Order of the National Green Tribunal regarding schools and colleges in Delhi to install RWH systems, 11/09/2019

  • 11/09/2019

Order of the National Green Tribunal in the matter of Vinod Kumar Jain Vs NCT of Delhi & Others dated 11/09/2019 regarding all the schools and colleges in Delhi to install RWH systems within two months from the date of the order (November 16, 2017) failing which compensation of Rs. 5 lakhs will be required to be paid.

Through its order dated January 30, 2019 the Tribunal had directed recovery of compensation from the schools and colleges which have not complied with the order of the Tribunal and on February 20, 2019 the Tribunal dismissed applications of non-compliant schools seeking waiver of environmental compensation. Similar order was passed on March 13, 2019. The relevant authorities have been directed to enforce the order of the Tribunal dated November 16, 2017 and furnish a report.