case of an accident taking place. Based on the same, proposed safeguard measures should be provided. Measures to guard against fire hazards should also be provided.
xxxv) Detailed plan for raising Green belt of 100 m width and consisting of at least 3 tiers around plant boundary with tree density not less than 2500 trees per ha and survival rate atleast 75% shall be submitted.
xxxvi) Details of litigation pending or otherwise with respect to project in any courts, tribunal etc. shall be provided.
Further, the following shall be strictly followed (as applicable):
a) The land requirement for the projects should be limited to barest minimum. If the site includes or is located close to marshy areas and backwaters, these areas must be excluded from the site and the project boundary should be atleast 500 away from the ecologically sensitive areas. If backwaters form a part of the site, CRZ clearance is a must.
b) The soil levelling should be minimum with no or minimal disturbance to the natural drainage of the area. If the minor canals (if any) have to be diverted, the design for diversion should be such that the diverted canals not only drains the plant area but also collect the volume of flood water from the surrounding areas and discharge into marshy areas/major canals that enter into creek. Major canals should not be altered but their bunds should be strengthened and desilted.
c) Additional soil for leveling of the sites should be generated within the sites in a way that natural drainage system of the area is protected and improved
d) The marshy areas (if any) which hold large quantities of water should not be disturbed.
e) No waste should be discharged into canal systems, backwaters, marshy areas and seas without treatment. The outfall should be first treated in guard pond and then discharged into deep sea (12 to 15 m depth). Similarly, the intake should be from deep sea to avoid aggregation of fish. The brine that comes out from desalinization plants (if any) should not be discharged into sea but it should be recycled.
f) To absorb the ground level pollutants, to act as buffer against strong winds arising out of tropical cyclones/ storms, to reduce heat load and ameliorate environment, there is a need for shelterbelts / greenbelts / tree cover along the coastline, bunds around marshy areas, roadsides, around the project boundaries, around village boundaries, ash dykes, railway lines, around protected monuments, forts, waste places, School Campuses and other vacant lots. Coconut plantations can be developed along the coastline and near villages, Schools and forts. Stands of Casuariana should also be developed on some dunes and along coasts. Bamboos, neem and other native trees should be planted in and around at the villages.
g) To meet the expenditure of these plantations and their management, a common Green Endowment Fund should be created by the project proponents out of EMP budgets. The interest earned out of it should be used for the development and management of green cover of the area.
h) The villages bordering the sites may be predominantly inhabitated by fishermen and the TPP may have impacts on their livelihood, even though most of the fishing activity is confined to deep seas. An endowment of Fishermen Welfare Fund should be created out of CSR grants not only to enhance their quality of life through creation of facilities for fish landing platforms / fishing harbour / cold storage, but also to provide relief in case of emergency situations such as missing of fishermen on duty due to rough seas, tropical cyclones and storms etc.
i) There should not be any contamination of soil, ground and surface waters (canals & village pond) with sea water in and around the project sites. In other wards necessary preventive measures for spillage from pipelines, such as lining of guard pond used for the treatment of outfall before discharging into the sea and surface RCC channels along the pipelines of outfall and intake should be adopted. This is just because the areas around the projects boundaries is fertile agricultural land used for paddy cultivation.
Besides all the above, the following general points will be followed:-
a) All documents to be properly referenced with index, page numbers and continuous page numbering.
b) Where data is presented in the report especially in table, the period in which the data was collected and the source should invariably be indicated.
c) Where the documents provided are in a language other than English, an English translation should be provided.
d) The Questionnaire for environmental appraisal of thermal power projects as devised earlier by the Ministry shall also be filled and submitted.
In addition, information on the following may also be incorporated in the EIA report.
1). Is the project intended to have CDM-intent?
i) If not, then reasons thereof?
ii) If yes, then details under mentioned to be provided:
f) Has PIN (Project Idea Note) {or PCN (Project Concept Note)} been submitted to the NCA? (National CDM Authority) in the MoEF?
g) If not, then by when is that expected?
h) Has PDD (Project Design Document) been prepared?
i) What is the Carbon intensity from your electricity generation projected (i.e. CO2 Tons/MWH or Kg/KWH)
j) Amount of CO2 in Tons/year expected to be reduced from the baseline data available on the CEA’s web-site (www.cea.nic.in)
2. Notwithstanding 1(i) above, data on (d) & (e) above to be worked out and reported.
The Committee informed the project proponent that after preparing the draft EIA (as per the generic structure prescribed in Appendix-III of the EIA Notification, 2006) covering the above mentioned issues, the same shall be submitted to the SPCB for conducting the public hearing as per procedure of EIA notification 2006. The issues which emerge during public hearing shall be further incorporated in the Draft EIA/EMP report. The final EIA/EMP report along with public hearing report and the requisite documents (including written objections, if any) shall be submitted to the Ministry for appraisal by the Expert Appraisal Committee for consideration of awarding environmental clearance under the provisions of Environmental Impact Assessment notification dated September 14, 2006.
2.13 4x660 MW Coal Based Thermal Power Plant of M/s Global Powmin Ltd. at villages Shahpur, Ahiyapur, Ratanpur and Upperdih, at Sirdala Taluk, in Nawada Distt., in Bihar - reg. TOR.
The proposal was considered for determination of terms of reference for undertaking EIA/EMP study as per provisions of EIA notification 2006. The project proponent along with its consultant viz. M/s GIS Enabled Environment & Neo-Graphics Centre, Vaishali gave a presentation and provided the following information:
The proposal is for setting up of 4 x660 MW Super-Critical Coal Based TPP at villages Shahpur, Ahiyapur, Ratanpur and Upperdih, at Sirdala Taluk, in Nawada Distt., in Bihar. Land requirement will be 1613 acres, which comprises of 484 acres of single crop agricultural land; and 1129.33 acres of barren land. The co-ordinates of the proposed site will be within Latitude 240 39’47.03” to 240 41’3.66” N and Longitude 850 23’ 0.0” to 850 23’ 48.7” E. Coal requirement will be 12.42 MTPA. Domestic coal will be used as fuel, which will be obtained from CCL Coal mines through linkage. Water requirement will be 80 MCM, which will be obtained from River Sakri through an Intake Well at a distance of 25 Km from the site. There are no National parks, Wildlife sanctuaries, Heritage sites, Tiger/Biosphere reserves etc. within 10 km of the site.
The Committee noted that the identified preferred site seem a fertile agricultural land purportedly shown as barren land. In the absence of detail information of the site and / or other suitable alternative sites the Committee expressed its inability to recommended the site for setting up of a thermal power plant. The Committee therefore decided that the project proponent shall explore other alternative sites. In case the preferred site in the instant case is the only option left, adequate justification along with details of the land including names of owners etc. may be provided. The information of the preferred site shall be provided by an undertaking in the form of an affidavit on a stamp paper. Accordingly the proposal was deferred for re-consideration at a later stage.
2.14 6x660 MW Coal Based Thermal Power Plant of M/s Excel Powmin Ltd. at village Dabaura, in Jawa Block, in Reva Distt., in Madhya Pradesh - reg. TOR.
The proposal was placed for determination of terms of reference for undertaking EIA/EMP study as per provisions of EIA notification 2006. The project proponent along with its consultant M/s Green Circle Inc., Vadodara gave a presentation and provided the following information:
The proposal is for setting up of 6x660 MW Super Critical Coal Based TPP at village Dabaura, in Jawa Block, in Reva Distt., in Madhya Pradesh. Land requirement shall be restricted to 2000 acres, which is a single crop agricultural land. The co-ordinates of the proposed site will be within Latitude 25006’70” to 250 08’05” N and Longitude 81019’52” to 81023’01” E. Coal requirement will be 18.647.5 MTPA. Water requirement of 150 MCM, which will be sourced from Tamas River, from a Weir near Pathera-Atrela Road Bridge, 25 Km from the site. There are no wildlife sanctuary, national park, biosphere/tiger reserve, heritage sites etc. with 15 km of the proposed site.
Based on the information provided and presentation made the Committee prescribed the following specific TORs for undertaking detailed EIA study and preparation of EMP.
i) Vision document specifying prospective long term plan of the site shall be formulated and submitted.
ii) Executive summary of the project indicating relevant details along with photograph of site shall be provided and issues raised in public hearing along with action plan to address the same shall be provided in tabular form including requisite allocation of funds.
iii) Conformity of the site with the prescribed guidelines in terms of distance of 500 m from HFL of the river, highways, railway line shall be shown on the study area map.
iv) The project proponent shall provide confirmed GPS readings of plant boundary.
v) No water body/nallah (if any) shall be touched. It shall also be ensured that atleast 100 m distance is kept away from the HFL of the nallah/ river (if any) passing in and around the proposed site.
vi) Detailed hydro-geological study of the area shall be conducted from an institute/ organisation of repute to assess impact of on ground and surface water regime. Specific mitigation measures shall be spelt out and action plan for implementation of the same shall be provided.
vii) Detailed source sustainability study of water requirement shall be carried out by an institute of repute. The study shall also specify the source of water for meeting the requirement during lean season and proposed plan of action.
viii) Study on the impact on river/reservoir/marine ecology (as applicable) due to the proposed discharge of treated wastewater into the river/creek shall be carried out and submitted alongwith the EIA Report.
ix) Ash pond shall be shifted away as far as possible from any surface water source and its location shall be chosen taking into consideration the elevation and water drainage pattern in the area. The coordinates of the proposed site including location of ash pond shall be submitted along with topo sheet.
x) Action plan for identification of local employable youth for training in skills relevant to the project for eventual employment in the project itself shall be formulated and details submitted along with EIA/EMP Report.
xi) Layout of the plant indicating break-up of plant, green belt, infrastructure, roads etc. shall be provided.
xii) Land requirement for the project shall be optimized. Item wise break up of land requirement and its availability to be furnished. It should also include land to be acquired, if any, for coal transportation system as well as for laying of pipeline including ROW. It may clearly be confirmed that the land including ROW is free of all encumbrances. The issues relating to land acquisition and R&R should be clearly discussed in the EIA report.
xiii) Land use based on satellite imagery or authenticated map indicating drainage, cropping pattern, water bodies (rivers, nallahs, ponds etc.), location of nearest villages, creeks, rivers, reservoirs, national parks, wildlife sanctuaries, tiger reserves, biosphere reserves, heritage sites etc in the study area shall be provided. Location of any National Park, Sanctuary, Elephant/Tiger Reserve (existing as well as proposed), migratory routes, if any, within 10 km of the project site shall be specified and marked on the map duly authenticated by the Chief Wildlife Warden.
xiv) Study on land-use pattern in the study area shall be carried out, including identification of common property resources available for conversion into productive land and action plan for abatement and compensation for damage to agricultural land/ common property land (if any) in the nearby villages, due to proposed project shall be prepared.
xv) Detailed socio-economic study shall be carried out for the study area comprising of 10 km from the plant site.
xvi) CSR component shall be prepared based on need based assessment study to be carried out in the study area. Income generating measures which can help in upliftment of poor section of society which is consistent with the traditional skills of the people shall be identified. The programme can include activities such as development of fodder farm, fruit bearing orchards, vocational training etc. In addition, vocational training for individuals shall be imparted so that poor section of society can take up self employment and jobs. Separate budget for community development activities and income generating programmes shall be specified. Financial allocation to be taken up under CSR shall be specified.
xvii) While formulating CSR schemes it shall be ensured that an in-built monitoring mechanism for the schemes identified is in place and mechanism for conducting annual social audit from the nearest government institute of repute in the region shall be prepared. The project proponent shall also provide plan for the status of implementation of the scheme from time to time.
xviii) Possibility for adopting nearest three villages shall be explored and details of civic amenities such as roads, drinking water, power etc proposed to be provided at the company’s expenses shall be submitted.
xix) Location of intake and outfall points (with coordinates) should be given. These locations should be selected based on detailed modeling studies. Details of modeling and the results obtained there from should be furnished. It may be kept in view that the intake and outfall points are away from the mangroves or other eco sensitive areas. A river/marine ecology study (as applicable) should also be done to assess impact on river/marine ecology. River/Marine impact of such activities should be clearly brought out in the EIA report.
xx) Topography of the area should be given clearly indicating whether the site requires any filling. If so, details of filling, quantity of fill material required, its source, transportation etc. should be given.
xxi) One complete season AAQ data (except monsoon) to be given along with the dates of monitoring. The parameters to be covered shall include SPM, RSPM(PM10,PM2.5), SO2, NOx, Hg and Ozone (ground level). The location of the monitoring stations should be so decided so as to take into consideration the pre-dominant downwind direction, population zone and sensitive receptors including reserved forests. There should be at least one monitoring station each in the upwind and in the pre dominant downwind direction at a location where maximum ground level concentration is likely to occur.
xxii) Cumulative impact assessment on ambient air quality due to proposed plant and others (including existing as well as other proposed source of emission) shall be carried out and result submitted in the EIA Report. Mitigative measures as necessary shall be clearly spelt out.
xxiii) Impact of the project on the AAQ of the area. Details of the model used and the input data used for modelling should also be provided. The air quality contours may be plotted on a location map showing the location of project site, habitation nearby, sensitive receptors, if any. The wind roses should also be shown on this map.
xxiv) Fuel analysis shall be provided. Details of auxillary fuel, if any including its quantity, quality, storage etc should also be given.
xxv) Quantity of fuel required, its source and transportation route and mode and a confirmed fuel linkage documents shall be provided.
xxvi) Source of water and its availability. Commitment regarding availability of requisite quantity of water from the competent authority shall be provided along with firm linkage.
xxvii) Detailed plan for carrying out rainwater harvesting and proposed utilisation in the plant shall be provided.
xxviii) Feasibility of zero discharge shall be examined and detailed justification shall be submitted if in case the same is not possible. Proposed discharge (if any), its quantity, quality and point of discharge, users downstream etc. shall be provided.
xxix) Optimization of COC for water conservation. Other water conservation measures proposed in the project should also be given. Quantity of water requirement for the project should be optimized.
xxx) Details of water balance taking into account reuse and re-circulation of effluents.
xxxi) Detailed plan for conducting monitoring of water quality regularly and mechanism for maintenance of records shall be formulated. Details of methodology and identification of monitoring points (between the plant and drainage in the direction of flow of surface / ground water) shall be submitted. It shall be ensured that parameter to be monitored also include heavy metals in surface and ground water.
xxxii) Details regarding infrastructure facilities such as sanitation, fuel, restroom, medical facilities, safety during construction phase etc. to be provided to the labour force during construction as well as to the casual workers including truck drivers during operation phase.
xxxiii) EMP to mitigate the adverse impacts due to the project along with item wise cost of its implementation.
xxxiv) A Disaster Management Plan along with risk assessment study including fire and explosion issues due to storage and use of fuel should be carried out. It should take into account the maximum inventory of storage at site at any point in time. The risk contours should be plotted on the plant layout map clearly showing which of the proposed activities would be affected in case of an accident taking place. Based on the same, proposed safeguard measures should be provided. Measures to guard against fire hazards should also be provided.
xxxv) Detailed plan for raising Green belt of 100 m width and consisting of at least 3 tiers around plant boundary with tree density not less than 2500 trees per ha and survival rate atleast 75% shall be submitted.
xxxvi) Details of litigation pending or otherwise with respect to project in any courts, tribunal etc. shall be provided.
Besides all the above, the following general points will be followed:-
a) All documents to be properly referenced with index, page numbers and continuous page numbering.
b) Where data is presented in the report especially in table, the period in which the data was collected and the source should invariably be indicated.
c) Where the documents provided are in a language other than English, an English translation should be provided.
d) The Questionnaire for environmental appraisal of thermal power projects as devised earlier by the Ministry shall also be filled and submitted.
In addition, information on the following may also be incorporated in the EIA report.
1). Is the project intended to have CDM-intent?
i) If not, then reasons thereof?
ii) If yes, then details under mentioned to be provided:
k) Has PIN (Project Idea Note) {or PCN (Project Concept Note)} been submitted to the NCA? (National CDM Authority) in the MoEF?
l) If not, then by when is that expected?
m) Has PDD (Project Design Document) been prepared?
n) What is the Carbon intensity from your electricity generation projected (i.e. CO2 Tons/MWH or Kg/KWH)
o) Amount of CO2 in Tons/year expected to be reduced from the baseline data available on the CEA’s web-site (www.cea.nic.in)
2. Notwithstanding 1(i) above, data on (d) & (e) above to be worked out and reported.
The Committee informed the project proponent that after preparing the draft EIA (as per the generic structure prescribed in Appendix-III of the EIA Notification, 2006) covering the above mentioned issues, the same shall be submitted to the SPCB for conducting the public hearing as per procedure of EIA notification 2006. The issues which emerge during public hearing shall be further incorporated in the Draft EIA/EMP report. The final EIA/EMP report along with public hearing report and the requisite documents (including written objections, if any) shall be submitted to the Ministry for appraisal by the Expert Appraisal Committee for consideration of awarding environmental clearance under the provisions of Environmental Impact Assessment notification dated September 14, 2006.
2.15 Expansion by addition of 2x500 MW Coal Based Thermal Power Plant of M/s NTPC Ltd. at village Ramagundam, in Ramagundam Mandal, in Karimnagar Distt., in Andhra Pradesh - reg. TOR.
The proposal was placed for determination of terms of reference for undertaking EIA/EMP study as per provisions of EIA notification 2006. The project proponent gave a presentation and provided the following information:
The proposal is for expansion of existing Ramagungam Super Thermal Power Plant by addition of 2x500 MW Coal Based TPP at village Ramagundam, in Ramagundam Mandal, in Karimnagar Distt., in Andhra Pradesh. Existing unit of 3x200 MW (Stage-I); 3x500 MW (Stage-II); and 1x500 MW (Stage-III) are under operation. No additional land is required for the expansion project. Coal requirement will be 5.0 MTPA. Water requirement of 35 cusecs which will be met from existing allocation. Source of water will be from Sri Ram Sagar Dam on Godavari River. There are no wildlife sanctuary, national park, biosphere/tiger reserve, heritage sites etc. with 15 km of the proposed site.
Based on the information provided and presentation made the Committee prescribed the following specific TORs for undertaking detailed EIA study and preparation of EMP.
i) Status of compliance to the conditions stipulated in the environmental clearance accorded for Stage-I to III) shall be submitted along with EIA/EMP report.
ii) Vision document specifying prospective long term plan of the site shall be formulated and submitted.
iii) Executive summary of the project indicating relevant details along with photograph of site shall be provided and issues raised in public hearing along with action plan to address the same shall be provided in tabular form including requisite allocation of funds.
iv) Conformity of the site with the prescribed guidelines in terms of distance of 500 m from HFL of the river, highways, railway line shall be shown on the study area map.
v) The project proponent shall provide confirmed GPS readings of plant boundary.
vi) No water body/nallah (if any) shall be touched. It shall also be ensured that atleast 100 m distance is kept away from the HFL of the nallah/ river (if any) passing in and around the proposed site.
vii) Detailed hydro-geological study of the area shall be conducted from an institute/ organisation of repute to assess impact of on ground and surface water regime. Specific mitigation measures shall be spelt out and action plan for implementation of the same shall be provided.
viii) Detailed source sustainability study of water requirement shall be carried out by an institute of repute. The study shall also specify the source of water for meeting the requirement during lean season and proposed plan of action.
ix) Study on the impact on river/reservoir/marine ecology (as applicable) due to the proposed discharge of treated wastewater into the river/creek shall be carried out and submitted alongwith the EIA Report.
x) Ash pond shall be shifted away as far as possible from any surface water source and its location shall be chosen taking into consideration the elevation and water drainage pattern in the area. The coordinates of the proposed site including location of ash pond shall be submitted along with topo sheet.
xi) Action plan for identification of local employable youth for training in skills relevant to the project for eventual employment in the project itself shall be formulated and details submitted along with EIA/EMP Report.
xii) Layout of the plant indicating break-up of plant, green belt, infrastructure, roads etc. shall be provided.
xiii) Land requirement for the project shall be optimized. Item wise break up of land requirement and its availability to be furnished. It should also include land to be acquired, if any, for coal transportation system as well as for laying of pipeline including ROW. It may clearly be confirmed that the land including ROW is free of all encumbrances. The issues relating to land acquisition and R&R should be clearly discussed in the EIA report.
xiv) Land use based on satellite imagery or authenticated map indicating drainage, cropping pattern, water bodies (rivers, nallahs, ponds etc.), location of nearest villages, creeks, rivers, reservoirs, national parks, wildlife sanctuaries, tiger reserves, biosphere reserves, heritage sites etc in the study area shall be provided. Location of any National Park, Sanctuary, Elephant/Tiger Reserve (existing as well as proposed), migratory routes, if any, within 10 km of the project site shall be specified and marked on the map duly authenticated by the Chief Wildlife Warden.
xv) Study on land-use pattern in the study area shall be carried out, including identification of common property resources available for conversion into productive land and action plan for abatement and compensation for damage to agricultural land/ common property land (if any) in the nearby villages, due to proposed project shall be prepared.
xvi) Detailed socio-economic study shall be carried out for the study area comprising of 10 km from the plant site.
xvii) CSR component shall be prepared based on need based assessment study to be carried out in the study area. Income generating measures which can help in upliftment of poor section of society which is consistent with the traditional skills of the people shall be identified. The programme can include activities such as development of fodder farm, fruit bearing orchards, vocational training etc. In addition, vocational training for individuals shall be imparted so that poor section of society can take up self employment and jobs. Separate budget for community development activities and income generating programmes shall be specified. Financial allocation to be taken up under CSR shall be specified.
xviii) While formulating CSR schemes it shall be ensured that an in-built monitoring mechanism for the schemes identified is in place and mechanism for conducting annual social audit from the nearest government institute of repute in the region shall be prepared. The project proponent shall also provide plan for the status of implementation of the scheme from time to time.
xix) Possibility for adopting nearest three villages shall be explored and details of civic amenities such as roads, drinking water, power etc proposed to be provided at the company’s expenses shall be submitted.
xx) Location of intake and outfall points (with coordinates) should be given. These locations should be selected based on detailed modeling studies. Details of modeling and the results obtained there from should be furnished. It may be kept in view that the intake and outfall points are away from the mangroves or other eco sensitive areas. A river/marine ecology study (as applicable) should also be done to assess impact on river/marine ecology. River/Marine impact of such activities should be clearly brought out in the EIA report.
xxi) Topography of the area should be given clearly indicating whether the site requires any filling. If so, details of filling, quantity of fill material required, its source, transportation etc. should be given.
xxii) One complete season AAQ data (except monsoon) to be given along with the dates of monitoring. The parameters to be covered shall include SPM, RSPM(PM10,PM2.5), SO2, NOx, Hg and Ozone (ground level). The location of the monitoring stations should be so decided so as to take into consideration the pre-dominant downwind direction, population zone and sensitive receptors including reserved forests. There should be at least one monitoring station each in the upwind and in the pre dominant downwind direction at a location where maximum ground level concentration is likely to occur.
xxiii) Cumulative impact assessment on ambient air quality due to proposed plant and others (including existing as well as other proposed source of emission) shall be carried out and result submitted in the EIA Report. Mitigative measures as necessary shall be clearly spelt out.
xxiv) Impact of the project on the AAQ of the area. Details of the model used and the input data used for modelling should also be provided. The air quality contours may be plotted on a location map showing the location of project site, habitation nearby, sensitive receptors, if any. The wind roses should also be shown on this map.
xxv) Fuel analysis shall be provided. Details of auxillary fuel, if any including its quantity, quality, storage etc should also be given.
xxvi) Quantity of fuel required, its source and transportation route and mode and a confirmed fuel linkage documents shall be provided.
xxvii) Source of water and its availability. Commitment regarding availability of requisite quantity of water from the competent authority shall be provided along with firm linkage.
xxviii) Detailed plan for carrying out rainwater harvesting and proposed utilisation in the plant shall be provided.
xxix) Feasibility of zero discharge shall be examined and detailed justification shall be submitted if in case the same is not possible. Proposed discharge (if any), its quantity, quality and point of discharge, users downstream etc. shall be provided.
xxx) Optimization of COC for water conservation. Other water conservation measures proposed in the project should also be given. Quantity of water requirement for the project should be optimized.
xxxi) Details of water balance taking into account reuse and re-circulation of effluents.
xxxii) Detailed plan for conducting monitoring of water quality regularly and mechanism for maintenance of records shall be formulated. Details of methodology and identification of monitoring points (between the plant and drainage in the direction of flow of surface / ground water) shall be submitted. It shall be ensured that parameter to be monitored also include heavy metals in surface and ground water.
xxxiii) Details regarding infrastructure facilities such as sanitation, fuel, restroom, medical facilities, safety during construction phase etc. to be provided to the labour force during construction as well as to the casual workers including truck drivers during operation phase.
xxxiv) EMP to mitigate the adverse impacts due to the project along with item wise cost of its implementation.
xxxv) A Disaster Management Plan along with risk assessment study including fire and explosion issues due to storage and use of fuel should be carried out. It should take into account the maximum inventory of storage at site at any point in time. The risk contours should be plotted on the plant layout map clearly showing which of the proposed activities would be affected in case of an accident taking place. Based on the same, proposed safeguard measures should be provided. Measures to guard against fire hazards should also be provided.
xxxvi) Detailed plan for raising Green belt of 100 m width and consisting of at least 3 tiers around plant boundary with tree density not less than 2500 trees per ha and survival rate atleast 75% shall be submitted.
xxxvii) Details of litigation pending or otherwise with respect to project in any courts, tribunal etc. shall be provided.
Besides all the above, the following general points will be followed:-
a) All documents to be properly referenced with index, page numbers and continuous page numbering.
b) Where data is presented in the report especially in table, the period in which the data was collected and the source should invariably be indicated.
c) Where the documents provided are in a language other than English, an English translation should be provided.
d) The Questionnaire for environmental appraisal of thermal power projects as devised earlier by the Ministry shall also be filled and submitted.
In addition, information on the following may also be incorporated in the EIA report.
1). Is the project intended to have CDM-intent?
i) If not, then reasons thereof?
ii) If yes, then details under mentioned to be provided:
a) Has PIN (Project Idea Note) {or PCN (Project Concept Note)} been submitted to the NCA? (National CDM Authority) in the MoEF?
b) If not, then by when is that expected?
c) Has PDD (Project Design Document) been prepared?
d) What is the Carbon intensity from your electricity generation projected (i.e. CO2 Tons/MWH or Kg/KWH)
e) Amount of CO2 in Tons/year expected to be reduced from the baseline data available on the CEA’s web-site (www.cea.nic.in)
2. Notwithstanding 1(i) above, data on (d) & (e) above to be worked out and reported.
The Committee informed the project proponent that after preparing the draft EIA (as per the generic structure prescribed in Appendix-III of the EIA Notification, 2006) covering the above mentioned issues, the same shall be submitted to the SPCB for conducting the public hearing as per procedure of EIA notification 2006. The issues which emerge during public hearing shall be further incorporated in the Draft EIA/EMP report. The final EIA/EMP report along with public hearing report and the requisite documents (including written objections, if any) shall be submitted to the Ministry for appraisal by the Expert Appraisal Committee for consideration of awarding environmental clearance under the provisions of Environmental Impact Assessment notification dated September 14, 2006.
2.16 Expansion by addition of 1x250 MW (Stage-II) Coal Based Thermal Power Plant of M/s NTPC Ltd. at village Kumguri, in Kokrajhar Taluk & Distt., in Assam - reg. TOR.
The proposal was placed for determination of terms of reference for undertaking EIA/EMP study as per provisions of EIA notification 2006. The project proponent gave a presentation and provided the following information:
The proposal is for expansion of existing Bongaigan Thermal Power Plant by addition of 1x250 MW (Stage-II) Coal Based TPP at village Kumguri, in Kokrajhar Taluk & Distt., in Assam. Existing units of 3x250 MW (Stage-I) are under construction. No additional land is required for the expansion project. Coal requirement will be 1.3 MTPA. Water requirement of 13 cusecs which will be met from Champamati River. Chakrashila Wildlife Sanctuary is located at 7.0 Km of the proposed site.
Based on the information provided and presentation made the Committee prescribed the following specific TORs for undertaking detailed EIA study and preparation of EMP.
i) Status of compliance to the conditions stipulated in the environmental clearance accorded for Stage-I to III) shall be submitted along with EIA/EMP report.
ii) Vision document specifying prospective long term plan of the site shall be formulated and submitted.
iii) Executive summary of the project indicating relevant details along with photograph of site shall be provided and issues raised in public hearing along with action plan to address the same shall be provided in tabular form including requisite allocation of funds.
iv) A primary survey of fauna and flora in the study area along with the authentic list from the concerned Department shall be submitted.
v) A wildlife conservation plan prepared in consultation and vetted by the Office of the Chief Wildlife Warden concerned shall be submitted. The plan shall have an in-built monitoring mechanism and implementation shall be immediately undertaken.
vi) A copy of application for clearance from the Standing Committee of the National Board of Wildlife shall be submitted.
vii) Conformity of the site with the prescribed guidelines in terms of distance of 500 m from HFL of the river, highways, railway line shall be shown on the study area map.
viii) The project proponent shall provide confirmed GPS readings of plant boundary.
ix) No water body/nallah (if any) shall be touched. It shall also be ensured that atleast 100 m distance is kept away from the HFL of the nallah/ river (if any) passing in and around the proposed site.
x) Detailed hydro-geological study of the area shall be conducted from an institute/ organisation of repute to assess impact of on ground and surface water regime. Specific mitigation measures shall be spelt out and action plan for implementation of the same shall be provided.
xi) Detailed source sustainability study of water requirement shall be carried out by an institute of repute. The study shall also specify the source of water for meeting the requirement during lean season and proposed plan of action.
xii) Study on the impact on river/reservoir/marine ecology (as applicable) due to the proposed discharge of treated wastewater into the river/creek shall be carried out and submitted alongwith the EIA Report.
xiii) Ash pond shall be shifted away as far as possible from any surface water source and its location shall be chosen taking into consideration the elevation and water drainage pattern in the area. The coordinates of the proposed site including location of ash pond shall be submitted along with topo sheet.
xiv) Action plan for identification of local employable youth for training in skills relevant to the project for eventual employment in the project itself shall be formulated and details submitted along with EIA/EMP Report.
xv) Layout of the plant indicating break-up of plant, green belt, infrastructure, roads etc. shall be provided.
xvi) Land requirement for the project shall be optimized. Item wise break up of land requirement and its availability to be furnished. It should also include land to be acquired, if any, for coal transportation system as well as for laying of pipeline including ROW. It may clearly be confirmed that the land including ROW is free of all encumbrances. The issues relating to land acquisition and R&R should be clearly discussed in the EIA report.
xvii) Land use based on satellite imagery or authenticated map indicating drainage, cropping pattern, water bodies (rivers, nallahs, ponds etc.), location of nearest villages, creeks, rivers, reservoirs, national parks, wildlife sanctuaries, tiger reserves, biosphere reserves, heritage sites etc in the study area shall be provided. Location of any National Park, Sanctuary, Elephant/Tiger Reserve (existing as well as proposed), migratory routes, if any, within 10 km of the project site shall be specified and marked on the map duly authenticated by the Chief Wildlife Warden.
xviii) Study on land-use pattern in the study area shall be carried out, including identification of common property resources available for conversion into productive land and action plan for abatement and compensation for damage to agricultural land/ common property land (if any) in the nearby villages, due to proposed project shall be prepared.
xix) Detailed socio-economic study shall be carried out for the study area comprising of 10 km from the plant site.
xx) CSR component shall be prepared based on need based assessment study to be carried out in the study area. Income generating measures which can help in upliftment of poor section of society which is consistent with the traditional skills of the people shall be identified. The programme can include activities such as development of fodder farm, fruit bearing orchards, vocational training etc. In addition, vocational training for individuals shall be imparted so that poor section of society can take up self employment and jobs. Separate budget for community development activities and income generating programmes shall be specified. Financial allocation to be taken up under CSR shall be specified.
xxi) While formulating CSR schemes it shall be ensured that an in-built monitoring mechanism for the schemes identified is in place and mechanism for conducting annual social audit from the nearest government institute of repute in the region shall be prepared. The project proponent shall also provide plan for the status of implementation of the scheme from time to time.
xxii) Possibility for adopting nearest three villages shall be explored and details of civic amenities such as roads, drinking water, power etc proposed to be provided at the company’s expenses shall be submitted.
xxiii) Location of intake and outfall points (with coordinates) should be given. These locations should be selected based on detailed modeling studies. Details of modeling and the results obtained there from should be furnished. It may be kept in view that the intake and outfall points are away from the mangroves or other eco sensitive areas. A river/marine ecology study (as applicable) should also be done to assess impact on river/marine ecology. River/Marine impact of such activities should be clearly brought out in the EIA report.
xxiv) Topography of the area should be given clearly indicating whether the site requires any filling. If so, details of filling, quantity of fill material required, its source, transportation etc. should be given.
xxv) One complete season AAQ data (except monsoon) to be given along with the dates of monitoring. The parameters to be covered shall include SPM, RSPM(PM10,PM2.5), SO2, NOx, Hg and Ozone (ground level). The location of the monitoring stations should be so decided so as to take into consideration the pre-dominant downwind direction, population zone and sensitive receptors including reserved forests. There should be at least one monitoring station each in the upwind and in the pre dominant downwind direction at a location where maximum ground level concentration is likely to occur.
xxvi) Cumulative impact assessment on ambient air quality due to proposed plant and others (including existing as well as other proposed source of emission) shall be carried out and result submitted in the EIA Report. Mitigative measures as necessary shall be clearly spelt out.
xxvii) Impact of the project on the AAQ of the area. Details of the model used and the input data used for modelling should also be provided. The air quality contours may be plotted on a location map showing the location of project site, habitation nearby, sensitive receptors, if any. The wind roses should also be shown on this map.
xxviii) Fuel analysis shall be provided. Details of auxillary fuel, if any including its quantity, quality, storage etc should also be given.
xxix) Quantity of fuel required, its source and transportation route and mode and a confirmed fuel linkage documents shall be provided.
xxx) Source of water and its availability. Commitment regarding availability of requisite quantity of water from the competent authority shall be provided along with firm linkage.
xxxi) Detailed plan for carrying out rainwater harvesting and proposed utilisation in the plant shall be provided.
xxxii) Feasibility of zero discharge shall be examined and detailed justification shall be submitted if in case the same is not possible. Proposed discharge (if any), its quantity, quality and point of discharge, users downstream etc. shall be provided.
xxxiii) Optimization of COC for water conservation. Other water conservation measures proposed in the project should also be given. Quantity of water requirement for the project should be optimized.
xxxiv) Details of water balance taking into account reuse and re-circulation of effluents.
xxxv) Detailed plan for conducting monitoring of water quality regularly and mechanism for maintenance of records shall be formulated. Details of methodology and identification of monitoring points (between the plant and drainage in the direction of flow of surface / ground water) shall be submitted. It shall be ensured that parameter to be monitored also include heavy metals in surface and ground water.
xxxvi) Details regarding infrastructure facilities such as sanitation, fuel, restroom, medical facilities, safety during construction phase etc. to be provided to the labour force during construction as well as to the casual workers including truck drivers during operation phase.
xxxvii) EMP to mitigate the adverse impacts due to the project along with item wise cost of its implementation.
xxxviii) A Disaster Management Plan along with risk assessment study including fire and explosion issues due to storage and use of fuel should be carried out. It should take into account the maximum inventory of storage at site at any point in time. The risk contours should be plotted on the plant layout map clearly showing which of the proposed activities would be affected in case of an accident taking place. Based on the same, proposed safeguard measures should be provided. Measures to guard against fire hazards should also be provided.
xxxix) Detailed plan for raising Green belt of 100 m width and consisting of at least 3 tiers around plant boundary with tree density not less than 2500 trees per ha and survival rate atleast 75% shall be submitted.
xl) Details of litigation pending or otherwise with respect to project in any courts, tribunal etc. shall be provided.
Besides all the above, the following general points will be followed:-
a) All documents to be properly referenced with index, page numbers and continuous page numbering.
b) Where data is presented in the report especially in table, the period in which the data was collected and the source should invariably be indicated.
c) Where the documents provided are in a language other than English, an English translation should be provided.
d) The Questionnaire for environmental appraisal of thermal power projects as devised earlier by the Ministry shall also be filled and submitted.
In addition, information on the following may also be incorporated in the EIA report.
1). Is the project intended to have CDM-intent?
i) If not, then reasons thereof?
ii) If yes, then details under mentioned to be provided:
a) Has PIN (Project Idea Note) {or PCN (Project Concept Note)} been submitted to the NCA? (National CDM Authority) in the MoEF?
b) If not, then by when is that expected?
c) Has PDD (Project Design Document) been prepared?
d) What is the Carbon intensity from your electricity generation projected (i.e. CO2 Tons/MWH or Kg/KWH)
e) Amount of CO2 in Tons/year expected to be reduced from the baseline data available on the CEA’s web-site (www.cea.nic.in)
2. Notwithstanding 1(i) above, data on (d) & (e) above to be worked out and reported.
The Committee informed the project proponent that after preparing the draft EIA (as per the generic structure prescribed in Appendix-III of the EIA Notification, 2006) covering the above mentioned issues, the same shall be submitted to the SPCB for conducting the public hearing as per procedure of EIA notification 2006. The issues which emerge during public hearing shall be further incorporated in the Draft EIA/EMP report. The final EIA/EMP report along with public hearing report and the requisite documents (including written objections, if any) shall be submitted to the Ministry for appraisal by the Expert Appraisal Committee for consideration of awarding environmental clearance under the provisions of Environmental Impact Assessment notification dated September 14, 2006.
2.17 2x660 MW Coal Based Thermal Power Plant of M/s Arissan Power Ltd. at villages Domuhan, Jamua, Kakwara, Garbaran and Nandiraidih, in Banka & Katoriya Taluk, in Banka Distt., in Bihar - reg. TOR.
The proposal was placed for determination of terms of reference for undertaking EIA/EMP study as per provisions of EIA notification 2006. The project proponent along with its consultant viz. M/s JM EnviroNet Pvt. Ltd. gave a presentation and provided the following information:
The proposal is for setting up of 2x660 MW Super-Critical Coal Based TPP at villages Domuhan, Jamua, Kakwara, Garbaran and Nandiraidih, in Banka & Katoriya Taluk, in Banka Distt., in Bihar. Land requirement will be restricted to 900 acres, which comprises of single crop and barren land. The co-ordinates of the proposed site will be within Latitude 24046’28” to 240 48’22” N and Longitude 86051’15” to 86053’28” E. Coal requirement will be 7.15 MTPA. Water requirement of 40 MCM, which will be sourced from Orhni Dam, 6.0 Km from the site. There are no wildlife sanctuary, national park, biosphere/tiger reserve, heritage sites etc. with 15 km of the proposed site.
Based on the information provided and presentation made the Committee prescribed the following specific TORs for undertaking detailed EIA study and preparation of EMP.
i) Vision document specifying prospective long term plan of the site shall be formulated and submitted.
ii) Executive summary of the project indicating relevant details along with photograph of site shall be provided and issues raised in public hearing along with action plan to address the same shall be provided in tabular form including requisite allocation of funds.
iii) Conformity of the site with the prescribed guidelines in terms of distance of 500 m from HFL of the river, highways, railway line shall be shown on the study area map.
iv) The project proponent shall provide confirmed GPS readings of plant boundary.
v) No water body/nallah (if any) shall be touched. It shall also be ensured that atleast 100 m distance is kept away from the HFL of the nallah/ river (if any) passing in and around the proposed site.
vi) Detailed hydro-geological study of the area shall be conducted from an institute/ organisation of repute to assess impact of on ground and surface water regime. Specific mitigation measures shall be spelt out and action plan for implementation of the same shall be provided.
vii) Detailed source sustainability study of water requirement shall be carried out by an institute of repute. The study shall also specify the source of water for meeting the requirement during lean season and proposed plan of action.
viii) Study on the impact on river/reservoir/marine ecology (as applicable) due to the proposed discharge of treated wastewater into the river/creek shall be carried out and submitted alongwith the EIA Report.
ix) Ash pond shall be shifted away as far as possible from any surface water source and its location shall be chosen taking into consideration the elevation and water drainage pattern in the area. The coordinates of the proposed site including location of ash pond shall be submitted along with topo sheet.
x) Action plan for identification of local employable youth for training in skills relevant to the project for eventual employment in the project itself shall be formulated and details submitted along with EIA/EMP Report.
xi) Layout of the plant indicating break-up of plant, green belt, infrastructure, roads etc. shall be provided.
xii) Land requirement for the project shall be optimized. Item wise break up of land requirement and its availability to be furnished. It should also include land to be acquired, if any, for coal transportation system as well as for laying of pipeline including ROW. It may clearly be confirmed that the land including ROW is free of all encumbrances. The issues relating to land acquisition and R&R should be clearly discussed in the EIA report.
xiii) Land use based on satellite imagery or authenticated map indicating drainage, cropping pattern, water bodies (rivers, nallahs, ponds etc.), location of nearest villages, creeks, rivers, reservoirs, national parks, wildlife sanctuaries, tiger reserves, biosphere reserves, heritage sites etc in the study area shall be provided. Location of any National Park, Sanctuary, Elephant/Tiger Reserve (existing as well as proposed), migratory routes, if any, within 10 km of the project site shall be specified and marked on the map duly authenticated by the Chief Wildlife Warden.
xiv) Study on land-use pattern in the study area shall be carried out, including identification of common property resources available for conversion into productive land and action plan for abatement and compensation for damage to agricultural land/ common property land (if any) in the nearby villages, due to proposed project shall be prepared.
xv) Detailed socio-economic study shall be carried out for the study area comprising of 10 km from the plant site.
xvi) CSR component shall be prepared based on need based assessment study to be carried out in the study area. Income generating measures which can help in upliftment of poor section of society which is consistent with the traditional skills of the people shall be identified. The programme can include activities such as development of fodder farm, fruit bearing orchards, vocational training etc. In addition, vocational training for individuals shall be imparted so that poor section of society can take up self employment and jobs. Separate budget for community development activities and income generating programmes shall be specified. Financial allocation to be taken up under CSR shall be specified.
xvii) While formulating CSR schemes it shall be ensured that an in-built monitoring mechanism for the schemes identified is in place and mechanism for conducting annual social audit from the nearest government institute of repute in the region shall be prepared. The project proponent shall also provide plan for the status of implementation of the scheme from time to time.
xviii) Possibility for adopting nearest three villages shall be explored and details of civic amenities such as roads, drinking water, power etc proposed to be provided at the company’s expenses shall be submitted.
xix) Location of intake and outfall points (with coordinates) should be given. These locations should be selected based on detailed modeling studies. Details of modeling and the results obtained there from should be furnished. It may be kept in view that the intake and outfall points are away from the mangroves or other eco sensitive areas. A river/marine ecology study (as applicable) should also be done to assess impact on river/marine ecology. River/Marine impact of such activities should be clearly brought out in the EIA report.
xx) Topography of the area should be given clearly indicating whether the site requires any filling. If so, details of filling, quantity of fill material required, its source, transportation etc. should be given.
xxi) One complete season AAQ data (except monsoon) to be given along with the dates of monitoring. The parameters to be covered shall include SPM, RSPM(PM10,PM2.5), SO2, NOx, Hg and Ozone (ground level). The location of the monitoring stations should be so decided so as to take into consideration the pre-dominant downwind direction, population zone and sensitive receptors including reserved forests. There should be at least one monitoring station each in the upwind and in the pre dominant downwind direction at a location where maximum ground level concentration is likely to occur.
xxii) Cumulative impact assessment on ambient air quality due to proposed plant and others (including existing as well as other proposed source of emission) shall be carried out and result submitted in the EIA Report. Mitigative measures as necessary shall be clearly spelt out.
xxiii) Impact of the project on the AAQ of the area. Details of the model used and the input data used for modelling should also be provided. The air quality contours may be plotted on a location map showing the location of project site, habitation nearby, sensitive receptors, if any. The wind roses should also be shown on this map.
xxiv) Fuel analysis shall be provided. Details of auxillary fuel, if any including its quantity, quality, storage etc should also be given.
xxv) Quantity of fuel required, its source and transportation route and mode and a confirmed fuel linkage documents shall be provided.
xxvi) Source of water and its availability. Commitment regarding availability of requisite quantity of water from the competent authority shall be provided along with firm linkage.
xxvii) Detailed plan for carrying out rainwater harvesting and proposed utilisation in the plant shall be provided.
xxviii) Feasibility of zero discharge shall be examined and detailed justification shall be submitted if in case the same is not possible. Proposed discharge (if any), its quantity, quality and point of discharge, users downstream etc. shall be provided.
xxix) Optimization of COC for water conservation. Other water conservation measures proposed in the project should also be given. Quantity of water requirement for the project should be optimized.
xxx) Details of water balance taking into account reuse and re-circulation of effluents.
xxxi) Detailed plan for conducting monitoring of water quality regularly and mechanism for maintenance of records shall be formulated. Details of methodology and identification of monitoring points (between the plant and drainage in the direction of flow of surface / ground water) shall be submitted. It shall be ensured that parameter to be monitored also include heavy metals in surface and ground water.
xxxii) Details regarding infrastructure facilities such as sanitation, fuel, restroom, medical facilities, safety during construction phase etc. to be provided to the labour force during construction as well as to the casual workers including truck drivers during operation phase.
xxxiii) EMP to mitigate the adverse impacts due to the project along with item wise cost of its implementation.
xxxiv) A Disaster Management Plan along with risk assessment study including fire and explosion issues due to storage and use of fuel should be carried out. It should take into account the maximum inventory of storage at site at any point in time. The risk contours should be plotted on the plant layout map clearly showing which of the proposed activities would be affected in case of an accident taking place. Based on the same, proposed safeguard measures should be provided. Measures to guard against fire hazards should also be provided.
xxxv) Detailed plan for raising Green belt of 100 m width and consisting of at least 3 tiers around plant boundary with tree density not less than 2500 trees per ha and survival rate atleast 75% shall be submitted.
xxxvi) Details of litigation pending or otherwise with respect to project in any courts, tribunal etc. shall be provided.
Besides all the above, the following general points will be followed:-
e) All documents to be properly referenced with index, page numbers and continuous page numbering.
f) Where data is presented in the report especially in table, the period in which the data was collected and the source should invariably be indicated.
g) Where the documents provided are in a language other than English, an English translation should be provided.
h) The Questionnaire for environmental appraisal of thermal power projects as devised earlier by the Ministry shall also be filled and submitted.
In addition, information on the following may also be incorporated in the EIA report.
1). Is the project intended to have CDM-intent?
iii) If not, then reasons thereof?
iv) If yes, then details under mentioned to be provided:
f) Has PIN (Project Idea Note) {or PCN (Project Concept Note)} been submitted to the NCA? (National CDM Authority) in the MoEF?
g) If not, then by when is that expected?
h) Has PDD (Project Design Document) been prepared?
i) What is the Carbon intensity from your electricity generation projected (i.e. CO2 Tons/MWH or Kg/KWH)
j) Amount of CO2 in Tons/year expected to be reduced from the baseline data available on the CEA’s web-site (www.cea.nic.in)
2. Notwithstanding 1(i) above, data on (d) & (e) above to be worked out and reported.
The Committee informed the project proponent that after preparing the draft EIA (as per the generic structure prescribed in Appendix-III of the EIA Notification, 2006) covering the above mentioned issues, the same shall be submitted to the SPCB for conducting the public hearing as per procedure of EIA notification 2006. The issues which emerge during public hearing shall be further incorporated in the Draft EIA/EMP report. The final EIA/EMP report along with public hearing report and the requisite documents (including written objections, if any) shall be submitted to the Ministry for appraisal by the Expert Appraisal Committee for consideration of awarding environmental clearance under the provisions of Environmental Impact Assessment notification dated September 14, 2006.
2.18 2x80 MW Captive Coal Rejects Based Thermal Power Plant of M/s Tata Steel Ltd. at village Loiyo, in Mandu Taluk, in Ramgarh Distt., in Jharkhand - reg. TOR.
The proposal was placed for determination of terms of reference for undertaking EIA/EMP study as per provisions of EIA notification 2006. The project proponent along with its consultant viz. M/s Tata Consulting Engineers Ltd. gave a presentation and provided the following information:
The proposal is for setting up of 2x80 MW Captive Coal Rejects from Beneficiation Plant Based TPP at village Loiyo, in Mandu Taluk, in Ramgarh Distt., in Jharkhand. Land requirement will be 30 acres, which comprises of 10.5 acres of forests land (minor vegetation) and 19.5 acres of Tand land (non-agricultural elevated land). The co-ordinates of the proposed site will be within Latitude 23047’57” to 230 48’07” N and Longitude 85038’32” to 85038’40” E. Coal rejects from Beneficiation Plant requirement will be 1.45 MTPA. Water requirement of 16.8 MLD, which will be sourced from Tenughat Reservoir, upstream at 20.0 Km from the site. There are no wildlife sanctuary, national park, biosphere/tiger reserve, heritage sites etc. with 15 km of the proposed site.
The Committee noted that the area proposed may be part of coal bearing area and therefore desired that prior clearance from the Ministry of Coal for setting up the Captive Power Plant may be obtained.
Based on the information provided and presentation made the Committee prescribed the following specific TORs for undertaking detailed EIA study and preparation of EMP.
i) Prior clearance from the Competent Authority with respect to the area where Captive TPP is proposed to be set up shall be obtained and a copy of the same shall be submitted.
ii) Vision document specifying prospective long term plan of the site shall be formulated and submitted.
iii) Executive summary of the project indicating relevant details along with photograph of site shall be provided and issues raised in public hearing along with action plan to address the same shall be provided in tabular form including requisite allocation of funds.
iv) Conformity of the site with the prescribed guidelines in terms of distance of 500 m from HFL of the river, highways, railway line shall be shown on the study area map.
v) The project proponent shall provide confirmed GPS readings of plant boundary.
vi) No water body/nallah (if any) shall be touched. It shall also be ensured that atleast 100 m distance is kept away from the HFL of the nallah/ river (if any) passing in and around the proposed site.
vii) Detailed hydro-geological study of the area shall be conducted from an institute/ organisation of repute to assess impact of on ground and surface water regime. Specific mitigation measures shall be spelt out and action plan for implementation of the same shall be provided.
viii) Detailed source sustainability study of water requirement shall be carried out by an institute of repute. The study shall also specify the source of water for meeting the requirement during lean season and proposed plan of action.
ix) Study on the impact on river/reservoir/marine ecology (as applicable) due to the proposed discharge of treated wastewater into the river/creek shall be carried out and submitted alongwith the EIA Report.
x) Ash pond shall be shifted away as far as possible from any surface water source and its location shall be chosen taking into consideration the elevation and water drainage pattern in the area. The coordinates of the proposed site including location of ash pond shall be submitted along with topo sheet.
xi) Action plan for identification of local employable youth for training in skills relevant to the project for eventual employment in the project itself shall be formulated and details submitted along with EIA/EMP Report.
xii) Layout of the plant indicating break-up of plant, green belt, infrastructure, roads etc. shall be provided.
xiii) Land requirement for the project shall be optimized. Item wise break up of land requirement and its availability to be furnished. It should also include land to be acquired, if any, for coal transportation system as well as for laying of pipeline including ROW. It may clearly be confirmed that the land including ROW is free of all encumbrances. The issues relating to land acquisition and R&R should be clearly discussed in the EIA report.
xiv) Land use based on satellite imagery or authenticated map indicating drainage, cropping pattern, water bodies (rivers, nallahs, ponds etc.), location of nearest villages, creeks, rivers, reservoirs, national parks, wildlife sanctuaries, tiger reserves, biosphere reserves, heritage sites etc in the study area shall be provided. Location of any National Park, Sanctuary, Elephant/Tiger Reserve (existing as well as proposed), migratory routes, if any, within 10 km of the project site shall be specified and marked on the map duly authenticated by the Chief Wildlife Warden.
xv) Study on land-use pattern in the study area shall be carried out, including identification of common property resources available for conversion into productive land and action plan for abatement and compensation for damage to agricultural land/ common property land (if any) in the nearby villages, due to proposed project shall be prepared.
xvi) Detailed socio-economic study shall be carried out for the study area comprising of 10 km from the plant site.
xvii) CSR component shall be prepared based on need based assessment study to be carried out in the study area. Income generating measures which can help in upliftment of poor section of society which is consistent with the traditional skills of the people shall be identified. The programme can include activities such as development of fodder farm, fruit bearing orchards, vocational training etc. In addition, vocational training for individuals shall be imparted so that poor section of society can take up self employment and jobs. Separate budget for community development activities and income generating programmes shall be specified. Financial allocation to be taken up under CSR shall be specified.
xviii) While formulating CSR schemes it shall be ensured that an in-built monitoring mechanism for the schemes identified is in place and mechanism for conducting annual social audit from the nearest government institute of repute in the region shall be prepared. The project proponent shall also provide plan for the status of implementation of the scheme from time to time.
xix) Possibility for adopting nearest three villages shall be explored and details of civic amenities such as roads, drinking water, power etc proposed to be provided at the company’s expenses shall be submitted.
xx) Location of intake and outfall points (with coordinates) should be given. These locations should be selected based on detailed modeling studies. Details of modeling and the results obtained there from should be furnished. It may be kept in view that the intake and outfall points are away from the mangroves or other eco sensitive areas. A river/marine ecology study (as applicable) should also be done to assess impact on river/marine ecology. River/Marine impact of such activities should be clearly brought out in the EIA report.
xxi) Topography of the area should be given clearly indicating whether the site requires any filling. If so, details of filling, quantity of fill material required, its source, transportation etc. should be given.
xxii) One complete season AAQ data (except monsoon) to be given along with the dates of monitoring. The parameters to be covered shall include SPM, RSPM(PM10,PM2.5), SO2, NOx, Hg and Ozone (ground level). The location of the monitoring stations should be so decided so as to take into consideration the pre-dominant downwind direction, population zone and sensitive receptors including reserved forests. There should be at least one monitoring station each in the upwind and in the pre dominant downwind direction at a location where maximum ground level concentration is likely to occur.
xxiii) Cumulative impact assessment on ambient air quality due to proposed plant and others (including existing as well as other proposed source of emission) shall be carried out and result submitted in the EIA Report. Mitigative measures as necessary shall be clearly spelt out.
xxiv) Impact of the project on the AAQ of the area. Details of the model used and the input data used for modelling should also be provided. The air quality contours may be plotted on a location map showing the location of project site, habitation nearby, sensitive receptors, if any. The wind roses should also be shown on this map.
xxv) Fuel analysis shall be provided. Details of auxillary fuel, if any including its quantity, quality, storage etc should also be given.
xxvi) Quantity of fuel required, its source and transportation route and mode and a confirmed fuel linkage documents shall be provided.
xxvii) Source of water and its availability. Commitment regarding availability of requisite quantity of water from the competent authority shall be provided along with firm linkage.
xxviii) Detailed plan for carrying out rainwater harvesting and proposed utilisation in the plant shall be provided.
xxix) Feasibility of zero discharge shall be examined and detailed justification shall be submitted if in case the same is not possible. Proposed discharge (if any), its quantity, quality and point of discharge, users downstream etc. shall be provided.
xxx) Optimization of COC for water conservation. Other water conservation measures proposed in the project should also be given. Quantity of water requirement for the project should be optimized.
xxxi) Details of water balance taking into account reuse and re-circulation of effluents.
xxxii) Detailed plan for conducting monitoring of water quality regularly and mechanism for maintenance of records shall be formulated. Details of methodology and identification of monitoring points (between the plant and drainage in the direction of flow of surface / ground water) shall be submitted. It shall be ensured that parameter to be monitored also include heavy metals in surface and ground water.
xxxiii) Details regarding infrastructure facilities such as sanitation, fuel, restroom, medical facilities, safety during construction phase etc. to be provided to the labour force during construction as well as to the casual workers including truck drivers during operation phase.
xxxiv) EMP to mitigate the adverse impacts due to the project along with item wise cost of its implementation.
xxxv) A Disaster Management Plan along with risk assessment study including fire and explosion issues due to storage and use of fuel should be carried out. It should take into account the maximum inventory of storage at site at any point in time. The risk contours should be plotted on the plant layout map clearly showing which of the proposed activities would be affected in case of an accident taking place. Based on the same, proposed safeguard measures should be provided. Measures to guard against fire hazards should also be provided.
xxxvi) Detailed plan for raising Green belt of 100 m width and consisting of at least 3 tiers around plant boundary with tree density not less than 2500 trees per ha and survival rate atleast 75% shall be submitted.
xxxvii) Details of litigation pending or otherwise with respect to project in any courts, tribunal etc. shall be provided.
Besides all the above, the following general points will be followed:-
a) All documents to be properly referenced with index, page numbers and continuous page numbering.
b) Where data is presented in the report especially in table, the period in which the data was collected and the source should invariably be indicated.
c) Where the documents provided are in a language other than English, an English translation should be provided.
d) The Questionnaire for environmental appraisal of thermal power projects as devised earlier by the Ministry shall also be filled and submitted.
In addition, information on the following may also be incorporated in the EIA report.
1). Is the project intended to have CDM-intent?
i) If not, then reasons thereof?
ii) If yes, then details under mentioned to be provided:
a) Has PIN (Project Idea Note) {or PCN (Project Concept Note)} been submitted to the NCA? (National CDM Authority) in the MoEF?
b) If not, then by when is that expected?
c) Has PDD (Project Design Document) been prepared?
d) What is the Carbon intensity from your electricity generation projected (i.e. CO2 Tons/MWH or Kg/KWH)
e) Amount of CO2 in Tons/year expected to be reduced from the baseline data available on the CEA’s web-site (www.cea.nic.in)
2. Notwithstanding 1(i) above, data on (d) & (e) above to be worked out and reported.
The Committee informed the project proponent that after preparing the draft EIA (as per the generic structure prescribed in Appendix-III of the EIA Notification, 2006) covering the above mentioned issues, the same shall be submitted to the SPCB for conducting the public hearing as per procedure of EIA notification 2006. The issues which emerge during public hearing shall be further incorporated in the Draft EIA/EMP report. The final EIA/EMP report along with public hearing report and the requisite documents (including written objections, if any) shall be submitted to the Ministry for appraisal by the Expert Appraisal Committee for consideration of awarding environmental clearance under the provisions of Environmental Impact Assessment notification dated September 14, 2006.
2.19 2000 MW Coal Based Thermal Power Plant of M/s Essar Power Jharkhand Ltd. at village Chandwa, in Taluk Chandwa, in Latehar Distt, in Jharkhand - reg. Environmental Clearance.
The proposal was earlier placed for consideration for environmental clearance in the 42nd Meeting of the Committee held during March 12, 2009, wherein environmental clearance was recommended for 1ix600 MW as confirmed water allocation for then available only for meeting the requirement of 1x600 MW. The Committee in the said meeting decided that the following information will be also provided before reconsideration of the remaining units.
i) Confirmation that land projected in the public hearing is the same project land;
ii) Green belt area should be indicated separately from water bodies and also area under staff colony and R&R site;
iii) Fly ash utilization plan for the ultimate capacity;
iv) AAQ value for NOx should be rechecked;
v) A dedicated R&R plan with compensation details etc. and CSR activities with budgetry allocation; and
vi) Coal analysis report.
On submission of the above the matter was again placed for re-consideration. The project proponent and its consultant viz. M/s GIS Enabled Environment & Neo-Graphic Centre, New Delhi gave a presentation and provided the following information:
Environmental clearance for 1x600 MW was accorded on 08.05.2009. The proposal is for 2x600 (Phase-I) and 1x800 MW (Phase-II). However, it is proposed to change the unit configuration of Phase –II i.e 1x800 MW by 1x600 MW for purpose of convenience in synchronization and other technical issues. Land requirement for both the phases will be 1700 acres (including ash pond). Out of total land required, 358 acres is agricultural land; 60 acres are habitations; 282 acres is rocky waste land; 800 acres is land with scrub; 47 acres is baren land; and 153 acres is water bodies. The co-ordinates of the plant site are within Latitude 23º42’11” N to 23º43’49” N and Longitude 84º46’12” E to 84º47’57” E. Coal required will be 9.0 MTPA, which will be obtained from Chakla Coal Block and Ashok Karkata Coal Block in North Karanpura Coalfields. Environmental clearance for Chakla Coal Block has been recommended. Ash content in coal will be maximum 34% and Sulphur content 0.5 % (maximum). Medium concentration Slurry Disposal system will be adopted. Quantity of Fly ash and bottom ash to be generated will be 2.9 MTPA and 0.7 MTPA respectively. Water requirement will be 72 MCMPA which will be obtained from Damodar and Amanat Rivers from a point 20 Kms and 30 Kms respectively from the site. Water allocation has been obtained from the state govt. There are no national parks, wildlife sanctuaries, biosphere / tiger reserves, heritage sites etc. within 10 km of the plant boundary. Public hearing was conducted on 21.04.2008. Cost of the project will be Rs. 9400.0 Crores.
The Committee informed the project proponent that in case they intend to change the unit configuration for the Phase-II from 1x800 MW to 1x600 MW, they shall submit revised Form-I and EIA/EMP report giving details of impact analysis under the changed configuration.
The Committee also noted that Chakla Coal Block can cater to only 1x600 MW (2nd Unit of Phase-I) and its mining capacity is 4.5 MTPA. The Committee therefore decided that recommendation for environmental clearance can be made only for 1x600 MW (2nd Unit of Phase-I). The project proponent also declared that no litigation is pending in any court pertaining to the project.
Based on the information and clarifications provided, the Committee recommended the project for environmental clearance subject to stipulation of the following specific conditions:
i) Environmental clearance shall be only for 1x600 MW. However as and when environmental clearance for Ashok Karkata Coal Block is available and after fulfillment of necessary technical and procedural requirements the Ministry may extend the environmental clearance for the remaining unit.
ii) Vision document specifying prospective plan for the site shall be formulated and submitted to the Ministry within six months.
iii) The project proponent shall provide space for FGD system for future installation as and when required.
iv) The project proponent shall ensure that no fugitive fly ash generation takes place at any point of time.
v) 100 % fly ash disposal shall be ensured from 4th year of operation of the plant. Detailed status for 100% utilization after the 4th year of operation of the plant shall be submitted every six months to the Ministry.
vi) Height of stack shall be 275 m each with flue gas velocity not less than 22 m/s.
vii) It shall be ensured that the area drainage is not disturbed due to the proposed power plant.
viii) Hydro geological study of the area shall be reviewed annually and report submitted to the Ministry.
ix) Monitoring of surface water quantity and quality shall also be regularly conducted and records maintained. The monitored data shall be submitted to the Ministry regularly. Further, monitoring points shall be located between the plant and drainage in the direction of flow of ground water and records maintained. Monitoring for heavy metals in ground water shall be undertaken.
x) Green Belt consisting of 3 tiers of plantations of native species around plant and at least 100 m width shall be raised. Wherever 100 m width is not feasible a 50 m width shall be raised and adequate justification shall be submitted to the Ministry.
xi) Waste water generated from the plant shall be treated before discharge to comply limits prescribed by the SPCB.
xii) A well designed rain water harvesting system shall be put in place within six months, which shall comprise of rain water collection from the built up and open area in the plant premises. Action plan and road map for implementation shall be submitted to the Ministry within six months.
xiii) Well designed acoustic enclosures for the DG sets and noise emitting equipments to achieve the desirable insertion loss viz. 25 dB (A) should be provided.
xiv) Additional soil for leveling of the sites should be generated within the site in a way that natural drainage system of the area is protected and improved.
xv) R&R action plan (as applicable) with time bound implementation schedule and compensation proposed to be paid with details of families etc. shall be submitted within six months.
xvi) An amount of Rs. 37.60 Crores as one time investment should be earmarked for activities to be taken up under CSR by the above proponent. Recurring expenditure for CSR shall not be less than Rs. 7.50 Crores per annum till the operation of the plant. Detailed action plan with break-up of activities shall be submitted within six months to the Ministry.
xvii) While identifying CSR activities it shall be ensured that need based assessment for the nearby villages within study area shall be conducted to study economic measures with action plan which can help in upliftment of poorer sections of society especially SC/STs. Income generating projects consistent with the traditional skills of the people shall be undertaken. Development of fodder farm, fruit bearing orchards, vocational training etc. can form a part of such programme. Company shall provide separate budget for community development activities and income generating programmes. Vocational training programme for possible self employment shall be imparted to pre identified villagers free of cost.
xviii) The project proponent shall also adequately contribute in the development of other neighbouring villages. Special package with implementation schedule for providing potable drinking water supply in the nearby villages and schools shall be undertaken in a time bound manner.
xix) It shall be ensured that an in-built monitoring mechanism for the CSR schemes identified is in place and annual social audit shall be got done from a government institute of repute in the region. The project proponent shall also submit the status of implementation of the scheme from time to time.
xx) An Environmental Cell shall be created at the project site itself and shall be headed by an officer of appropriate seniority and qualification. It shall be ensured that the head of the Cell shall directly report to the head of the organization.
2.20 2x35 MW Captive Imported Coal Based Thermal Power Plant of M/s Tulsyan NEC Ltd. at village Sinthoornatham, in Gummidipoondi Taluk, in Thiruvallur Distt., in Tamil Nadu -reg. Environmental Clearance.
The proposal is for consideration for environmental clearance. The proposal is an inter state case and hence is being considered at the Centre. TOR was prescribed by the SEIAA in December, 2009. The project proponent and its consultant viz. M/s Environment System Consultants & Ambiente Lab Solutions Pvt., Chennai gave a presentation and provided the following information:
The proposal is for setting up 2x35 MW Captive Imported Coal Based Thermal Power Plant at village Sinthoornatham, in Gummidipoondi Taluk, in Thiruvallur Distt., in Tamil Nadu. The plant will be captive to Steel Plant located at about 4.0 Km from the site. Land requirement will be 40 acres which is a single crop agriculture land and under possession. The co-ordinates of the plant site are within Latitude 13º24’54” N to 13º25’20” N and Longitude 80º3’21” E to 80º3’47” E. Imported Coal required will be 0.34 MTPA, which will be obtained from Indonesia. Ash content in coal will be 9% and Sulphur content 01.2 % (maximum). Quantity of Fly ash and bottom ash to be generated will be 0.0248 MTPA and 0.00584 MTPA respectively. Air cooled condenser will be used for condensate cooling. Water requirement will be 92 KLD which will be met from harvested rain water. There are no national parks, wildlife sanctuaries, biosphere / tiger reserves, heritage sites etc. within 10 km of the plant boundary. Public hearing was conducted on 09.06.2010. Cost of the project will be Rs. 380.0 Crores.
During the course of the deliberation, the Committee noted that wind rose diagram based on which the ambient air quality impact assessment /prediction has been calculated was found to be grossly erroneous. The same was also admitted by the consultant. The Committee also noted that the data presented in the documents with respect to air quality and the presentation are at variance.
The Committee also noted that the proposal for using harvested rain water only need detail examination and has apprehension for its viability incase of very less rainfall in a particular year. The Committee informed the project proponent that withdrawal of ground water for power plant shall not be permitted. The Committee also noted that no concrete fly ash utitlisation agreements / MoU with prospective users have been submitted.
The Committee viewed the lapses very seriously and decided that the project proponent and its consultant seem to be making a perfunctory approach while seeking environmental clearance rendering the whole process of appraisal which are based on information submitted by the project proponent redundant in case of an oversight of any major issue of environmental concern. The Committee therefore decided that the Ministry may like to seek clarification from the project proponent and also the consultant i.e M/s Environment System Consultants & Ambiente Lab Solutions Pvt., Chennai, on the matter.
The Committee also decided that the project proponent shall first submit the following before their case is re-considered for environmental clearance:
i) Point wise compliance of TORs prescribed shall be submitted;
ii) Ambient air quality data shall be re-assessed and cumulative impact of ambient air quality predictions accounting all possible sources of emissions shall be re-done using appropriate wind rose diagram;
iii) Action plan with time bound implementation schedule for development of three tier green belt all around Ash Dyke (avoiding non feasible areas with justification) shall be submitted;
iv) Source of water sustainability study in the event of failure of rain water harvesting system during dry spell or less rainfall;
v) CSR action plan with time bound implementation schedule and budgetry allocation activity wise shall be submitted;
vi) Action plan for time bound implementation on issues raised in public hearing and others shall be prepared and submitted along with firm commitment;
vii) Proposal for fly ash utilization alongwith copy of agreements/MoUs firmed up with prospective fly ash users shall be submitted.
The Committee also decided that the above information / documents shall be submitted along with an undertaking in a notorised stamp paper of appropriate amount and duly signed by the Head of the Organisation or an officer of appropriate superiority (authorized to sign).
Accordingly the proposal was deferred for reconsideration at a later stage. The Committee also decided that since the above may take some time the proposal may be de-listed from the pending list for the time being.
2.21 4x60 MW Captive Coal Based Thermal Power Plant and 1.0 MTPA Cement Grinding Unit and 1.0 MTPA Coal Washery of M/s Jaiprakash Associates Ltd. at village Churk, in Robertganj Taluk, in Sonebhadra Distt., in Uttar Pradesh - reg. Environmental Clearance.
The proposal is for consideration for environmental clearance. The proposal is ‘B’ category but being located near wildlife sanctuary the project proponent has submitted at the Centre as per provisions of EIA Notification, 2006. The project proponent and its consultant viz. M/s Vimta Labs Ltd., Hyderabad gave a presentation and provided the following information:
The proposal is for setting up of 4x60 MW Captive Coal Based Thermal Power Plant and 1.0 MTPA Cement Grinding Unit and 1.0 MTPA Coal Washery at village Churk, in Robertganj Taluk, in Sonebhadra Distt., in Uttar Pradesh. The power plant will be captive to Cement Grinding Unit and Coal Washery. Land requirement will be 150 acres which is available within the old Cement Plant, which is not in operation since 1991. The co-ordinates of the plant site are within Latitude 24º38’08” to 24º38’29” N and Longitude 83º05’541” E to 83º06’18” E. Washery rejects will be used as fuel for the power plant. Requirement of washery reject will be 2.0 MTPA. Ash content in coal will be 8-60% and Sulphur content 0.1-7.5 % (maximum). Quantity of Fly ash and bottom ash to be generated will be 2880 TPD and 720 TPD respectively. Air cooled condenser will be used for condensate cooling. Water requirement will be 5513 cum/day which will be met from harDhanrol Dam on Ghaggar River. Allocation of 4.5 cusec of water has been obtained. Kaimur Wildlife Sanctuary is located at a distance of 0.5 Km from the site. Public hearing was conducted on 02.06.2010. Cost of the project will be Rs. 1178.0 Crores.
The Committee noted from records available that the project proponent have not declared the existence of the wildlife sanctuary while submitting the proposal for seeking recommendation of terms of reference. The Committee noted that, had the then Committee known of the facts regarding wildlife sanctuary, the recommendation for TOR would not have been made.
The Committee viewed the suppression of information very seriously and decided the proposal may be referred to the Wildlife Division in the Ministry for its views and only after submission of the clearance from the Wildlife Division / Standing Committee of the National Board of Wildlife (as the case may be) the project proponent may re-submit for re-consideration after compliance of the following:
i) Point wise compliance of TORs prescribed shall be submitted;
ii) Revised Form-I shall be submitted along with a map duly vetted by the concerned Office of the Chief Wildlife Warden, indication location (nearest boundary) of the wildlife sanctuary from
iii) A detailed primary survey of fauna and flora in the study area shall be carried out and submitted along with the authenticated list from the Competent Authority;
iv) A wildlife conservation plan prepared in consultation with the concerned Office of the Chief Wildlife Warden and duly vetted by the said office. The plan shall consists of an in-built monitoring mechanism;
v) Separate year marked financial budget for implementation shall be indicated in the wildlife plan and implementation shall begin before the proposal is submitted for re-consideration.
vi) Ambient air quality data shall be re-assessed and cumulative impact of ambient air quality predictions accounting all possible sources of emissions shall be re-done using appropriate wind rose diagram;
vii) CSR action plan with time bound implementation schedule and budgetry allocation activity wise shall be submitted;
viii) Action plan for time bound implementation on issues raised in public hearing and others shall be prepared and submitted along with firm commitment;
The Committee felt that the project proponent cannot feign ignorance of the location of the wildlife sanctuary as clarified by them and viewed lapse very seriously. The Committee further expressed that the project proponent seem to be making a perfunctory approach in dealing with the process of seeking environmental clearance, rendering the whole process of appraisal based on information submitted by them redundant in case of an oversight. The Committee therefore decided that the Ministry may like to seek written clarification from the project proponent and the consultant i.e M/s Vimta Labs Ltd., on the matter.
The Committee also decided that the above information / documents shall be submitted along with an undertaking in a notorised stamp paper of appropriate amount and duly signed by the Head of the Organisation or an officer of appropriate superiority (authorized to sign).
Accordingly the proposal was deferred for reconsideration at a later stage. The Committee also decided that since the above may take some time the proposal may be de-listed from the pending list for the time being.
2.22 2x800 MW Coal Based Thermal Power Plant of M/s Gujarat State Electricity Corporation Ltd., at village Sinor, in Dabhoi Taluk, in Vadodara Distt., in Gujarat - Reg. TOR.
The proposal was earlier placed in the 62nd Meeting of the Committee held during January 11-12, 2010 for determination of terms of reference for undertaking EIA/EMP study as per provisions of EIA notification 2006. In the said meeting the Committee noted that the identified site as well as other alternative sites suggested by the project proponent is unsuitable for location of a thermal power plant. The project proponent was therefore advised to come with alternative sites which shall be away from human habitation /town and also not disturb any natural drainage system in the area.
After submission of further information and clarification the proposal was again placed for re-consideration. The project proponent gave a presentation along with ist consultant Viz. M/s PCRI BHEL, Haridwar and provided the following information:
The proposal is for setting of 2x800 Super-Critical MW Coal Based TPP at village Dhamapur, in Sinor Taluk, in Vadodara Distt., in Gujarat. Land requirement will be 725 acres. The co-ordinates of the proposed site will be at Latitude 210 55’ 55” to 210 57’02” N and Longitude 730 18’ 43” to 730 19’ 42” E. Coal requirement will be 7.17 MTPA at 85% PLF, which will be sourced from Machakata Coal Block. Area requirement for Ash pond/Dyke will be 70 hectares. Water requirement will be 51 cusecs, which will be obtained from Narmada River through a Jack well over a distance of 4 km from the project site. There are no National parks, Wildlife sanctuaries, Heritage sites, Tiger/Biosphere reserves etc. within 10 km of the site. Cost of the project will be Rs. 7870.0 Crores.
The Committee noted that the site identified is the same site as was earlier proposed when the matter was discussed in the 62nd Meeting. The project proponent has however changed the location of ash pond. The Committee also noted that even though Sinor town has a very less population of less than 5000 as reported, the expansion of the town is bound to happen during the course of time and health aspects cannot be ignored irrespective of the present population. The Committee therefore decided that the site can be agreed subject o the condition that FGD shall be installed before commissioning the plant and 100% fly ash utilization shall be ensured from day one of operation of the plant and Ash Pond shall be for emergency purpose only.
Based on the information provided and presentation made the Committee prescribed the following specific TORs for undertaking detailed EIA study and preparation of EMP.
i) Detail plan for installation of FGD before commission of the plant shall be prepared and submitted.
ii) Vision document specifying prospective long term plan of the site shall be formulated and submitted.
iii) Executive summary of the project indicating relevant details along with photograph of site shall be provided and issues raised in public hearing along with action plan to address the same shall be provided in tabular form including requisite allocation of funds.
iv) Conformity of the site with the prescribed guidelines in terms of distance of 500 m from HFL of the river, highways, railway line shall be shown on the study area map.
v) The project proponent shall provide confirmed GPS readings of plant boundary.
vi) No water body/nallah (if any) shall be touched. It shall also be ensured that atleast 100 m distance is kept away from the HFL of the nallah/ river (if any) passing in and around the proposed site.
vii) Detailed hydro-geological study of the area shall be conducted from an institute/ organisation of repute to assess impact of on ground and surface water regime. Specific mitigation measures shall be spelt out and action plan for implementation of the same shall be provided.
viii) Detailed source sustainability study of water requirement shall be carried out by an institute of repute. The study shall also specify the source of water for meeting the requirement during lean season and proposed plan of action.
ix) Study on the impact on river/reservoir/marine ecology (as applicable) due to the proposed discharge of treated wastewater into the river/creek shall be carried out and submitted alongwith the EIA Report.
x) Detail plan for utilization of 100% Fly Ash from day one of the commissioning of the plant shall be submitted. The plan shall have an in-built monitoring and third party audit mechanism.
xi) Ash pond shall be shifted away as far as possible from any surface water source and its location shall be chosen taking into consideration the elevation and water drainage pattern in the area. The coordinates of the proposed site including location of ash pond shall be submitted along with topo sheet.
xii) Action plan for identification of local employable youth for training in skills relevant to the project for eventual employment in the project itself shall be formulated and details submitted along with EIA/EMP Report.
xiii) Layout of the plant indicating break-up of plant, green belt, infrastructure, roads etc. shall be provided.
xiv) Land requirement for the project shall be optimized. Item wise break up of land requirement and its availability to be furnished. It should also include land to be acquired, if any, for coal transportation system as well as for laying of pipeline including ROW. It may clearly be confirmed that the land including ROW is free of all encumbrances. The issues relating to land acquisition and R&R should be clearly discussed in the EIA report.
xv) Land use based on satellite imagery or authenticated map indicating drainage, cropping pattern, water bodies (rivers, nallahs, ponds etc.), location of nearest villages, creeks, rivers, reservoirs, national parks, wildlife sanctuaries, tiger reserves, biosphere reserves, heritage sites etc in the study area shall be provided. Location of any National Park, Sanctuary, Elephant/Tiger Reserve (existing as well as proposed), migratory routes, if any, within 10 km of the project site shall be specified and marked on the map duly authenticated by the Chief Wildlife Warden.
xvi) Study on land-use pattern in the study area shall be carried out, including identification of common property resources available for conversion into productive land and action plan for abatement and compensation for damage to agricultural land/ common property land (if any) in the nearby villages, due to proposed project shall be prepared.
xvii) Detailed socio-economic study shall be carried out for the study area comprising of 10 km from the plant site.
xviii) CSR component shall be prepared based on need based assessment study to be carried out in the study area. Income generating measures which can help in upliftment of poor section of society which is consistent with the traditional skills of the people shall be identified. The programme can include activities such as development of fodder farm, fruit bearing orchards, vocational training etc. In addition, vocational training for individuals shall be imparted so that poor section of society can take up self employment and jobs. Separate budget for community development activities and income generating programmes shall be specified. Financial allocation to be taken up under CSR shall be specified.
xix) While formulating CSR schemes it shall be ensured that an in-built monitoring mechanism for the schemes identified is in place and mechanism for conducting annual social audit from the nearest government institute of repute in the region shall be prepared. The project proponent shall also provide plan for the status of implementation of the scheme from time to time.
xx) Possibility for adopting nearest three villages shall be explored and details of civic amenities such as roads, drinking water, power etc proposed to be provided at the company’s expenses shall be submitted.
xxi) Location of intake and outfall points (with coordinates) should be given. These locations should be selected based on detailed modeling studies. Details of modeling and the results obtained there from should be furnished. It may be kept in view that the intake and outfall points are away from the mangroves or other eco sensitive areas. A river/marine ecology study (as applicable) should also be done to assess impact on river/marine ecology. River/Marine impact of such activities should be clearly brought out in the EIA report.
xxii) Topography of the area should be given clearly indicating whether the site requires any filling. If so, details of filling, quantity of fill material required, its source, transportation etc. should be given.
xxiii) One complete season AAQ data (except monsoon) to be given along with the dates of monitoring. The parameters to be covered shall include SPM, RSPM(PM10,PM2.5), SO2, NOx, Hg and Ozone (ground level). The location of the monitoring stations should be so decided so as to take into consideration the pre-dominant downwind direction, population zone and sensitive receptors including reserved forests. There should be at least one monitoring station each in the upwind and in the pre dominant downwind direction at a location where maximum ground level concentration is likely to occur.
xxiv) Cumulative impact assessment on ambient air quality due to proposed plant and others (including existing as well as other proposed source of emission) shall be carried out and result submitted in the EIA Report. Mitigative measures as necessary shall be clearly spelt out.
xxv) Impact of the project on the AAQ of the area. Details of the model used and the input data used for modelling should also be provided. The air quality contours may be plotted on a location map showing the location of project site, habitation nearby, sensitive receptors, if any. The wind roses should also be shown on this map.
xxvi) Fuel analysis shall be provided. Details of auxillary fuel, if any including its quantity, quality, storage etc should also be given.
xxvii) Quantity of fuel required, its source and transportation route and mode and a confirmed fuel linkage documents shall be provided.
xxviii) Source of water and its availability. Commitment regarding availability of requisite quantity of water from the competent authority shall be provided along with firm linkage.
xxix) Detailed plan for carrying out rainwater harvesting and proposed utilisation in the plant shall be provided.
xxx) Feasibility of zero discharge shall be examined and detailed justification shall be submitted if in case the same is not possible. Proposed discharge (if any), its quantity, quality and point of discharge, users downstream etc. shall be provided.
xxxi) Optimization of COC for water conservation. Other water conservation measures proposed in the project should also be given. Quantity of water requirement for the project should be optimized.
xxxii) Details of water balance taking into account reuse and re-circulation of effluents.
xxxiii) Detailed plan for conducting monitoring of water quality regularly and mechanism for maintenance of records shall be formulated. Details of methodology and identification of monitoring points (between the plant and drainage in the direction of flow of surface / ground water) shall be submitted. It shall be ensured that parameter to be monitored also include heavy metals in surface and ground water.
xxxiv) Details regarding infrastructure facilities such as sanitation, fuel, restroom, medical facilities, safety during construction phase etc. to be provided to the labour force during construction as well as to the casual workers including truck drivers during operation phase.
xxxv) EMP to mitigate the adverse impacts due to the project along with item wise cost of its implementation.
xxxvi) A Disaster Management Plan along with risk assessment study including fire and explosion issues due to storage and use of fuel should be carried out. It should take into account the maximum inventory of storage at site at any point in time. The risk contours should be plotted on the plant layout map clearly showing which of the proposed activities would be affected in case of an accident taking place. Based on the same, proposed safeguard measures should be provided. Measures to guard against fire hazards should also be provided.
xxxvii) Detailed plan for raising Green belt of 100 m width and consisting of at least 3 tiers around plant boundary with tree density not less than 2500 trees per ha and survival rate atleast 75% shall be submitted.
xxxviii) Details of litigation pending or otherwise with respect to project in any courts, tribunal etc. shall be provided.
Besides all the above, the following general points will be followed:-
a) All documents to be properly referenced with index, page numbers and continuous page numbering.
b) Where data is presented in the report especially in table, the period in which the data was collected and the source should invariably be indicated.
c) Where the documents provided are in a language other than English, an English translation should be provided.
d) The Questionnaire for environmental appraisal of thermal power projects as devised earlier by the Ministry shall also be filled and submitted.
In addition, information on the following may also be incorporated in the EIA report.
1). Is the project intended to have CDM-intent?
i) If not, then reasons thereof?
ii) If yes, then details under mentioned to be provided:
a) Has PIN (Project Idea Note) {or PCN (Project Concept Note)} been submitted to the NCA? (National CDM Authority) in the MoEF?
b) If not, then by when is that expected?
c) Has PDD (Project Design Document) been prepared?
d) What is the Carbon intensity from your electricity generation projected (i.e. CO2 Tons/MWH or Kg/KWH)
e) Amount of CO2 in Tons/year expected to be reduced from the baseline data available on the CEA’s web-site (www.cea.nic.in)
2. Notwithstanding 1(i) above, data on (d) & (e) above to be worked out and reported.
The Committee informed the project proponent that after preparing the draft EIA (as per the generic structure prescribed in Appendix-III of the EIA Notification, 2006) covering the above mentioned issues, the same shall be submitted to the SPCB for conducting the public hearing as per procedure of EIA notification 2006. The issues which emerge during public hearing shall be further incorporated in the Draft EIA/EMP report. The final EIA/EMP report along with public hearing report and the requisite documents (including written objections, if any) shall be submitted to the Ministry for appraisal by the Expert Appraisal Committee for consideration of awarding environmental clearance under the provisions of Environmental Impact Assessment notification dated September 14, 2006.
2.23 2x660 MW Coal Based Super Critical TPP of M/s Welspun Energy Anuppur Pvt. Ltd. at Village Chhatai, in Kotma Taluk, in Anuppur Distt., in Madhya pradesh - reg. TOR.
The proposal was considered for determination of terms of reference for undertaking EIA/EMP study as per provisions of EIA notification 2006. The project proponent along with its consultant viz. M/s GIS Enabled Environment & NEO-Graphic Centre, NCR, Ghaziabad gave a presentation and provided the following information:
The proposal is for setting of 2x660 MW Coal Based TPP at village Chhatai, in Kotma Taluk in Anuppur Distt., in Madhya pradesh. Land requirement will be restricted to 900 acres. Land comprising of 653 acres single crop agricultural land and 462 acres wasteland has been identified. The co-ordinates of the proposed site will be at Latitude 23020’57.64” to 23022’45.59” N and Longitude 820 1’41.31” to 820 3’14.74”E. Coal requirement will be 6.4 MTPA. Water requirement will be 44 MCM, which will be obtained from River Kewai through a pipeline over a distance of 1.0 km from the project site. There are no National parks, Wildlife sanctuaries, Heritage sites, Tiger/Biosphere reserves etc. within 10 km of the site.
Based on the information provided and presentation made the Committee prescribed the following specific TORs for undertaking detailed EIA study and preparation of EMP.
i) Vision document specifying prospective long term plan of the site shall be formulated and submitted.
ii) Executive summary of the project indicating relevant details along with photograph of site shall be provided and issues raised in public hearing along with action plan to address the same shall be provided in tabular form including requisite allocation of funds.
iii) Conformity of the site with the prescribed guidelines in terms of distance of 500 m from HFL of the river, highways, railway line shall be shown on the study area map.
iv) The project proponent shall provide confirmed GPS readings of plant boundary.
v) No water body/nallah (if any) shall be touched. It shall also be ensured that atleast 100 m distance is kept away from the HFL of the nallah/ river (if any) passing in and around the proposed site.
vi) Detail information on water allocation by the Govt. of Madhya Pradesh for various purposes such as drinking, irrigation, industrial (including thermal power) shall be obtained and submitted.
vii) Detailed hydro-geological study of the area shall be conducted from an institute/ organisation of repute to assess impact of on ground and surface water regime. Specific mitigation measures shall be spelt out and action plan for implementation of the same shall be provided.
viii) Detailed source sustainability study of water requirement shall be carried out by an institute of repute. The study shall also specify the source of water for meeting the requirement during lean season and proposed plan of action.
ix) Study on the impact on river/reservoir/marine ecology (as applicable) due to the proposed discharge of treated wastewater into the river/creek shall be carried out and submitted alongwith the EIA Report.
x) Ash pond shall be shifted away as far as possible from any surface water source and its location shall be chosen taking into consideration the elevation and water drainage pattern in the area. The coordinates of the proposed site including location of ash pond shall be submitted along with topo sheet.
xi) Action plan for identification of local employable youth for training in skills relevant to the project for eventual employment in the project itself shall be formulated and details submitted along with EIA/EMP Report.
xii) Layout of the plant indicating break-up of plant, green belt, infrastructure, roads etc. shall be provided.
xiii) Land requirement for the project shall be optimized. Item wise break up of land requirement and its availability to be furnished. It should also include land to be acquired, if any, for coal transportation system as well as for laying of pipeline including ROW. It may clearly be confirmed that the land including ROW is free of all encumbrances. The issues relating to land acquisition and R&R should be clearly discussed in the EIA report.
xiv) Land use based on satellite imagery or authenticated map indicating drainage, cropping pattern, water bodies (rivers, nallahs, ponds etc.), location of nearest villages, creeks, rivers, reservoirs, national parks, wildlife sanctuaries, tiger reserves, biosphere reserves, heritage sites etc in the study area shall be provided. Location of any National Park, Sanctuary, Elephant/Tiger Reserve (existing as well as proposed), migratory routes, if any, within 10 km of the project site shall be specified and marked on the map duly authenticated by the Chief Wildlife Warden.
xv) Study on land-use pattern in the study area shall be carried out, including identification of common property resources available for conversion into productive land and action plan for abatement and compensation for damage to agricultural land/ common property land (if any) in the nearby villages, due to proposed project shall be prepared.
xvi) Detailed socio-economic study shall be carried out for the study area comprising of 10 km from the plant site.
xvii) Details of acquisition of tribal land and compliance to tribal rights as per existing Central and State legislations as may be applicable shall be submitted.
xviii) CSR component shall be prepared based on need based assessment study to be carried out in the study area. Income generating measures which can help in upliftment of poorer sections of society which is consistent with the traditional skills of the people shall be identified. The programme can include activities such as development of fodder farm, fruit bearing orchards, vocational training etc. In addition, vocational training for individuals shall be imparted so that poorer sections of society can take up self employment and jobs. Separate budget for community development activities and income generating programmes shall be specified. Financial allocation to be taken up under CSR shall be specified.
xix) While formulating CSR schemes it shall be ensured that an in-built monitoring mechanism for the schemes identified is in place and mechanism for conducting annual social audit from the nearest government institute of repute in the region shall be prepared. The project proponent shall also provide plan for the status of implementation of the scheme from time to time.
xx) Possibility for adopting nearest three villages shall be explored and details of civic amenities such as roads, drinking water, power etc proposed to be provided at the company’s expenses shall be submitted.
xxi) Location of intake and outfall points (with coordinates) should be given. These locations should be selected based on detailed modeling studies. Details of modeling and the results obtained there from should be furnished. It may be kept in view that the intake and outfall points are away from the mangroves or other eco sensitive areas. A river/marine ecology study (as applicable) should also be done to assess impact on river/marine ecology. River/Marine impact of such activities should be clearly brought out in the EIA report.
xxii) Topography of the area should be given clearly indicating whether the site requires any filling. If so, details of filling, quantity of fill material required, its source, transportation etc. should be given.
xxiii) One complete season AAQ data (except monsoon) to be given along with the dates of monitoring. The parameters to be covered shall include RSPM(PM10,PM2.5), SO2, NOx, Hg and Ozone (ground level). The location of the monitoring stations should be so decided so as to take into consideration the pre-dominant downwind direction, population zone and sensitive receptors including reserved forests. There should be at least one monitoring station each in the upwind and in the pre dominant downwind direction at a location where maximum ground level concentration is likely to occur.
xxiv) Cumulative impact assessment on ambient air quality due to proposed plant and others (including existing as well as other proposed source of emission) shall be carried out and result submitted in the EIA Report. Mitigative measures as necessary shall be clearly spelt out.
xxv) Impact of the project on the AAQ of the area. Details of the model used and the input data used for modelling should also be provided. The air quality contours may be plotted on a location map showing the location of project site, habitation nearby, sensitive receptors, if any. The wind roses should also be shown on this map.
xxvi) Fuel analysis shall be provided. Details of auxillary fuel, if any including its quantity, quality, storage etc should also be given.
xxvii) Quantity of fuel required, its source and transportation route and mode and a confirmed fuel linkage documents shall be provided.
xxviii) Source of water and its availability. Commitment regarding availability of requisite quantity of water from the competent authority shall be provided along with firm linkage.
xxix) Detailed plan for carrying out rainwater harvesting and proposed utilisation in the plant shall be provided.
xxx) Feasibility of zero discharge shall be examined and detailed justification shall be submitted if in case the same is not possible. Proposed discharge (if any), its quantity, quality and point of discharge, users downstream etc. shall be provided.
xxxi) Optimization of COC for water conservation. Other water conservation measures proposed in the project should also be given. Quantity of water requirement for the project should be optimized.
xxxii) Details of water balance taking into account reuse and re-circulation of effluents.
xxxiii) Detailed plan for conducting monitoring of water quality regularly and mechanism for maintenance of records shall be formulated. Details of methodology and identification of monitoring points (between the plant and drainage in the direction of flow of surface / ground water) shall be submitted. It shall be ensured that parameter to be monitored also include heavy metals in surface and ground water.
xxxiv) Details regarding infrastructure facilities such as sanitation, fuel, restroom, medical facilities, safety during construction phase etc. to be provided to the labour force during construction as well as to the casual workers including truck drivers during operation phase.
xxxv) EMP to mitigate the adverse impacts due to the project along with item wise cost of its implementation.
xxxvi) A Disaster Management Plan along with risk assessment study including fire and explosion issues due to storage and use of fuel should be carried out. It should take into account the maximum inventory of storage at site at any point in time. The risk contours should be plotted on the plant layout map clearly showing which of the proposed activities would be affected in case of an accident taking place. Based on the same, proposed safeguard measures should be provided. Measures to guard against fire hazards should also be provided.
xxxvii) Detailed plan for raising Green belt of 100 m width on the western side of the plant and 50m wide on the other sides and consisting of at least 3 tiers around plant boundary with tree density not less than 2500 trees per ha and survival rate atleast 75% shall be submitted.
xxxviii) Details of litigation pending or otherwise with respect to project in any courts, tribunal etc. shall be provided.
Besides all the above, the following general points will be followed:-
a) All documents to be properly referenced with index, page numbers and continuous page numbering.
b) Where data is presented in the report especially in table, the period in which the data was collected and the source should invariably be indicated.
c) Where the documents provided are in a language other than English, an English translation should be provided.
d) The Questionnaire for environmental appraisal of thermal power projects as devised earlier by the Ministry shall also be filled and submitted.
In addition, information on the following may also be incorporated in the EIA report.
1). Is the project intended to have CDM-intent?
i) If not, then reasons thereof?
ii) If yes, then details under mentioned to be provided:
2. Notwithstanding 1(i) above, data on (d) & (e) above to be worked out and reported.
The Committee informed the project proponent that after preparing the draft EIA (as per the generic structure prescribed in Appendix-III of the EIA Notification, 2006) covering the above mentioned issues, the same shall be submitted to the SPCB for conducting the public hearing as per procedure of EIA notification 2006. The issues which emerge during public hearing shall be further incorporated in the Draft EIA/EMP report. The final EIA/EMP report along with public hearing report and the requisite documents (including written objections, if any) shall be submitted to the Ministry for appraisal by the Expert Appraisal Committee for consideration of awarding environmental clearance under the provisions of Environmental Impact Assessment notification dated September 14, 2006.
2.24 1300 MW Natural Gas Based Combined Cycle Power Plant of M/s Delhi Mumbai Industrial Corridor Development Corporation Ltd. at Villages Rajpur & Shahpur, in Vadnagar Taluk, in Mehsana Distt., in Gujarat - reg. TOR.
The proposal was considered for determination of terms of reference for undertaking EIA/EMP study as per provisions of EIA notification 2006. The project proponent along with its consultant viz. M/s Detox Corporation Pvt. Ltd. Surat gave a presentation and provided the following information:
The proposal is for setting of 1300 MW Natural Gas Based Combined Cycle Power Plant Project at Villages Rajpur and Shahpur, in Vadnagar Taluk, in Mehsana Distt., in Gujarat. Land requirement will be 173 acres, which is a Govt. waste barren land. The co-ordinates of the proposed site will be at Latitude 23047’25” to 23047’54” N and Longitude 72042’12” to 72042’49”E. Fuel Requirement will be Natural Gas which will be 4.7-5.3 MMSCMD and sourced from the GSPL Kalor Mehsana Pipeline. Water requirement will be 33000 m3 /day, which will be obtained from Sardar Sarovar Narmada Canal through an Intake Well at a distance of 80 km from the project site. There are monuments located such as Ajapal Kund, Vadanagar, Inscription and Arjun Bari gate Vadnagar, Torana, Vadnagar within 10 km of the project site. No other ecologically sensitive areas such as national parks, wildlife sanctuaries, biosphere and tiger reserves etc. are located within 10 Km of the site.
Based on the information provided and presentation made the Committee prescribed the following specific TORs for undertaking detailed EIA study and preparation of EMP.
i) Prior approval from ASI shall be obtained and a copy of the clearance submitted.
ii) Vision document specifying prospective long term plan of the site shall be formulated and submitted.
iii) Executive summary of the project indicating relevant details along with photograph of site shall be provided and issues raised in public hearing along with action plan to address the same shall be provided in tabular form including requisite allocation of funds.
iv) Conformity of the site with the prescribed guidelines in terms of distance of 500 m from HFL of the river, highways, railway line shall be shown on the study area map.
v) The project proponent shall provide confirmed GPS readings of plant boundary.
vi) No water body/nallah (if any) shall be touched. It shall also be ensured that atleast 100 m distance is kept away from the HFL of the nallah/ river (if any) passing in and around the proposed site.
vii) Hydro-geological study (including sustainability study during lean season) of the area shall be conducted from an institute/ organisation of repute to assess impact of water regime in the area. Specific mitigation measures shall be spelt out and action plan for implementation of the same shall be provided.
viii) Action plan for identification of local employable youth for training in skills relevant to the project for eventual employment in the project itself shall be formulated.
ix) Layout of the plant indicating break-up of plant, green belt, infrastructure, roads etc. shall be provided.
x) Land requirement for the project shall be optimized. Item wise break up of land requirement and its availability to be furnished. It should also include land to be acquired, if any, for fuel transportation system as well as for laying of pipeline including ROW. It may clearly be confirmed that the land including ROW is free of all encumbrances. The issues relating to land acquisition and R&R should be clearly discussed in the EIA report.
xi) Land use based on satellite imagery or authenticated map indicating drainage, cropping pattern, water bodies (rivers, nallahs, ponds etc.), location of nearest villages, creeks, rivers, reservoirs, national parks, wildlife sanctuaries, tiger reserves, biosphere reserves, heritage sites etc (as applicable) in the study area shall be provided. Location of any National Park, Sanctuary, Elephant/Tiger Reserve (existing as well as proposed), migratory routes, if any, within 10 km of the project site shall be specified and marked on the map duly authenticated by the Chief Wildlife Warden.
xii) Study on land-use pattern in the study area shall be carried out, including identification of common property resources available for conversion into productive land and action plan for abatement and compensation for damage to agricultural land/ common property land (if any) in the nearby villages, due to proposed project shall be prepared.
xiii) Detailed socio-economic study shall be carried out for the study area comprising of 10 km from the plant site.
xiv) CSR component shall be prepared based on need based assessment study to be carried out in the study area. Income generating measures which can help in upliftment of poor section of society which is consistent with the traditional skills of the people shall be identified. The programme can include activities such as development of fodder farm, fruit bearing orchards, vocational training etc. In addition, vocational training for individuals shall be imparted so that poor section of society can take up self employment and jobs. Separate budget for community development activities and income generating programmes shall be specified. Financial allocation to be taken up under CSR shall be specified.
xv) While formulating CSR schemes it shall be ensured that an in-built monitoring mechanism for the schemes identified is in place and mechanism for conducting annual social audit from the nearest government institute of repute in the region shall be prepared. The project proponent shall also provide plan for the status of implementation of the scheme from time to time.
xvi) Possibility for adopting nearest three villages shall be explored and details of civic amenities such as roads, drinking water, power etc proposed to be provided at the company’s expenses shall be submitted.
xvii) Topography of the area should be given clearly indicating whether the site requires any filling. If so, details of filling, quantity of fill material required, its source, transportation etc. should be given.
xviii) One complete season AAQ data (except monsoon) to be given along with the dates of monitoring. The parameters to be covered shall include SPM, RSPM(PM10,PM2.5), SO2, NOx, Hg and Ozone (ground level). The location of the monitoring stations should be so decided so as to take into consideration the pre-dominant downwind direction, population zone and sensitive receptors including reserved forests. There should be at least one monitoring station each in the upwind and in the pre dominant downwind direction at a location where maximum ground level concentration is likely to occur.
xix) Cumulative impact assessment on ambient air quality due to proposed plant and others (including existing as well as other proposed source of emission) shall be carried out and result submitted in the EIA Report. Mitigative measures as necessary shall be clearly spelt out.
xx) Impact of the project on the AAQ of the area. Details of the model used and the input data used for modelling should also be provided. The air quality contours may be plotted on a location map showing the location of project site, habitation nearby, sensitive receptors, if any. The wind roses should also be shown on this map.
xxi) Fuel analysis shall be provided. Details of auxillary fuel, if any including its quantity, quality, storage etc should also be given.
xxii) Quantity of fuel required, its source and transportation route and mode and a confirmed fuel linkage documents shall be provided.
xxiii) Detailed plan for carrying out rainwater harvesting and proposed utilisation in the plant shall be provided.
xxiv) Feasibility of zero discharge shall be examined and detailed justification shall be submitted if in case the same is not possible. Proposed discharge (if any), its quantity, quality and point of discharge, users downstream etc. shall be provided.
xxv) Optimization of COC for water conservation. Other water conservation measures proposed in the project should also be given. Quantity of water requirement for the project should be optimized.
xxvi) Details of water balance taking into account reuse and re-circulation of effluents.
xxvii) Detailed plan for conducting monitoring of water quality regularly and mechanism for maintenance of records shall be formulated. Details of methodology and identification of monitoring points (between the plant and drainage in the direction of flow of surface / ground water) shall be submitted. It shall be ensured that parameter to be monitored also include heavy metals in surface and ground water.
xxviii) Details regarding infrastructure facilities such as sanitation, fuel, restroom, medical facilities, safety during construction phase etc. to be provided to the labour force during construction as well as to the casual workers including truck drivers during operation phase.
xxix) EMP to mitigate the adverse impacts due to the project along with item wise cost of its implementation.
xxx) A Disaster Management Plan along with risk assessment study including fire and explosion issues due to storage and use of fuel should be carried out. It should take into account the maximum inventory of storage at site at any point in time. The risk contours should be plotted on the plant layout map clearly showing which of the proposed activities would be affected in case of an accident taking place. Based on the same, proposed safeguard measures should be provided. Measures to guard against fire hazards should also be provided.
xxxi) Detailed plan for raising Green belt of 50 m width and consisting of at least 3 tiers around plant boundary with tree density not less than 2500 trees per ha and survival rate atleast 75% shall be submitted. If the same is not feasible detailed justification shall be submitted.
xxxii) Details of litigation pending or otherwise with respect to project in any courts, tribunal etc. shall be provided.
Besides all the above, the following general points will be followed:-
a) All documents to be properly referenced with index, page numbers and continuous page numbering.
b) Where data is presented in the report especially in table, the period in which the data was collected and the source should invariably be indicated.
c) Where the documents provided are in a language other than English, an English translation should be provided.
d) The Questionnaire for environmental appraisal of thermal power projects as devised earlier by the Ministry shall also be filled and submitted.
In addition, information on the following may also be incorporated in the EIA report.
1). Is the project intended to have CDM-intent?
i) If not, then reasons thereof?
ii) If yes, then details under mentioned to be provided:
a) Has PIN (Project Idea Note) {or PCN (Project Concept Note)} been submitted to the NCA? (National CDM Authority) in the MoEF?
b) If not, then by when is that expected?
c) Has PDD (Project Design Document) been prepared?
d) What is the Carbon intensity from your electricity generation projected (i.e019. CO2 Tons/MWH or Kg/KWH)
e) Amount of CO2 in Tons/year expect]
f) {|ed to be reduced from the baseline data available on the CEA’s web-site (-*/)
2. Notwithstanding 1(i) above, data on (d) & (e) above to be worked out and reported.
The Committee informed the project proponent that after preparing the draft EIA (as per the generic structure prescribed in Appendix-III of the EIA Notification, 2006) covering the above mentioned issues, the same shall be submitted to the SPCB for conducting the public hearing as per procedure of EIA notification 2006. The issues which emerge during public hearing shall be further incorporated in the Draft EIA/EMP report. The final EIA/EMP report along with public hearing report and the requisite documents (including written objections, if any) shall be submitted to the Ministry for appraisal by the Expert Appraisal Committee for consideration of awarding environmental clearance under the provisions of Environmental Impact Assessment notification dated September 14, 2006.
2.25 1300 MW Natural Gas Based Combined Cycle Power Plant of M/s DMICDC Vaghel Power Company Ltd. at village Vaghel, in Sami Taluka, in Patan Distt., in Gujarat - reg. TOR.
The proposal was considered for determination of terms of reference for undertaking EIA/EMP study as per provisions of EIA notification 2006. The project proponent along with its consultant viz. M/s Detox Corporation Pvt. Ltd. Surat gave a presentation and provided the following information:
The proposal is for setting of 1300 MW Natural Gas Based Combined Cycle Power Plant Project at village Vaghel, in Sami Taluka, in Patan Distt., in Gujarat. Land requirement will be 226 acres, which is Govt. waste barren land. The co-ordinates of the proposed site will be at Latitude 23037’25.46” to 23038’11.80” N and Longitude 71056’15.58” to 72002’39.77”E. Fuel Requirement will be Natural Gas which will be 4.7-5.3 MMSCMD/annum and sourced from the GSPL Pipeline located at Sidhpur. Water requirement will be 33000 m3 /day, which will be obtained from Bolera Branch Canal of Sardar Sarovar Narmada Canal through an Intake Well at a distance of 8 km from the project site. There are no National parks, Wildlife sanctuaries, Heritage sites, Tiger/Biosphere reserves etc. within 10 km of the site.
Based on the information provided and presentation made the Committee prescribed the following specific TORs for undertaking detailed EIA study and preparation of EMP.
i) Vision document specifying prospective long term plan of the site shall be formulated and submitted.
ii) Executive summary of the project indicating relevant details along with photograph of site shall be provided and issues raised in public hearing along with action plan to address the same shall be provided in tabular form including requisite allocation of funds.
iii) Conformity of the site with the prescribed guidelines in terms of distance of 500 m from HFL of the river, highways, railway line shall be shown on the study area map.
iv) The project proponent shall provide confirmed GPS readings of plant boundary.
v) No water body/nallah (if any) shall be touched. It shall also be ensured that atleast 100 m distance is kept away from the HFL of the nallah/ river (if any) passing in and around the proposed site.
vi) Hydro-geological study (including sustainability study during lean season) of the area shall be conducted from an institute/ organisation of repute to assess impact of water regime in the area. Specific mitigation measures shall be spelt out and action plan for implementation of the same shall be provided.
vii) Action plan for identification of local employable youth for training in skills relevant to the project for eventual employment in the project itself shall be formulated.
viii) Layout of the plant indicating break-up of plant, green belt, infrastructure, roads etc. shall be provided.
ix) Land requirement for the project shall be optimized. Item wise break up of land requirement and its availability to be furnished. It should also include land to be acquired, if any, for fuel transportation system as well as for laying of pipeline including ROW. It may clearly be confirmed that the land including ROW is free of all encumbrances. The issues relating to land acquisition and R&R should be clearly discussed in the EIA report.
x) Land use based on satellite imagery or authenticated map indicating drainage, cropping pattern, water bodies (rivers, nallahs, ponds etc.), location of nearest villages, creeks, rivers, reservoirs, national parks, wildlife sanctuaries, tiger reserves, biosphere reserves, heritage sites etc (as applicable) in the study area shall be provided. Location of any National Park, Sanctuary, Elephant/Tiger Reserve (existing as well as proposed), migratory routes, if any, within 10 km of the project site shall be specified and marked on the map duly authenticated by the Chief Wildlife Warden.
xi) Study on land-use pattern in the study area shall be carried out, including identification of common property resources available for conversion into productive land and action plan for abatement and compensation for damage to agricultural land/ common property land (if any) in the nearby villages, due to proposed project shall be prepared.
xii) Detailed socio-economic study shall be carried out for the study area comprising of 10 km from the plant site.
xiii) CSR component shall be prepared based on need based assessment study to be carried out in the study area. Income generating measures which can help in upliftment of poor section of society which is consistent with the traditional skills of the people shall be identified. The programme can include activities such as development of fodder farm, fruit bearing orchards, vocational training etc. In addition, vocational training for individuals shall be imparted so that poor section of society can take up self employment and jobs. Separate budget for community development activities and income generating programmes shall be specified. Financial allocation to be taken up under CSR shall be specified.
xiv) While formulating CSR schemes it shall be ensured that an in-built monitoring mechanism for the schemes identified is in place and mechanism for conducting annual social audit from the nearest government institute of repute in the region shall be prepared. The project proponent shall also provide plan for the status of implementation of the scheme from time to time.
xv) Possibility for adopting nearest three villages shall be explored and details of civic amenities such as roads, drinking water, power etc proposed to be provided at the company’s expenses shall be submitted.
xvi) Topography of the area should be given clearly indicating whether the site requires any filling. If so, details of filling, quantity of fill material required, its source, transportation etc. should be given.
xvii) One complete season AAQ data (except monsoon) to be given along with the dates of monitoring. The parameters to be covered shall include SPM, RSPM(PM10,PM2.5), SO2, NOx, Hg and Ozone (ground level). The location of the monitoring stations should be so decided so as to take into consideration the pre-dominant downwind direction, population zone and sensitive receptors including reserved forests. There should be at least one monitoring station each in the upwind and in the pre dominant downwind direction at a location where maximum ground level concentration is likely to occur.
xviii) Cumulative impact assessment on ambient air quality due to proposed plant and others (including existing as well as other proposed source of emission) shall be carried out and result submitted in the EIA Report. Mitigative measures as necessary shall be clearly spelt out.
xix) Impact of the project on the AAQ of the area. Details of the model used and the input data used for modelling should also be provided. The air quality contours may be plotted on a location map showing the location of project site, habitation nearby, sensitive receptors, if any. The wind roses should also be shown on this map.
xx) Fuel analysis shall be provided. Details of auxillary fuel, if any including its quantity, quality, storage etc should also be given.
xxi) Quantity of fuel required, its source and transportation route and mode and a confirmed fuel linkage documents shall be provided.
xxii) Detailed plan for carrying out rainwater harvesting and proposed utilisation in the plant shall be provided.
xxiii) Feasibility of zero discharge shall be examined and detailed justification shall be submitted if in case the same is not possible. Proposed discharge (if any), its quantity, quality and point of discharge, users downstream etc. shall be provided.
xxiv) Optimization of COC for water conservation. Other water conservation measures proposed in the project should also be given. Quantity of water requirement for the project should be optimized.
xxv) Details of water balance taking into account reuse and re-circulation of effluents.
xxvi) Detailed plan for conducting monitoring of water quality regularly and mechanism for maintenance of records shall be formulated. Details of methodology and identification of monitoring points (between the plant and drainage in the direction of flow of surface / ground water) shall be submitted. It shall be ensured that parameter to be monitored also include heavy metals in surface and ground water.
xxvii) Details regarding infrastructure facilities such as sanitation, fuel, restroom, medical facilities, safety during construction phase etc. to be provided to the labour force during construction as well as to the casual workers including truck drivers during operation phase.
xxviii) EMP to mitigate the adverse impacts due to the project along with item wise cost of its implementation.
xxix) A Disaster Management Plan along with risk assessment study including fire and explosion issues due to storage and use of fuel should be carried out. It should take into account the maximum inventory of storage at site at any point in time. The risk contours should be plotted on the plant layout map clearly showing which of the proposed activities would be affected in case of an accident taking place. Based on the same, proposed safeguard measures should be provided. Measures to guard against fire hazards should also be provided.
xxx) Detailed plan for raising Green belt of 50 m width and consisting of at least 3 tiers around plant boundary with tree density not less than 2500 trees per ha and survival rate atleast 75% shall be submitted. If the same is not feasible detailed justification shall be submitted.
xxxi) Details of litigation pending or otherwise with respect to project in any courts, tribunal etc. shall be provided.
Besides all the above, the following general points will be followed:-
a) All documents to be properly referenced with index, page numbers and continuous page numbering.
b) Where data is presented in the report especially in table, the period in which the data was collected and the source should invariably be indicated.
c) Where the documents provided are in a language other than English, an English translation should be provided.
d) The Questionnaire for environmental appraisal of thermal power projects as devised earlier by the Ministry shall also be filled and submitted.
In addition, information on the following may also be incorporated in the EIA report.
1). Is the project intended to have CDM-intent?
i) If not, then reasons thereof?
ii) If yes, then details under mentioned to be provided:
a) Has PIN (Project Idea Note) {or PCN (Project Concept Note)} been submitted to the NCA? (National CDM Authority) in the MoEF?
b) If not, then by when is that expected?
c) Has PDD (Project Design Document) been prepared?
d) What is the Carbon intensity from your electricity generation projected (i.e019. CO2 Tons/MWH or Kg/KWH)
e) Amount of CO2 in Tons/year expect]
f) {|ed to be reduced from the baseline data available on the CEA’s web-site (-*/)
2. Notwithstanding 1(i) above, data on (d) & (e) above to be worked out and reported.
The Committee informed the project proponent that after preparing the draft EIA (as per the generic structure prescribed in Appendix-III of the EIA Notification, 2006) covering the above mentioned issues, the same shall be submitted to the SPCB for conducting the public hearing as per procedure of EIA notification 2006. The issues which emerge during public hearing shall be further incorporated in the Draft EIA/EMP report. The final EIA/EMP report along with public hearing report and the requisite documents (including written objections, if any) shall be submitted to the Ministry for appraisal by the Expert Appraisal Committee for consideration of awarding environmental clearance under the provisions of Environmental Impact Assessment notification dated September 14, 2006.
2.26 1300 MW Natural Gas Based Combined Cycle Power Plant Project of M/s DMICDC Ltd. at Village Saag Doongri, in Bagidora Tehsil, in Banswara Distt., in Rajasthan - reg. TOR.
The proposal was considered for determination of terms of reference for undertaking EIA/EMP study as per provisions of EIA notification 2006. The project proponent gave a presentation and provided the following information:
The proposal is for setting of 1300 MW Natural Gas Based Combined Cycle Power Plant Project of M/s DMICDC Ltd. at Village Saag Doongri, in Bagidora Tehsil, in Banswara Distt., in Rajasthan. Land requirement will be 232 acres, which is Govt. waste barren land. 107.25.36 acres land will be utilized for proposed power plant, 12.67 acres will be utilized for Township area and 112.08 acres will be green Belt area. The co-ordinates of the proposed site will be at Latitude 23023’21” to 230’23’55” N and Longitude 74014’13” to 74014’48”E. Fuel Requirement will be Natural Gas which will be 4.7-5.3 MMSCMD/annum and sourced from Jhabua which is around 80-100 km from project site. Water requirement will be 33000m3/day, which will be obtained from Mahi River through a pipeline over a distance of 35km from the project site. There are no National parks, Wildlife sanctuaries, Heritage sites, Tiger/Biosphere reserves etc. within 10 km of the site.
The Committee noted that the area may be tribal area and therefore decided that the project proponent shall address relevant issues with regard to protection of rights for the community.
Based on the information provided and presentation made the Committee prescribed the following specific TORs for undertaking detailed EIA study and preparation of EMP.
i) Vision document specifying prospective long term plan of the site shall be formulated and submitted.
ii) Executive summary of the project indicating relevant details along with photograph of site shall be provided and issues raised in public hearing along with action plan to address the same shall be provided in tabular form including requisite allocation of funds.
iii) Conformity of the site with the prescribed guidelines in terms of distance of 500 m from HFL of the river, highways, railway line shall be shown on the study area map.
iv) The project proponent shall provide confirmed GPS readings of plant boundary.
v) No water body/nallah (if any) shall be touched. It shall also be ensured that atleast 100 m distance is kept away from the HFL of the nallah/ river (if any) passing in and around the proposed site.
vi) Hydro-geological study (including sustainability study during lean season) of the area shall be conducted from an institute/ organisation of repute to assess impact of water regime in the area. Specific mitigation measures shall be spelt out and action plan for implementation of the same shall be provided.
vii) Action plan for identification of local employable youth for training in skills relevant to the project for eventual employment in the project itself shall be formulated.
viii) Layout of the plant indicating break-up of plant, green belt, infrastructure, roads etc. shall be provided.
ix) Land requirement for the project shall be optimized. Item wise break up of land requirement and its availability to be furnished. It should also include land to be acquired, if any, for fuel transportation system as well as for laying of pipeline including ROW. It may clearly be confirmed that the land including ROW is free of all encumbrances. The issues relating to land acquisition and R&R should be clearly discussed in the EIA report.
x) Land use based on satellite imagery or authenticated map indicating drainage, cropping pattern, water bodies (rivers, nallahs, ponds etc.), location of nearest villages, creeks, rivers, reservoirs, national parks, wildlife sanctuaries, tiger reserves, biosphere reserves, heritage sites etc (as applicable) in the study area shall be provided. Location of any National Park, Sanctuary, Elephant/Tiger Reserve (existing as well as proposed), migratory routes, if any, within 10 km of the project site shall be specified and marked on the map duly authenticated by the Chief Wildlife Warden.
xi) Study on land-use pattern in the study area shall be carried out, including identification of common property resources available for conversion into productive land and action plan for abatement and compensation for damage to agricultural land/ common property land (if any) in the nearby villages, due to proposed project shall be prepared.
xii) Detailed socio-economic study shall be carried out for the study area comprising of 10 km from the plant site.
xiii) CSR component shall be prepared based on need based assessment study to be carried out in the study area. Income generating measures which can help in upliftment of poor section of society especially SCs/STs which is consistent with the traditional skills of the people shall be identified. The programme can include activities such as development of fodder farm, fruit bearing orchards, vocational training etc. In addition, vocational training for individuals shall be imparted so that poor section of society can take up self employment and jobs. Separate budget for community development activities and income generating programmes shall be specified. Financial allocation to be taken up under CSR shall be specified.
xiv) While formulating CSR schemes it shall be ensured that an in-built monitoring mechanism for the schemes identified is in place and mechanism for conducting annual social audit from the nearest government institute of repute in the region shall be prepared. The project proponent shall also provide plan for the status of implementation of the scheme from time to time.
xv) Details of acquisition of tribal land and compliance to tribal rights as per existing Central and State legislations as may be applicable shall be submitted.
xvi) The project proponent shall formulate a scheme for empowerment / upliftment of tribal population in the area and shall ensured that the rights of tribals are protected.
xvii) Possibility for adopting nearest three villages shall be explored and details of civic amenities such as roads, drinking water, power etc proposed to be provided at the company’s expenses shall be submitted.
xviii) Topography of the area should be given clearly indicating whether the site requires any filling. If so, details of filling, quantity of fill material required, its source, transportation etc. should be given.
xix) One complete season AAQ data (except monsoon) to be given along with the dates of monitoring. The parameters to be covered shall include SPM, RSPM(PM10,PM2.5), SO2, NOx, Hg and Ozone (ground level). The location of the monitoring stations should be so decided so as to take into consideration the pre-dominant downwind direction, population zone and sensitive receptors including reserved forests. There should be at least one monitoring station each in the upwind and in the pre dominant downwind direction at a location where maximum ground level concentration is likely to occur.
xx) Cumulative impact assessment on ambient air quality due to proposed plant and others (including existing as well as other proposed source of emission) shall be carried out and result submitted in the EIA Report. Mitigative measures as necessary shall be clearly spelt out.
xxi) Impact of the project on the AAQ of the area. Details of the model used and the input data used for modelling should also be provided. The air quality contours may be plotted on a location map showing the location of project site, habitation nearby, sensitive receptors, if any. The wind roses should also be shown on this map.
xxii) Fuel analysis shall be provided. Details of auxillary fuel, if any including its quantity, quality, storage etc should also be given.
xxiii) Quantity of fuel required, its source and transportation route and mode and a confirmed fuel linkage documents shall be provided.
xxiv) Detailed plan for carrying out rainwater harvesting and proposed utilisation in the plant shall be provided.
xxv) Feasibility of zero discharge shall be examined and detailed justification shall be submitted if in case the same is not possible. Proposed discharge (if any), its quantity, quality and point of discharge, users downstream etc. shall be provided.
xxvi) Optimization of COC for water conservation. Other water conservation measures proposed in the project should also be given. Quantity of water requirement for the project should be optimized.
xxvii) Details of water balance taking into account reuse and re-circulation of effluents.
xxviii) Detailed plan for conducting monitoring of water quality regularly and mechanism for maintenance of records shall be formulated. Details of methodology and identification of monitoring points (between the plant and drainage in the direction of flow of surface / ground water) shall be submitted. It shall be ensured that parameter to be monitored also include heavy metals in surface and ground water.
xxix) Details regarding infrastructure facilities such as sanitation, fuel, restroom, medical facilities, safety during construction phase etc. to be provided to the labour force during construction as well as to the casual workers including truck drivers during operation phase.
xxx) EMP to mitigate the adverse impacts due to the project along with item wise cost of its implementation.
xxxi) A Disaster Management Plan along with risk assessment study including fire and explosion issues due to storage and use of fuel should be carried out. It should take into account the maximum inventory of storage at site at any point in time. The risk contours should be plotted on the plant layout map clearly showing which of the proposed activities would be affected in case of an accident taking place. Based on the same, proposed safeguard measures should be provided. Measures to guard against fire hazards should also be provided.
xxxii) Detailed plan for raising Green belt of 50 m width and consisting of at least 3 tiers around plant boundary with tree density not less than 2500 trees per ha and survival rate atleast 75% shall be submitted. If the same is not feasible detailed justification shall be submitted.
xxxiii) Details of litigation pending or otherwise with respect to project in any courts, tribunal etc. shall be provided.
Besides all the above, the following general points will be followed:-
a) All documents to be properly referenced with index, page numbers and continuous page numbering.
b) Where data is presented in the report especially in table, the period in which the data was collected and the source should invariably be indicated.
c) Where the documents provided are in a language other than English, an English translation should be provided.
d) The Questionnaire for environmental appraisal of thermal power projects as devised earlier by the Ministry shall also be filled and submitted.
In addition, information on the following may also be incorporated in the EIA report.
1). Is the project intended to have CDM-intent?
i) If not, then reasons thereof?
ii) If yes, then details under mentioned to be provided:
a) Has PIN (Project Idea Note) {or PCN (Project Concept Note)} been submitted to the NCA? (National CDM Authority) in the MoEF?
b) If not, then by when is that expected?
c) Has PDD (Project Design Document) been prepared?
d) What is the Carbon intensity from your electricity generation projected (i.e019. CO2 Tons/MWH or Kg/KWH)
e) Amount of CO2 in Tons/year expect]
f) {|ed to be reduced from the baseline data available on the CEA’s web-site (-*/)
2. Notwithstanding 1(i) above, data on (d) & (e) above to be worked out and reported.
The Committee informed the project proponent that after preparing the draft EIA (as per the generic structure prescribed in Appendix-III of the EIA Notification, 2006) covering the above mentioned issues, the same shall be submitted to the SPCB for conducting the public hearing as per procedure of EIA notification 2006. The issues which emerge during public hearing shall be further incorporated in the Draft EIA/EMP report. The final EIA/EMP report along with public hearing report and the requisite documents (including written objections, if any) shall be submitted to the Ministry for appraisal by the Expert Appraisal Committee for consideration of awarding environmental clearance under the provisions of Environmental Impact Assessment notification dated September 14, 2006.
2.27 2x300 MW and 1x660 MW Coal Based TPP of M/s Jinbhuvish Power Generating Pvt. Ltd. at village Ghanmukh (Bijora), in Tehsil- Mahagaon, in Yavatmal Distt, in Maharashtra - reg. TOR.
The proposal was placed for determination of terms of reference for undertaking EIA/EMP study as per provisions of EIA notification 2006. The project proponent along with its consultant viz. Yogiraja Industrial Consultant gave a presentation and provided the following information:
The proposal is for setting up of 2x270MW + 1x660 MW Coal Based TPP at village Ghanmukh (Bijora), in Tehsil- Mahagaon, in Yavatmal Distt, in Maharashtra. Earlier the project proponent obtained TOR for 2x270, issued by the Ministry on 16.01.2009. However as no construction activity has started and change in configuration and addition of 1x660 MW, is involved, the project proponent requested for cancellation of the TOR prescribed for 2x270 MW and applied afresh for the changed configuration. Land requirement will be about 760 acres for main plant. Domestic and Imported coal in the ratio 70:30 will be used. There are no wildlife sanctuary, national parks, biosphere/tiger reserve, heritage sites etc. within 15 km of the site.
Based on the information provided and presentation made the Committee prescribed the following specific TORs for undertaking detailed EIA study and preparation of EMP.
i) Vision document specifying prospective long term plan of the site shall be formulated and submitted.
ii) Executive summary of the project indicating relevant details along with photograph of site shall be provided and issues raised in public hearing along with action plan to address the same shall be provided in tabular form including requisite allocation of funds.
iii) Conformity of the site with the prescribed guidelines in terms of distance of 500 m from HFL of the river, highways, railway line shall be shown on the study area map.
iv) The project proponent shall provide confirmed GPS readings of plant boundary.
v) No water body/nallah (if any) shall be touched. It shall also be ensured that atleast 100 m distance is kept away from the HFL of the nallah/ river (if any) passing in and around the proposed site.
vi) Detailed hydro-geological study of the area shall be conducted from an institute/ organisation of repute to assess impact of on ground and surface water regime. Specific mitigation measures shall be spelt out and action plan for implementation of the same shall be provided.
vii) Detailed source sustainability study of water requirement shall be carried out by an institute of repute. The study shall also specify the source of water for meeting the requirement during lean season and proposed plan of action.
viii) Study on the impact on river/reservoir/marine ecology (as applicable) due to the proposed discharge of treated wastewater into the river/creek shall be carried out and submitted alongwith the EIA Report.
ix) Ash pond shall be shifted away as far as possible from any surface water source and its location shall be chosen taking into consideration the elevation and water drainage pattern in the area. The coordinates of the proposed site including location of ash pond shall be submitted along with topo sheet.
x) Action plan for identification of local employable youth for training in skills relevant to the project for eventual employment in the project itself shall be formulated and details submitted along with EIA/EMP Report.
xi) Layout of the plant indicating break-up of plant, green belt, infrastructure, roads etc. shall be provided.
xii) Land requirement for the project shall be optimized. Item wise break up of land requirement and its availability to be furnished. It should also include land to be acquired, if any, for coal transportation system as well as for laying of pipeline including ROW. It may clearly be confirmed that the land including ROW is free of all encumbrances. The issues relating to land acquisition and R&R should be clearly discussed in the EIA report.
xiii) Land use based on satellite imagery or authenticated map indicating drainage, cropping pattern, water bodies (rivers, nallahs, ponds etc.), location of nearest villages, creeks, rivers, reservoirs, national parks, wildlife sanctuaries, tiger reserves, biosphere reserves, heritage sites etc in the study area shall be provided. Location of any National Park, Sanctuary, Elephant/Tiger Reserve (existing as well as proposed), migratory routes, if any, within 10 km of the project site shall be specified and marked on the map duly authenticated by the Chief Wildlife Warden.
xiv) Study on land-use pattern in the study area shall be carried out, including identification of common property resources available for conversion into productive land and action plan for abatement and compensation for damage to agricultural land/ common property land (if any) in the nearby villages, due to proposed project shall be prepared.
xv) Detailed socio-economic study shall be carried out for the study area comprising of 10 km from the plant site.
xvi) CSR component shall be prepared based on need based assessment study to be carried out in the study area. Income generating measures which can help in upliftment of poorer sections of society which is consistent with the traditional skills of the people shall be identified. The programme can include activities such as development of fodder farm, fruit bearing orchards, vocational training etc. In addition, vocational training for individuals shall be imparted so that poorer sections of society can take up self employment and jobs. Separate budget for community development activities and income generating programmes shall be specified. Financial allocation to be taken up under CSR shall be specified.
xvii) While formulating CSR schemes it shall be ensured that an in-built monitoring mechanism for the schemes identified is in place and mechanism for conducting annual social audit from the nearest government institute of repute in the region shall be prepared. The project proponent shall also provide plan for the status of implementation of the scheme from time to time.
xviii) Possibility for adopting nearest three villages shall be explored and details of civic amenities such as roads, drinking water, power etc proposed to be provided at the company’s expenses shall be submitted.
xix) Location of intake and outfall points (with coordinates) should be given. These locations should be selected based on detailed modeling studies. Details of modeling and the results obtained there from should be furnished. It may be kept in view that the intake and outfall points are away from the mangroves or other eco sensitive areas. A river/marine ecology study (as applicable) should also be done to assess impact on river/marine ecology. River/Marine impact of such activities should be clearly brought out in the EIA report.
xx) Topography of the area should be given clearly indicating whether the site requires any filling. If so, details of filling, quantity of fill material required, its source, transportation etc. should be given.
xxi) One complete season AAQ data (except monsoon) to be given along with the dates of monitoring. The parameters to be covered shall include RSPM(PM10,PM2.5), SO2, NOx, Hg and Ozone (ground level). The location of the monitoring stations should be so decided so as to take into consideration the pre-dominant downwind direction, population zone and sensitive receptors including reserved forests. There should be at least one monitoring station each in the upwind and in the pre dominant downwind direction at a location where maximum ground level concentration is likely to occur.
xxii) Cumulative impact assessment on ambient air quality due to proposed plant and others (including existing as well as other proposed source of emission) shall be carried out and result submitted in the EIA Report. Mitigative measures as necessary shall be clearly spelt out.
xxiii) Impact of the project on the AAQ of the area. Details of the model used and the input data used for modelling should also be provided. The air quality contours may be plotted on a location map showing the location of project site, habitation nearby, sensitive receptors, if any. The wind roses should also be shown on this map.
xxiv) Fuel analysis shall be provided. Details of auxillary fuel, if any including its quantity, quality, storage etc should also be given.
xxv) Quantity of fuel required, its source and transportation route and mode and a confirmed fuel linkage documents shall be provided.
xxvi) Source of water and its availability. Commitment regarding availability of requisite quantity of water from the competent authority shall be provided along with firm linkage.
xxvii) Detailed plan for carrying out rainwater harvesting and proposed utilisation in the plant shall be provided.
xxviii) Feasibility of zero discharge shall be examined and detailed justification shall be submitted if in case the same is not possible. Proposed discharge (if any), its quantity, quality and point of discharge, users downstream etc. shall be provided.
xxix) Optimization of COC for water conservation. Other water conservation measures proposed in the project should also be given. Quantity of water requirement for the project should be optimized.
xxx) Details of water balance taking into account reuse and re-circulation of effluents.
xxxi) Detailed plan for conducting monitoring of water quality regularly and mechanism for maintenance of records shall be formulated. Details of methodology and identification of monitoring points (between the plant and drainage in the direction of flow of surface / ground water) shall be submitted. It shall be ensured that parameter to be monitored also include heavy metals in surface and ground water.
xxxii) Details regarding infrastructure facilities such as sanitation, fuel, restroom, medical facilities, safety during construction phase etc. to be provided to the labour force during construction as well as to the casual workers including truck drivers during operation phase.
xxxiii) EMP to mitigate the adverse impacts due to the project along with item wise cost of its implementation.
xxxiv) A Disaster Management Plan along with risk assessment study including fire and explosion issues due to storage and use of fuel should be carried out. It should take into account the maximum inventory of storage at site at any point in time. The risk contours should be plotted on the plant layout map clearly showing which of the proposed activities would be affected in case of an accident taking place. Based on the same, proposed safeguard measures should be provided. Measures to guard against fire hazards should also be provided.
xxxv) Detailed plan for raising Green belt of 100 m width on the western side of the plant and 50m wide on the other sides and consisting of at least 3 tiers around plant boundary with tree density not less than 2500 trees per ha and survival rate atleast 75% shall be submitted.
xxxvi) Details of litigation pending or otherwise with respect to project in any courts, tribunal etc. shall be provided.
Besides all the above, the following general points will be followed:-
a) All documents to be properly referenced with index, page numbers and continuous page numbering.
b) Where data is presented in the report especially in table, the period in which the data was collected and the source should invariably be indicated.
c) Where the documents provided are in a language other than English, an English translation should be provided.
d) The Questionnaire for environmental appraisal of thermal power projects as devised earlier by the Ministry shall also be filled and submitted.
In addition, information on the following may also be incorporated in the EIA report.
1). Is the project intended to have CDM-intent?
i) If not, then reasons thereof?
ii) If yes, then details under mentioned to be provided:
a) Has PIN (Project Idea Note) {or PCN (Project Concept Note)} been submitted to the NCA? (National CDM Authority) in the MoEF?
b) If not, then by when is that expected?
c) Has PDD (Project Design Document) been prepared?
d) What is the Carbon intensity from your electricity generation projected (i.e. CO2 Tons/MWH or Kg/KWH)
e) Amount of CO2 in Tons/year expected to be reduced from the baseline data available on the CEA’s web-site (www.cea.nic.in)
2. Notwithstanding 1(i) above, data on (d) & (e) above to be worked out and reported.
The Committee informed the project proponent that after preparing the draft EIA (as per the generic structure prescribed in Appendix-III of the EIA Notification, 2006) covering the above mentioned issues, the same shall be submitted to the SPCB for conducting the public hearing as per procedure of EIA notification 2006. The issues which emerge during public hearing shall be further incorporated in the Draft EIA/EMP report. The final EIA/EMP report along with public hearing report and the requisite documents (including written objections, if any) shall be submitted to the Ministry for appraisal by the Expert Appraisal Committee for consideration of awarding environmental clearance under the provisions of Environmental Impact Assessment notification dated September 14, 2006.
2.28 1x660 MW Coal Based Super Critical TPP of M/s Corporate Power Ltd. at Village Bhusar, in Chandwa Block, in Latehar Distt., in Jharkhand - reg. TOR.
The proposal was considered for determination of terms of reference for undertaking EIA/EMP study as per provisions of EIA notification 2006. The project proponent along with its consultant viz. M/s Green Circle Inc., Vadodara gave a presentation and provided the following information:
The proposal is for setting of 1x660 MW Coal Based TPP at village Bhusar, in Chandwa Block, in Latehar Distt., in Jharkhand. Land requirement will be 303 acres, which is a barren land. The co-ordinates of the proposed site will be at Latitude 230 41’ 7.32” to 230 41’37.42” N and Longitude 840 45’41.88” to 840 46’ 7.7” E. Coal requirement will be 3.1 MTPA. Area requirement for ash pond/dyke will be 50 acres. Water requirement will be 2200 cum/hour, which will be obtained from Damodar River through a pipeline over a distance of 30.5 km from the project site. There are no National parks, Wildlife sanctuaries, Heritage sites, Tiger/Biosphere reserves etc. within 10 km of the site.
Based on the information provided and presentation made the Committee prescribed the following specific TORs for undertaking detailed EIA study and preparation of EMP.
i) Vision document specifying prospective long term plan of the site shall be formulated and submitted.
ii) Executive summary of the project indicating relevant details along with photograph of site shall be provided and issues raised in public hearing along with action plan to address the same shall be provided in tabular form including requisite allocation of funds.
iii) Conformity of the site with the prescribed guidelines in terms of distance of 500 m from HFL of the river, highways, railway line shall be shown on the study area map.
iv) The project proponent shall provide confirmed GPS readings of plant boundary.
v) No water body/nallah (if any) shall be touched. It shall also be ensured that atleast 100 m distance is kept away from the HFL of the nallah/ river (if any) passing in and around the proposed site.
vi) Detailed hydro-geological study of the area shall be conducted from an institute/ organisation of repute to assess impact of on ground and surface water regime. Specific mitigation measures shall be spelt out and action plan for implementation of the same shall be provided.
vii) Detailed source sustainability study of water requirement shall be carried out by an institute of repute. The study shall also specify the source of water for meeting the requirement during lean season and proposed plan of action.
viii) Study on the impact on river/reservoir/marine ecology (as applicable) due to the proposed discharge of treated wastewater into the river/creek shall be carried out and submitted alongwith the EIA Report.
ix) Ash pond shall be shifted away as far as possible from any surface water source and its location shall be chosen taking into consideration the elevation and water drainage pattern in the area. The coordinates of the proposed site including location of ash pond shall be submitted along with topo sheet.
x) Action plan for identification of local employable youth for training in skills relevant to the project for eventual employment in the project itself shall be formulated and details submitted along with EIA/EMP Report.
xi) Layout of the plant indicating break-up of plant, green belt, infrastructure, roads etc. shall be provided.
xii) Land requirement for the project shall be optimized. Item wise break up of land requirement and its availability to be furnished. It should also include land to be acquired, if any, for coal transportation system as well as for laying of pipeline including ROW. It may clearly be confirmed that the land including ROW is free of all encumbrances. The issues relating to land acquisition and R&R should be clearly discussed in the EIA report.
xiii) Land use based on satellite imagery or authenticated map indicating drainage, cropping pattern, water bodies (rivers, nallahs, ponds etc.), location of nearest villages, creeks, rivers, reservoirs, national parks, wildlife sanctuaries, tiger reserves, biosphere reserves, heritage sites etc in the study area shall be provided. Location of any National Park, Sanctuary, Elephant/Tiger Reserve (existing as well as proposed), migratory routes, if any, within 10 km of the project site shall be specified and marked on the map duly authenticated by the Chief Wildlife Warden.
xiv) Study on land-use pattern in the study area shall be carried out, including identification of common property resources available for conversion into productive land and action plan for abatement and compensation for damage to agricultural land/ common property land (if any) in the nearby villages, due to proposed project shall be prepared.
xv) Details of acquisition of tribal land and compliance to tribal rights as per existing Central and State legislations as may be applicable shall be submitted.
xvi) Detailed socio-economic study shall be carried out for the study area comprising of 10 km from the plant site.
xvii) CSR component shall be prepared based on need based assessment study to be carried out in the study area. Income generating measures which can help in upliftment of poorer sections of society which is consistent with the traditional skills of the people shall be identified. The programme can include activities such as development of fodder farm, fruit bearing orchards, vocational training etc. In addition, vocational training for individuals shall be imparted so that poorer sections of society can take up self employment and jobs. Separate budget for community development activities and income generating programmes shall be specified. Financial allocation to be taken up under CSR shall be specified.
xviii) While formulating CSR schemes it shall be ensured that an in-built monitoring mechanism for the schemes identified is in place and mechanism for conducting annual social audit from the nearest government institute of repute in the region shall be prepared. The project proponent shall also provide plan for the status of implementation of the scheme from time to time.
xix) Possibility for adopting nearest three villages shall be explored and details of civic amenities such as roads, drinking water, power etc proposed to be provided at the company’s expenses shall be submitted.
xx) Location of intake and outfall points (with coordinates) should be given. These locations should be selected based on detailed modeling studies. Details of modeling and the results obtained there from should be furnished. It may be kept in view that the intake and outfall points are away from the mangroves or other eco sensitive areas. A river/marine ecology study (as applicable) should also be done to assess impact on river/marine ecology. River/Marine impact of such activities should be clearly brought out in the EIA report.
xxi) Topography of the area should be given clearly indicating whether the site requires any filling. If so, details of filling, quantity of fill material required, its source, transportation etc. should be given.
xxii) One complete season AAQ data (except monsoon) to be given along with the dates of monitoring. The parameters to be covered shall include RSPM(PM10,PM2.5), SO2, NOx, Hg and Ozone (ground level). The location of the monitoring stations should be so decided so as to take into consideration the pre-dominant downwind direction, population zone and sensitive receptors including reserved forests. There should be at least one monitoring station each in the upwind and in the pre dominant downwind direction at a location where maximum ground level concentration is likely to occur.
xxiii) Cumulative impact assessment on ambient air quality due to proposed plant and others (including existing as well as other proposed source of emission) shall be carried out and result submitted in the EIA Report. Mitigative measures as necessary shall be clearly spelt out.
xxiv) Impact of the project on the AAQ of the area. Details of the model used and the input data used for modelling should also be provided. The air quality contours may be plotted on a location map showing the location of project site, habitation nearby, sensitive receptors, if any. The wind roses should also be shown on this map.
xxv) Fuel analysis shall be provided. Details of auxillary fuel, if any including its quantity, quality, storage etc should also be given.
xxvi) Quantity of fuel required, its source and transportation route and mode and a confirmed fuel linkage documents shall be provided.
xxvii) Source of water and its availability. Commitment regarding availability of requisite quantity of water from the competent authority shall be provided along with firm linkage.
xxviii) Detailed plan for carrying out rainwater harvesting and proposed utilisation in the plant shall be provided.
xxix) Feasibility of zero discharge shall be examined and detailed justification shall be submitted if in case the same is not possible. Proposed discharge (if any), its quantity, quality and point of discharge, users downstream etc. shall be provided.
xxx) Optimization of COC for water conservation. Other water conservation measures proposed in the project should also be given. Quantity of water requirement for the project should be optimized.
xxxi) Details of water balance taking into account reuse and re-circulation of effluents.
xxxii) Detailed plan for conducting monitoring of water quality regularly and mechanism for maintenance of records shall be formulated. Details of methodology and identification of monitoring points (between the plant and drainage in the direction of flow of surface / ground water) shall be submitted. It shall be ensured that parameter to be monitored also include heavy metals in surface and ground water.
xxxiii) Details regarding infrastructure facilities such as sanitation, fuel, restroom, medical facilities, safety during construction phase etc. to be provided to the labour force during construction as well as to the casual workers including truck drivers during operation phase.
xxxiv) EMP to mitigate the adverse impacts due to the project along with item wise cost of its implementation.
xxxv) A Disaster Management Plan along with risk assessment study including fire and explosion issues due to storage and use of fuel should be carried out. It should take into account the maximum inventory of storage at site at any point in time. The risk contours should be plotted on the plant layout map clearly showing which of the proposed activities would be affected in case of an accident taking place. Based on the same, proposed safeguard measures should be provided. Measures to guard against fire hazards should also be provided.
xxxvi) Detailed plan for raising Green belt of 100 m width on the western side of the plant and 50m wide on the other sides and consisting of at least 3 tiers around plant boundary with tree density not less than 2500 trees per ha and survival rate atleast 75% shall be submitted.
xxxvii) Details of litigation pending or otherwise with respect to project in any courts, tribunal etc. shall be provided.
Besides all the above, the following general points will be followed:-
a) All documents to be properly referenced with index, page numbers and continuous page numbering.
b) Where data is presented in the report especially in table, the period in which the data was collected and the source should invariably be indicated.
c) Where the documents provided are in a language other than English, an English translation should be provided.
d) The Questionnaire for environmental appraisal of thermal power projects as devised earlier by the Ministry shall also be filled and submitted.
In addition, information on the following may also be incorporated in the EIA report.
1). Is the project intended to have CDM-intent?
i) If not, then reasons thereof?
ii) If yes, then details under mentioned to be provided:
a) Has PIN (Project Idea Note) {or PCN (Project Concept Note)} been submitted to the NCA? (National CDM Authority) in the MoEF?
b) If not, then by when is that expected?
c) Has PDD (Project Design Document) been prepared?
d) What is the Carbon intensity from your electricity generation projected (i.e. CO2 Tons/MWH or Kg/KWH)
e) Amount of CO2 in Tons/year expected to be reduced from the baseline data available on the CEA’s web-site (www.cea.nic.in)
2. Notwithstanding 1(i) above, data on (d) & (e) above to be worked out and reported.
The Committee informed the project proponent that after preparing the draft EIA (as per the generic structure prescribed in Appendix-III of the EIA Notification, 2006) covering the above mentioned issues, the same shall be submitted to the SPCB for conducting the public hearing as per procedure of EIA notification 2006. The issues which emerge during public hearing shall be further incorporated in the Draft EIA/EMP report. The final EIA/EMP report along with public hearing report and the requisite documents (including written objections, if any) shall be submitted to the Ministry for appraisal by the Expert Appraisal Committee for consideration of awarding environmental clearance under the provisions of Environmental Impact Assessment notification dated September 14, 2006.
2.29 3x660 MW Coal Based Super Critical TPP of M/s Regal Energy Ltd. at Village Kurur, in Wadsa Tehsil, in Gadchiroli Distt., in Maharashtra - reg. TOR.
The proposal was considered for determination of terms of reference for undertaking EIA/EMP study as per provisions of EIA notification 2006. The project proponent along with its consultant gave a presentation and provided the following information:
The proposal is for setting of 3x660 MW Coal Based TPP at Village Kurur, in Wadsa Tehsil, in Gadchiroli Distt., in Maharashtra. Land requirement will be 1000 acres, which is mostly non-irrigated agricultural land including some barren land. Coal requirement will be 10.5 MTPA. Water requirement will be 67.6 MCM which will be obtained from Waingaga River which flows at 2 Km in the West. River Garhvi flows at 7 Km in the East. There are several reserve forests in the vicinity, the nearest being Armori R.F at 0.6 Km. There are no National parks, Wildlife sanctuaries, Heritage sites, Tiger/Biosphere reserves etc. within 10 km of the site.
The discussions were also held regarding the Rampur site. The Committee observed that there are several reserve forest nearest being Armori reserve forest at 0.6 km distance. The railway line to be constructed for railway siding would have to pass through reserve forest which is not desirable. There are three water bodies viz. Wainganga River, Garhvi Nadi and Khobragarhi Nadi within 10 km distance of Rampur site.
In view of the above, the Committee decided that the site no. 3 at Village Kurur, Tehsil Wadsa in Gadchiroli District, Maharashtra.
Based on the information provided and presentation made the Committee prescribed the following specific TORs for undertaking detailed EIA study and preparation of EMP.
i) Primary survey of fauna and flora shall be carried out and data submitted along with authenticated list from the Office of the concerned Chief Wildlife Warden.
ii) A wildlife conservation plan shall be prepared in consultation with the Office of the Chief Wildlife Warden and duly vetted by the Office for implementation (as may be necessary).
iii) Vision document specifying prospective long term plan of the site shall be formulated and submitted.
iv) Executive summary of the project indicating relevant details along with photograph of site shall be provided and issues raised in public hearing along with action plan to address the same shall be provided in tabular form including requisite allocation of funds.
v) Conformity of the site with the prescribed guidelines in terms of distance of 500 m from HFL of the river, highways, railway line shall be shown on the study area map.
vi) The project proponent shall provide confirmed GPS readings of plant boundary.
vii) No water body/nallah (if any) shall be touched. It shall also be ensured that atleast 100 m distance is kept away from the HFL of the nallah/ river (if any) passing in and around the proposed site.
viii) Detailed hydro-geological study of the area shall be conducted from an institute/ organisation of repute to assess impact of on ground and surface water regime. Specific mitigation measures shall be spelt out and action plan for implementation of the same shall be provided.
ix) Detailed source sustainability study of water requirement shall be carried out by an institute of repute. The study shall also specify the source of water for meeting the requirement during lean season and proposed plan of action.
x) Study on the impact on river/reservoir/marine ecology (as applicable) due to the proposed discharge of treated wastewater into the river/creek shall be carried out and submitted alongwith the EIA Report.
xi) Ash pond shall be shifted away as far as possible from any surface water source and its location shall be chosen taking into consideration the elevation and water drainage pattern in the area. The coordinates of the proposed site including location of ash pond shall be submitted along with topo sheet.
xii) Action plan for identification of local employable youth for training in skills relevant to the project for eventual employment in the project itself shall be formulated and details submitted along with EIA/EMP Report.
xiii) Layout of the plant indicating break-up of plant, green belt, infrastructure, roads etc. shall be provided.
xiv) Land requirement for the project shall be optimized. Item wise break up of land requirement and its availability to be furnished. It should also include land to be acquired, if any, for coal transportation system as well as for laying of pipeline including ROW. It may clearly be confirmed that the land including ROW is free of all encumbrances. The issues relating to land acquisition and R&R should be clearly discussed in the EIA report.
xv) Land use based on satellite imagery or authenticated map indicating drainage, cropping pattern, water bodies (rivers, nallahs, ponds etc.), location of nearest villages, creeks, rivers, reservoirs, national parks, wildlife sanctuaries, tiger reserves, biosphere reserves, heritage sites etc in the study area shall be provided. Location of any National Park, Sanctuary, Elephant/Tiger Reserve (existing as well as proposed), migratory routes, if any, within 10 km of the project site shall be specified and marked on the map duly authenticated by the Chief Wildlife Warden.
xvi) Study on land-use pattern in the study area shall be carried out, including identification of common property resources available for conversion into productive land and action plan for abatement and compensation for damage to agricultural land/ common property land (if any) in the nearby villages, due to proposed project shall be prepared.
xvii) Detailed socio-economic study shall be carried out for the study area comprising of 10 km from the plant site.
xviii) CSR component shall be prepared based on need based assessment study to be carried out in the study area. Income generating measures which can help in upliftment of poorer sections of society which is consistent with the traditional skills of the people shall be identified. The programme can include activities such as development of fodder farm, fruit bearing orchards, vocational training etc. In addition, vocational training for individuals shall be imparted so that poorer sections of society can take up self employment and jobs. Separate budget for community development activities and income generating programmes shall be specified. Financial allocation to be taken up under CSR shall be specified.
xix) While formulating CSR schemes it shall be ensured that an in-built monitoring mechanism for the schemes identified is in place and mechanism for conducting annual social audit from the nearest government institute of repute in the region shall be prepared. The project proponent shall also provide plan for the status of implementation of the scheme from time to time.
xx) Possibility for adopting nearest three villages shall be explored and details of civic amenities such as roads, drinking water, power etc proposed to be provided at the company’s expenses shall be submitted.
xxi) Location of intake and outfall points (with coordinates) should be given. These locations should be selected based on detailed modeling studies. Details of modeling and the results obtained there from should be furnished. It may be kept in view that the intake and outfall points are away from the mangroves or other eco sensitive areas. A river/marine ecology study (as applicable) should also be done to assess impact on river/marine ecology. River/Marine impact of such activities should be clearly brought out in the EIA report.
xxii) Topography of the area should be given clearly indicating whether the site requires any filling. If so, details of filling, quantity of fill material required, its source, transportation etc. should be given.
xxiii) One complete season AAQ data (except monsoon) to be given along with the dates of monitoring. The parameters to be covered shall include RSPM(PM10,PM2.5), SO2, NOx, Hg and Ozone (ground level). The location of the monitoring stations should be so decided so as to take into consideration the pre-dominant downwind direction, population zone and sensitive receptors including reserved forests. There should be at least one monitoring station each in the upwind and in the pre dominant downwind direction at a location where maximum ground level concentration is likely to occur.
xxiv) Cumulative impact assessment on ambient air quality due to proposed plant and others (including existing as well as other proposed source of emission) shall be carried out and result submitted in the EIA Report. Mitigative measures as necessary shall be clearly spelt out.
xxv) Impact of the project on the AAQ of the area. Details of the model used and the input data used for modelling should also be provided. The air quality contours may be plotted on a location map showing the location of project site, habitation nearby, sensitive receptors, if any. The wind roses should also be shown on this map.
xxvi) Fuel analysis shall be provided. Details of auxillary fuel, if any including its quantity, quality, storage etc should also be given.
xxvii) Quantity of fuel required, its source and transportation route and mode and a confirmed fuel linkage documents shall be provided.
xxviii) Source of water and its availability. Commitment regarding availability of requisite quantity of water from the competent authority shall be provided along with firm linkage.
xxix) Detailed plan for carrying out rainwater harvesting and proposed utilisation in the plant shall be provided.
xxx) Feasibility of zero discharge shall be examined and detailed justification shall be submitted if in case the same is not possible. Proposed discharge (if any), its quantity, quality and point of discharge, users downstream etc. shall be provided.
xxxi) Optimization of COC for water conservation. Other water conservation measures proposed in the project should also be given. Quantity of water requirement for the project should be optimized.
xxxii) Details of water balance taking into account reuse and re-circulation of effluents.
xxxiii) Detailed plan for conducting monitoring of water quality regularly and mechanism for maintenance of records shall be formulated. Details of methodology and identification of monitoring points (between the plant and drainage in the direction of flow of surface / ground water) shall be submitted. It shall be ensured that parameter to be monitored also include heavy metals in surface and ground water.
xxxiv) Details regarding infrastructure facilities such as sanitation, fuel, restroom, medical facilities, safety during construction phase etc. to be provided to the labour force during construction as well as to the casual workers including truck drivers during operation phase.
xxxv) EMP to mitigate the adverse impacts due to the project along with item wise cost of its implementation.
xxxvi) A Disaster Management Plan along with risk assessment study including fire and explosion issues due to storage and use of fuel should be carried out. It should take into account the maximum inventory of storage at site at any point in time. The risk contours should be plotted on the plant layout map clearly showing which of the proposed activities would be affected in case of an accident taking place. Based on the same, proposed safeguard measures should be provided. Measures to guard against fire hazards should also be provided.
xxxvii) Detailed plan for raising Green belt of 100 m width on the western side of the plant and 50m wide on the other sides and consisting of at least 3 tiers around plant boundary with tree density not less than 2500 trees per ha and survival rate atleast 75% shall be submitted.
xxxviii) Details of litigation pending or otherwise with respect to project in any courts, tribunal etc. shall be provided.
Besides all the above, the following general points will be followed:-
a) All documents to be properly referenced with index, page numbers and continuous page numbering.
b) Where data is presented in the report especially in table, the period in which the data was collected and the source should invariably be indicated.
c) Where the documents provided are in a language other than English, an English translation should be provided.
d) The Questionnaire for environmental appraisal of thermal power projects as devised earlier by the Ministry shall also be filled and submitted.
In addition, information on the following may also be incorporated in the EIA report.
1). Is the project intended to have CDM-intent?
i) If not, then reasons thereof?
ii) If yes, then details under mentioned to be provided:
a) Has PIN (Project Idea Note) {or PCN (Project Concept Note)} been submitted to the NCA? (National CDM Authority) in the MoEF?
b) If not, then by when is that expected?
c) Has PDD (Project Design Document) been prepared?
d) What is the Carbon intensity from your electricity generation projected (i.e. CO2 Tons/MWH or Kg/KWH)
e) Amount of CO2 in Tons/year expected to be reduced from the baseline data available on the CEA’s web-site (www.cea.nic.in)
2. Notwithstanding 1(i) above, data on (d) & (e) above to be worked out and reported.
The Committee informed the project proponent that after preparing the draft EIA (as per the generic structure prescribed in Appendix-III of the EIA Notification, 2006) covering the above mentioned issues, the same shall be submitted to the SPCB for conducting the public hearing as per procedure of EIA notification 2006. The issues which emerge during public hearing shall be further incorporated in the Draft EIA/EMP report. The final EIA/EMP report along with public hearing report and the requisite documents (including written objections, if any) shall be submitted to the Ministry for appraisal by the Expert Appraisal Committee for consideration of awarding environmental clearance under the provisions of Environmental Impact Assessment notification dated September 14, 2006.
2.30 4x660 MW Coal Based TPP of M/s Ellora Paper Mills Ltd. at village Dewada, in Mohadi Tehsil, in Bhandra & Gondia Distt., in Maharastra. - reg. TOR.
The proposal was considered for determination of terms of reference for undertaking EIA/EMP study as per provisions of EIA notification 2006. The project proponent along with its consultant viz. M/s Green Circle Inc., Vadodara gave a presentation and provided the following information:
The proposal is for setting of 4x660 MW Coal Based TPP at Village Dewada, in Mohadi Tehsil, in Bhandra & Gondia Distt., in Maharastra. The TPP is proposed near the existing paper Mill which has been closed down a year back. Colony for staff of TPP is proposed in the Paper Mill area. Land requirement will be 1215 acres, out of which 974.74 acres is single crop agricultural land and 115.53 acres is waste land. The co-ordinates of the proposed site will be at Latitude 21019’ 10” to 210 20’30” N and Longitude 790 48’42” to 79050’10” E. Coal requirement will be 14.0 MTPA. Area requirement for ash pond/dyke will be 140 acres. Water requirement will be 85 MCM, which will be obtained from Wainganga river through a pipeline over a distance of 25 km from the project site. There are no National parks, Wildlife sanctuaries, Heritage sites, Tiger/Biosphere reserves etc. within 10 km of the site. Mangroves are present within 10 km of the site.
The Committee noted that the site chosen even though partly industrial area as informed by the project proponent seem to be fertile agricultural land with marshes and mangroves in the vicinity. In the absence of adequate details of the site, the Committee therefore expressed its inability to recommend the site. The Committee therefore decided that the project proponent shall furnish details of the site (including information such as type of industries and the status of the industrial area; status of mangroves present nearby etc.) before their case can be considered. The Committee further decided that the project proponent shall also come up with two suitable alternative sites for re-consideration of their case. Accordingly the matter was deferred.
2.31 2x660 MW Coal Based TPP of M/s Sew Thermal Power Corporation Ltd. at villages Barodamall, Kurmithel, Para, Barodaraiyyat and Hudmal, in Ghansore Taluk, in Seoni Distt., in Madhya pradesh. - reg. TOR.
The proposal was considered for determination of terms of reference for undertaking EIA/EMP study as per provisions of EIA notification 2006. The project proponent along with its consultant viz. M/s Anacon Laboratories Pvt. Ltd. Nagpur gave a presentation and provided the following information:
The proposal is for setting of 2x660 MW Coal Based TPP at villages Barodamall, Kurmithel, Para, Barodaraiyyat and Hudmal, in Ghansore Taluk, in Seoni Distt., in Madhya pradesh. Land requirement will be 303.5 hectare, out of which 34.16 ha is Govt. land and 179.84 ha is private un-irrigated single crop agricultural land and other 75.24 ha is Adivasi land. The co-ordinates of the proposed site will be at Latitude 22040’41” to 22041’31” N and Longitude 79051’24” to 79052’30” E. Coal requirement will be 6.50 MTPA. Water requirement will be 40 MCM, which will be obtained from Narmada river(Bargi Reservoir) through a pipeline over a distance of 19 km from the project site. There are no National parks, Wildlife sanctuaries, Heritage sites, Tiger/Biosphere reserves etc. within 10 km of the site.
Based on the information provided and presentation made the Committee prescribed the following specific TORs for undertaking detailed EIA study and preparation of EMP.
i) Vision document specifying prospective long term plan of the site shall be formulated and submitted.
ii) Executive summary of the project indicating relevant details along with photograph of site shall be provided and issues raised in public hearing along with action plan to address the same shall be provided in tabular form including requisite allocation of funds.
iii) Conformity of the site with the prescribed guidelines in terms of distance of 500 m from HFL of the river, highways, railway line shall be shown on the study area map.
iv) The project proponent shall provide confirmed GPS readings of plant boundary.
v) No water body/nallah (if any) shall be touched. It shall also be ensured that atleast 100 m distance is kept away from the HFL of the nallah/ river (if any) passing in and around the proposed site.
vi) Detailed hydro-geological study of the area shall be conducted from an institute/ organisation of repute to assess impact of on ground and surface water regime. Specific mitigation measures shall be spelt out and action plan for implementation of the same shall be provided.
vii) Detailed source sustainability study of water requirement shall be carried out by an institute of repute. The study shall also specify the source of water for meeting the requirement during lean season and proposed plan of action.
viii) Study on the impact on river/reservoir/marine ecology (as applicable) due to the proposed discharge of treated wastewater into the river/creek shall be carried out and submitted alongwith the EIA Report.
ix) Ash pond shall be shifted away as far as possible from any surface water source and its location shall be chosen taking into consideration the elevation and water drainage pattern in the area. The coordinates of the proposed site including location of ash pond shall be submitted along with topo sheet.
x) Action plan for identification of local employable youth for training in skills relevant to the project for eventual employment in the project itself shall be formulated and details submitted along with EIA/EMP Report.
xi) Layout of the plant indicating break-up of plant, green belt, infrastructure, roads etc. shall be provided.
xii) Land requirement for the project shall be optimized. Item wise break up of land requirement and its availability to be furnished. It should also include land to be acquired, if any, for coal transportation system as well as for laying of pipeline including ROW. It may clearly be confirmed that the land including ROW is free of all encumbrances. The issues relating to land acquisition and R&R should be clearly discussed in the EIA report.
xiii) Land use based on satellite imagery or authenticated map indicating drainage, cropping pattern, water bodies (rivers, nallahs, ponds etc.), location of nearest villages, creeks, rivers, reservoirs, national parks, wildlife sanctuaries, tiger reserves, biosphere reserves, heritage sites etc in the study area shall be provided. Location of any National Park, Sanctuary, Elephant/Tiger Reserve (existing as well as proposed), migratory routes, if any, within 10 km of the project site shall be specified and marked on the map duly authenticated by the Chief Wildlife Warden.
xiv) Study on land-use pattern in the study area shall be carried out, including identification of common property resources available for conversion into productive land and action plan for abatement and compensation for damage to agricultural land/ common property land (if any) in the nearby villages, due to proposed project shall be prepared.
xv) Details of acquisition of tribal land and compliance to tribal rights as per existing Central and State legislations as may be applicable shall be submitted.
xvi) Detailed socio-economic study shall be carried out for the study area comprising of 10 km from the plant site.
xvii) CSR component shall be prepared based on need based assessment study to be carried out in the study area. Income generating measures which can help in upliftment of poorer sections of society which is consistent with the traditional skills of the people shall be identified. The programme can include activities such as development of fodder farm, fruit bearing orchards, vocational training etc. In addition, vocational training for individuals shall be imparted so that poorer sections of society can take up self employment and jobs. Separate budget for community development activities and income generating programmes shall be specified. Financial allocation to be taken up under CSR shall be specified.
xviii) While formulating CSR schemes it shall be ensured that an in-built monitoring mechanism for the schemes identified is in place and mechanism for conducting annual social audit from the nearest government institute of repute in the region shall be prepared. The project proponent shall also provide plan for the status of implementation of the scheme from time to time.
xix) Possibility for adopting nearest three villages shall be explored and details of civic amenities such as roads, drinking water, power etc proposed to be provided at the company’s expenses shall be submitted.
xx) Location of intake and outfall points (with coordinates) should be given. These locations should be selected based on detailed modeling studies. Details of modeling and the results obtained there from should be furnished. It may be kept in view that the intake and outfall points are away from the mangroves or other eco sensitive areas. A river/marine ecology study (as applicable) should also be done to assess impact on river/marine ecology. River/Marine impact of such activities should be clearly brought out in the EIA report.
xxi) Topography of the area should be given clearly indicating whether the site requires any filling. If so, details of filling, quantity of fill material required, its source, transportation etc. should be given.
xxii) One complete season AAQ data (except monsoon) to be given along with the dates of monitoring. The parameters to be covered shall include RSPM(PM10,PM2.5), SO2, NOx, Hg and Ozone (ground level). The location of the monitoring stations should be so decided so as to take into consideration the pre-dominant downwind direction, population zone and sensitive receptors including reserved forests. There should be at least one monitoring station each in the upwind and in the pre dominant downwind direction at a location where maximum ground level concentration is likely to occur.
xxiii) Cumulative impact assessment on ambient air quality due to proposed plant and others (including existing as well as other proposed source of emission) shall be carried out and result submitted in the EIA Report. Mitigative measures as necessary shall be clearly spelt out.
xxiv) Impact of the project on the AAQ of the area. Details of the model used and the input data used for modelling should also be provided. The air quality contours may be plotted on a location map showing the location of project site, habitation nearby, sensitive receptors, if any. The wind roses should also be shown on this map.
xxv) Fuel analysis shall be provided. Details of auxillary fuel, if any including its quantity, quality, storage etc should also be given.
xxvi) Quantity of fuel required, its source and transportation route and mode and a confirmed fuel linkage documents shall be provided.
xxvii) Source of water and its availability. Commitment regarding availability of requisite quantity of water from the competent authority shall be provided along with firm linkage.
xxviii) Detailed plan for carrying out rainwater harvesting and proposed utilisation in the plant shall be provided.
xxix) Feasibility of zero discharge shall be examined and detailed justification shall be submitted if in case the same is not possible. Proposed discharge (if any), its quantity, quality and point of discharge, users downstream etc. shall be provided.
xxx) Optimization of COC for water conservation. Other water conservation measures proposed in the project should also be given. Quantity of water requirement for the project should be optimized.
xxxi) Details of water balance taking into account reuse and re-circulation of effluents.
xxxii) Detailed plan for conducting monitoring of water quality regularly and mechanism for maintenance of records shall be formulated. Details of methodology and identification of monitoring points (between the plant and drainage in the direction of flow of surface / ground water) shall be submitted. It shall be ensured that parameter to be monitored also include heavy metals in surface and ground water.
xxxiii) Details regarding infrastructure facilities such as sanitation, fuel, restroom, medical facilities, safety during construction phase etc. to be provided to the labour force during construction as well as to the casual workers including truck drivers during operation phase.
xxxiv) EMP to mitigate the adverse impacts due to the project along with item wise cost of its implementation.
xxxv) A Disaster Management Plan along with risk assessment study including fire and explosion issues due to storage and use of fuel should be carried out. It should take into account the maximum inventory of storage at site at any point in time. The risk contours should be plotted on the plant layout map clearly showing which of the proposed activities would be affected in case of an accident taking place. Based on the same, proposed safeguard measures should be provided. Measures to guard against fire hazards should also be provided.
xxxvi) Detailed plan for raising Green belt of 100 m width on the western side of the plant and 50m wide on the other sides and consisting of at least 3 tiers around plant boundary with tree density not less than 2500 trees per ha and survival rate atleast 75% shall be submitted.
xxxvii) Details of litigation pending or otherwise with respect to project in any courts, tribunal etc. shall be provided.
Besides all the above, the following general points will be followed:-
a) All documents to be properly referenced with index, page numbers and continuous page numbering.
b) Where data is presented in the report especially in table, the period in which the data was collected and the source should invariably be indicated.
c) Where the documents provided are in a language other than English, an English translation should be provided.
d) The Questionnaire for environmental appraisal of thermal power projects as devised earlier by the Ministry shall also be filled and submitted.
In addition, information on the following may also be incorporated in the EIA report.
1). Is the project intended to have CDM-intent?
i) If not, then reasons thereof?
ii) If yes, then details under mentioned to be provided:
a) Has PIN (Project Idea Note) {or PCN (Project Concept Note)} been submitted to the NCA? (National CDM Authority) in the MoEF?
b) If not, then by when is that expected?
c) Has PDD (Project Design Document) been prepared?
d) What is the Carbon intensity from your electricity generation projected (i.e. CO2 Tons/MWH or Kg/KWH)
e) Amount of CO2 in Tons/year expected to be reduced from the baseline data available on the CEA’s web-site (www.cea.nic.in)
2. Notwithstanding 1(i) above, data on (d) & (e) above to be worked out and reported.
The Committee informed the project proponent that after preparing the draft EIA (as per the generic structure prescribed in Appendix-III of the EIA Notification, 2006) covering the above mentioned issues, the same shall be submitted to the SPCB for conducting the public hearing as per procedure of EIA notification 2006. The issues which emerge during public hearing shall be further incorporated in the Draft EIA/EMP report. The final EIA/EMP report along with public hearing report and the requisite documents (including written objections, if any) shall be submitted to the Ministry for appraisal by the Expert Appraisal Committee for consideration of awarding environmental clearance under the provisions of Environmental Impact Assessment notification dated September 14, 2006.
2.32 Expansion addition of 1200 MW Gas based Combined Cycle Power Project of M/s Reliance Infrastructure Limited at Samalkot Power Station, in IDA Peddapuram Industrial Estate, in East Godavari Distt., in Andhra Pradesh.- reg. TOR .
The proposal was placed for consideration for environmental clearance. A presentation was also made by the project proponent gave a presentation and provided the following information:
The proposal is for expansion by addition of 1200 MW Gas based Combined Cycle Power Plant at Samalkot Power Station, in IDA Peddapuram Industrial Estate, in East Godavari Distt., in Andhra Pradesh. Environmental clearance for 220 MW was accorded on 11.11.1998 and for 1200 MW (Phase-I) on 28.05.2010. No additional land will be required for the proposed expansion plant. The co-ordinates of the proposed site will be at ratio of Latitude and Lognitude 17002’37” N to 82008’30” E. Natural gas requirement will be 4.0 MMSCM which will be sourced from RNRL. Water requirement will be 45 MLD, which will be obatained from Dowlaiswaram Barrage at Godavari river through existing pipeline from Yeleru drain. There are no National park, wild life sanctuary, Biosphere/ tiger /Elephant reserves, Heritage sites etc within 10km of the project boundary.
The Committee decided that since the present proposal is an expansion case and previous phase was accorded environmental clearance only on 28.05.2010 and being in notified industrial area, the present proposal may be exempted from public hearing.
Based on the information provided and presentation made the Committee prescribed the following specific TORs for undertaking detailed EIA study and preparation of EMP.
i) Status of compliance to the conditions stipulated in the environmental clearance accorded for the previous units shall be submitted.
ii) Vision document specifying prospective long term plan of the site shall be formulated and submitted.
iii) Executive summary of the project indicating relevant details along with photograph of site shall be provided and issues raised in public hearing along with action plan to address the same shall be provided in tabular form including requisite allocation of funds.
iv) Conformity of the site with the prescribed guidelines in terms of distance of 500 m from HFL of the river, highways, railway line shall be shown on the study area map.
v) The project proponent shall provide confirmed GPS readings of plant boundary.
vi) No water body/nallah (if any) shall be touched. It shall also be ensured that atleast 100 m distance is kept away from the HFL of the nallah/ river (if any) passing in and around the proposed site.
vii) Hydro-geological study (including sustainability study during lean season) of the area shall be conducted from an institute/ organisation of repute to assess impact of water regime in the area. Specific mitigation measures shall be spelt out and action plan for implementation of the same shall be provided.
viii) Action plan for identification of local employable youth for training in skills relevant to the project for eventual employment in the project itself shall be formulated.
ix) Layout of the plant indicating break-up of plant, green belt, infrastructure, roads etc. shall be provided.
x) Land requirement for the project shall be optimized. Item wise break up of land requirement and its availability to be furnished. It should also include land to be acquired, if any, for fuel transportation system as well as for laying of pipeline including ROW. It may clearly be confirmed that the land including ROW is free of all encumbrances. The issues relating to land acquisition and R&R should be clearly discussed in the EIA report.
xi) Land use based on satellite imagery or authenticated map indicating drainage, cropping pattern, water bodies (rivers, nallahs, ponds etc.), location of nearest villages, creeks, rivers, reservoirs, national parks, wildlife sanctuaries, tiger reserves, biosphere reserves, heritage sites etc (as applicable) in the study area shall be provided. Location of any National Park, Sanctuary, Elephant/Tiger Reserve (existing as well as proposed), migratory routes, if any, within 10 km of the project site shall be specified and marked on the map duly authenticated by the Chief Wildlife Warden.
xii) Study on land-use pattern in the study area shall be carried out, including identification of common property resources available for conversion into productive land and action plan for abatement and compensation for damage to agricultural land/ common property land (if any) in the nearby villages, due to proposed project shall be prepared.
xiii) Detailed socio-economic study shall be carried out for the study area comprising of 10 km from the plant site.
xiv) CSR component shall be prepared based on need based assessment study to be carried out in the study area. Income generating measures which can help in upliftment of poor section of society especially SCs/STs which is consistent with the traditional skills of the people shall be identified. The programme can include activities such as development of fodder farm, fruit bearing orchards, vocational training etc. In addition, vocational training for individuals shall be imparted so that poor section of society can take up self employment and jobs. Separate budget for community development activities and income generating programmes shall be specified. Financial allocation to be taken up under CSR shall be specified.
xv) While formulating CSR schemes it shall be ensured that an in-built monitoring mechanism for the schemes identified is in place and mechanism for conducting annual social audit from the nearest government institute of repute in the region shall be prepared. The project proponent shall also provide plan for the status of implementation of the scheme from time to time.
xvi) Possibility for adopting nearest three villages shall be explored and details of civic amenities such as roads, drinking water, power etc proposed to be provided at the company’s expenses shall be submitted.
xvii) Topography of the area should be given clearly indicating whether the site requires any filling. If so, details of filling, quantity of fill material required, its source, transportation etc. should be given.
xviii) One complete season AAQ data (except monsoon) to be given along with the dates of monitoring. The parameters to be covered shall include SPM, RSPM(PM10,PM2.5), SO2, NOx, Hg and Ozone (ground level). The location of the monitoring stations should be so decided so as to take into consideration the pre-dominant downwind direction, population zone and sensitive receptors including reserved forests. There should be at least one monitoring station each in the upwind and in the pre dominant downwind direction at a location where maximum ground level concentration is likely to occur.
xix) Cumulative impact assessment on ambient air quality due to proposed plant and others (including existing as well as other proposed source of emission) shall be carried out and result submitted in the EIA Report. Mitigative measures as necessary shall be clearly spelt out.
xx) Impact of the project on the AAQ of the area. Details of the model used and the input data used for modelling should also be provided. The air quality contours may be plotted on a location map showing the location of project site, habitation nearby, sensitive receptors, if any. The wind roses should also be shown on this map.
xxi) Fuel analysis shall be provided. Details of auxillary fuel, if any including its quantity, quality, storage etc should also be given.
xxii) Quantity of fuel required, its source and transportation route and mode and a confirmed fuel linkage documents shall be provided.
xxiii) Detailed plan for carrying out rainwater harvesting and proposed utilisation in the plant shall be provided.
xxiv) Feasibility of zero discharge shall be examined and detailed justification shall be submitted if in case the same is not possible. Proposed discharge (if any), its quantity, quality and point of discharge, users downstream etc. shall be provided.
xxv) Optimization of COC for water conservation. Other water conservation measures proposed in the project should also be given. Quantity of water requirement for the project should be optimized.
xxvi) Details of water balance taking into account reuse and re-circulation of effluents.
xxvii) Detailed plan for conducting monitoring of water quality regularly and mechanism for maintenance of records shall be formulated. Details of methodology and identification of monitoring points (between the plant and drainage in the direction of flow of surface / ground water) shall be submitted. It shall be ensured that parameter to be monitored also include heavy metals in surface and ground water.
xxviii) Details regarding infrastructure facilities such as sanitation, fuel, restroom, medical facilities, safety during construction phase etc. to be provided to the labour force during construction as well as to the casual workers including truck drivers during operation phase.
xxix) EMP to mitigate the adverse impacts due to the project along with item wise cost of its implementation.
xxx) A Disaster Management Plan along with risk assessment study including fire and explosion issues due to storage and use of fuel should be carried out. It should take into account the maximum inventory of storage at site at any point in time. The risk contours should be plotted on the plant layout map clearly showing which of the proposed activities would be affected in case of an accident taking place. Based on the same, proposed safeguard measures should be provided. Measures to guard against fire hazards should also be provided.
xxxi) Detailed plan for raising Green belt of 50 m width and consisting of at least 3 tiers around plant boundary with tree density not less than 2500 trees per ha and survival rate atleast 75% shall be submitted. If the same is not feasible detailed justification shall be submitted.
xxxii) Details of litigation pending or otherwise with respect to project in any courts, tribunal etc. shall be provided.
Besides all the above, the following general points will be followed:-
a) All documents to be properly referenced with index, page numbers and continuous page numbering.
b) Where data is presented in the report especially in table, the period in which the data was collected and the source should invariably be indicated.
c) Where the documents provided are in a language other than English, an English translation should be provided.
d) The Questionnaire for environmental appraisal of thermal power projects as devised earlier by the Ministry shall also be filled and submitted.
In addition, information on the following may also be incorporated in the EIA report.
1). Is the project intended to have CDM-intent?
i) If not, then reasons thereof?
ii) If yes, then details under mentioned to be provided:
a) Has PIN (Project Idea Note) {or PCN (Project Concept Note)} been submitted to the NCA? (National CDM Authority) in the MoEF?
b) If not, then by when is that expected?
c) Has PDD (Project Design Document) been prepared?
d) What is the Carbon intensity from your electricity generation projected (i.e019. CO2 Tons/MWH or Kg/KWH)
e) Amount of CO2 in Tons/year expected to be reduced from the baseline data available on the CEA’s web-site.
2. Notwithstanding 1(i) above, data on (d) & (e) above to be worked out and reported.
The Committee informed the project proponent that after preparing the EIA (as per the generic structure prescribed in Appendix-III of the EIA Notification, 2006) covering the above mentioned issues, the same shall be submitted to the Ministry for appraisal by the Expert Appraisal Committee for consideration of awarding environmental clearance under the provisions of Environmental Impact Assessment notification dated September 14, 2006.
2.33 Expansion of 50 MW Gas Based Co-Generation Plant of M/s Reliance Industries Ltd. at Kharadpada and Naroli, in the Union Territory of Dadra & Nagar Haveli - reg. TOR.
The project proponent have withdrawn the proposal and hence was not discussed.
2.34 2x660 MW Coal Based TPP of M/s Prakash Industries Limited. at Villages Bhada, Gound, Akaltari, Gaadapali and Udaiband, in Champa Taluk, in Jangir & Champa Distt., in Chhatitisgarh. - reg. TOR.
The proposal was considered for determination of terms of reference for undertaking EIA/EMP study as per provisions of EIA notification 2006. The project proponent along with its consultant viz. M/s Sun Consultancy and services gave a presentation and provided the following information:
The proposal is for setting of 2x660 MW Coal Based TPP at villages Bhada, Gound, Akaltari, Gaadapali and Udaiband, in Champa Taluk, in Jangir & Champa Distt., in Chhatitisgarh. Land requirement will be 1128 acres, out of which 792.30 acres is general land;199.47 acres is Adivasi land; 2.19 acres is Bhoodan land and other 133.95 acres is Government land. The co-ordinates of the proposed site will be at Latitude 21056’ 51.8” to 210 58’15.7” N and Longitude 820 39’15.7” to 82040’31.6” E. Coal requirement will be 6.08 MTPA. Area requirement for ash pond/dyke will be 110 acres. Water requirement will be 39.42 MCM which will be obtained from Hasdeo River through a pipeline over a distance of 2 km from the project site. There are no National parks, Wildlife sanctuaries, Heritage sites, Tiger/Biosphere reserves etc. within 10 km of the site.
Based on the information provided and presentation made the Committee prescribed the following specific TORs for undertaking detailed EIA study and preparation of EMP.
i) Vision document specifying prospective long term plan of the site shall be formulated and submitted.
ii) Executive summary of the project indicating relevant details along with photograph of site shall be provided and issues raised in public hearing along with action plan to address the same shall be provided in tabular form including requisite allocation of funds.
iii) Conformity of the site with the prescribed guidelines in terms of distance of 500 m from HFL of the river, highways, railway line shall be shown on the study area map.
iv) The project proponent shall provide confirmed GPS readings of plant boundary.
v) Details of acquisition of tribal land and compliance to tribal rights as per existing Central and State legislations as may be applicable shall be submitted.
vi) No water body/nallah (if any) shall be touched. It shall also be ensured that atleast 100 m distance is kept away from the HFL of the nallah (if any) passing in and around the proposed site.
vii) Hydro-geological study of the area shall be conducted from an institute/ organisation of repute to assess impact of on ground and surface water regime. Specific mitigation measures shall be spelt out and action plan for implementation of the same shall be provided.
viii) Source sustainability study of water requirement shall be carried out by an institute of repute. The study shall also specify the source of water for meeting the requirement during lean season and proposed plan of action.
ix) Study on the impact on catchment area of the river due to proposed withdrawal of such huge quantity of water for running the power plant shall be carried out and submitted.
x) Source of water and its availability. Commitment regarding availability of requisite quantity of water from the competent authority shall be provided along with firm linkage.
xi) Detailed plan for carrying out rainwater harvesting and proposed utilisation in the plant shall be provided.
xii) Feasibility of zero discharge shall be examined and detailed justification shall be submitted if in case the same is not possible. Proposed discharge (if any), its quantity, quality and point of discharge, users downstream etc. shall be provided.
xiii) Optimization of COC for water conservation. Other water conservation measures proposed in the project should also be given. Quantity of water requirement for the project should be optimized.
xiv) Details of water balance taking into account reuse and re-circulation of effluents.
xv) Detailed plan for conducting monitoring of water quality regularly and mechanism for maintenance of records shall be formulated. Details of methodology and identification of monitoring points (between the plant and drainage in the direction of flow of surface / ground water) shall be submitted. It shall be ensured that parameter to be monitored also include heavy metals in surface and ground water.
xvi) Ash pond shall be shifted away as far as possible from any surface water source. The coordinates of the proposed site including location of ash pond shall be submitted along with topo sheet.
xvii) Action plan for identification of local employable youth for training in skills relevant to the project for eventual employment in the project itself shall be formulated.
xviii) Layout of the plant indicating break-up of plant, green belt, infrastructure, roads etc. shall be provided.
xix) Land requirement for the project shall be optimized. Item wise break up of land requirement and its availability to be furnished. It should also include land to be acquired, if any, for coal transportation system as well as for laying of pipeline including ROW. It may clearly be confirmed that the land including ROW is free of all encumbrances. The issues relating to land acquisition and R&R should be clearly discussed in the EIA report.
xx) Land use based on satellite imagery or authenticated map indicating drainage, cropping pattern, water bodies (rivers, nallahs, ponds etc.), location of nearest villages, creeks, rivers, reservoirs, national parks, wildlife sanctuaries, tiger reserves, biosphere reserves, heritage sites etc in the study area shall be provided. Location of any National Park, Sanctuary, Elephant/Tiger Reserve (existing as well as proposed), migratory routes, if any, within 10 km of the project site shall be specified and marked on the map duly authenticated by the Chief Wildlife Warden.
xxi) Study on land-use pattern in the study area shall be carried out, including identification of common property resources available for conversion into productive land and action plan for abatement and compensation for damage to agricultural land/ common property land (if any) in the nearby villages, due to proposed project shall be prepared.
xxii) Detailed socio-economic study shall be carried out for the study area comprising of 10 km from the plant site.
xxiii) A detailed R&R action plan (as applicable) with time schedule for implementation and also consisting of an in-built monitoring mechanism by an independent third party shall be prepared.
xxiv) CSR component shall be prepared based on need based assessment study to be carried out in the study area. Income generating measures which can help in upliftment of poor section of society which is consistent with the traditional skills of the people shall be identified. The programme can include activities such as development of fodder farm, fruit bearing orchards, vocational training etc. In addition, vocational training for individuals shall be imparted so that poor section of society can take up self employment and jobs. Separate budget for community development activities and income generating programmes shall be specified. Financial allocation to be taken up under CSR shall be specified.
xxv) While formulating CSR schemes it shall be ensured that an in-built monitoring mechanism for the schemes identified is in place and mechanism for conducting annual social audit from the nearest government institute of repute in the region shall be prepared. The project proponent shall also provide plan for the status of implementation of the scheme from time to time.
xxvi) Possibility for adopting nearest three villages shall be explored and details of civic amenities such as roads, drinking water, power etc proposed to be provided at the company’s expenses shall be submitted.
xxvii) Location of intake and outfall points (with coordinates) should be given and the method of disposal of treated waste water from power plant shall be submitted.
xxviii) Topography of the area should be given clearly indicating whether the site requires any filling. If so, details of filling, quantity of fill material required, its source, transportation etc. should be given.
xxix) One complete season AAQ data (except monsoon) shall be given along with the dates of monitoring. The parameters to be covered shall include SPM, RSPM (PM10,PM2.5), SO2, NOx, Hg and Ozone (ground level). The location of the monitoring stations should be so decided so as to take into consideration the pre-dominant downwind direction, population zone and sensitive receptors including reserved forests. There should be at least one monitoring station each in the upwind and in the pre dominant downwind direction at a location where maximum ground level concentration is likely to occur.
xxx) Cumulative impact assessment on ambient air quality due to proposed plant and others (including existing as well as other proposed source of emission) shall be carried out and result submitted in the EIA Report. Mitigative measures as necessary shall be clearly spelt out.
xxxi) Impact of the project on the AAQ of the area. Details of the model used and the input data used for modelling should also be provided. The air quality contours may be plotted on a location map showing the location of project site, habitation nearby, sensitive receptors, if any. The wind roses should also be shown on this map.
xxxii) Fuel analysis shall be provided. Details of auxillary fuel, if any including its quantity, quality, storage etc should also be given.
xxxiii) Quantity of fuel required, its source and transportation route and mode and a confirmed fuel linkage documents shall be provided.
xxxiv) Details regarding infrastructure facilities such as sanitation, fuel, restroom, medical facilities, safety during construction phase etc. to be provided to the labour force during construction as well as to the casual workers including truck drivers during operation phase.
xxxv) EMP to mitigate the adverse impacts due to the project along with item wise cost of its implementation.
xxxvi) A Disaster Management Plan along with risk assessment study including fire and explosion issues due to storage and use of fuel should be carried out. It should take into account the maximum inventory of storage at site at any point in time. The risk contours should be plotted on the plant layout map clearly showing which of the proposed activities would be affected in case of an accident taking place. Based on the same, proposed safeguard measures should be provided. Measures to guard against fire hazards should also be provided.
xxxvii) Detailed plan for raising Green belt of 100 m width and consisting of at least 3 tiers around plant boundary with tree density not less than 2500 trees per ha and survival rate atleast 75% shall be submitted.
xxxviii) Details of litigation pending or otherwise with respect to project in any courts, tribunal etc. shall be provided.
Besides all the above, the following general points will be followed:-
a) All documents to be properly referenced with index, page numbers and continuous page numbering.
b) Where data is presented in the report especially in table, the period in which the data was collected and the source should invariably be indicated.
c) Where the documents provided are in a language other than English, an English translation should be provided.
d) The Questionnaire for environmental appraisal of thermal power projects as devised earlier by the Ministry shall also be filled and submitted.
In addition, information on the following may also be incorporated in the EIA report.
1). Is the project intended to have CDM-intent?
i) If not, then reasons thereof?
ii) If yes, then details under mentioned to be provided:
a) Has PIN (Project Idea Note) {or PCN (Project Concept Note)} been submitted to the NCA? (National CDM Authority) in the MoEF?
b) If not, then by when is that expected?
c) Has PDD (Project Design Document) been prepared?
d) What is the Carbon intensity from your electricity generation projected (i.e. CO2 Tons/MWH or Kg/KWH)
e) Amount of CO2 in Tons/year expected to be reduced from the baseline data available on the CEA’s web-site (www.cea.nic.in)
2. Notwithstanding 1(i) above, data on (d) & (e) above to be worked out and reported.
The Committee informed the project proponent that after preparing the draft EIA (as per the generic structure prescribed in Appendix-III of the EIA Notification, 2006) covering the above mentioned issues, the same shall be submitted to the SPCB for conducting the public hearing as per procedure of EIA notification 2006. The issues which emerge during public hearing shall be further incorporated in the Draft EIA/EMP report. The final EIA/EMP report along with public hearing report and the requisite documents (including written objections, if any) shall be submitted to the Ministry for appraisal by the Expert Appraisal Committee for consideration of awarding environmental clearance under the provisions of Environmental Impact Assessment notification dated September 14, 2006.
2.35 2x660 MW Coal Based TPP of M/s Prakash Industries Limited. at Villages Parasi, Kotmi, Dhurwasin, Kikripodi Champa in Anuppur Taluk, in Anuppur Distt., in Madhya Pradesh. - reg. TOR.
The proposal was considered for determination of terms of reference for undertaking EIA/EMP study as per provisions of EIA notification 2006. The project proponent along with its consultant viz. M/s Sun Consultancy and services gave a presentation and provided the following information:
The proposal is for setting of 2x660 MW Coal Based TPP at Villages Parasi, Kotmi, Dhurwasin, Kikripodi Champa in Anuppur Taluk, in Anuppur Distt., in Madhya Pradesh. Land requirement will be 1680 acres, out of which 266.89 acres is general land; 1318.91 acres is Adivasi land and other 43.90 acres is Government land. The co-ordinates of the proposed site will be at Latitude 23006’ 44.1” to 23008’4.1” N and Longitude 81051’23.2” to 81053’15.5” E. Coal requirement will be 6.08 MTPA. Which will be obtained from Domestic Coal block. Area requirement for ash pond/dyke will be 115 acres. Water requirement will be 39.42 MCM/annum, which will be obtained from Junction of son & Kewai river through a pipeline over a distance of 2 km from the project site. There are no National parks, Wildlife sanctuaries, Heritage sites, Tiger/Biosphere reserves etc. within 10 km of the site.
Based on the information provided and presentation made the Committee prescribed the following specific TORs for undertaking detailed EIA study and preparation of EMP.
i) Vision document specifying prospective long term plan of the site shall be formulated and submitted.
ii) Executive summary of the project indicating relevant details along with photograph of site shall be provided and issues raised in public hearing along with action plan to address the same shall be provided in tabular form including requisite allocation of funds.
iii) Conformity of the site with the prescribed guidelines in terms of distance of 500 m from HFL of the river, highways, railway line shall be shown on the study area map.
iv) The project proponent shall provide confirmed GPS readings of plant boundary.
v) Details of acquisition of tribal land and compliance to tribal rights as per existing Central and State legislations as may be applicable shall be submitted.
vi) No water body/nallah (if any) shall be touched. It shall also be ensured that atleast 100 m distance is kept away from the HFL of the nallah (if any) passing in and around the proposed site.
vii) Hydro-geological study of the area shall be conducted from an institute/ organisation of repute to assess impact of on ground and surface water regime. Specific mitigation measures shall be spelt out and action plan for implementation of the same shall be provided.
viii) Source sustainability study of water requirement shall be carried out by an institute of repute. The study shall also specify the source of water for meeting the requirement during lean season and proposed plan of action.
ix) Study on the impact on catchment area of the river due to proposed withdrawal of such huge quantity of water for running the power plant shall be carried out and submitted.
x) Source of water and its availability. Commitment regarding availability of requisite quantity of water from the competent authority shall be provided along with firm linkage.
xi) Detailed plan for carrying out rainwater harvesting and proposed utilisation in the plant shall be provided.
xii) Feasibility of zero discharge shall be examined and detailed justification shall be submitted if in case the same is not possible. Proposed discharge (if any), its quantity, quality and point of discharge, users downstream etc. shall be provided.
xiii) Optimization of COC for water conservation. Other water conservation measures proposed in the project should also be given. Quantity of water requirement for the project should be optimized.
xiv) Details of water balance taking into account reuse and re-circulation of effluents.
xv) Detailed plan for conducting monitoring of water quality regularly and mechanism for maintenance of records shall be formulated. Details of methodology and identification of monitoring points (between the plant and drainage in the direction of flow of surface / ground water) shall be submitted. It shall be ensured that parameter to be monitored also include heavy metals in surface and ground water.
xvi) Ash pond shall be shifted away as far as possible from any surface water source. The coordinates of the proposed site including location of ash pond shall be submitted along with topo sheet.
xvii) Action plan for identification of local employable youth for training in skills relevant to the project for eventual employment in the project itself shall be formulated.
xviii) Layout of the plant indicating break-up of plant, green belt, infrastructure, roads etc. shall be provided.
xix) Land requirement for the project shall be optimized. Item wise break up of land requirement and its availability to be furnished. It should also include land to be acquired, if any, for coal transportation system as well as for laying of pipeline including ROW. It may clearly be confirmed that the land including ROW is free of all encumbrances. The issues relating to land acquisition and R&R should be clearly discussed in the EIA report.
xx) Land use based on satellite imagery or authenticated map indicating drainage, cropping pattern, water bodies (rivers, nallahs, ponds etc.), location of nearest villages, creeks, rivers, reservoirs, national parks, wildlife sanctuaries, tiger reserves, biosphere reserves, heritage sites etc in the study area shall be provided. Location of any National Park, Sanctuary, Elephant/Tiger Reserve (existing as well as proposed), migratory routes, if any, within 10 km of the project site shall be specified and marked on the map duly authenticated by the Chief Wildlife Warden.
xxi) Study on land-use pattern in the study area shall be carried out, including identification of common property resources available for conversion into productive land and action plan for abatement and compensation for damage to agricultural land/ common property land (if any) in the nearby villages, due to proposed project shall be prepared.
xxii) Detailed socio-economic study shall be carried out for the study area comprising of 10 km from the plant site.
xxiii) A detailed R&R action plan (as applicable) with time schedule for implementation and also consisting of an in-built monitoring mechanism by an independent third party shall be prepared.
xxiv) CSR component shall be prepared based on need based assessment study to be carried out in the study area. Income generating measures which can help in upliftment of poor section of society which is consistent with the traditional skills of the people shall be identified. The programme can include activities such as development of fodder farm, fruit bearing orchards, vocational training etc. In addition, vocational training for individuals shall be imparted so that poor section of society can take up self employment and jobs. Separate budget for community development activities and income generating programmes shall be specified. Financial allocation to be taken up under CSR shall be specified.
xxv) While formulating CSR schemes it shall be ensured that an in-built monitoring mechanism for the schemes identified is in place and mechanism for conducting annual social audit from the nearest government institute of repute in the region shall be prepared. The project proponent shall also provide plan for the status of implementation of the scheme from time to time.
xxvi) Possibility for adopting nearest three villages shall be explored and details of civic amenities such as roads, drinking water, power etc proposed to be provided at the company’s expenses shall be submitted.
xxvii) Location of intake and outfall points (with coordinates) should be given and the method of disposal of treated waste water from power plant shall be submitted.
xxviii) Topography of the area should be given clearly indicating whether the site requires any filling. If so, details of filling, quantity of fill material required, its source, transportation etc. should be given.
xxix) One complete season AAQ data (except monsoon) shall be given along with the dates of monitoring. The parameters to be covered shall include SPM, RSPM (PM10,PM2.5), SO2, NOx, Hg and Ozone (ground level). The location of the monitoring stations should be so decided so as to take into consideration the pre-dominant downwind direction, population zone and sensitive receptors including reserved forests. There should be at least one monitoring station each in the upwind and in the pre dominant downwind direction at a location where maximum ground level concentration is likely to occur.
xxx) Cumulative impact assessment on ambient air quality due to proposed plant and others (including existing as well as other proposed source of emission) shall be carried out and result submitted in the EIA Report. Mitigative measures as necessary shall be clearly spelt out.
xxxi) Impact of the project on the AAQ of the area. Details of the model used and the input data used for modelling should also be provided. The air quality contours may be plotted on a location map showing the location of project site, habitation nearby, sensitive receptors, if any. The wind roses should also be shown on this map.
xxxii) Fuel analysis shall be provided. Details of auxillary fuel, if any including its quantity, quality, storage etc should also be given.
xxxiii) Quantity of fuel required, its source and transportation route and mode and a confirmed fuel linkage documents shall be provided.
xxxiv) Details regarding infrastructure facilities such as sanitation, fuel, restroom, medical facilities, safety during construction phase etc. to be provided to the labour force during construction as well as to the casual workers including truck drivers during operation phase.
xxxv) EMP to mitigate the adverse impacts due to the project along with item wise cost of its implementation.
xxxvi) A Disaster Management Plan along with risk assessment study including fire and explosion issues due to storage and use of fuel should be carried out. It should take into account the maximum inventory of storage at site at any point in time. The risk contours should be plotted on the plant layout map clearly showing which of the proposed activities would be affected in case of an accident taking place. Based on the same, proposed safeguard measures should be provided. Measures to guard against fire hazards should also be provided.
xxxvii) Detailed plan for raising Green belt of 100 m width and consisting of at least 3 tiers around plant boundary with tree density not less than 2500 trees per ha and survival rate atleast 75% shall be submitted.
xxxviii) Details of litigation pending or otherwise with respect to project in any courts, tribunal etc. shall be provided.
Besides all the above, the following general points will be followed:-
a) All documents to be properly referenced with index, page numbers and continuous page numbering.
b) Where data is presented in the report especially in table, the period in which the data was collected and the source should invariably be indicated.
c) Where the documents provided are in a language other than English, an English translation should be provided.
d) The Questionnaire for environmental appraisal of thermal power projects as devised earlier by the Ministry shall also be filled and submitted.
In addition, information on the following may also be incorporated in the EIA report.
1). Is the project intended to have CDM-intent?
i) If not, then reasons thereof?
ii) If yes, then details under mentioned to be provided:
a) Has PIN (Project Idea Note) {or PCN (Project Concept Note)} been submitted to the NCA? (National CDM Authority) in the MoEF?
b) If not, then by when is that expected?
c) Has PDD (Project Design Document) been prepared?
d) What is the Carbon intensity from your electricity generation projected (i.e. CO2 Tons/MWH or Kg/KWH)
e) Amount of CO2 in Tons/year expected to be reduced from the baseline data available on the CEA’s web-site (www.cea.nic.in)
2. Notwithstanding 1(i) above, data on (d) & (e) above to be worked out and reported.
The Committee informed the project proponent that after preparing the draft EIA (as per the generic structure prescribed in Appendix-III of the EIA Notification, 2006) covering the above mentioned issues, the same shall be submitted to the SPCB for conducting the public hearing as per procedure of EIA notification 2006. The issues which emerge during public hearing shall be further incorporated in the Draft EIA/EMP report. The final EIA/EMP report along with public hearing report and the requisite documents (including written objections, if any) shall be submitted to the Ministry for appraisal by the Expert Appraisal Committee for consideration of awarding environmental clearance under the provisions of Environmental Impact Assessment notification dated September 14, 2006.
2.36 Expansion by addition of 5X270 under Stage-II of M/s Indiabulls Realtech Limited at Additional Sinnar Industrial Area, at village Sinnar, in Sinnar Taluk, in Nashik Distt., in Maharastra.- reg. TOR .
The proposal was placed for consideration for environmental clearance. A presentation was also made by the project proponent and its consultant M/s GIS Enabled Environment & Neo- Graphic Centre on the salient features and other details of the project and provided the following information:
The proposal is for expansion from 1350 MW to 2700 MW (addition of 5x270 MW) Coal Based TPP at Additional Sinar Industrial Area, at village Sinnar, In Sinnar Taluk, in Nashik Distt., in Maharastra. Phase-I (1350 MW) is under construction. Land requirement will be 1200 acres which is in at notified Industiral area. The co-ordinates of the proposed site will be at Latitude 19051’35.42 ” to 19052’11.18” N and Longitude 7404’2.48” to 7604’24.28” E. Coal requirement will be 7.2 MTPA, which will be indigenous Coal. Area requirement for ash pond/dyke will be 306 acres. Water requirement will be approx. 40 cusecs, which will be obtained from treated water from STP of Nasik Municipal Corporation through a pipeline over a distance of 30km. There are no National park, wild life sanctuary, Biosphere/ tiger /Elephant reserves, Heritage sites etc within 10km of the project boundary.
The Committee decided that since the present proposal is an expansion case and previous phase was accorded environmental clearance only this year and being in notified industrial area, the present proposal may be exempted from public hearing as per provisions of EIA notification, 2006.
Based on the information provided and presentation made the Committee prescribed the following specific TORs for undertaking detailed EIA study and preparation of EMP.
i) Status of compliance to the conditions stipulated in the environmental clearance accorded for Phase-I shall be submitted.
ii) Vision document specifying prospective long term plan of the site shall be formulated and submitted.
iii) Executive summary of the project indicating relevant details along with photograph of site shall be provided and issues raised in public hearing along with action plan to address the same shall be provided in tabular form including requisite allocation of funds.
iv) Copy of Gazette Notification of notified industrial area along with environmental clearance for the industrial area/estate shall be submitted
v) Conformity of the site with the prescribed guidelines in terms of distance of 500 m from HFL of the river, highways, railway line shall be shown on the study area map.
vi) The project proponent shall provide confirmed GPS readings of plant boundary.
vii) No water body/nallah (if any) shall be touched. It shall also be ensured that atleast 100 m distance is kept away from the HFL of the nallah (if any) passing in and around the proposed site.
viii) Hydro-geological study of the area shall be conducted from an institute/ organisation of repute to assess impact of on ground and surface water regime. Specific mitigation measures shall be spelt out and action plan for implementation of the same shall be provided.
ix) Source sustainability study of water requirement shall be carried out by an institute of repute. The study shall also specify the source of water for meeting the requirement during lean season and proposed plan of action.
x) Study on the impact on catchment area of the river due to proposed withdrawal of such huge quantity of water for running the power plant shall be carried out and submitted.
xi) Source of water and its availability. Commitment regarding availability of requisite quantity of water from the competent authority shall be provided along with firm linkage.
xii) Detailed plan for carrying out rainwater harvesting and proposed utilisation in the plant shall be provided.
xiii) Feasibility of zero discharge shall be examined and detailed justification shall be submitted if in case the same is not possible. Proposed discharge (if any), its quantity, quality and point of discharge, users downstream etc. shall be provided.
xiv) Optimization of COC for water conservation. Other water conservation measures proposed in the project should also be given. Quantity of water requirement for the project should be optimized.
xv) Details of water balance taking into account reuse and re-circulation of effluents.
xvi) Detailed plan for conducting monitoring of water quality regularly and mechanism for maintenance of records shall be formulated. Details of methodology and identification of monitoring points (between the plant and drainage in the direction of flow of surface / ground water) shall be submitted. It shall be ensured that parameter to be monitored also include heavy metals in surface and ground water.
xvii) Ash pond shall be shifted away as far as possible from any surface water source. The coordinates of the proposed site including location of ash pond shall be submitted along with topo sheet.
xviii) Action plan for identification of local employable youth for training in skills relevant to the project for eventual employment in the project itself shall be formulated.
xix) Layout of the plant indicating break-up of plant, green belt, infrastructure, roads etc. shall be provided.
xx) Land requirement for the project shall be optimized. Item wise break up of land requirement and its availability to be furnished. It should also include land to be acquired, if any, for coal transportation system as well as for laying of pipeline including ROW. It may clearly be confirmed that the land including ROW is free of all encumbrances. The issues relating to land acquisition and R&R should be clearly discussed in the EIA report.
xxi) Land use based on satellite imagery or authenticated map indicating drainage, cropping pattern, water bodies (rivers, nallahs, ponds etc.), location of nearest villages, creeks, rivers, reservoirs, national parks, wildlife sanctuaries, tiger reserves, biosphere reserves, heritage sites etc in the study area shall be provided. Location of any National Park, Sanctuary, Elephant/Tiger Reserve (existing as well as proposed), migratory routes, if any, within 10 km of the project site shall be specified and marked on the map duly authenticated by the Chief Wildlife Warden.
xxii) Study on land-use pattern in the study area shall be carried out, including identification of common property resources available for conversion into productive land and action plan for abatement and compensation for damage to agricultural land/ common property land (if any) in the nearby villages, due to proposed project shall be prepared.
xxiii) Detailed socio-economic study shall be carried out for the study area comprising of 10 km from the plant site.
xxiv) A detailed R&R action plan (as applicable) with time schedule for implementation and also consisting of an in-built monitoring mechanism by an independent third party shall be prepared.
xxv) CSR component shall be prepared based on need based assessment study to be carried out in the study area. Income generating measures which can help in upliftment of poor section of society which is consistent with the traditional skills of the people shall be identified. The programme can include activities such as development of fodder farm, fruit bearing orchards, vocational training etc. In addition, vocational training for individuals shall be imparted so that poor section of society can take up self employment and jobs. Separate budget for community development activities and income generating programmes shall be specified. Financial allocation to be taken up under CSR shall be specified.
xxvi) While formulating CSR schemes it shall be ensured that an in-built monitoring mechanism for the schemes identified is in place and mechanism for conducting annual social audit from the nearest government institute of repute in the region shall be prepared. The project proponent shall also provide plan for the status of implementation of the scheme from time to time.
xxvii) Possibility for adopting nearest three villages shall be explored and details of civic amenities such as roads, drinking water, power etc proposed to be provided at the company’s expenses shall be submitted.
xxviii) Location of intake and outfall points (with coordinates) should be given and the method of disposal of treated waste water from power plant shall be submitted.
xxix) Topography of the area should be given clearly indicating whether the site requires any filling. If so, details of filling, quantity of fill material required, its source, transportation etc. should be given.
xxx) One complete season AAQ data (except monsoon) shall be given along with the dates of monitoring. The parameters to be covered shall include SPM, RSPM (PM10,PM2.5), SO2, NOx, Hg and Ozone (ground level). The location of the monitoring stations should be so decided so as to take into consideration the pre-dominant downwind direction, population zone and sensitive receptors including reserved forests. There should be at least one monitoring station each in the upwind and in the pre dominant downwind direction at a location where maximum ground level concentration is likely to occur.
xxxi) Cumulative impact assessment on ambient air quality due to proposed plant and others (including existing as well as other proposed source of emission) shall be carried out and result submitted in the EIA Report. Mitigative measures as necessary shall be clearly spelt out.
xxxii) Impact of the project on the AAQ of the area. Details of the model used and the input data used for modelling should also be provided. The air quality contours may be plotted on a location map showing the location of project site, habitation nearby, sensitive receptors, if any. The wind roses should also be shown on this map.
xxxiii) Fuel analysis shall be provided. Details of auxillary fuel, if any including its quantity, quality, storage etc should also be given.
xxxiv) Quantity of fuel required, its source and transportation route and mode and a confirmed fuel linkage documents shall be provided.
xxxv) Details regarding infrastructure facilities such as sanitation, fuel, restroom, medical facilities, safety during construction phase etc. to be provided to the labour force during construction as well as to the casual workers including truck drivers during operation phase.
xxxvi) EMP to mitigate the adverse impacts due to the project along with item wise cost of its implementation.
xxxvii) A Disaster Management Plan along with risk assessment study including fire and explosion issues due to storage and use of fuel should be carried out. It should take into account the maximum inventory of storage at site at any point in time. The risk contours should be plotted on the plant layout map clearly showing which of the proposed activities would be affected in case of an accident taking place. Based on the same, proposed safeguard measures should be provided. Measures to guard against fire hazards should also be provided.
xxxviii) Detailed plan for raising Green belt of 100 m width and consisting of at least 3 tiers around plant boundary with tree density not less than 2500 trees per ha and survival rate atleast 75% shall be submitted.
xxxix) Details of litigation pending or otherwise with respect to project in any courts, tribunal etc. shall be provided.
Besides all the above, the following general points will be followed:-
a) All documents to be properly referenced with index, page numbers and continuous page numbering.
b) Where data is presented in the report especially in table, the period in which the data was collected and the source should invariably be indicated.
c) Where the documents provided are in a language other than English, an English translation should be provided.
d) The Questionnaire for environmental appraisal of thermal power projects as devised earlier by the Ministry shall also be filled and submitted.
In addition, information on the following may also be incorporated in the EIA report.
1). Is the project intended to have CDM-intent?
i) If not, then reasons thereof?
ii) If yes, then details under mentioned to be provided:
a) Has PIN (Project Idea Note) {or PCN (Project Concept Note)} been submitted to the NCA? (National CDM Authority) in the MoEF?
b) If not, then by when is that expected?
c) Has PDD (Project Design Document) been prepared?
d) What is the Carbon intensity from your electricity generation projected (i.e. CO2 Tons/MWH or Kg/KWH)
e) Amount of CO2 in Tons/year expected to be reduced from the baseline data available on the CEA’s web-site (www.cea.nic.in)
2. Notwithstanding 1(i) above, data on (d) & (e) above to be worked out and reported.
The Committee informed the project proponent that after preparing the EIA (as per the generic structure prescribed in Appendix-III of the EIA Notification, 2006) covering the above mentioned issues, the same shall be submitted to the Ministry for appraisal by the Expert Appraisal Committee for consideration of awarding environmental clearance under the provisions of Environmental Impact Assessment notification dated September 14, 2006.
2.37 Expansion of Coal based TPP by setting up additional units of 5X270 under Stage-II (Form 1350 MW to 2700 MW) of M/s Indiabulls Power Limited at village Nandgaonpeth, In Amravati Taluk, in Amravati Distt., in Maharastra.- reg. TOR .
The proposal was placed for consideration for environmental clearance. A presentation was also made by the project proponent and its consultant M/s GIS Enabled Environment & Neo- Graphic Centre gave a presentation and provided the following information:
The proposal is for setting up for expansion of Coal based Thermal Power Plant from 1350 MW to 2700 MW at village Sinnare, In Sinnar Taluk, in Nashik Distt., in Maharashtra. Land requirement will be 1350 acres which is other land and placed at notified Industiral area. The co-ordinates of the proposed site will be at Latitude 2103’26.30” to 2105’27.03”N and Longitude 77053’19.15” to 77054’29.41” E. Coal requirement will be 7.2 MTPA, which is Indigenous Coal block will be obtained from SECL through long-term linkage. Area requirement for ash pond/dyke will be 346 acres (for stage I & Stage II). Water requirement will be approx. 43 MCM/annum, which will be obtained from Wardha Dam through a pipeline over a distance of 35km. There are no National park, wild life sanctuary, Biosphere/ tiger /Elephant reserves, Heritage sites etc within 10km of the project boundary.
The Committee decided that since the present proposal is an expansion case and previous phase was accorded environmental clearance only in the recently and being in notified industrial area, the present proposal may be exempted from public hearing as per provisions of EIA notification, 2006.
Based on the information provided and presentation made the Committee prescribed the following specific TORs for undertaking detailed EIA study and preparation of EMP.
i) Status of compliance to the conditions stipulated in the environmental clearance accorded for Phase-I shall be submitted.
ii) Vision document specifying prospective long term plan of the site shall be formulated and submitted.
iii) Executive summary of the project indicating relevant details along with photograph of site shall be provided and issues raised in public hearing along with action plan to address the same shall be provided in tabular form including requisite allocation of funds.
iv) Copy of Gazette Notification of notified industrial area along with environmental clearance for the industrial area/estate shall be submitted
v) Conformity of the site with the prescribed guidelines in terms of distance of 500 m from HFL of the river, highways, railway line shall be shown on the study area map.
vi) The project proponent shall provide confirmed GPS readings of plant boundary.
vii) No water body/nallah (if any) shall be touched. It shall also be ensured that atleast 100 m distance is kept away from the HFL of the nallah (if any) passing in and around the proposed site.
viii) Hydro-geological study of the area shall be conducted from an institute/ organisation of repute to assess impact of on ground and surface water regime. Specific mitigation measures shall be spelt out and action plan for implementation of the same shall be provided.
ix) Source sustainability study of water requirement shall be carried out by an institute of repute. The study shall also specify the source of water for meeting the requirement during lean season and proposed plan of action.
x) Study on the impact on catchment area of the river due to proposed withdrawal of such huge quantity of water for running the power plant shall be carried out and submitted.
xi) Source of water and its availability. Commitment regarding availability of requisite quantity of water from the competent authority shall be provided along with firm linkage.
xii) Detailed plan for carrying out rainwater harvesting and proposed utilisation in the plant shall be provided.
xiii) Feasibility of zero discharge shall be examined and detailed justification shall be submitted if in case the same is not possible. Proposed discharge (if any), its quantity, quality and point of discharge, users downstream etc. shall be provided.
xiv) Optimization of COC for water conservation. Other water conservation measures proposed in the project should also be given. Quantity of water requirement for the project should be optimized.
xv) Details of water balance taking into account reuse and re-circulation of effluents.
xvi) Detailed plan for conducting monitoring of water quality regularly and mechanism for maintenance of records shall be formulated. Details of methodology and identification of monitoring points (between the plant and drainage in the direction of flow of surface / ground water) shall be submitted. It shall be ensured that parameter to be monitored also include heavy metals in surface and ground water.
xvii) Ash pond shall be shifted away as far as possible from any surface water source. The coordinates of the proposed site including location of ash pond shall be submitted along with topo sheet.
xviii) Action plan for identification of local employable youth for training in skills relevant to the project for eventual employment in the project itself shall be formulated.
xix) Layout of the plant indicating break-up of plant, green belt, infrastructure, roads etc. shall be provided.
xx) Land requirement for the project shall be optimized. Item wise break up of land requirement and its availability to be furnished. It should also include land to be acquired, if any, for coal transportation system as well as for laying of pipeline including ROW. It may clearly be confirmed that the land including ROW is free of all encumbrances. The issues relating to land acquisition and R&R should be clearly discussed in the EIA report.
xxi) Land use based on satellite imagery or authenticated map indicating drainage, cropping pattern, water bodies (rivers, nallahs, ponds etc.), location of nearest villages, creeks, rivers, reservoirs, national parks, wildlife sanctuaries, tiger reserves, biosphere reserves, heritage sites etc in the study area shall be provided. Location of any National Park, Sanctuary, Elephant/Tiger Reserve (existing as well as proposed), migratory routes, if any, within 10 km of the project site shall be specified and marked on the map duly authenticated by the Chief Wildlife Warden.
xxii) Study on land-use pattern in the study area shall be carried out, including identification of common property resources available for conversion into productive land and action plan for abatement and compensation for damage to agricultural land/ common property land (if any) in the nearby villages, due to proposed project shall be prepared.
xxiii) Detailed socio-economic study shall be carried out for the study area comprising of 10 km from the plant site.
xxiv) A detailed R&R action plan (as applicable) with time schedule for implementation and also consisting of an in-built monitoring mechanism by an independent third party shall be prepared.
xxv) CSR component shall be prepared based on need based assessment study to be carried out in the study area. Income generating measures which can help in upliftment of poor section of society which is consistent with the traditional skills of the people shall be identified. The programme can include activities such as development of fodder farm, fruit bearing orchards, vocational training etc. In addition, vocational training for individuals shall be imparted so that poor section of society can take up self employment and jobs. Separate budget for community development activities and income generating programmes shall be specified. Financial allocation to be taken up under CSR shall be specified.
xxvi) While formulating CSR schemes it shall be ensured that an in-built monitoring mechanism for the schemes identified is in place and mechanism for conducting annual social audit from the nearest government institute of repute in the region shall be prepared. The project proponent shall also provide plan for the status of implementation of the scheme from time to time.
xxvii) Possibility for adopting nearest three villages shall be explored and details of civic amenities such as roads, drinking water, power etc proposed to be provided at the company’s expenses shall be submitted.
xxviii) Location of intake and outfall points (with coordinates) should be given and the method of disposal of treated waste water from power plant shall be submitted.
xxix) Topography of the area should be given clearly indicating whether the site requires any filling. If so, details of filling, quantity of fill material required, its source, transportation etc. should be given.
xxx) One complete season AAQ data (except monsoon) shall be given along with the dates of monitoring. The parameters to be covered shall include SPM, RSPM (PM10,PM2.5), SO2, NOx, Hg and Ozone (ground level). The location of the monitoring stations should be so decided so as to take into consideration the pre-dominant downwind direction, population zone and sensitive receptors including reserved forests. There should be at least one monitoring station each in the upwind and in the pre dominant downwind direction at a location where maximum ground level concentration is likely to occur.
xxxi) Cumulative impact assessment on ambient air quality due to proposed plant and others (including existing as well as other proposed source of emission) shall be carried out and result submitted in the EIA Report. Mitigative measures as necessary shall be clearly spelt out.
xxxii) Impact of the project on the AAQ of the area. Details of the model used and the input data used for modelling should also be provided. The air quality contours may be plotted on a location map showing the location of project site, habitation nearby, sensitive receptors, if any. The wind roses should also be shown on this map.
xxxiii) Fuel analysis shall be provided. Details of auxillary fuel, if any including its quantity, quality, storage etc should also be given.
xxxiv) Quantity of fuel required, its source and transportation route and mode and a confirmed fuel linkage documents shall be provided.
xxxv) Details regarding infrastructure facilities such as sanitation, fuel, restroom, medical facilities, safety during construction phase etc. to be provided to the labour force during construction as well as to the casual workers including truck drivers during operation phase.
xxxvi) EMP to mitigate the adverse impacts due to the project along with item wise cost of its implementation.
xxxvii) A Disaster Management Plan along with risk assessment study including fire and explosion issues due to storage and use of fuel should be carried out. It should take into account the maximum inventory of storage at site at any point in time. The risk contours should be plotted on the plant layout map clearly showing which of the proposed activities would be affected in case of an accident taking place. Based on the same, proposed safeguard measures should be provided. Measures to guard against fire hazards should also be provided.
xxxviii) Detailed plan for raising Green belt of 100 m width and consisting of at least 3 tiers around plant boundary with tree density not less than 2500 trees per ha and survival rate atleast 75% shall be submitted.
xxxix) Details of litigation pending or otherwise with respect to project in any courts, tribunal etc. shall be provided.
Besides all the above, the following general points will be followed:-
a) All documents to be properly referenced with index, page numbers and continuous page numbering.
b) Where data is presented in the report especially in table, the period in which the data was collected and the source should invariably be indicated.
c) Where the documents provided are in a language other than English, an English translation should be provided.
d) The Questionnaire for environmental appraisal of thermal power projects as devised earlier by the Ministry shall also be filled and submitted.
In addition, information on the following may also be incorporated in the EIA report.
1). Is the project intended to have CDM-intent?
i) If not, then reasons thereof?
ii) If yes, then details under mentioned to be provided:
a) Has PIN (Project Idea Note) {or PCN (Project Concept Note)} been submitted to the NCA? (National CDM Authority) in the MoEF?
b) If not, then by when is that expected?
c) Has PDD (Project Design Document) been prepared?
d) What is the Carbon intensity from your electricity generation projected (i.e. CO2 Tons/MWH or Kg/KWH)
e) Amount of CO2 in Tons/year expected to be reduced from the baseline data available on the CEA’s web-site (www.cea.nic.in)
2. Notwithstanding 1(i) above, data on (d) & (e) above to be worked out and reported.
The Committee informed the project proponent that after preparing the EIA (as per the generic structure prescribed in Appendix-III of the EIA Notification, 2006) covering the above mentioned issues, the same shall be submitted to the Ministry for appraisal by the Expert Appraisal Committee for consideration of awarding environmental clearance under the provisions of Environmental Impact Assessment notification dated September 14, 2006.
2.38 Expansion by addition of 11.5 MW HSD Based Backup Power along with 2x50 MT Propane Bullet of M/s Honda Motorcycle & Scooter India Pvt. Ltd. at Tapukara Industrial area, in Tijara Taluk, in Alwar Distt. In Rajasthan- reg. TOR .
The proposal was placed for consideration for environmental clearance. A presentation was also made by the project proponent and its consultant M/s EQMS India Pvt. Ltd. gave a presentation and provided the following information:
The proposal is for setting up addition of 11.5 MW HSD Based Backup Power along with 2x50 MT Propane Bullet at Tapukara Industrial area, in Tijara Taluk in Alwar Distt. in Rajasthan. Presently power is obtained from express feeder but since there is an average 300 hours of tripping a year the back up power plant is proposed. Land requirement will be 0.19 ha for Power house and 0.21 ha fro Propane yard. The land selected for proposed expansion of project is within the plant premised of M/s HMSI. The co-ordinates of the proposed site will be at Latitude 28007’24.61” to 28007’35.30” N and Longitude 76048’44.50” to 76049’16.51” E. Fuel requirement will be 550 KL/annum HSD and 40000 TPA propane and will be sourced from oil depot at Rewari and GAIL(Auraiya (UP)/Vijaypur(MP) respectively. Water requirement will be obtained from ground water. There are no National park, wild life sanctuary, Biosphere/ tiger /Elephant reserves, Heritage sites etc within 10km of the project boundary.
The Committee deliberated on the matter and felt that diesel based power plant even for back up power of such capacity is not an encouraging proposition and therefore decided that the project proponent shall explore all possibilities such as obtaining power from open access etc. before the proposal is agreed. The Committee therefore decided the proposal be deferred and shall be re-considered only after submission of detail clarification/ information as stated above.
2.39 Order of the NEAA in the matter of 2640 MW Bhavapadu Coal Based TPP of M/s East Coast Energy Pvt. Ltd. in Sompeta Mandal, in Srikakulam Distt., in Andhra Pradesh.
The Order of the National Environment Appellate Authority (NEAA) in the matter of 2640 MW Bhavapadu Coal Based TPP of M/s East Coast Energy Pvt. Ltd. in Sompeta Mandal, in Srikakulam Distt., in Andhra Pradesh, was taken up. The Committee however felt that members may be circulated the copy of the Order for their reference and views (if any). The matter was accordingly dropped.
2.40 225 MW Gas Based Combined Cycle Power Plant of M/s Gama Infraprop Pvt. Ltd. at village Mahuakherganj, in Kashipur Taluk, in Udham Singh nagar Distt., in Uttarakhand.
The above proposal was placed for information of the Committee that the project proposal was recommended for TOR in the 5th Meeting of the Committee held during August 9-10, 2010. The Ministry accordingly issued TOR on September 09, 2010 for undertaking detailed EIA studies and for preparation of EIA/EMP. The project proponent have submitted EIA/EMP report to the Ministry on September 13, 2010.
The Committee decided that the following line of action may be taken:
i) The EIA/EMP report submitted by the project proponent shall be supplemented with one month data on AAQ.
iii) The project proponent may be asked to submit copy of the gazette notification of the industrial area where their project is to be located along with copy of the environmental clearance of the industrial area/estate.
iv) A map (layout) of the industrial area indicating location of their power plant and duly vetted by the Competent Authority in the State Govt.; and
iii) Point wise compliance of the TOR prescribed along with revised EIA/EMP report.
2.41 1x75 MW Kutch Lignite TPS Unit-IV of M/s Gujarat State Electricity Corpn. Ltd. at village Panandhro, in Kuch Distt., in Gujarat - chimney height reg.
The proposal was not taken up as the members desired that details of the previous deliberations may be made available first for reference.
2.42 Change in unit configuration from 2x500 MW to 2x660 MW Coal Based TPP of M/s Hibra Power Ltd., at villages Devaldi and Pratappura, in Khandwa Distt., in Madhya Pradesh - reg.
The above matter was taken up for consideration. The Committee noted that the request for change is for better technology and need encouragement. The Committee therefore decided that the request may be agreed.
There being no agenda item left the meeting ended with thanks to the Chair. It was also decided that the next meeting of the Committee will be held on December 06 and December 07, 2010.
-------------